Why Social Infrastructure Projects Experience Cost Overrun ...
Transcript of Why Social Infrastructure Projects Experience Cost Overrun ...
Why Social Infrastructure Projects Experience Cost Overrun
Xinyi Chen
Thesis submitted to the University of Ottawa in partial Fulfillment of the requirements for the
MSc. in Management Degree
Telfer School of Management University of Ottawa
© Xinyi Chen, Ottawa, Canada, 2020
Why Social Infrastructure Projects Experience Cost Overrun?
ii
Table of Contents
ACKNOWLEDGEMENT _____________________________________________________________ IV
ABSTRACT _________________________________________________________________________ V
LIST OF TABLES ___________________________________________________________________ VI
LIST OF FIGURES __________________________________________________________________ VI
1. INTRODUCTION _______________________________________________________________ 1
1.1. INFRASTRUCTURE AND ITS ROLE IN ECONOMIC DEVELOPMENT _________________________ 2 1.2. CONSEQUENCES OF COST OVERRUN IN THE INFRASTRUCTURE INDUSTRY _________________ 5 1.3. SOCIAL INFRASTRUCTURE: THE MISSING PIECE IN COST OVERRUN RESEARCH _____________ 7 1.4. WHAT IS SOCIAL INFRASTRUCTURE? ______________________________________________ 8
2. LITERATURE REVIEW ________________________________________________________ 12
2.1. THE DEFINITION OF COST OVERRUN _____________________________________________ 12 2.2. HOW TO CALCULATE COST OVERRUN? ___________________________________________ 13
2.2.1. Estimated Budget at ToD Stage. _____________________________________________ 25 2.2.2. Estimated Budget Before the Construction Stage ________________________________ 25
2.3. COST OVERRUN CALCULATION METHOD ADOPTED BY THE CURRENT STUDY _____________ 27 2.3.1. The Budget Estimation Procedure in China. ____________________________________ 28 2.3.2. The Conceptual Budget Overrun and Cost Overrun ______________________________ 31 2.3.3. Cost Overrun Definition and Calculation Method in This Thesis ____________________ 34 2.3.4. Calculation Formula ______________________________________________________ 35
2.4. WHAT ARE THE CAUSES OF COST OVERRUN? ______________________________________ 36 2.4.1. Psycho Theory ___________________________________________________________ 37 2.4.2. Evolutional Theory ________________________________________________________ 40 2.4.3. Mechanism Flaw _________________________________________________________ 44 2.4.4. The Potential Solutions to Cost Overrun. ______________________________________ 46
3. METHODOLOGY ______________________________________________________________ 50
3.1. DATA SELECTION ___________________________________________________________ 52 3.2. OVERVIEW OF THE CASES _____________________________________________________ 53 3.3. DATA ANALYSIS ____________________________________________________________ 66
3.3.1. Documentary analysis _____________________________________________________ 66 3.3.2. Comparative Analysis _____________________________________________________ 68
4. FINDINGS _____________________________________________________________________ 71
4.1. WITHIN-CASE FINDINGS ______________________________________________________ 71 4.1.1. CASE#1 ________________________________________________________________ 71 4.1.2. CASE #2 ________________________________________________________________ 77
Why Social Infrastructure Projects Experience Cost Overrun?
iii
4.1.3. CASE#3 ________________________________________________________________ 80 4.1.4. CASE#4 ________________________________________________________________ 83
4.2. CROSS-CASE FINDINGS _______________________________________________________ 86 4.2.1. Cost Overrun Contributors _________________________________________________ 86
4.3. STAKEHOLDERS _____________________________________________________________ 94
5. DISCUSSION _________________________________________________________________ 102
5.1. EVOLUTION THEORIES _______________________________________________________ 102 5.1.1. The paradox of narrowing down the budget ___________________________________ 105
5.2. PSYCHO THEORIES __________________________________________________________ 106
6. CONCLUSION ________________________________________________________________ 109
6.1. THE CAUSES OF COST OVERRUN ________________________________________________ 110 6.1.1. Time pressure ___________________________________________________________ 110 6.1.2. Changes of orders and project scope _________________________________________ 111 6.1.3. Theoretical contribution __________________________________________________ 111
6.2. PRACTICAL IMPLICATIONS ____________________________________________________ 112 6.3. LIMITATIONS OF THE STUDY __________________________________________________ 114 6.4. SUGGESTIONS FOR FUTURE RESEARCH __________________________________________ 115
APPENDIX: CRS CODE OF SOCIAL INFRASTRUCTURE FACILITY ___________________ 117
REFERENCE ______________________________________________________________________ 128
Why Social Infrastructure Projects Experience Cost Overrun?
iv
Acknowledgement
I would first like to thank my thesis supervisor Professor Lavagnon Ika of the Telfer
School of Management at University of Ottawa. The door to Prof. Ika’s office (and the
Skype line) was always open whenever I ran into a trouble spot or had a question about
my research or writing. He helps me overcoming the “writing crisis” which nearly
knocked me down.
I would also like to acknowledge Dr. Muriel Mignerat and Dr. Stephane Tywoniak of
the Telfer School of Management at University of Ottawa as the committee of this thesis,
and I am gratefully indebted to their very valuable comments on this thesis.
Finally, I must express my very profound gratitude to my parents for providing me
with unfailing support and continuous encouragement throughout my years of study and
through the process of researching and writing this thesis. This accomplishment would
not have been possible without them.
At this difficult moment, when the whole world seems to be torn apart, I am really
grateful that I am able to still continue with my thesis and finally finish it with the great
support one can ever have. Thank you for a million times!
Author
Xinyi Chen
Why Social Infrastructure Projects Experience Cost Overrun?
v
Abstract
The infrastructure industry has witnessed incredible growth around the world in the
past decade. Large-scale investments have been made by governments in the
infrastructure industry as an effective way to stimulate the economy. However, it is worth
noting that infrastructure projects worldwide suffer from frequent cases of cost overrun.
As a critical challenge in the infrastructure industry, cost overrun remains however an
under-researched academic topic. Previous studies in this field have mainly adopted
quantitative methodological research methods and analyzed data from economic
infrastructure projects. Social infrastructure projects, however, have received
comparatively less academic attention. This study seeks to fill this gap and to analyze the
reasons why social infrastructure projects experience cost overrun. Data were collected
from four cases of social infrastructure projects in China and a multiple case-study
approach was taken to analyze the data. The findings of the research suggest that, first,
the time pressure and changes of orders/scope are the main factors causing the cost
overrun in the context of Chinese social infrastructure projects. Moreover, combining the
practical cases with existing theorists, it is clear that the evolutional theorist performs
better in explaining the cost overrun in the context of Chinese social infrastructure
projects comparing to the psycho theorist.
Why Social Infrastructure Projects Experience Cost Overrun?
vi
List of Tables
Table 1 the Difference between Economic and Social Infrastructure ......................... 9
Table 2 Key Studies and Their Ways of Calculating Cost Overrun .......................... 15
Table 3 Summary of Three Theories and Key Authors ............................................ 46
Table 4 Project Information ....................................................................................... 56
Table 5 Stakeholders and Their Roles ....................................................................... 63
Table 6 Keywords and counting for CAES#1 ........................................................... 71
Table 7 Keywords and counting for CASE #2 .......................................................... 77
Table 8 Keywords and counting for CASE #3 .......................................................... 80
Table 9 Keywords and counting for CASE #4 .......................................................... 83
Table 10 Cross-case keywords summary .................................................................. 86
Table 11 Keywords related to time pressure ............................................................ 87
Table 12 Keywords related to changes of orders/scope ........................................... 91
Table 13 the Cross-case analysis of contributors and stakeholders ........................... 98
Table 14 Overrun caused by increased workload (change order/scope) ................. 103
Table 15 Overrun caused by increased workload (omission) .................................. 105
Table 16 the Comparison Between Two Schools of Thought ................................. 108
List of Figures
Figure 1 the Relationship between Budget Evolution and Stakeholders .................. 26
Figure 2 Cost Escalation and Cost Overrun .............................................................. 27
Figure 3 the Budget Estimation Process in China ..................................................... 28
Figure 4 Conceptual Budget Overrun ........................................................................ 33
Figure 5 Conceptual Budget Overrun and Cost Overrun according to Chinese
Regulation .......................................................................................................... 34
Figure 6 Documentary analysis step .......................................................................... 68
Why Social Infrastructure Projects Experience Cost Overrun?
vii
Figure 7 Stakeholders and involvements ................................................................... 93
Figure 8 CASE#1 ...................................................................................................... 95
Figure 9 CASE#2 ...................................................................................................... 96
Figure 10 CASE#3 .................................................................................................... 97
Figure 11 CASE#4 .................................................................................................... 98
Figure 12 Time Pressure .......................................................................................... 110
Why Social Infrastructure Projects Experience Cost Overrun?
1
1. Introduction
The infrastructure industry has grown rapidly all around the world in recent years.
Infrastructure, especially social infrastructure, is indispensable for an efficient operation
of the society and a sustainable growth of the economy. Social infrastructure commonly
refers to facilities such as hospitals, public schools and libraries that are funded,
constructed and/or by the government authority. Even though governments have had
abundant experience in organizing and procuring social infrastructure projects, cost
overrun still occurs and causes massive loss in capital and resources. The current study
seeks to analyze why social infrastructure projects experience cost overrun. It relies on a
case study of four social infrastructure projects in China.
This proposal is composed of three sections. In the first section, an introduction is
given on the role and importance of social infrastructure, and the research question will
be elucidated. The second section is a literature review, providing a summary of existing
studies focusing on reasons behind cost overrun and a detailed description of the budget
estimation process of Chinese social infrastructure projects. Also in this section, the
author discusses the definition of a social infrastructure project. The third section--the
methodology section--begins with an overview of how the current study is conducted,
followed by the introduction of a coding book guiding the documentary analysis. As
mentioned above, cost overrun has been a prevailing problem for a long period and
considerable academic resources have been devoted to this field trying to solve the
problem. However, those studies are mainly conducted in the context of economic
infrastructure with very little attention on social ones. The current study then hopes to
contribute in filling in this gap.
The current study aims to explore why social infrastructure projects experience cost
overrun by borrowing insights from existing theories and documentary analyses on
practical cases. The analysis will contain three steps: the document interpretation, the
Why Social Infrastructure Projects Experience Cost Overrun?
2
factor extraction, and cross-case comparation. It will categorize the explanations from
documentation and archive based on two dominant schools of thought in the field.
Moreover, this study will compare the similarities and differences of explanations within
and between cases from different stakeholders’ perspectives.
1.1. Infrastructure and Its Role in Economic Development
The infrastructure industry has seen an unprecedented growth worldwide during the
past decade. In 2008, however, the economic crisis hit the globe. In order to stimulate the
economy and get the unemployment rate off the hook, countries around the world
launched numerous investment plans on infrastructure projects. As for developing
countries, take China and India as examples, the infrastructure investment budgets in
2008 reached respectively 537.6 billion Yuan (approximately 84.8 billion in USD)
("2018 Central Construction Expenditure Budget Table," 2018) and RS 5.97 lakh crore
(approximately 85 billion in USD) ("Budget 2018: Annual infrastructure spending hiked
to Rs 6 lakh crore," 2018). Looking into developed countries, just in the single month of
February in 2018, the United States proposed a massive infrastructure plan worth USD
1.5 trillion to rebuild crumbling highways, bridges, railways and seaports (Calia, 2018),
and Canada plans to deliver projects worth CAD 33 billion (approximately 24.92 billion
in USD) in 2017 (Investing in Canada plan Bilateral Agreements, 2018).
As an essential driving force of economic growth, infrastructure projects increase
productivity and generate more economic opportunities in three ways. Firstly,
infrastructure investment helps to create a large amount of vacant jobs in construction
and maintenance, thus prevents employment rate from further decrease. According to the
Brookings Institution Analysis Bureau of Labor Statistics data, 14 million people, or 11
percent of the US workforce, live on their salaries in industries directly related to
infrastructure, from electrical power line installers, truck drivers to construction laborers
(Puentes, 2015).
Why Social Infrastructure Projects Experience Cost Overrun?
3
Secondly, infrastructure investment can boost domestic economy by consuming a
great quantity of construction materials and promoting mobility of labor, resources and
products. Before 2008, thanks to a robust export, China’s iron and steel industry
expanded at a rapid rate with an annual production capacity of 600 million tons. Due to
the 2008 international economic crisis, nevertheless, the whole industry was forced to cut
production significantly facing a sluggish export demand, though most factories cannot
afford the loss. Consequently, the annual output of iron and steel fell to 420 million tons
in October 2008, down 26% from the highest level of the year. In 2009, the Chinese
government responded by launching a railway network plan worth 3.5 trillion Yuan,
comprising 150 construction projects including railways, bridges, tunnels, culverts and
electrification. Just in 2010, this plan consumed more than 580 million tons of iron and
steel, which saved the iron and steel industry from misery. As the state’s economic
stimulus plan released hundreds of thousands of infrastructure construction works
(including low-capacity highways, high-speed railways and fixed connection lines etc.),
domestic consumption began to grow and gradually made up for the sharp decline in
exports. In 2009, the domestic consumption of iron and steel reached a record of 560.04
million tons, increased by 24.8% than the past year; the annual output of iron and steel
was 576.84 million tons with an increase of 67.53 million tons (13.5%) compared with
the previous year.
Thirdly, infrastructure investment also enhances the transportation system, enables
the mobility of labor, resources and products, and even stimulates the growth of other
entirely different industries (Zheng, 2011). The express delivery industry in China is one
typical example. Back in 2006, the Chinese express delivery business was only one-tenth
of that of the United States in terms of production value. Yet, the figure in 2016 is twice
of that of the United States, with the total amount exceeding 30 billion, accounting for
40% of the global business (Hu, 2017). Since the reform of the postal system in 2006,
Why Social Infrastructure Projects Experience Cost Overrun?
4
especially after the revision of the postal law, the advantage of the express delivery
industry has come into light. For the next six consecutive years, the express delivery
business maintains a skyrocketing growth speed of around 50%. Nowadays, people in
China are accustomed to shopping online through platform like Taobao.com (the largest
online shopping platform operated by Alibaba), buying small luxuries such as diamond
and jewelry as well as large and clumpy items such as furniture. On November 11th of
2017, 850 million parcels were ordered and delivered during an online shopping festival,
and it cost only 2.8 days for the express delivery industry (90% whose transport methods
relies on the expressway) to deliver the first 100 million parcels thanks to the advanced
transportation system (X. Wang, 2017). The well-developed express delivery network
brings Chinese people much convenience to access to whatever they need within a short
time from every corner of the country without stepping out of their houses. Moreover, by
spreading into even the smallest village, the highway system makes it possible for people
in remote villages to bring in resources and export farm products and specialty which
helps promote the local economy.
All in all, infrastructure serves as a tool to keep the economy develop at a steady and
sustainable pace by adjusting domestic manufacturing and consumption. Besides,
infrastructure facility plays an indispensable role in creating investment opportunities for
other industries. Whenever a well-prepared new railway line, road or water treatment
plant is completed, economies grow through new employment opportunities and
increased social productivity. OECD and IMF analyses have shown that for every dollar
of investment in infrastructure, “there is a plus 1.6 multiplier in the form of a boost to
short-term employment combined with a longer-term productivity gain” ("Why
infrastructure matters," 2017).
Why Social Infrastructure Projects Experience Cost Overrun?
5
1.2. Consequences of Cost Overrun in the Infrastructure Industry
It is a widely recognized fact that basic infrastructure facilities and related services
are vital for the economic development of a country (Fazekas & Tóth, 2018). If well
developed, they stimulate economic development, yet hinder it if inadequate. Moreover,
the role of infrastructure as a stimulant of economic growth and development can only be
obtained only when its quality is guaranteed (Calderón, Moral‐Benito, & Servén, 2015).
Once certain problems occur in projects, the expected benefits will vanish but even worse
situations are likely to appear instead, as most infrastructure projects require huge
financial expenditures. Among those problems, perhaps one of the most recurrent is cost
overrun.
Cost overrun refers to the situation when the final cost of a project exceeds the
estimated budget. According to Flyvbjerg, Skamris Holm, and Buhl (2003), this
phenomenon occurs across the world including both developed and developing countries,
in all kinds of infrastructure projects including the railway, road, tunnel and highway
project, spanning a long time period from 1920 till 2000 and is expected to linger on.
Along with the boom of the infrastructure industry, cost overrun has also become the
“new normal” in infrastructure projects as reported by academic studies, media outlets
and government reports. Cost has been widely recognized as a prevailing problem
confronting the infrastructure industry worldwide1. From the Sydney Opera House to the
Hong Kong–Zhuhai–Macau Bridge, cost overrun in construction projects has become a
historic, industry-wide and global problem which is in urgent need to be fixed.
In recent years, many projects have experienced huge cost overrun. Massive cost
overrun and endless schedule delays in infrastructure projects seem to lead to serious
1 The outcome ranged from -11 to 106% (Pickrell, 1990), -59 to 183% (Odeck, 2004),-34 to 22.8% (Cantarelli,
Flybjerg, Molin, & Van Wee, 2013b; Cantarelli, Flyvbjerg, & Buhl, 2012), -69.4—to 343.8% (Love, Sing, Ika, &
Newton, 2019) this phenomenon is due, inter alia, to the geographical differences and the variation in the definition of
cost overrun which will be further illustrated later in this paper.
Why Social Infrastructure Projects Experience Cost Overrun?
6
consequences, casting a shadow on the industry. One of the most serious consequence is
the unbearable finance burden resulting from the sunk cost effect caused by cost overrun.
Unable to abandon the unfinished infrastructure facility, governments have to deal with
the remaining mess with limited budget reallocation and to face the risk of potential
difficulty in cash flow. Though part of the escalating cost will be absorbed by contractors,
particularly for those projects delivered through PPP procurement, the majority of the
additional cost will be passed on to the government, and ultimately to the taxpayers in
most cases. Such unreasonable budget allocation increases finance burden and sometimes
may lead to sacrificing other projects, thus undermining public trust in government. Take
the Ottawa City Government’s case as an example. Take the Ottawa Light Rail Transit
(LRT) project as an example. The Ottawa City Government was harshly criticized by its
citizens for a lack of guidance and management ability, after the Mayor Jim Watson
announced constantly delay of this $2.1 billion LRT project. The LRT project was
originally due on May 24th in 2018, yet it was not until September 14th in 2019, 478 days
later than the schedule handoff date, that the LRT started to roll(Foote, 2019). As
documented in a memo to the city council on June 20th, 2019, an extra cost reached 33
million (Whan, 2019b), resulted from the extended operation of buses to offset the transit
pressure caused by the delay of the project. Even after the launch of the project, new
problem surfaced. At the first week, two lines broke down for several times2, and the OC
transport found that they don’t have enough O-Trains to accommodate the commuters,
leading to sudden route cancelation and overcrowded trains. In order to conciliate public
anger, 7.5 million Canadian dollars was allocated to purchase 40 O-Trains to improve the
LRT system, which means increasing financial burdens (Curry, 2019). With the first
stage of the LRT project continuingly frustrating Ottawa citizens, the city council
2 Since September 14th in 2019, Line 1 had broken down for altogether 21 hours and 30 minutes, and Line 2 6 hours
and 45 minutes (Foote, 2019).
Why Social Infrastructure Projects Experience Cost Overrun?
7
approved to spend 4.66 billion Canadian dollars on the second stage for improvement
(Whan, 2019a)
Moreover, once governments are unable to fill this black hole of investment, they
might be forced to adjust project scope and hand out an “emasculated” project that
definitely will not perform as expected. One direct outcome is the waste of all kinds of
resources including money, labor, manufacturing materials, etc. In this case, companies
responsible for the construction usually respond by reducing essential expenditure either
by selecting cheaper material with poor quality or adopting adjusted design plan without
detailed review to deal with their immediate cash crisis. The construction plan of the
Berlin Brandenburg Airport, for instance, originally aimed to replace both the Schönefeld
and Berlin Tegel Airports and to function as a single commercial airport serving Berlin
and the surrounding states of Brandenburg. However, because of the serious cost overrun
and schedule delay, now it is only able to replace the Tegel Airport. Moreover, the
construction that started in 2006 is now deemed to continue till 2021, ten years later than
the original completion date with a budget overrun exceeding twice than the original plan
(Fabricius, 2015)
1.3. Social Infrastructure: The Missing Piece in Cost Overrun Research
Infrastructure, as classified by Hansen (1965), can be divided into two types —
economic infrastructure and social infrastructure3. The most commonly known
infrastructure are constructions including highways, railway networks and links, while
others of small scale, such as schools, hospitals, government buildings and community
centers are also dispensable parts of the infrastructure system. The former ones related to
transportation are economic infrastructure, and the latter are under the category of social
infrastructure. It should be noted that social infrastructure cannot be defined according to
3 The difference between these two kinds of infrastructure will be discussed in the literature review section.
Why Social Infrastructure Projects Experience Cost Overrun?
8
their scale or size as it includes not only small-sized facilities but also large projects like
theatres and stadiums, which plays an indispensable role in the daily life of human
beings.
Despite the frequent occurrence of cost overrun in both economic and social
infrastructure projects, most of the relevant studies mainly address economic ones
(Flyvbjerg et al., 2003; Odeck, 2004; Marion Terrill & Lucille Danks, 2016), thus leaving
social infrastructure projects little explored .
The scarcity of studies on social infrastructure projects may lead to a misperception
that it is not as important. Nevertheless, the society would not be able to function well
without the support of quality social infrastructure. Just as economic infrastructure
encourages growth, social infrastructure promotes human development. Since economic
growth and human development are interdependent and mutually reinforcing, economic
and social infrastructures should be attached equal importance. In the case of China, as
the most populous country in the world, it views social infrastructure facilities as with
irreplaceable value, and hence places a great emphasis on the development and quality of
social infrastructure. Therefore, the key for economic development is to expand the
coverage and improve the quality of infrastructure projects, from which both public
welfare and domestic economy would benefit a great deal. It can be said that Chinese
economy would not develop at the current pace without the solid foundation provided by
functional social infrastructure facilities in areas like health system, education and social
housing.
1.4. What is social infrastructure?
In China, infrastructure refers to the facilities that provide public services available to
every member of the society (China Statistical Yearbook, 2016). Quality social
infrastructure plays an essential role in facilitating social and economic activities and
Why Social Infrastructure Projects Experience Cost Overrun?
9
promoting the development of its spatial distribution. Based on the classification by
Hansen (1965)4, the Chinese National Development and Reform Commission divided
infrastructure projects into two sets — productive infrastructure and social infrastructure.
By accommodating the growing demands from the public, the efficient provision of
social infrastructure assets ensures a well-functioning society (Hansen, 1965). Social
infrastructure is the foundation and supporting structure of a nation, region, city and
neighborhood. In this case, social infrastructure should include all facilities that go
beyond basic economic functions to make a community an appealing place to live. Thus,
compared to economic infrastructure, social infrastructure is closer to everyday life
(Torrisi, 2009).
Although a few studies analyzed social infrastructure projects, the definition of social
infrastructure project remains unsettled in the academic field. One possible reason is that
the media, academics and even governments have simply assumed that the reviewers and
audience have understood the meaning of social infrastructure and that there is no
necessity to write extensively to explain social infrastructure projects.
After reviewing the websites of the public sections in charge of infrastructure
investment in several countries, we found that most countries prefer to list examples of
social infrastructure projects rather than give a formal and theoretic definition. The most
common introduction is that “the social infrastructure includes ……” which is followed
by examples such as social housing or stadium.
Therefore, this paper will try to define social infrastructure by listing differences
between social infrastructure and economic infrastructure.
Table 1 the Difference between Economic and Social Infrastructure
Differences Economic Infrastructure Social Infrastructure
4 Niles M Hansen is the first academic to propose the categories of the economic and social infrastructure project. In
his paper, he used the term “economic overhead capital” i.e. EOC and “social overhead capital” i.e. SOC.
Why Social Infrastructure Projects Experience Cost Overrun?
10
(hereafter EOC) (hereafter SOC) General purpose (Moteff & Parfomak, 2004)
EOC refers to all such elements of economic changes which serve as a foundation of economic activity.
SOC refers to the core elements of social changes which are required to provide social services.
Relationship with Economic Development (Eberts, 1990) (Torrisi, 2009)
EOC offers direct support to productive activity and accelerates the movement of economic products. EOC pushes forward the economic growth in a direct way.
SOC is designed to primarily increase social comfort and ultimately act on economic productivity. SOC promotes economic growth in a more subtle and indirect way.
Example of Classification of EOC and SOC in Italy (ISTAT, 2006)
Transportation Network road transport, railway transport, air transport, sea transport. Energy Network electricity network gas network water-system
Health Infrastructure free hospital treatment, health service, social security. Educational Infrastructure nursery, primary, school for pupils aged 11–14, secondary school, compulsory education, universities.
Example of Classification of EOC and SOC in Canada ("Investing in Social Infrastructure," 2018)
Information not found indigenous communities early education and childcare affordable housing home care cultural and recreational infrastructure
Example of Classification of EOC and SOC in China (State Council's Opinions on Strengthening Urban Infrastructure Construction, 2013)
Productive Infrastructure road, railway, airport, communication, water, electricity and gas system
Social infrastructure education, technology, health care, sports, culture
Why Social Infrastructure Projects Experience Cost Overrun?
11
Examples of Classification of EOC and SOC in China (State Council's Opinions on Strengthening Urban Infrastructure Construction, 2013)
Productive Infrastructure road, railway, airport, communication, water, electricity and gas system
Social infrastructure education, technology, health care, sports, culture
The paper shows a table retrieved from the OECD (abbreviation of the Organization
for Economic Co-operation and Development) website in the Appendix, which
demonstrates the referring purpose code sorted by section classification that can be used
to calculate the economic data of the member countries of OECD. The mission of OECD
is to “promote policies that will improve the economic and social well-being of people
around the world” ("About the OECD,"). It now has 36 developing and developed
countries in the membership including China and has published an annual economic
report of the member countries receiving great credence worldwide from the academia,
media, public and authority. Thus, the table in Appendix A serves as a credible reference
for selecting cases in the next section of data collection.
For the purpose of ensuring the healthy growth of Chinese economy, a healthy social
infrastructure industry is indispensable. This paper uses case study approach to analyze
social infrastructure projects in the context of China in an effort to identify the potential
explanations of cost overrun. By doing so, this paper hopes to improve the quality of
future construction management of social infrastructure projects and their delivery within
time and budget constraints. Only when the hidden reasons are found can the problem be
better addressed in the future. In the next section, the author will review relevant
literature on social infrastructure and cost overrun.
Why Social Infrastructure Projects Experience Cost Overrun?
12
2. Literature Review
This section will focus on four issues: definitions of cost overrun in previous
research; the way to calculate cost overrun; the definition of cost overrun and the way to
calculate it in the current study; the possible explanations of cost overrun in the existing
literature.
2.1. The Definition of Cost Overrun
The definition of cost overrun in existing literature is not as abundant as expected.
One of the definitions was given by Flyvbjerg et al. (2018):
“Cost overrun is the amount by which actual cost exceeds estimated cost, with cost
measured in the local currency, constant prices, and against a consistent baseline.
Overrun is typically measured in percent of estimated cost, with a positive value
indicating cost overrun and a negative value underrun. Size, frequency, and
distribution of cost overrun should all be measured as part of measuring cost
overrun for a certain investment type. “
Other commonly adopted definitions are quite plain and straightforward as stated by
Invernizzi, Locatelli, and Brookes (2018) -- “a cost overrun refers to the situation where
the actual cost is higher than the original estimate”. It seems that cost overrun is regarded
as a self-explanatory term.
The meaning of cost overrun can be shown clearly by the equation below:
Margin= Final Cost - Estimated Budget
If margin > 0, it means that the final cost exceeds the estimated budget, and that is
when cost overrun happens. Though the equation is clear, researchers are divided on their
views about the definition and calculation of cost overrun. Looking closer into the
equation, the debate is actually around the different interpretations of the original budget
instead of the final cost since the latter is fixed in every project. As pointed out by Love,
Why Social Infrastructure Projects Experience Cost Overrun?
13
Zhou, Edwards, Irani, and Sing (2017), the secret rests in the “point of reference from
where the cost overrun is measured”.
2.2. How to Calculate Cost Overrun?
The statistical analyses on cost overrun of infrastructure projects are well-
documented in the literature, official government publications, and the media. Research
on the frequency and scale of cost overrun in infrastructure projects varies in results.
Flyvbjerg, Holm, and Buhl (2002) reported a mean cost overrun of 20% for railway,
roads and links projects, whilst Odeck (2004) revealed a more modest mean of 7.9% in
road projects. Despite geography, size and time of the cases being studied, the divergent
findings of previous studies mainly resulted from the choice of a reference point.
The infrastructure projects tend to go through a long definition period after the
inception, during which more than one estimated budgets will be built. According to
several studies investigating cost overrun worldwide, using the estimated budget in
different stages will definitely influence the final outcome of the analysis (Cantarelli et
al., 2013b; Lind & Brunes, 2015; M Terrill & L Danks, 2016). As argued by Love et al.
(2019), defining “the initial reference point for determining a project’s cost performance”
remains a bone of contention. Otherwise, it may end up with a misleading conclusion
resulted from an inappropriate definition of cost overrun.
Though cost overrun is a global phenomenon, there is currently no internationally
acknowledged formula of calculating cost overrun (Eliasson & Fosgerau, 2013), nor a
guidance of project management similar to A guide to the project management body of
knowledge (PMBOK® Guide).5th ed. 2013). Without a unified calculation formula, the
argument about the reference point that should be used remains unsettled. In this section,
the author will discuss the most commonly used reference points and explain why.
Why Social Infrastructure Projects Experience Cost Overrun?
14
In order to better display the most commonly used reference points, this paper makes
a summary of different approaches to calculating cost overrun based on twenty-two
papers. The result is shown in the table below.
Why Social Infrastructure Projects Experience Cost Overrun?
15
Table 2 Key Studies and Their Ways of Calculating Cost Overrun
Title Sample Size &
Year
Data Resource Sample Scale Reference Point for Determination of the
Cost Overrun (Equation)
(Love, 2002) Questionnaire survey on 161 Australian construction projects
Stratified random sampling from telephone directory “yellow pages”
N/A Project Cost Growth = Contract Value on Practical Completion – Original Contract Value
Outcome & Conclusion
- The maximum cost growth is 244% and the minimum cost growth is 284%, which results in a range of 328%
(Baccarini & Love, 2013)
228 Australian water infrastructure projects
Closeout report provided by an Australian water authority
N/A Cost Overrun= Actual Final Expenditure (Including Scope Changes) – Approved Budget (Base Cost + Cost Contingency)
Outcome & Conclusion
- The final mean costs of project exceeded the approved budgets including contingency. The mean contingency
percentage addition is 8.46%.
- The mean contingency required for the final cost is 13.58% for the sampled projects. (Love, Sing, Wang, Irani, & Thwala, 2014)
Questionnaire survey on 58 Australian transportation projects
Stratified random sampling from telephone directory “yellow pages”
N/A Project Cost Growth = Contract Value on Practical Completion – Original Contract Value
Outcome & Conclusion:
- The mean cost-overrun of the 58 projects is 13.28%.
Why Social Infrastructure Projects Experience Cost Overrun?
16
(Love, Zhou, et al., 2017)
16 railway projects constructed from 2011 to 2014
one contractor in Australia
AU$3.4 to AU$353 million
Cost Overrun = Final Cost - Contract Award (Tender Price)
Outcome & Conclusion
- The total value of rail projects that had been originally awarded to the contractor was AU $539,569,997, with an M =
AU$33,723,124 and SD = AU$78,398,023, and the actual total value of work that was undertaken is AU$665,479,369,
with an increase of 19%.
- The mean cost overrun from the contract award of the 16 sampled projects is 23% (Love et al., 2019)
85 transportation projects out of more than 320 projects of varying types (e.g., civil engineering, drainage and sewerage, transport, and social infrastructure) by several public departments in Hong Kong from 1999 to 2017
Hong Kong Legislative Council
approved budget of HK$115 billion (~U$14 billion)
The paper analyzes the differences among the approved budget, pre-tender estimates, contract sum and final cost
Outcome & Conclusion
- 47% of the projects deviate from their approved budget.
- Between the approved budget and pre-tender estimate, a mean reduction of 28% in the estimated cost occurred.
- Between the pre-tender estimate and the contract sum, 36% of projects experienced a reduction in cost.
- Cost performance of the projects from the contract award to the final contract sum was found 42% were delivered on
Why Social Infrastructure Projects Experience Cost Overrun?
17
and under the contract sum. (Odeck, 2004) 620 projects
completed in the period from 1992 to 1995
Trunk road projects carried out and managed by Norwegian Public Roads Administration (NPRA). (no tendered projects included)
15 to 100 million NOK
Cost Overrun = actual costs of the project – estimated cost at the stage of design, specifications and final cost estimates.
Outcome & Conclusion
- A mean cost-overrun of 7.9% and a range of 759% to 183%. (Liu, Wehbe, & Sisovic, 2010)
52 road projects during 2000 and 2005
- Authority of Australia
- Office of the Auditor General
Total value of $2.7 billion
Cost Overrun = Actual Costs of the Project – Detailed Estimated Cost
Outcome & Conclusion
- Compared to the historical average mean of 34.7% and standard deviation of 37.8% (see Table 1), a mean of −9.71%
and SD of 14.48% of the hybrid sample represent a remarkable improvement.
(Wood, 2010) 46 infrastructure construction projects using alliance procurement deliver method in Australia
Alliancing Association of Australia
Valued over $100 million
Cost Overrun = Final Target Outturn Cost – Initial Target Outturn Cost
Why Social Infrastructure Projects Experience Cost Overrun?
18
Procured within the last five years (2005-2010) Current or completed after 2004
Outcome & Conclusion
- The average increase is of 5 – 10%.
- The agreed TOC is higher than the business case cost, estimating the average increase is of the order of 35-45%.
(Andrić, Mahamadu, Wang, Zou, & Zhong, 2019)
102 major infrastructure projects were performed covering railways, roadways and energy sectors in different regions in Asia
Asian Development Bank (ADB)
In sum, the actual costs of these projects are US$ 69592.083 million
Cost Overrun = ActualCosts − AppraisalCosts
AppraisalCosts
Actual costs are estimated after the project completion Appraisal costs are determined at the time of formal approval to begin with the construction
Outcome & Conclusion
- 56.86% of projects encounters cost overrun; 2% of projects completed on budget; and 41.18% of projects were cost
underrun of which the true payoffs on average is lower than forecasted, even if forecasts were unbiased for all projects.
- The average cost overrun is 26.24% (SD = 25.63) in projects with a cost overrun and the average cost underrun is –
12.24% (SD = 12.25) in projects with cost underrun.
Why Social Infrastructure Projects Experience Cost Overrun?
19
(Ahiaga-Dagbui & Smith, 2014a) (Ahiaga-Dagbui & Smith, 2014c)
- Data-mining cluster:
- 1600 completed projects from 2004 to 2012
- Research sample: 100 out of the 1600 cases mentioned above
Data mining £4000 to £15 million
Cost Overrun = Actual Costs of Project – Estimated Cost At Pre-Contract Stage
Outcome & Conclusion
- 92 out of the 100 validation predictions were within ±10% of the actual final cost; while 77% of the 92 were within ±5%
of actual final cost.
- Only eight out of the 100 validations had predictions beyond ±10% comparing to the final cost of the project case.
(Shehu, Endut, Akintoye, & Holt, 2014)
359 recently completed construction projects in Malaysia
N/A N/A Cost Overrun = Final Cost – Contract Sum
Outcome & Conclusion
- More than half of Malaysian construction projects (55%) suffered cost overrun and that public sector projects
performed better than private sector projects.
- Overall, the sample presented a mean overrun of 2% and among positive overrun projects the figure was 11.7%. (Koch, 2014) Seven offshore wind
farm of Danish and Swedish (operation lasted from 2001 to 2010)
N/A N/A Cost Overrun = Actual Cost – Initial Estimated Budget
Why Social Infrastructure Projects Experience Cost Overrun?
20
Outcome & Conclusion
- Three of the projects overruns the initial estimated budget.
- Two of them underrun the initial estimated budget.
- Two of them delivered to the initial estimated budget. (Al-Hazim & Salem, 2015)
25 major projects in Jordan in the period of 2000- 2008
cost at completion and that originally estimated
N/A Cost Overrun = Cost at Completion - Originally Estimated
Outcome & Conclusion
- Cost overrun between estimated and final cost ranging from 101% to 600% with an average of 214%. (Marion Terrill & Lucille Danks, 2016)
836 transport infrastructure projects planned or built in the past 15 years
Deloitte economics and Grattan Institute
valued at $20 million or more each
Cost Overrun = Final Cost – Initial Budget Estimate at First Public Cost
Outcome & Conclusion
- Overall, these projects cost $28 billion more than they planned. This is 24 percent more than the costs that were
announced.
- Only 9 percent of the projects were finished within their announced cost. (Hwang, Zhu, Wang, & Cheong, 2017)
242 traditional and 121 green building projects by 30 different companies were collected through a
government websites, reports from private institutions, and journal papers
N/A Equation 1 Project Cost Growth = ActualTotalProjectCost − InitialPredictedProjectCost
InitialPredictedProjectCost
Equation 2 Project Budget Factor =
Why Social Infrastructure Projects Experience Cost Overrun?
21
survey in Singapore
ActualTotalProjectCostInitialPredictedProjectCost + ApprovedChanges
Outcome & Conclusion
- The overall mean of green cost premiums ranged from 2.5% to 12.5%.
- Green building projects were generally over budget (4.5% to 7%). (Flyvbjerg et al., 2003)
258 transportation infrastructure projects
20 nations on five continents
- Total US $90 billion (1995 price)
- Ranged from US 1.5 million to $8.5 million
Cost Overrun = :;<<;=>C?@< − E@<BCD<EFC?@<
G@<BCD<EFC?@<
Estimated costs are defined as budgeted or forecasted construction costs determined at the time of the decision to build.
Outcome & Conclusion
- Rail projects have a mean overrun rate of 44.7%.
- Fixed links (bridge and tunnel) projects have a mean overrun rate of 33.8%.
- Road projects have a mean overrun rate of 20.4%.
(Cantarelli, Molin, van Wee, & Flyvbjerg, 2012) (Cantarelli, Flyvbjerg, et al., 2012)
- 78 Dutch projects that completed after the year of 1980 and before 2012; 806 international projects including road,
Dutch project: - interviews with former project leaders and project teams
- archives research at the Ministry of Infrastructure
Dutch project: 20 million Euros (2010 prices) each
Cost Overrun = Actual Cost at Opening Year – Estimated Cost at the Time Of Formal Decision to Build (hereafter ToD) (note that this is the engineering estimate and not the tender price) - Actual opening year: year in which operations begin.
- ToD:
Why Social Infrastructure Projects Experience Cost Overrun?
22
(Cantarelli, van Wee, Molin, & Flyvbjerg, 2012) (Cantarelli et al., 2013b)
rail, tunnel and bridge
and the Environment
- RWS2 Direction Large Projects and RWSD direction Zuid - Holland; internet search
- the MIRT (translated as the Multi-year program for infrastructure) reports
- This is one specific point in the process when a decision is made to go ahead with the project, that is, the ‘‘go-decision’’.
Outcome & Conclusion:
78 Netherlands projects:
- Cost overrun is almost as common as cost underruns, but the average overrun in value is larger than the average
underrun in value.
- Overall projects have an average overrun of 16.5%.
806 international projects:
- Rail projects have a mean overrun rate 34.1%.
- Fixed links (bridge and tunnel) projects have a mean overrun rate 30.3%.
- Road projects have a mean overrun rate 19.8%.
(Miranda Sarmento,
243 projects that were developed from 1999 to 2012
Portuguese Court of Audits and the Ministry of
N/A Cost Overrun = FinalC?@< − InitialBudgetC?@<
G@<BCD<EFC?@<
Why Social Infrastructure Projects Experience Cost Overrun?
23
Renneboog, & Policy, 2017)
Finance Internal Audit (IGF)
final cost was indicated in the audit reports and was calculated by the audit institutions, in an ex post audit
Outcome & Conclusion
- The average cost deviation is approximately 24% (Table 4), with a weighted average (based on the initial budget cost)
deviation of approximately 28%.
- If we limit the samples to projects with cost overrun, then the mean is 36%.
Why Social Infrastructure Projects Experience Cost Overrun?
24
The Table 2 above clearly shows that two reference points are the most popular
among academics—the original estimated budget around the time of decision-to-build
(hereafter ToD budget) and the latest estimation budget previous to the construction stage
when design and construction documents are in place. Accordingly, two schools of
thought emerge on the calculation method of cost overrun.
It is generally held that the budget established at the beginning will deviate more
from the final actual cost compared with the budget forecasted at later stages (Cantarelli,
Flyvbjerg, et al., 2012; Flyvbjerg et al., 2018). Based on efficient data, a clear scope and
a refined design, forecasters are able to estimate the budget based on a solid foundation.
Actually, most of the situations where cost escalation take place are during the phase
between the decision to build and early stage of construction (Ameyaw, Chan, Owusu-
Manu, & Coleman, 2015; Odeyinka et al., 2012), during which more stakeholders are
involved and the related documents are reviewed and verified by separate parties
(Invernizzi et al., 2018). Parties formed by professionals such as a construction team help
to rectify and adjust the original plan, and the budget might fluctuate during the check-
and-balance process and will stabilize at a level which reflects the real core of the
projects, after a period of time.
The Big Dig project in Boston is a perfect example to illustrate how unknown
brownfield condition will adversely change the development process of an infrastructure
project. The construction of Big Dig began in 1991 and finally concluded on December
31st, 2007, five years later than the scheduled completion date. The project was originally
expected to complete at $2.6 billion (which was $5.8 billion in 2007 if taking inflation
into account). Yet, the total expenses eventually surpassed $15 billion, and reached a total
figure of $21.93 billion with interest counted. The cost overrun figure reached a
whopping 300%. The project was then hindered by the incident of continual leak in the
tunnel dating back to 2001, which threatened the safety of the drivers and passengers.
Why Social Infrastructure Projects Experience Cost Overrun?
25
Thousands of leaking points from the ceiling and wall fissures damaged the steel supports
and fireproofing systems and overloaded the drainage systems.
2.2.1. Estimated Budget at ToD Stage.
Researchers in favor of ToD budget hold the view that this figure should be
developed when decision makers choose to start a particular project. As stated by
Flyvbjerg et al. (2018), the goal is to “understand whether decision makers make well-
informed decisions” and to “know whether the cost estimate on the basis of which
decision makers decide to go ahead with a project is accurate”. If public sectors have no
idea about the cost performance and benefit ratio of a project when allocating the fiscal
funds, they won’t be able to make any decision that guarantees value for money (VfM)
but rather those causing lingering burdens to taxpayers and constituents. In reality,
however, the incumbent governments in most cases decide to start infrastructure projects
before a detailed cost-benefit study is completed or even launched (Marion Terrill &
Lucille Danks, 2016). Moreover, politicians who are eager to seek for re-election
repeatedly choose to launch a great deal of infrastructure projects with made to look good
cost-benefit ratio, so as to gain support from constituents (Miranda Sarmento &
Renneboog, 2017; Marion Terrill & Lucille Danks, 2016). According to Flyvbjerg, this
political trick appears as the main cause of incurring strategic misrepresentation leading
to cost overrun in public sectors around the world, which the author will discuss in details
in the causation section.
2.2.2. Estimated Budget Before the Construction Stage
Other researchers prefer to input the contract value or the latest estimating budget
into the calculation formula of cost overrun right before the construction. They regard it
as absurd to ask a forecaster to present a precise figure since the project at the current
stage is still subject to adjustment with a lack of detailed design documents, a full
investigation of brownfield structure and a definite project scope (Adafin, Rotimi, &
Why Social Infrastructure Projects Experience Cost Overrun?
26
Wilkinson, 2015; Hegazy, 2002). The more the data are gathered gradually at later stages,
the clearer the scope will be defined and the better the related parties will integrate. Until
then, the forecaster is incapable of conducting a valid forecast, and thus the budget would
become increasingly closer to the actual cost in the future (Love, Ahiaga-Dagbui, & Irani,
2016). Only when the estimated budget goes through rigorous risk assessment can the
whole picture of the projects be grasped, including the labor and material market price,
brownfield structure and condition, the promising future benefit, and the list goes on. The
process of a slowly- and gradually-developed budget estimation is demonstrated in
Figure 1 as below.
Figure 1 the Relationship between Budget Evolution and Stakeholders
Scholars from the latter school do not just discard the initial cost estimation at the
early stage. Instead, they come up with a specific term – cost growth – to describe the
difference between the initial cost estimation and the estimated budget forecasted around
the time when the construction began. This term is used to separate the cost increase in
this period from the real cost overrun (Ahiaga-Dagbui & Smith, 2014c). The relation
between budget at different phases and the two terms are showed as in Figure 2.
In order to better set apart cost growth and cost overrun, scholars appeal to
contingency which can offset the increase in cost provoked by scope change, flaws or
omissions in design documents or unexpected incidence during the construction (De
Why Social Infrastructure Projects Experience Cost Overrun?
27
Marco, Rafele, & Thaheem, 2015; Love, 2002). Rather than a fixed figure, budgets
should be more flexible, so that the project will be more resilient to unexpected or
uncontrolled events.
Figure 2 Cost Escalation and Cost Overrun
In the study conducted by Marion Terrill and Lucille Danks (2016), every step in the
entire life-cycle of the infrastructure projects has been examined and analyzed. Cost
overrun in this study has been defined as “…the amount by which the actual cost at the
end of a particular phase exceeded the estimated cost at the start of that phase, expressed
as a percentage of each project’s first cost”. The incumbent government announces to
conduct infrastructure projects before a detailed cost-benefit study is completed. The
similar process of examining cost overrun by adopting more than one reference points is
practiced by other scholars as well. (Cantarelli, Molin, et al., 2012; Love et al., 2019).
2.3. Cost Overrun Calculation Method Adopted by the Current Study
In this paper, cost overrun calculation relies on the specific budget estimation process
in Chinese infrastructure industry. The budget estimation of social infrastructure in China
consists of several stages. The next section will illustrate the budget estimation procedure
in China and compare it with the reference point mentioned in the literature above.
Why Social Infrastructure Projects Experience Cost Overrun?
28
2.3.1. The Budget Estimation Procedure in China.
The budget estimation procedure involves five stages. In each stage, the government,
assisted by professional agencies, will confirm an estimating budget figure based on
available and existing information (Wang, 2006). Depending on the project information
provided, the accuracy of the budget estimation figures varies from stage to stage. Figure
3 below illustrated the sequence of five stages supported by information and documents
(Wan, 2007). The Capital Budgeting Group (1984) sets up rules and regulations to
narrow down the estimation budget. In other words, the estimated budget should
normally be smaller than that of the previous stage. If there is an increase in budget, the
promoters need to file a report to explain it, which the government authority should
review to decide whether or not to approve it (Capital Budgeting Group, 1984). Next, this
paper will provide with a detailed illustation by using the estimation procedure of Theatre
A with 1500 seats as an example.
Figure 3 the Budget Estimation Process in China
Take the example of the project to build Theatre A. At the first stage, the estimation
is based on the project proposal and experience from previous constructing projects with
similar features (capacity, scale, function, etc.). The project promoters only have a vague
Why Social Infrastructure Projects Experience Cost Overrun?
29
vision of Theatre A at this stage. Questions such as how many seats are there in the
theatre or what kind or level of activities this theatre can hold will be considered for
selecting reference projects. Next, forecasters responsible for the estimation will review
some as-built theatre projects with identical capacity (for example1500 seats) to Theatre
A. Forecasters will calculate the average figure of the final cost from projects that are
chosen as reference group, and take it as a key reference of the estimating budget of
Theatre A at the current stage. Once the project proposal is approved by the government
authority, the architecture design company will be involved (Wan, 2007).
It the second stage, the most important basis of the estimation will be the effect of the
drawing of the architecture provided by the design company. The style, shape and
construction materials of the architecture have a considerable impact on the estimation. If
the government authority chooses the design plan with great constructing difficulty for
Theatre A, the budget estimation might need to be adjusted to accommodate difficulties.
The construction of the Sydney Opera House is a typical example which encounters
severe obstables due to unexpected construction difficulties. The astonishing cost
escalation of the project is mainly due to the extraordinary and modern appearance of the
theatre. When the Sydney municipal government chose this design out of numerous
competitors, they did not foresee the nightmare brought about by the complex building
structure during the construction period. The distinct construction features of the theatre
will cause extra construction fees, so the estimating budget is higher than the average cost
of the as-built reference projects (Wild, 2015). For Theatre A, the government authority
prefers the design plan with a long span and a beamless structure which will definitely
create a new landmark for the city. Because this design requires a longer construction
period, larger labor investment and advanced construction techniques, the budget grows
accordingly (Dong, 2009).
Why Social Infrastructure Projects Experience Cost Overrun?
30
Even though the preliminary design has provided many clues about the vision of
Theatre A, a concrete analysis is hardly available due to the lack of detailed documents in
this estimation stage. In that case, the estimating budget is still not valid and tenable
enough. Later the government authority begins to spend money to hire the design
company, suggesting that it has officially decided to construct Theatre A. Also, as stated
by Miranda Sarmento and Renneboog (2017), sometimes, government authority, due to
political reasons, will publicize the message of the project construction at this stage. Such
stage can be taken as the ToD timing that is frequently used as a reference point for
calculating cost overrun in studies of psycho theorists.
At the third and fourth stages, the architecture design company begins to optimize
the design by improving details such as the supporting structure and landscape design on
the basis of partial filed exploration and other available data. The design company will
present the precise design drawings and plans covering different aspects including the
requirements for labor, the type, quantity and quality of construction materials and the
construction workload of forecasters (Darwish, 2005). During these two stages,
estimation is built upon reliable and concrete information to make sure that the estimated
budget will be closer to reality compared with that estimated at the previous stage. It
should be noted that additional documents, design details and site exploration might help
to make the estimating budget more reliable, while, more often than not, also increases it
for a clearer understanding of the difficulties in the complicated construction work or
unexpected site geographical structure (Jarkas, 2014).
In the architecture design industry, the architecture design department is only
responsible for the design of building appearance and indoor space, whose work of the
building effect drawing is normally finished at the second stage. The data, documents and
blueprints crucial at the third and fourth stages are prepared by the engineering
Why Social Infrastructure Projects Experience Cost Overrun?
31
department. The division of work, as a result, resulted in unexpected cost growth during
this period since more information is added up to the file.
Different from the four stages discussed above, the estimated figure at the fifth stage
is not on the basis of forecasts, but is instead confirmed in the bidding, during which the
government authority invites several construction companies to compete for the contract
(Capital Budgeting Group, 1984). Normally, the criterion, simple and straightforward, is
that the company with the lowest tender price wins. Consequently, the contract price is,
in most cases, lower than the estimated budget.
The practice during the fouth stage and the contract value are mostly adopted by
evolutional theorists when calculating cost overrun.
2.3.2. The Conceptual Budget Overrun and Cost Overrun
The most distinguishing feature of Chinese estimation procedure from other
countries’ methods is its emphasis on the conceptual budget. The Chinese government
puts more emphasis on the conceptual budget than on the cost overrun (calculated using
the final cost at the end of project lifecycle) (Capital Budgeting Group, 1984). The
conceptual budget is the figure that is calculated at the fourth stage before heading to the
bidding process. It is normally regarded as the figure reflecting the reality, as forecasters
have gathered sufficient information about the project, which enables them to bring up a
precise estimation. Still, overrun happens.
Conceptual budget overrun occured when the original conceptual budget needs to be
adjusted due to specific reasons. According to several post-access reports and audit
reports, it is found that cost overrun (i.e. final cost is lower than the approved conceptual
budget) seldom take palce in social infrastructure projects, even though their final cost
does exceed the original conceptual budget. The reason behind this paradox is the
adjustment mechanism of the conceptual budget. Once the project manager detects the
possibility of cost overrun, they will file a report to the government authority, asking to
Why Social Infrastructure Projects Experience Cost Overrun?
32
raise the conceptual budget (Dong, 2009). Thereofore, the adjustment mechanism leaves
a flexible space for the project manager to keep the project completed within or even
under the ultimate budget. During the project lifecycle, the conceptual budget can be
adjusted for many times till it can fully cover the final cost. In some cases, the
“estimated” conceptual budget can be adjusted even when the construction is completed.
Though social infrastructure projects hardly experienced “cost overrun” in China,
these projects did bring about severe financial burdens to the government and the society.
In other words, taxpayers pay more money than they were originally promised (by the
government/politician) for a certain project. Frequent budget adjustments may reflect that
the government did not think it through when making the decision to launch a certain
project instead of other options. These “on budget” or even “under budget” projects seem
to be harmless, nevertheless, they are the possible causes of terrible social and economic
problems in the Chinese infrastructure industy (Liao, Lei, Fang, & Liu, 2014).
Actually, the Chinese government has also realized the problems behind this
adjustment mechanism (Wang, 2006). The adjustment should follow stirct procedures
and the project manager needs to provide convincing explanation for approval (Capital
Budgeting Group, 1984). The conceptual budget adjustment mechanism cannot be
regarded as the way to conceal or “avoid” cost overrun, as it is a simple part in the
estimation procedure of the Chinese infrastructure industry. In the as-built appraisal
documents such as the post-access reports and the audit reports, the Chinese government
discusses and analyzes the conceptual budget overrun specifically.
The conceptual budget overrun, though terminologically different, shares the similar
characteritics with cost overrun and causes similar problems to the economy and society.
In this paper, cost overrun and conceptual budget overrun will both be discussed and
hopefullty with the analysis in the following case study it can be figured out the overrun
problems in the Chinese social infrastructure industry.
Why Social Infrastructure Projects Experience Cost Overrun?
33
Figure 4 Conceptual Budget Overrun
The notion of conceptual budget overrun is interesting for three reasons: (1) Cost
escalation often occurs along the project lifecycle due to reasons like rework, scope
change, material change, the increase of labor expense and so on; (2) Thus it requires
government to allocate more resources in order to accomplish the project as planned; and
(3) It does have social consequences such as worry and accusation from media and
taxpayers. In so doing, one can take into account the cost increase/escalation due to
conceptual budget overrun which hence reflects the budget problem before the project
closure, and thus leaves room to make some adaptations on the estimated budget so that
the funding problem can be addressed during the project lifecycle (Wan, 2007).
Why Social Infrastructure Projects Experience Cost Overrun?
34
Figure 5 Conceptual Budget Overrun and Cost Overrun according to Chinese Regulation
2.3.3. Cost Overrun Definition and Calculation Method in This Thesis
In this paper, cost overrun is defined as
the amount by which actual cost exceeds the most original conceptual budget that
has been approved by the government, with cost measured in the local currency,
constant prices, and against a consistent baseline.
In this paper, the original conceptual budget is used in calculatiing the cost overrun
considering two aspects. First, the original conceptual budget is proposed at the forth
stage when, in theroy, the project has been carefully designed and the feasiblity study has
been completed, based on which the estimation of the original conceptual budget should
be accurate, namely, to cover the actual cost. However, in most cases, it did not work this
way. Second, if the cost overrun is calculated by using the actual cost to minus the final
(adjusted) conceptual budget rather than the original conceptual budget, as has been
metioned in the last section, the outcome will be negative (which means there is no
overrun)in most social infrastructure projects in China.
Based on this definition, the data concerning estimated budget at the second and the
fourth stages are accumulated together with the final cost. These two stages are the most
common reference points adopted by psycho and evolution theorists respectively. Hence,
Why Social Infrastructure Projects Experience Cost Overrun?
35
a better understanding of the debate between the two schools may be obtained by
comparing the results (final cost minus estimated budget at the second stage versus final
cost minus estimated budget at the fourth stage ). As for the conceptual budget developed
at the fourth stage, the author will review every report that mentioned a conceptual buget,
compare the figures in each report and draw out the adjustment process of the figure.
With the use of final cost minus the most original conceptual budget figure, cost voerrun
will be precisely calculated. Once the final cost is higher than the original conceptual
budget figure (i.e. the conceptual budget is adjusted and get approved by the government
at the very first time), the project is considered to be a case of cost overrun, even though
the final conceptual budget figure covers the final cost after the adjustment.
2.3.4. Calculation Formula
Cost overrun is usually calculated in two ways, namely in absolute and relative terms
(Flyvbjerg et al., 2018). In this paper, both absolute term and comparative terms will be
presented. The absolute term will show the exact amount of money the project incurs on
the taxpayer while the comparative term will elaborate on the evaluation of the
percentage of loss resulting from the overrun on the project.
The formula of cost overrun calculation in this paper is as follows:
Absolute term:
COAcon = Final Cost – Original Conceptual Budget (budget at the fourth stage)
The project experiences cost overrun when COAcon > 0 (using the original
conceptual budget)
(Comparative group: COApre = Final Cost – Preliminary Budget (budget at the
second stage))
Comparative term
COCcon = !"#$%&
!%&$'()*+,.*/0')
Why Social Infrastructure Projects Experience Cost Overrun?
36
The project experiences cost overrun when COCcon > 1 (using the original
conceptual budget)
(Comparative group: COCpre = !"#(1'
21',343&+15.*/0'))
By comparing these figures, the author intends to, first, understand the difference
between the psycho and evolution theorists, and second, to understand cost overrun in the
context of Chinese social infrastructure projects.
2.4. What Are the Causes of Cost Overrun?
According to previous research, causes of cost overrun include technical difficulties,
psychological factors (optimistic bias and strategic misrepresentation), managerial
incompetence and so on. Generally, the obligations of a project team consist of social
responsibility, consulting and coordinating companies, contractors, construction teams
and operations and management team as well as their clients (taxpayer). It is usually
expected to deliver the project within an acceptable and pre-agreed budget and time
constraints. However, the truth is that cost overrun in infrastructure projects is becoming
entrenched in work practice (Love, 2011). In this section, this paper will review the
current theories about the reasons that lead to cost overrun in infrastructure projects.
The existing studies about the causation of cost overrun can be divided into two
types. The first type is simple factor correlation analysis, such as research conducted by
Devi and Ananthanarayanan (2017), Mansfield, Ugwu, and Doran (1994), Rosenfeld
(2013), Ubani, Okorocha, and Emeribe (2013) and so on and so forth. Take the study
conducted by Shehu et al. (2014) as an example. The authors distributed questionnaires
which were designed on the basis of the “specific features of the projects that were
identified from the literature as having potential bearing on cost variance” to the “entire
of quantity-surveying consultants in Malaysia” (p…). The data of this study were from
359 projects, mainly in infrastructure, educational and residential field. It analyzed the
Why Social Infrastructure Projects Experience Cost Overrun?
37
data and concluded the impact of a typical feature on the cost variance using correlation
analysis method. According to this paper, project characteristics including the size, tender
method and procurement method significantly affects the cost performance. There are
overt relationships among cost overrun and these characteristics.
However, as pointed out by Ahiaga-Dagbui, Love, Smith, and Ackermann (2017),
correlation is merely a “causal link depending greatly on the particular circumstances
involved” (p…), thus it cannot serve as causation itself. For example, in the study on the
Malaysia project described above, the project with a bigger size tends to be more likely to
experience cost overrun, yet we cannot take it for granted that project size is the reason
why projects perform differently. Size is indeed an influential feature here, but not the
roots. Taking all these into consideration, factor correlation analysis is thus beyond the
purpose of this paper. Instead, the second type concentrating on identifying the essential
causes of cost overrun will be adopted in this paper. The existing theories on the key
explanations of cost overrun fall into three categories, namely the evolutionist theory,
psychological theory and mechanism flaw theory.
2.4.1. Psycho Theory
The psychological theory is mainly explained by three concepts: planning fallacy,
optimistic bias, and strategic misrepresentation. Researchers who support this theory
unequivocally insist that causes of cost overrun rest in the human mind rather than the
objective world.
Your biggest risk is you (Flyvbjerg et al., 2018).
Optimistic bias occurs when promoters are overly optimistic about the prospect of
the project and understate the potential risks in the appraisal phase of the project so that
they underestimate the budget while at the same time overestimate the profit
unconsciously. This psychological mechanism involved in optimistic bias, as noted by
Flyvbjerg et al. (2003), is self-deception. Deception is another mechanism involved, this
Why Social Infrastructure Projects Experience Cost Overrun?
38
time when promoters engage in strategic misrepresentation or deliberately “cook” the
report, lower the budget and make the project plan seem perfect in the report in order to
have the projects approved and started. In either circumstance, project promoters
underestimate the budget whether intentionally or not, ending up with exceeding the
actual cost and thus causing cost overrun. In fact, Flyvbjerg, as the most prominent
author in this school, noted in his latest research (Flyvbjerg et al., 2018), “overrun is a
consequence of underestimation” (p…). In other words, it is underestimation incurred by
self-deception or delusion that leads to the subsequent cost overrun.
Human beings firmly regard themselves as rational creature, however, as revealed by
behavioral science (Gilovich, Griffin, & Kahneman, 2002; Kahneman & Egan, 2011;
Tversky & Kahneman, 1974), humans are prone to being unconsciously and overly
optimistic about the future especially towards the one they in favor of. They tend to
overestimate the future of their own lives and underestimate the possibility of
encountering difficulties such as divorce, unemployment and disease. Likewise, project
promoters are usually too optimistic about their own projects to make appropriate
judgements of the contingency and adversity, and meanwhile they are likely to
exaggerate the feasibility and profit. Optimistic bias, derived from cognitive biases
(Flyvbjerg et al., 2002), has long been an influential factor in the project management
area.
Unlike optimistic bias which is a subconsciously unintended error, strategic
misrepresentation should be taken as purposeful delusion by promoters. Even though
Flyvbjerg (2007b) claims that strategic misrepresentation and optimistic bias are both
noteworthy, he has his own preference between the two. He regarded strategic
misrepresentation as the best answer for the ubiquitous and ingrained problem of cost
underestimation (B. Flyvbjerg, 2009).
Why Social Infrastructure Projects Experience Cost Overrun?
39
Wachs (1989) is the first scholar to put forward the concept of strategic
misrepresentation to justify cost overrun, which later helps shift the focus to behavioral
science in the infrastructure project management field. Wachs (1989) describes the
dilemma confronted by every project forecaster due to their complex and conflicting roles
in the estimation process: both as a scientist and an advocator. As a scientist, they are
supposed to estimate the budget on the basis of valid data, and then provide the clients,
who are normally a part of the public sections in the infrastructure circumstance, with
“independent professional judgment” (p.476). Professional judgement with scientific
accreditation encourages them to make the most reasonable and profitable choice.
However, in reality, as revealed by (Wachs, 1989), many forecasters regard themselves as
advocates instead of scientific observers of the project. Actually, “these two roles
inherently conflict with one another”(p.476). If forecasters identify themselves as
advocates, they will care more about the approval of the project. Needless to say, this
perception affects their judgment and ultimately leads to a deliberate adjustment of the
data and analysis in order to show that the client-preferred option is the best choice. They
will take several manipulating methods to cook the estimation so as to please their
clients. With the help of the “perfect” cost-benefit ratio figure on paper, the project seems
to overweigh other projects. The project forecaster helps their client “win the battle”.
Strategic misrepresentation is normally associated with economic interest, be that of
the individual or the public (Flyvbjerg et al., 2002).Politicians, for instance, invest in
infrastructure projects mainly for reputation and political interest . This may explain why
many correlation factor analyses all reveal a close link between high overrun rate and the
projects initiated at election years. Noteworthy, politicians not only fight for their own
reputation but also for the local constituents. Pickrell (1990, 1992) argued that the limited
fiscal fund from central government left the local government no other choice but to
compete with each other for resources and capital. Faced with limited fund, cities resort
Why Social Infrastructure Projects Experience Cost Overrun?
40
to image projects—with “some make-up” on their proposed projects , which turns out to
be the ones allocated with investment from central governments (Flyvbjerg, 2009).
Generally, psychological theorists persist that optimistic bias and strategic
misrepresentation are sufficient to explain the primary causes of cost overrun. But they
are not the sole causes of cost overruns. The other causes include scope changes,
complexity and uncertainty and they are the ones that evolution theorists support.
2.4.2. Evolutional Theory
According to evolutional theorists, represented by Love, Edwards, and Irani (2012)
and Gil and Lundrigan (2012), projects are usually adjusted for several times at different
stages from the beginning to the completion, during which cost overrun is likely to
emerge for various reasons. The most prevalent adjustment is the changes in scope,
rework and unexpected uncertainties.
As proposed by evolution theorists, the project scope will be adapted for several
times during the whole process and ultimately lead to cost overrun (Odeyinka et al.,
2012). Sometimes scope changes should be responsible for nearly 90% of cases of cost
overrun5 (Auditor General of Western Australia, 2012). Actually, as reiterated by Love
and Ahiaga-Dagbui (2018), it is hard and even unrealistic to develop a precise project
scope at the initial stage that requires no amendment later. For most of the infrastructure
projects, especially those procured through methods like Traditional Lump Sum that
assign the design and construction work to two different parties, it is common to begin
with tender directly without completed or precise design documents (Love et al., 2012).
According to evolutional theorists, as more information is gathered through processes
like field investigations and coordination of different stakeholders, the project scope will
become more accurate and the design documents more detailed.
5 Here, the cost overrun definition is the difference between actual final cost and the initial estimated budget (the ToD
budget mentioned above).
Why Social Infrastructure Projects Experience Cost Overrun?
41
Notably, at the preliminary stage when the project is merely conceptual, the
government is likely to inform the public in advance that an infrastructure project will be
launched, thought in most cases without a precise description of the project including
budget, scope and benefits (Love et al., 2019; Marion Terrill & Lucille Danks, 2016).
The planning consultant hired by the public sector, on the one hand, is provided with
little information to conduct appropriate due diligence. More often than not, the public
sector will put pressure on their consultant who, as a result, has no choice other than
knowingly make up the budget. Therefore, “ ‘uncertainty’ prevails and ‘guesstimating’
occurs ” (Sing, Love, & Tam, 2011, 2012). According to the existing practice and project
process, it is obvious that the project scope developed this way is hardly feasible in
reality and will inevitably need adjustment in the future. Governments and the consultant
companies are all aware of the inaccurate and arbitrary estimation of the project scope in
the preliminary stage, and are prepared for the upcoming adjustment. However, taxpayers
are not. The media tend to omit the complicated and gradual evolving progress, and just
report the initial stage and the completion stage of a construction. This tendency and its
underlying two figures (initial budget and completion cost) prevaricates taxpayers’
understanding as they regard the decision of preparation and planning for an
infrastructure project as a mere snap of fingers. A huge gap then appears between reality
and reports created by the press, leaving people with an impression that the public sector
is constantly changing their mind. At last, with stories of endless cost overrun of
infrastructure projects all over the press, taxpayers feel disillusioned with the “perpetual
inability” of the public sector to deliver infrastructure projects within budget and on time.
Changes in scope sometimes cause the second incidence — rework, which refers to
“doing something at least one extra time due to nonconformance to requirements”, as
defined by Australia (1995). Love (2002) already revealed that rework contributes to
52% of the project’s cost growth. In addition to changes in scope estimation, rework also
Why Social Infrastructure Projects Experience Cost Overrun?
42
stems from errors, omissions, damages and incidence of “black swan” (Peter ED Love &
Hui Li, 2000; Love, Mandal, & Li, 1999). Infrastructure projects normally involve
stakeholders from various fields. Although they all want to complete the project
efficiently, there are inevitable obstacles preventing them from cooperating smoothly6.
Errors and omissions, as a result of inadequate information and inefficient
communication among stakeholders (such as between design and construction teams)
need to be remedied by rework, which finally leads to frequent cases of cost overrun
(Bordat, McCullouch, & Sinha, 2004). Coordination can to some extent be improved, but
“black swan” is something that is out of control. “Black swan” comes as a surprise and
has a tremendous effect on the cost performance of the infrastructure project. force
majeure including but not limited to severe weather, labor strike and construction site
fatality are all potential unpredictable events that might deteriorate cost escalation.
Some “black swan” incidences might not need to be fixed by restarting the whole
project, but the public sector is forced to add more capital and resources into the project.
After an extremely long period of preparation and planning, the initial estimated budget is
no longer realistic. Looking into the example of the Honolulu Rapid Transit project, one
can find that the project was originally budgeted $5.2 billion ($1.8 billion in federal
funding and $3.4 billion in taxation) in 2012, yet the forecasted completion cost turned
out to increase by 83% to $9.5 billion at the end of 2016 after construction
commenced(Hrushka, 2017). As examined by Love, Zhou, et al. (2017), the Honolulu
Rapid Transit Project suffered cost overrun mainly because the construction industry in
Hawaii witnessed dramatic changes during the long period of preparation for this project.
Thus, an unforeseen gap emerged between the original budget established in the midst of
a recession and the contractual value during the “construction boom”. The original
6 The unsatisfied cooperation might result from the unwillingness of collaborations from at least one party or
geography and/or time constraint.
Why Social Infrastructure Projects Experience Cost Overrun?
43
budget was unable to reflect the actual market condition later. A similar case is the Forest
Highway Project in Australia with an original estimated budget set at AU$136 million. At
the end of 2007, the cost rose by 406% at AU$ 631 billion due to the skyrocketing price
of local materials, labor and equipment owing to the insatiable export of raw material
including minerals, oil and gas to countries such as China, India and Korea (Love et al.,
2019).
Besides unpredictable events, unexpected construction difficulties on brownfield site
are another type of the uncertainties encountered by infrastructure projects. According to
Love et al. (2019), a pedestrian bridge constructed in a high-density downtown district in
Hong Kong ends up being accomplished at HK$113.20 million, with 122.4% of overrun
than the initial budget. The major trigger is the unpredicted constructing difficulties
caused by the complicated traffic management, which leads to the schedule delay.
Evolution theorists take infrastructure projects as a gradually developing and shaping
progress, arguing that those changes (sometimes improvements) along this procedure are
the elemental causes of cost overrun (Love & Ahiaga-Dagbui, 2018). Love (2011)
criticized Flyvbjerg and his colleagues of putting all eggs into one basket (strategic
misrepresentation and optimistic bias) and disregarding the fact that projects progresses
in a convoluted and changeable way. Moreover, Love (2011) further put forward a
“Pathogen” theory, claiming that the fundamental cause of cost overrun is a series of
pathogenic influences embedded in the project for a long period of time without being
recognized. Pathogenic influence is defined as a succession of “routine” decisions and
practices along the life-cycle of the project, before the “pathogens” get stimulated by a
specific event7. It can lay dormant within the project system and be treated as an “innate”
component of everyday work practices (Love et al., 2016). However, as these
7 For example strategic decisions conducted by senior decision-makers or project management.
Why Social Infrastructure Projects Experience Cost Overrun?
44
“pathogens” are intertwined in a very intricate way in the system, the outcome will be
devastating once it is activated.
2.4.3. Mechanism Flaw
This paper has no intention to further discuss about the deficiencies in risk
assessment or budget estimation. As pointed out by Flyvbjerg (2007b, 2014); Flyvbjerg,
Hon, and Fok (2017), a great effort has been made to improve the assessment and
estimating approaches such as the Reference Class Forecasting and they have been
proved to be effective8 in improving the accuracy of forecasting. In this section,
mechanism flaw is defined as unavoidable flaws embedded in the estimation and
procurement mechanism, such as selection bias and tendering system. Mechanism flaw is
different from psychological and evolutional problems discussed above, as mechanism
flaw is not from the outside environment but from the inherent shortcomings that result
from regulations or operation process through the project lifecycle(Eliasson & Fosgerau,
2013). These mechanism flaws are a stimulus of psychological and evolutional problems.
When mechanism flaws, psychological factors and evolution factors occur together, cost
overrun happens subsequently.
Researchers like Flyvbjerg and Love claim that the sample they used in their study is
randomly selected from a bigger population. However, a crucial fact should be noted that
the population itself has already been selected. Selective bias exists when the selection
process is influenced by a noisy prediction (Heckman, 1979). For example, the patients
recruited in the study for a particular disease will be more curious about the certain
disease or have higher expectation over the drug associated to the study, compared with
the other patients. This tendency will unconsciously affect the outcome of the study.
8 According to Flyvbjerg (2008), The RCF has had success in making impressive improvement in the cost
performance in mega transportation infrastructure project worth 15 billion pounds in the UK.
Why Social Infrastructure Projects Experience Cost Overrun?
45
Similarly, in studies about cost overrun, the projects catching the attention of the public
typically survived the strict selection process. The projects that survived are more
favorable than their competitors (other projects in the pipeline) with “appealing and
promising” benefit-cost ratio. As a result, they are more likely to be chosen by the
decision maker (Eliasson & Fosgerau, 2013). Since the projects that are finally launched
and accomplished all possess in principle a “perfect” benefit-cost ratio to win the battle,
they are more likely to fail to live up the expectation and encounter cost overrun. In other
words, a high benefit-cost ratio is the key determinant to choose a certain project.
Therefore, project promoters have the tendency to “calculate” a benefit-cost ratio that is
high enough to make the project approved. However, this “perfect” benefit-cost ratio is
hardly feasible, and the project selected in accord with this ratio is deemed to overrun its
budget along with the underperformed return. In this case, selection bias might be able to
explain the high frequency of cost overrun observed in the “randomly selected” sample.
The other mechanism flaw exists in the tender rule that is commonly adopted by
governments worldwide, namely the lowest bidding price wins the contract. However, as
demonstrated in numerous cases, the contractor who offers the lowest price is not the one
who can provide the best VfM (Love, 2011). If the contractor constantly fails to keep the
promise to complete the project in accord with contractual price, public sectors have to
dole out more funds, leading to cost overrun (Shehu et al., 2014). In the study conducted
by Flyvbjerg, Skamris Holm, and Buhl (2004), a positive correlation is claimed to exist
between contract value and cost overrun.
Why Social Infrastructure Projects Experience Cost Overrun?
46
Table 3 Summary of Three Theories and Key Authors
Theorist Theory Major Scholar
Evolutional Theorist
§ Scope Change (Love, Edwards, & Smith, 2005)
§ Change of Orders (Love, Irani, Smith, Regan, & Liu, 2017)
§ Rework (Love, 2002)
Peter ED Love Dominic Doe Ahiaga-Dagbui James Odeck Jim Smith Zahir Irani
Premature Announcement/political factors (Marion Terrill & Lucille Danks, 2016)/(Miranda Sarmento & Renneboog, 2017)
Marion Terrill
Psycho Theorist
Optimistic Bias/Planning Fallacy (Flyvbjerg, 2007b)
Bent Flyvbjerg Bert van Wee Chantal Cantarelli
Strategic Misrepresentation (Wachs, 1989)
Martin Wachs Bent Flyvbjerg
Other Theorist
Selection Bias (Eliasson & Fosgerau, 2013)
N/A * These theories have been mentioned by many scholar as supplementary points, but there is very few study taken them as the main topic. Thus, it is hard to conclude the major scholar of each theory.
Coordination (Minato, 2003)
Risk Management (Ökmen & Öztaş, 2010) Low Price Bidding (Shehu et al., 2014)
2.4.4. The Potential Solutions to Cost Overrun.
With a focus on the causation of cost overrun, in this section, the current research
aims to review the main ways in which cost overrun is addressed.
Admittedly, it has been verified that the Reference Class Forecast9 exerts a positive
impact on the certainty of estimated budget (Baccarini & Love, 2013; Flyvbjerg et al.,
9 A forecasting method that is adopted by governments worldwide. RCF method makes budget estimation based on
previous as-built projects that possessed features alike the project being estimated.
Why Social Infrastructure Projects Experience Cost Overrun?
47
2017). However, this approach is not the panacea10. Because of the unique characteristics
(for example, history, culture, geography and market) of different cities, there is a
limitation using the as-built documents or experience from the other projects to establish
an accurate budget for a certain project (Love, Zhou, et al., 2017). At the same time, it is
hard to find enough references that share similar features with a particular project, so it
seems difficult to draw a conclusion or come up with suggestions using a reference
consisting of only one or two cases. Railway projects, for example, resemble each other
at the planning stage as many vital components are standardized according to Council
(2012). In this case, the price and supply chain are in place and are controlled properly.
Nevertheless, at the construction phase, problems tend to surface, with unexpected
incidence in the brownfield site and complex and time-consuming coordination of several
parties including the public, contractors, sub-contractors, field workers, worker unions
and suppliers.
The concepts of strategic misrepresentation and optimistic bias, developed from
Flyvbjerg’s black and white theory which holds that cost overrun results from the two
aforementioned concepts (Love, Ahiaga-Dagbui, Welde, & Odeck, 2017), are commonly
used terms in social media, and taxpayers are quite familiar with these two terms. Some
of them firmly believe that the combination of strategic misrepresentation and optimistic
bias is the one and only cause for cost overrun. In order to regain the faith from the
public, governments place great emphasis on the two issues and spend enormous
resources and energy to address these two problems, which might lead to their negligence
of other factors such as change-orders that also affect the final cost and that are worth
equal attention (Love & Ahiaga-Dagbui, 2018).
10 Criticism of RCF approach can be found in studies conducted by Liu et al. (2010), Liu and Napier (2010), and Love
and Ahiaga-Dagbui (2018).
Why Social Infrastructure Projects Experience Cost Overrun?
48
While admitting the problem brought by strategic misrepresentation and optimistic
bias, Love insists that literature and government should move beyond these two concepts.
As mentioned earlier, the strategic misrepresentation and optimistic bias are not the only
explanations of cost overrun. Other possible factors regarding policies, procurement
method and delivery approach should also be taken into account. With all attention on the
“Psycho theory”, Love et al. (2019) are afraid that public sector might neglect other
important factors and thus fail to improve and innovate.
As a matter of fact, it is hard to determine whether a project has suffered from
strategic misrepresentation. The Hawaii Honolulu Rapid Transit Project mentioned
before is a typical example. When analyzing the severe cost overrun of this project,
Prevedouros (2016) listed an array of underlying issues such as change-orders, quality
and safety to justify that this project is riddled with instances of strategic
misrepresentation. In fact, this project used RCF approach in the budget estimation stage.
However, as the market price fluctuated dramatically after 201111, the estimated budget
calculated using scientific method failed to prevent a detrimental cost overrun from
happening (Love, Zhou, et al., 2017).
The second solution receiving great academic attention is Public–Private Partnership
(hereafter PPP) (Osei-Kyei & Chan, 2015). PPP is portrayed as a strategy of building a
long-term relationship between public sector and private organizations or companies,
which may bring about an efficient construction of infrastructure (Ke, Wang, Chan, &
Cheung, 2011). PPP has two unique features that differentiate it from other procurements
and that can ultimately lower the scale and frequency of cost overrun of the infrastructure
project. First, PPP requires a fully-defined scope and design documents in place before
proceeding to the contractual stage (Love, Zhou, et al., 2017). Second, the PPP
procurement builds a closer relationship among stakeholders, and contractors are involed
11 The as-built projects that were used in this project finished before 2011.
Why Social Infrastructure Projects Experience Cost Overrun?
49
in the process at an earlier stage (Wilson, Pelham, & Duffield, 2010). These two features
seek to mitigate, if not eliminate, the worries of “Evolution theorists”.
Why Social Infrastructure Projects Experience Cost Overrun?
50
3. Methodology
As shown in the literature review, early studies on cost overrun focused on economic
infrastructure projects such as railways, express road, and bridges, etc. Social
infrastructure, however, did not receive much academic attention. Therefore, the current
paper aims to contribute to filling the research gap in this regard.
This paper explores the following research questions: why social infrastructure in
China experiences cost overrun? This research conducts an in-depth exploration of
factors causing cost overrun in social infrastructure projects. The current study seeks to
offer suggestions to the Chinese government authorities in charge of promoting and
constructing social infrastructure to reduce the occurrence of cost overrun in their future
projects. This paper analyzes four cases of social infrastructure projects where severe cost
overrun occurred.
Two steps are involved in this research design. First, a case study approach is taken
to explore cost overrun in the four projects selected. Throughout the case study, the
author expects to gain more insights into the practical projects and that new explanations
or factors may emerge. Second, this study combines factors developed from the case
study and theories extracted from existing literature together. The combination can bring
better understanding about the research question.
The case study approach is relevant in this case because it helps unravel the factors
explaining cost overrun in social infrastructure projects in China. This approach fits the
situation where the boundaries between phenomenon and context are hard to identify
(Gil, 2016). As a good way to deal with various sources of information, especially
qualitative data like textual materials (Yin, 2017), this research approach performs well
for our analysis of government documents, meeting minutes and reports. Moreover, the
case study method is particularly suited to in-depth exploratory investigation of a social
phenomenon, especially of a contemporary event (Yin & Davis, 2007). In a nutshell, the
Why Social Infrastructure Projects Experience Cost Overrun?
51
case study approach is an appropriate method to explore the research question of the
current study.
The data for the case study are withdrawn from the government website for
Xiamen12. These data include feasibility study reports, application and approval of
preliminary budget, application and approval of the conceptual budget, application and
approval of the adjustment of the conceptual budget, meeting memos, post-evaluation
reports and final audit reports. By reviewing the documents, the author aims not only to
collect general information of the project, such as scale, scope, budget, actual cost and
official analysis, but more importantly to unravel the subtle differences in the stances
different stakeholders may take. Since all the documents are first-hand, the validity of the
information regarding the project is guaranteed. These documents contained valuable
context-specific content which is critical in addressing the research question.
According to the documents collected from different stakeholders, a wide range of
hierarchical levels are revealed, and the diversity of perspectives is provided, which
enable us to integrate different information and identify new factors. All documents are
written by front-line staff who have been devoted to infrastructure construction work for
years and who thus have a deep understanding of the projects they worked on (Pitsis,
Clegg, Marosszeky, & Rura-Polley, 2003). That is to say, those documents and memos
contain details that incur subtle differences and ultimately influence the project result.
With the case study method, we probe the prevailing two schools of thought in cost
overrun literature and hopefully contribute to the debate between “psycho theorists” and
“evolution theorists” with a fresh perspective from China. The research provides a strong
12 Xiamen is located at the southeast coast of the People's Republic of China, and has been one of the first four special
economic zones of China since 1992. The built-up area of Xiamen is 348.23 square kilometers, with a resident
population of 4.11 million by 2018.
Why Social Infrastructure Projects Experience Cost Overrun?
52
narrative of the practical cases, probing the theoretical framework developed from the
literature review.
3.1. Data Selection
There is a severe lack of studies on cost overrun in social infrastructure project. It is
understandable for two reasons. Firstly, cost overrun in projects is regarded as a
politically sensitive topic as most of the projects are promoted and invested by the
incumbent government. Secondly, even though sometimes the government is willing to
provide data, other problems, including omissions and absence of certain information of
the documents, are inevitable.
Multiple case study is considered as a more robust design than a single case study
since the former explores a phenomenon in several settings. (Casey & Houghton, 2010).
In order to lay a solid data foundation, this study selects four as-built social infrastructure
projects in China. It has been appealed by OECD that government should make the
database available to the public in order to promote transparency and accountability, in
that way, the author obtained permission to documents of infrastructure projects in
government sectors, state-owned companies and design companies, including a
completed dataset consisted of data sufficient for a case study. The dataset being used in
this study contains figures of the estimated budget at every stage and of the final cost.
More importantly, besides the statistical material, the author was provided with textual
documents with comprehensive descriptive information of the cases.
The selection criteria of the cases are as followed:
1. The project should be categorized into social infrastructure projects such as
government facility, social housing, education facility, cultural facility and
health facility.
2. The project should be invested by government. In other words, taxpayers pay for
the construction, operation and maintenance of the project.
Why Social Infrastructure Projects Experience Cost Overrun?
53
3. The project should experience dramatic budget adjustment. In other word, the
original conceptual budget has increased to adapt the massive change of the
project.
4. There are data of estimated budget on every stage.
5. The project should be accomplished, and the actual final cost has been
concluded13.
3.2. Overview of the Cases
In accordance with the criteria listed above, the following four cases were selected.
The four projects were undertaken in the city of Xiamen. The construction time ranged
from 2010 to 2018.
The first case (CASE#1) was an important part of a big portfolio which was aimed at
improving the cultural public service in Jimei district in Xiamen. The portfolio was
proposed and invested by the city government and commissioned to a city-owned
construction company called Eastern Develop (hereafter, ED). By implementing the
portfolio, the city government planned to provide advanced cultural and educational
services for people in this area. As a municipal project with influence on the regional
development, this project was under incredibly heavy time pressure in order to coordinate
and keep up with the intense construction schedule. Facing a seemingly unreasonable
completion deadline, the ED company had to start the tendering process and even the
ground-level construction without the guidance of detailed construction documents. This
13 The conclusion and auditing of final cost of infrastructure projects in China are extremely time-consuming,
especially of large projects. Take the Guangzhou-Baiyun-International-Conference center as an example. Despite the
fact that the project was completed in 2008, as reported in the Guangzhou Audit Bureau website, it took them 10 years
to finish the auditing and evaluation of the project. Incidentally, the website only informed that they have finished the
job, while no content of the auditing report was disclosed.
Why Social Infrastructure Projects Experience Cost Overrun?
54
resulted in incidences like rework, process reschedule, scope changes and so on, all of
which contributed to cost escalation.
CASE#2 aimed at improving the reception capacity of Hospital A, one of the top
hospitals in Xiamen. The project consisted of two parts—the construction of an
automated parking garage and a new outpatient hall. The hospital had long been criticized
for its poor reception capacity resulting from limited space, therefore this project would
undoubtedly be welcome among the citizens. As required by the government, the hospital
kept open when the project was under construction. Unfortunately, after the on-site
inspection and feasibility study, the best site for constructing the garage was right beside
the main entrance of the hospital. In order to avoid interfering with the normal operation
of the hospital, the construction team had to shorten the construction period. Moreover,
the location of the hospital also made it hard for the construction team to accomplish their
job in a common way. Time pressure and construction difficulty made the construction
more challenging and ultimately led to extra cost.
The third project (CASE #3) was the construction of the third waste incineration
plant in the city of Xiamen. This plant was designed to process 600 tons of garbage per
day. Along with the other two plants, 50% of the garbage produced by the city would be
incinerated to generate electricity. A feasibility study for the project was conducted in
2006 and was approved later. The Environment and Energy Company (hereafter EE
company), an equivalent of the ED company mentioned in CASE #1, was a city-owned
company, representing the government and responsible for choosing the design plan and
putting related contracts out to tender. The first version of the conceptual budget was
calculated and approved in 2008. However, when the construction began, problems
started to surface. The construction-related regulations and standards were modified, the
workload increased, and the cost escalated. As a result, the EE company raised the
conceptual budget by 17.6%. Finally, the project was delivered and went into operation in
Why Social Infrastructure Projects Experience Cost Overrun?
55
2014. While under construction, the promotion of the second stage of construction was
proposed and approved, and later accomplished and brought into operation in 2018.
The last case (CASE #4) was the construction of a new campus of a high-school
consisting of the south and north part. The plan to construct the south part was first
proposed in 2013 but was not approved at that time. The project was launched in the
early 2014. The north part was approved one year after. In the first version of the project
proposal, the Sponge City strategy was not mentioned (This will be presented below).
However, in 2016 when the construction of both parts started, the city government
included the project into a big portfolio as a part of the Sponge City strategy to improve
the city’s ability to address the issue of the urban flood. The changes included replacing
the pavement materials of the roads and playground, adding the rainwater recycling
pools, upgrading the drainage systems, for which the budget committee had to recalculate
the budget of the project.
The general information, including the background, scope, duration, budget at
different stages, and final cost, can be found in Table 4. Also, information on the three
groups of stakeholders participating in the project is presented in Table 5.
Why Social Infrastructure Projects Experience Cost Overrun?
56
Table 4 Project Information
Case# Case Name/
Infrastructure Category/Duration
Project Scope Project Result
Budget Development Final Cost/Overrun Documents Used in
the Case Study
CA
SE#1
Name: the construction
work of the science
museum (this project is part
of a Cultural
Facility Center
Construction
Portfolio)
Scope: To improving
the cultural and
educational public
services in Jimei
district (Achieved)
§ 2011.01.18:
the preliminary
budget:
321.34 million
RMB
§ 2011.03.03:
the original conceptual budget:
261.47 million
§ 2014.10.29:
the adjusted conceptual budget:
Final cost: 368.49 million
§ Post-evaluation
report (256 pages
double side)
§ Budget estimation
report on
preliminary budget
§ Budget estimation
report on first
conceptual budget
§ Application to
adjust the
conceptual budget
§ Approval documents
for the adjustment of
the conceptual
budget
§ Final cost audit
report
Category: educational
infrastructure
Result: The science
museum was finished
and served as a new
educational
infrastructure facility
for Jimei district after
one year of operation.
The annual visitor
Overrun: overrun compared to
the preliminary budget: 14.67%
overrun compared to
the original
Why Social Infrastructure Projects Experience Cost Overrun?
57
Duration:
From 2011.03.09
to 2015.01.30
887 days later than
the expected
completion date
attendance reached the
expected level (210
thousand people per
year), and feedbacks
from visitors were
mostly positive.
375.58 million
(interior decoration
is not included14)
§ Conceptual budget overrun:
114.11 million
§ 2014.04.23:
the conceptual budget of the
interior decoration:
132.53 million
§ 2014.10.29:
the adjusted conceptual budget of the interior
decoration:
223.41 million
§ Conceptual budget overrun:
90.88 million
68.57%
conceptual budget:
40.93%
overrun compared to
the adjusted conceptual budget:
-1.89%
§ Meeting memos
from September
2010 to Jun 2014
14 The budget estimation of interior decoration and the exhibition installation was separated from the whole project. With the final conceptual budget estimation
of these two works were 132 million and 223 million respectively and were approved in 2014 April 23rd.
Why Social Infrastructure Projects Experience Cost Overrun?
58
CA
SE#2
Name: construction of an
automated public
parking garage and
expansion of a
reception building
hall
Scope: To improve the
reception capacity of
the Hospital A
(Achieved)
preliminary budget: 230.57 million
original conceptual budget:130.48 million
(garage: 90.63 million;
reception building
39.85 million)
adjusted conceptual budget: 141.00
million (garage: 92.09
million; reception
building 48.91
million)
conceptual budget overrun:10.52 million
7.4%
Final cost
135.50 million
§ Feasibility study
report (102 pages
double side)
§ Budget estimation
report on
preliminary budget
§ Budget estimation
report on first
conceptual budget
§ Application to adjust
the conceptual
budget
§ Approval documents
for the adjustment of
the conceptual
budget
§ Post-evaluation
report
§ Meeting memos
from November
2010 to January
2014
Category: health system
infrastructure
Result: The project
achieved its goal by
increasing the parking
space by 302%, and
the reception capacity
reached 1200 people
per day.
Overrun
overrun compared to
the original conceptual budget: 3.85%
overrun compared to
the adjusted conceptual budget: -3.90%
Duration: The foundation
construction started
on August 1st
201115
The upper part
construction started
on June 1st, 2012
and finished on
August 22nd, 201416
The estimated
construction period
15 According to the budget adjustment application submitted at August 31st, 2017 16 According to the Final Acceptance and Inspection report submitted at October 2014. The project is ready for delivery after the approval of this report.
Why Social Infrastructure Projects Experience Cost Overrun?
59
was 30 months17,
and the real
construction time
was 27 months
(upper part
construction). The
project was
accomplished three
months earlier than
the original
schedule.
CA
SE#3
Name: construction of a
waste incineration
plant
Scope: To increase the
waste-to-energy
recycling rate of
Xiamen (Achieved)
2009.07.29:
Original conceptual budget: 347.10
million
2012.10.28:
The first version of
modified conceptual budget: 355.34
million
Conceptual budget overrun: 8.24 million
(2.31%)
2017:
Final cost
398.61million
§ Feasibility study
report (102 pages
double side)
§ Budget estimation
report on
preliminary budget
§ Budget estimation
report on first
conceptual budget
§ Application to
adjust the
conceptual budget
§ Approval documents
Category: utility system
infrastructure
Result: The project
was delivered on
schedule, and the pilot
operation started in
2014. Later in 2015,
the full operation was
underway. This project
achieved its goal to
improve the waste-
Overrun
Overrun compared to
the original conceptual budget: 51.51million (14.84%)
Overrun compared to
the first version of the modified conceptual
Duration: The construction
started on
December 14th,
2010 and finished
17 According to the feasibility study report written at September 29th, 2011.
Why Social Infrastructure Projects Experience Cost Overrun?
60
on August 20th,
2014
energy recycling rate
of the city.
The second version of
modified conceptual budget: 408.27
million
Conceptual budget overrun:
61.17 million; 14.98%
compared to original
conceptual budget
52.83 million; 12.93%
compared to first
version
budget:43.27 million
(12.17%)
Overrun compared to
the second version of the modified conceptual budget:-9.66 million ( -2.3%)
for the adjustment of
the conceptual
budget
§ Post-evaluation
report
§ Meeting memos
from November
2010 to January
2014
CA
SE#4
Name: Construction of a
high-school campus
Scope:
§ First stage
objective
(Achieved):
The south campus:
two six-stories
building for
classrooms, one
building for cafeteria,
one building for
dormitory, outdoor
Preliminary budget: 312.50 million (both
north and south part) 18
Conceptual budget: south campus:
239.89 million
north campus:
102.71 million
Adjusted conceptual budget:
Final cost
§ south campus:
154.65 million
§ north campus: 71.11
million
§ Feasibility study
report (68 pages
double side)
§ Budget estimation
report on
preliminary budget
for the architecture
§ Budget estimation
report on first
conceptual budget
for the architecture
Category: educational
infrastructure
Overrun
§ overrun compared to
the preliminary budget:
-2.78%
18 The preliminary budget documented in the feasibility study report did not divided into two part. Thus, here when discussed the preliminary budget we considered the south
campus and north campus as a whole.
Why Social Infrastructure Projects Experience Cost Overrun?
61
playground and other
supporting facilities.
The north campus: the
main build which was
able to accommodate
twenty-four classes
with library,
multifunctional
gymnasium, hall and
outdoor playground (a
400-meter track)
Second stage
objective: apart from
the first stage goal, the
outdoor landscape
construction project
needed to be aligned
with the portfolio of
Sponge City
(Achieved)
south campus:
4.31 million
north campus:
6.26 million
*Here in this project
the adjustment is only
a reallocation of
budget. In other
words, part of the
budget was reallocated
for the new workload
related to the change
orders while the
budget did not
increase as a whole.
§ overrun compared to
the conceptual budget:
south part:
-35.53%
north part:
-30.77%
§ Application to
adjust the
conceptual budget to
accommodate the
additional design
and construction of
the upgraded
outdoor landscape
§ Approval documents
for the adjustment of
the conceptual
budget
§ Final cost audit
report
§ Meeting memos of
2016
Duration: The south campus
construction started
on June 27th,2015
and finished on
May 8th, 2018
Result: The project
was accomplished
within both schedule
and budget. The
project was awarded as
“the top-performing
Why Social Infrastructure Projects Experience Cost Overrun?
62
without any
schedule overrun. The north campus
construction started
on January 8th,
2016 and finished
on June 28th, 2018
without any
schedule overrun
social infrastructure
project” of the city.
Why Social Infrastructure Projects Experience Cost Overrun?
63
Table 5 Stakeholders and Their Roles
Case# Organization Stakeholders Roles Involvement Period
CA
SE#1
Government
Reformation and
Development Department decision maker/investor the whole project cycle
Budget Estimation
Committee budget estimator pre-preparation-Tod
Audit Department cost audit acceptance check
SOE Eastern Develop company agency company/project
manager/tendering organizer The whole project cycle
Contractor
design company design
pre-preparation-design
stage-the mid-period of
construction stage
construction company construction construction stage-
acceptance check
CA
SE#2
Government
Reformation and
Development Department decision maker/investor the whole project cycle
Budget Estimation
Committee budget estimator pre-preparation-Tod
Audit Department cost audit acceptance check
SOE Eastern Develop company agency company/project
manager/tendering organizer The whole project cycle
Why Social Infrastructure Projects Experience Cost Overrun?
64
Contractor
design company design
pre-preparation-design
stage-the mid-period of
construction stage
construction company construction construction stage-
acceptance check
CA
SE#3
Government
Reformation and
Development Department decision maker/investor the whole project cycle
Budget Estimation
Committee budget estimator pre-preparation-Tod
Audit Department cost audit acceptance check
SOE
Construction and
Development company
(hereafter: CD company)
agency company/project
manager/tendering organizer the whole project cycle
Hospital end-user/investor the whole project cycle
Contractor
design company design pre-preparation-design stage
construction company construction construction stage-
acceptance check
CA
SE#4
Government
Reformation and
Development Department
Project promoter /decision
maker/investor the whole project cycle
Budget Estimation
Committee budget estimator pre-preparation-Tod
Audit Department cost audit acceptance check
Why Social Infrastructure Projects Experience Cost Overrun?
65
SOE
Construction and
Development company
(hereafter: CD company)
agency company/project
manager/tendering organizer the whole project cycle
Contractor
design company design pre-preparation-design stage
construction company construction construction stage-
acceptance check
Why Social Infrastructure Projects Experience Cost Overrun?
66
3.3. Data Analysis
3.3.1. Documentary analysis
The documents used in this study include feasibility study reports, application and
approval of preliminary budget, application and approval of the conceptual budget,
application and approval of the adjustment of the conceptual budget, meeting memos,
post-evaluation reports and final audit reports.
First, figures of the original budget estimation and final cost were withdrawn from
the budget application filed by the Budget Estimation Committee. Then, budget
adjustment application filed by project manager and approval signed by the Reformation
and Development Department provided the adjustment process of the budget. Finally, the
final cost was recorded in the audit report signed by Audit apartment.
The feasibility study report was carried out before the official approval of the project,
and a qualified feasibility study could thus lay a solid foundation to soundly prepare the
stakeholders for the project as the opening of a project (Peter ED Love & Heng Li, 2000).
The feasibility study should include information about the necessity and the potential
influence of the project (social, environmental, economic, etc.), the source of funds, the
size and scale of the project, the selection of site and the estimated budget and duration
("Feasibility Study," 2020).
As for the post-project evaluation, it referred to a systematic and objective analysis
of the purpose, execution process, benefit, role, and impact of a plan or a completed
project (Myers, Fisher, Pickering, & Garnett, 2014). This evaluation conducted after the
delivery of the project was delegated to an independent third-party to ensure the
credibility, reporting concerning problems that occur in the implementation and operation
of the evaluated project, so as to improve investment efficiency (Anbari, Carayannis, &
Voetsch, 2008).
Why Social Infrastructure Projects Experience Cost Overrun?
67
The meeting memo is the overview of a certain meeting during the project lifecycle
(Pitsis et al., 2003). This kind of document is highly disorganized, therefore consumes
lots of time for a logical analysis and for extracting useful information. Reviewing the
meeting memo can reveal how a project develops along the time.
Two steps were taken in the documentary analysis. To begin with, a coding process
was carried out on the raw data. Then, a table was formed to show the counting of
keywords related to reasons behind the cost overrun concluded from the documentary
analysis.
Coding
The coding process went through two phases: a deductive one using a coding book
developed based on the existing literature on cost overrun and an inductive one driven by
the data. Although the case study, as a qualitative research method, is flexible, the coding
process should follow a strict logic chain to ensure trustworthiness or reliability
(Houghton, Casey, Shaw, & Murphy, 2013).
Firstly, explanations of cost overrun in the realm of social are used as topic codes. A
rough central codebook for the deductive coding analysis is then developed. When
reviewing the collected documents and memo of the cases, the author will use the
explanations, case number and title of documents to name the code. For example, a
paragraph or sentence written in the budget estimation report describing a field accident
that happened in Case #1 and that contributed to the occurrence of cost overrun will be
coded as Field-1-BudgetEst.
As well, an inductive coding approach was also be adopted to address emerging
explanations that come into light during the review of archives. Unlike deductive
analysis, inductive research allowing the new concepts to emerge from the content of the
raw data, does not involve the testing of pre-conceived hypotheses. As a bottom-up
approach, the inductive coding process is most helpful when researchers conduct
Why Social Infrastructure Projects Experience Cost Overrun?
68
exploratory research, which is the case of social infrastructure cost overrun research in
China (Fereday & Muir-Cochrane, 2006). A coding rule was developed during the
scanning of the documents in the inductive process. The combination of deductive and
inductive approaches offers a way to organize and present the structure of the data.
Next, using the coded data, we can conclude which contribution has been mentioned
most frequently.
Keywords and Counting
Distinguishing the sentence and keyword related to reasons behind overrun is a vital
part in the documentary analysis. First, sentences and paragraphs regarding why cost
overrun happened were highlighted. Second, since the documents were all written in
Chinese, the highlighted message was translated into English. Third, the keywords were
extracted from the highlighted message and comparison with the coding book was done.
Fourth, the keywords and their frequency were be recorded, and the keywords with
similar meaning (e.g., incomplete drawing and sketchy drawing) were be merged. An
example of how document analysis is given below.
Figure 6 Documentary analysis step
3.3.2. Comparative Analysis
After the documentary interpretation, explanations of cost overrun were grouped
together to identify common patterns and examine themes. With a clear structure of the
data, the author was able to draw the convergency of opinions and contrasts coming from
Why Social Infrastructure Projects Experience Cost Overrun?
69
various stakeholders (such as…) to explore the phenomenon of cost overrun in social
infrastructure projects in different settings in China.
For every case, the author collected and analyzed documents that came from
different stakeholders with different stances on the projects. Each stakeholder expresses
their own point of view of the project through documents. Therefore, the focus of the
research is to analyze and compare the archives developed by different stakeholder
organizations. Thus, similar or different perspectives among the stakeholders emerged
through different words they chose to explain and describe the cost overrun situation or
incidence. Through the vertical inner comparison, the author was able to identify the
similarity of explanations suggested by different stakeholders in documents explaining
cost overrun in social infrastructure projects.
Besides, a cross-case analysis or a method that enhances knowledge flow between
individual cases (Khan & VanWynsberghe, 2008), was also be used. Similar reasons
offered by different stakeholders for cost overrun might still function differently in each
case. A cross-case analysis was therefore applied to examine those similarities, to derive
patterns, and finally to reach potential conclusions. A cross-case analysis was both a way
of aggregating across cases and a mean to identify common patterns and, by doing so, it
promotes theoretical elaboration.
Four questions were proposed to examine each explanation/factor. These subsidiary
questions were asked in order to address the core research question stated before. The
case analysis section, the discussion section and the conclusion section were organized in
accordance with these four subsidiary questions.
1. How often is a certain explanation being mentioned as a contributor for cost
overrun?
2. Has a certain explanation been studied before? Does it fall into categories of the
“psycho theorists” or the “evolution theorists”?
Why Social Infrastructure Projects Experience Cost Overrun?
70
3. Which case is considered to be influenced by a certain explanation? To what
extent has it been influenced? How did the explanation function in adding up to
cost growth?
4. How many different organizations have mentioned a certain explanation? What
are their opinions towards this explanation? In their opinion, who is supposed to
be responsible for controlling this explanation?
Why Social Infrastructure Projects Experience Cost Overrun?
71
4. Findings
4.1. Within-case Findings
This section presents the within-case findings. For each case, first, a table of
keywords and the counting result is shown. This table includes the counting figures of the
keywords related to reasons/factors causing the cost overrun mentioned by documents
including the post-evaluation report, meeting memos, application of the budget
adjustment and final audit report. Second, documents used in the case study like
application to adjust the conceptual budge, post-evaluation report and meeting memo
have documented stakeholders’ opinion towards why cost overrun happened. Therefore,
in this section the recorded cases of cost escalation are listed. Last, we further explain in
detail how this recorded causes influenced the cases.
4.1.1. CASE#1
Table 6 Keywords and counting for CAES#1
Keyword time
constraint/time pressure
additional workload (outdoor
landscaping)
additional workload
(architecture style)
additional workload (omission)
additional
workload (internal
decoration design change)
Counting 59 23 43 33 18
Keyword rework (change of design)
rework (omission)
change order (elevator)
change order (fire regulation
change) extra design fee
Counting 24 15 27 17 41
Keyword idling
time/waiting time
incomplete design/sketchy design drawing
inflation (manpower/mat
erial)
extra fee for inspection of the construction site
Counting 21 37 22 16
List of the recorded causes for cost escalation:
1、Increased unit cost due to the special architecture style design (from post-evaluation
report/meeting memo #07-12)
2、Additional cost for ungraded material in order to follow regulations on fire prevention
that came into force during the construction period. (application to adjust the
Why Social Infrastructure Projects Experience Cost Overrun?
72
conceptual budge/meeting memo#08-10)
3、Workload (additional fees for extra materials and labors) because of the incomplete
design. (application to adjust the conceptual budge/post evaluate report)
4、Additional workload to compensate the idle time to wait for design documents to
complete (application to adjust the conceptual budge/post evaluate report/meeting
memo #11-17)
5、Design fees for outdoor landscaping (application to adjust the conceptual budge/post
evaluate report/ meeting memo #07-20)
6、Preparation for additional design document (meeting memo #15-20/ application to
adjust the conceptual budge/post evaluate report)
7、Additional workload (demolishing 25% of the indoor walls) to adapt to the new indoor
decoration plan.(post evaluate report/meeting memo #17-20)
8、Additional expense resulted from the change order of the elevator system, with
domestic brand replaced by imported one for security consideration (application to
adjust the conceptual budge/post evaluate report/ meeting memo #10-15)
9、Additional expense as a result of the upgrade of power distribution system to match the
the changed elevator system. (application to adjust the conceptual budge/post evaluate
report/ meeting memo #10-15)
Document Interpretation
The first problem which negative influenced the project was time pressure. As we
can see from the chart above, words such as “rush”, “time constraint” and “urgent” were
mentioned frequently in descriptions and analyses of the project, which means that the
project is under great time pressure throughout the whole project cycle. This project was
an important part of a significant municipal portfolio, in that case, the project needed to
coordinate with other projects in the portfolio. The need of coordination equates to mere
partial control of the project team and unexpected situations brought by other projects in
Why Social Infrastructure Projects Experience Cost Overrun?
73
the same portfolio. First, the fact that the government authority had to deal with multiple
projects at the same time makes approval procedures of budgets, design plans and
contracts longer than before. Next, with more than one mega-infrastructure projects being
constructed at the same period, they were competing for the scarce resources. The limited
resources not only influenced the schedule but also the cost. In an effort to avoid slowing
down the progress of the whole portfolio, project managers had no choice but speed up
the project at any cost. Under such enormous pressure, improper decisions might be
made, like starting the tender prematurely with incomplete design.
The delivery of shop drawing was originally set for April of 2011, but at the urging
of the government, delivered sooner by January 25th of 2011, two months earlier than the
plan. However, the truth is that the drawing was incomplete at that time, the government
only receive a set of unreview sketchy drawings. In order to accelerate the progress, with
the consent from the government, ED company used the unreviewed drawings to
calculate the workload then estimate the budget. Bidders gave their offers based on the
bidding documents and the estimated budget provided by the government, however, those
documents without thorough consideration did not reveal the whole picture of the project.
After the tender process and the signing of the contract, the contractor was surprised to
find that there was enormous omission in workload calculation and dramatic changed
orders from the client, making it impossible for the contractor to construct the project
within the original budget. In the end, the workload calculation omission led to an extra
of 57.62 million on top of the original conceptual budget calculated in accordance with
the unreviewed sketchy drawing. When comparing the unreviewed drawing to the
finalized reviewed drawing, the first great distinction is a modified layout with a series of
updates in the structure of the upper part building. The modification caused chain
reactions including the rework of some parts of the foundation and the additional support
units. To cope with the layout modification, the contractor had to reconsider the project,
Why Social Infrastructure Projects Experience Cost Overrun?
74
to reschedule a set of procedures, to rearrange the order of materials and to employ
additional manpower. The labor fee and the material cost were respectively 6.35 million
and 21.94 million higher than the original estimation.
The supplementary workload was not only derived from omissions, but also from the
changed orders from client, which in the case of social infrastructure projects refers to the
government.
While the upper part construction was under process, in August 2011, the
government decided to raise the standard by purchasing the imported elevators and lifts
instead of the domestic ones. The new decision regarding the equipment escalated the
budget by 4.15 million. Subsequently, to accommodate the imported equipment, the
power distribution system was upgraded as well. This generated 2.47 million of extra
design fees and material cost. Furthermore, when estimated the first version of the
conceptual budget, the outdoor landscaping plan was not included. While the government
took the outdoor landscaping into account when constructing the main architecture. This
newly added part counted for 5.92 million of the adjustment of the budget.
Actually, apart from the extra cost derived from the unreviewed sketchy drawing, the
work to improve the drawing itself cost the government more than 58.25 million to the
design company.
The second problem is the underestimation of budget in the first place. Being part of
a portfolio that targeted on improving the cultural and educational facilities in the district,
this project followed a specific architectural style called Jiageng style in memory of a
great man called Jiageng Chen who devoted his whole life and all his assets to the
development of this district about 100 years ago. This particular architectural style is
famous due to its extensive roof overhang, in need of extra amount of steel and concrete
compared to the regular style of same size. Yet, the planner did not take into
consideration of the increment needed in constructing the Jiageng style architectures
Why Social Infrastructure Projects Experience Cost Overrun?
75
when calculating the preliminary budget, despite his review of the data from as-built
scientific museums. The estimation built on poor referencing data was bound to be far
from the reality. Worse still, the conceptual budget developed using the same documents
that came out only one month after (once again, due to the time pressure) was cut by
20%, because the Chinese government required that the budgets should be narrowed
down stage by stage. The post-evaluation report shows that the conceptual budget
approved in 2011 March 3rd was 261.47 million, decreased by 20 % compared to the
preliminary budget, while the preliminary budget was already underestimated.
Besides, the interior decoration (accounted for 9.86% of the original conceptual
budget) was removed from the work course of the whole project since when the detailed
design was accomplished, it was found that to carry on this interior decoration plan
within the old conceptual budget was unrealistic. Therefore, the government decided to
separate the interior decoration from the project. The second version of conceptual
budget approved in 2014 October 29th did not cover the interior decoration, and so did the
conceptual budget that get adjusted and approved later. In other words, though it seems
that the adjusted conceptual budget was only 114.11 million higher than the original
conceptual budget, the real cost increase was much larger since the “disappeared” interior
decoration should be taken into account. The conceptual budgets of the interior
decoration and the exhibition installation were 132 million and 223 million respectively
and were approved in 2014 April 23rd.
The dramatic change of the interior decoration and exhibition installation resulted
from an absence of the future operating company at the design stage of the project.
Although the design company had certain experience in designing a science museum,
they had no clue what themes would be introduced and what exhibitions would be
presented because the future operating company had not yet been selected the time when
the design was going on. Worse still, the decision makers (government) had little
Why Social Infrastructure Projects Experience Cost Overrun?
76
experience in planning a science museum. As a result, the space arrangement of the
building was different from what the operating company expected of an extraordinary
science museum when the operating team was finally involved. To solve the problem, the
interior design has to be modified.
The unit cost of this project was 6.46 thousand per square meter. The post-evaluation
report compared it with other similar projects. The first referenced project was an art
gallery in the same portfolio, the formal inauguration of which was in 2012, in the same
period of CASE #1. The unit cost of this art gallery was 5.43 thousand per square meter,
lower than that of CASE #1. The second referenced project is a science museum located
Shaoxing, a city with a similar population size and economic status as Xiamen. The
science museum in Shaoxing was constructed over the same period and open to public in
2014. As for the unit cost, the Shaoxing science museum cost 6.97 thousand per square
meter, higher than that of CASE #1.
Because of several adjustments of the budget, the project was still under the
conceptual budget adjustment procedure even after the museum was handed in to the
operator and already open to the public. According to the laws and regulations, the
government would only formally allocate the money to the contractor after the conceptual
budget is finalized. Being stuck in the procedure implies that the contractor was unable to
be paid on time, which would cause serious social problems subsequently.
Why Social Infrastructure Projects Experience Cost Overrun?
77
4.1.2. CASE #2
Table 7 Keywords and counting for CASE #2
keyword time
pressure/cut the time
traffic jam/inconvenien
ce location
additional workload (omission)
additional workload (fire
prevention system)
counting 43 35 50 29 14
keyword additional equipment investment
space utilization extra design fee
counting 11 33 27
List of the recorded causes for cost escalation:
1. Additional cost for manpower due to a complex construction plan in order to relieve
the traffic burden caused by the project surrounding the hospital. (application to adjust
the conceptual budge/post evaluate report/meeting memo #4-6)
2. Workload (additional fees for materials and labors) because of the incomplete design
(application to adjust the conceptual budge/post evaluate report/meeting memo #6-8)
3. Additional workload as a result of the rearrangement of the internal space utilization.
(application to adjust the conceptual budge/post evaluate report/meeting memo #6-10)
4. Addition workload and additional equipment investment for the modification of the fire
prevention design. (application to adjust the conceptual budge/post evaluate
report/meeting memo #8-12)
5. Additional preparation for the design document (application to adjust the conceptual
budge /meeting memo #5-10)
Document Interpretation
The first problem was the time pressure. This hospital was located in the middle of
the downtown, surrounded by skyscrapers and subjected to heavy traffic. Therefore, the
construction site had to be confined to avoid blocking the traffic and disturbing the daily
life of the inhabitants in the nearby areas. Secondary, the hospital had to keep open to the
public during the construction period. Noteworthy, the construction site was right beside
Why Social Infrastructure Projects Experience Cost Overrun?
78
the entrance of the hospital which could not be separated from the hospital and would
inevitably interfere with the normal operation of the hospital. After the inspection of the
construction site, the project team found the original plan with open-cut method was time
consuming and occupied too much space, so, they decided to switch to a new
construction plan which would occupy less land to save more space for the entrance of
the hospital. The new construction plan not only requested more labor power, but also
consumed more time to complete.
Besides the complex location, the hospital served a massive daily flow of patients.
This created a great pressure on the project team to complete the construction as early as
they could to let the hospital resume its normal operation19. To achieve this, another
change in the order took place. The project team re-designed the beam structure of the
garage and the new reception building to shorten the construction period. Moreover,
according to the meeting memos, the project team came up with an uncommon solution
to reduce the impact. That is, after the main bodies of the garage and reception building
were finished, the project team would first resume the construction site that blocked the
entrance linking the hospital driveway to the main street (patients had to use a temporary
entrance where traffic was limited when the construction was going on). And the interior
decoration would proceed inside the building without further occupying the outdoor
space. The new beam structure provided enough support to support some dangerous
interior decoration constructions like directional demolish blasting. Undeniably, these
actions would minimize the impact, but these changes were also costly. In addition, other
structural changes include enlarging the windows on the ceiling of the outpatient hall to
let the air flow and more sunlight in.
19 As found in a report on Xiamen Daily newspaper (March 28th, 2012) (Xiaolong, 2012), a newspaper company
owned by the city, the construction was expected to end at October 2013. However, the reference of this data cannot be
found in any official document published by the city government.
Why Social Infrastructure Projects Experience Cost Overrun?
79
Time pressure to finish the project not only led to anxiety from the construction team
but also reckless actions from the government. If the project followed a regular approval
procedure, it would not begin construction until the end of 2011. However, in order to
start the construction as soon as possible, an action discussed in CASE #1 was adopted by
the team, who used the sketchy and unreviewed drawing and design in the tendering
process. Noteworthily, CASE #1 and Case #2 were being processed and constructed
around the same period. This action caused the same problem in both cases: as the design
and drawing were detailed and modified, the workload of the project increased, and the
cost subsequently raised as well. In the end, the original estimated budget was
underestimated and could hardly cover the actual workload.
As the project objective stated, it intended to improve the reception capacity of the
hospital on the basis of the existing space of the old garage. Thus, when assessing the
design plan, the commission complied with the rule that the winning design plan should
be the one that maximizes the utilization of the limited space. In the end, with the existing
space and the upgrade of the site considered, the plan that provided most parking space
and cost comparatively lower per unit was selected. However, this design plan did
observe the current construction standards for fire prevention. Also, a related regulation
on the modification of fire prevention design was still under revision at that time.
Fortunately, the project team followed previous conduct of a terminal construction
project in Xiamen by inviting the experts in fire prevention to put forward a proposal to
reinforce the fire protection system of the project. This proposal suggested solutions
including the use of a special fire-resistant roller shutter door, a smoke exhaust system
inside the garage, an automatic fire alarming and extinguishing system and sufficient
emergency luminaries and fire hydrants. Though the project was later approved by the
fire prevention authority with those solutions, all equated to additional investment not
calculated in the original conceptual budget.
Why Social Infrastructure Projects Experience Cost Overrun?
80
4.1.3. CASE#3
Table 8 Keywords and counting for CASE #3
keyword regulation modification
upgrade technology
design incomplete
additional workload (omission)
inflation
counting 51 42 31 30 18
keyword additional equipment investment
space utilization extra design fee environment
friendly
counting 32 33 27 36
List of the Recorded Causes for Cost Escalation:
1. Inflation of the price of manpower, construction materials and equipment during the
construction period (applications to adjust the conceptual budget/meeting memo #5-8)
2. Workload (additional fees for materials and labors) because of the incomplete design
(applications to adjust the conceptual budget/meeting memo #6-12)
3. Additional workload as a result of the design change in response with the regulation
modification (applications to adjust the conceptual budget/meeting memo #7-12)
4. Additional workload and equipment investment from upgraded technologies
(applications to adjust the conceptual budget/meeting memo #6-12)
5. Additional preparation for design documents (applications to adjust the conceptual
budget/meeting memo #8-10)
Document Interpretation
Similar to CASE #1, this project was also faced by the cost overrun derived from
change order –a modification of related construction regulations and standards. When the
project was under construction, a new governmental standard on the design of waste
incineration plants came into force. Although the design of the project had already been
finalized and the contract signed, the government requested the EE company to modify
the design in compliance with the new standard after careful consideration and
discussions. In order to achieve this goal, an array of civil engineering construction work
Why Social Infrastructure Projects Experience Cost Overrun?
81
has been added. Firstly, the design company was required to re-design the plant,
generating an additional design fee. Secondly, according to the new version of design in
accordance the new standard, the workload increased as the foundation ditch was
deepened by four meters and a slope was added in the construction to support the side
around the ditch. Thirdly, a wall which separated the plant outside was needed according
to the new standard. Those adjustment gave rise to an increased investment worth 4.71
million. Moreover, the ash silo, originally exposed in the air as planned in the first
design, should be covered to ensure that the plant would function properly, based on the
new standard. The architecture used to protect the ash silo costed an extra 2.36 million.
What may seem a relief to the contractor was that the agreement they signed with EE
company adopted a fixed unit price. In other words, though the actual workload may be
flexible in practice, the final settlement of the cost would be calculated in line with the
actual workload. Supplemental agreements were signed for additional work and
investment. Hence, this contract protected the benefit of the contractor so that they would
not be worried about the possible loss due to the endlessly increasing workload which
was not covered in the original contract.
Other changes of orders to observe the new standard included the import of advanced
equipment so as to be safe, harmless and eco-friendly. First, an extra expense of 1.89
million was deployed to increase the capacity of the drainage tank, add the cooling tank,
sludge tank and a water recycle unit and to construct supporting facilities for the water
recycle unit. Besides, an automatic controlling system was added, costing 19.74 million
together with the fees of designing the system and upgrading the supporting equipment.
Meanwhile, the pipe system of the project was adapted for the imported equipment. In
order to create and sustain a healthy and pleasant working environment, the project added
a deodorization stem in the hall and the elevators, costing another 1.04 million. The water
Why Social Infrastructure Projects Experience Cost Overrun?
82
pump system was also upgraded to comply with the newly adopted facility, spending
2.87 million.
Furthermore, the construction work in this project consisted of more categories than
those of other three cases. This compound project contained work in civil engineering,
industrial construction and electric power facility installation which required a better
coordination from the project manager with designers, suppliers and contractors from
different fields. As recorded in the meeting memos, the civil engineering bidding process
was completed on September 16th in 2010, yet most of the supporting facility was not
finished until December of the same year after the preparation of the bidding documents.
As for the electricity power system and the meter and instrument system, it was not until
August of 2012 when the supplier and contractor had been chosen. In order to accelerate
the process and reduce the idle time, the project team used the old trick. They adopted the
preliminary design for the bidding, and a modified version for the contract.
By the time when contracts were sign, the numbers of the complementary design
drawings for each category are listed as below.
§ Automatic controlling system: 14 sets
§ Incineration machine: 13 sets
§ Electricity power system: 16 sets
All these factors mentioned above not only raised the cost, but also triggered a chain
reaction. First was the additional fee of 1.58 million for detailing the design and another
1.28 million for the on-site management responding to the increasing workload. Second,
1.16 million was spent on environmental inspection during the construction to make sure
that the project could be approved in future examination. Finally, an electricity supply
system with higher reliability, with a price of 1.25 million, was installed to ensure an
effective and efficient construction.
Why Social Infrastructure Projects Experience Cost Overrun?
83
4.1.4. CASE#4
Table 9 Keywords and counting for CASE #4
keyword time
constraint/time pressure
additional workload
(sponge city)
change order (sponge city)
extra design fee
material upgrade (outdoor
pavement)
counting 12 55 34 33 41
keyword rework (change of design)
counting 24
List of the recorded causes for cost reallocation:
1. Additional workload (manpower and materials) for realizing the new landscape plan
in order to achieve the Sponge City strategy (applications to adjust the conceptual
budget/meeting memo #1-10/final cost audit report)
2. Additional Design fees for outdoor landscape plan in order to achieve the Sponge City
strategy (applications to adjust the conceptual budget/meeting memo #3-8)
3. Preparation for additional design document (applications to adjust the conceptual
budget/meeting memo #3-9/final cost audit report)
Document Interpretation
The world is in hustle and bustle amid climate change. Xiamen, as a city with
subtropical monsoon climate, has suffered a lot from urban flood caused by storm. Since
2014, the Chinese Central Government has proposed an innovative water management
strategy called “Sponge City” which aimed at resolving this problem. The Sponge
City indicated a particular type of city that acts like a sponge to absorb the rainwater,
which was then naturally filtered by the soil and reached the urban aquifers. The Sponge
City strategy served to replenish groundwater, reduce risks of flood and lower the
burdens on drainage systems. The Sponge City strategy could be implemented by
constructing more open green space like the storm water park and the green roof or by
paving the surface with permeable materials rather than traditional concrete. The whole
Why Social Infrastructure Projects Experience Cost Overrun?
84
idea of Sponge City strategy was to utilize the outdoor landscape of the city to absorb
rainwater and thus to prevent floods caused by large and sudden precipitation. It was an
effective and sustainable strategy to deal with the natural disasters caused by climate
change. However, because of the costly permeable materials and the extra design fees,
the private company lacked motivation to implement this strategy within their own
project. Therefore, the government managed to encourage the private company and
meanwhile implemented the Sponge City strategy in all suitable social infrastructure
projects. The construction project of the high-school campus in CASE #3 consists of
adequate open space, so it is suitable to carry out the strategy. It was also a good
opportunity to raise the awareness of environmental protection among teenagers by
promoting the strategy in this project.
According to the meeting memos, when the government made the decision to
conduct the Sponge City strategy in this project in June of 2016, the south part had
already been constructed for more than one year and the north part for half a year. The
government first invited the design company back into the project to redesign the outdoor
space of the campus. Then the project management team from the agency company
recalculated the budget and came up with a solution to accommodate the additional cost
out of the change of design. Instead of asking for more money, the project team
reallocated the budget. They increased the budget by 4.31 million to construct outdoor
space and by 6.26 million for the south and north parts of the campus respectively. This
change of the budget covered the work listed below:
§ Replacing the traditional materials used to pave roads, pathways and sidewalks with
permeable clay bricks and permeable concrete.
§ Adopting the permeable artificial turf technique for the outdoor soccer playground.
§ Adding reservoir and silos to store and recycle the rainfall.
§ Constructing green space with sunk face to better absorb the rainfall and to replenish
Why Social Infrastructure Projects Experience Cost Overrun?
85
ground water.
CASE #4 is distinct from the other cases in this study. As shown in the data of the
budget above, the project was not only finished as planned but was also within the
budget. It seems like this project was well-planned, -managed and -conducted, and
therefore awarded as “the top-performing social infrastructure project” of the city.
However, through detailed analysis, it is clear that the project was not without problems.
First, despite the fact that change orders took place during this project to adapt to the
special strategy, the final cost was lower than the conceptual budget and that the balance
was nearly one third of the total budget. It implies that, unlike the frequent
underestimation in other cases, the budget in this project was overestimated.
After the official approval of the conceptual budget for a certain project, the
government would reserve the money and resources to make sure that the project could
be proceeded smoothly. CASE #4 reveals that the government might reserve more money
than needed for a project. This overestimation resulted in a waste of resources. Some
projects under construction at the same period might be negatively affected and other
productive projects waiting in the pipeline might be sacrificed due to the overly
pessimistic allocation of budget.
In the psych theory discussion about optimistic bias and strategic misrepresentative,
an idea was introduced about deliberately underestimating the budget to make the project
competitive and more likely to be approved. When analyzing CASE #4, a contrasting
logic was found. Is it possible that the project planner exaggerated the cost to make sure
that the project would be completed within the budget so as to make the project
seemingly well-forecasted and well-performing?
Why Social Infrastructure Projects Experience Cost Overrun?
86
4.2. Cross-case Findings
The following section discusses the cross-case findings of this thesis. It provides an
overview of the common cost overrun contributors as mentioned in the documentation of
the four cases. The analysis of crucial events causing cost overrun along the project
lifecycle then follows. The stakeholders in those events are highlighted in each phase.
Through the discussion, factors leading to the problems can hopefully be identified and
concluded.
4.2.1. Cost Overrun Contributors
The key cross-case cost overrun contributors we found based on the analysis of the
four cases are as follows: time pressure, long period of ex-ante preparation, and
coordination among stakeholders.
Table 10 Cross-case keywords summary
CASE#1 CASE#2 CASE#3 CASE#4 time pressure-unrealistic time schedule
ü ü ü ü
change orders ü ü ü ü extra design fee ü ü ü ü additional workload after bidding process
ü ü ü
additional equipment investment
ü ü
inflation of labor/material
ü ü
idling time ü ü rework ü ü incomplete design ü ü scope change ü
Why Social Infrastructure Projects Experience Cost Overrun?
87
Time Pressure
Time pressure played a vital role in all four cases. The project team spared no effort
in order to shorten the construction period, yet, these approaches added up to the budget
burden of the project to cause cost overrun. The reasons behind time pressure include
unrealistic construction schedule, idle time, and utilization of incomplete design.
Table 11 Keywords related to time pressure 20
Unrealistic Construction Schedule
Unrealistic schedule arrangement was one of the main causes for constrained
construction time. An endeavor to stick to the unfeasible delivery date scheduled without
reasonable plan at an early stage caused the cost escalation.
As suggested by Marion Terrill and Lucille Danks (2016), the politicians know that
investment in social infrastructure projects can gain them popularity as they may provide
a healthy, fulfilled and productive life. Therefore, when scheduling a deadline of the
delivery, in some instances, planners put too much emphasis on political or economic
20 This table is an assembling of the keywords accounting for the four cases. In this table the bold cell shows the
keywords extracted from documents related to time pressure, whilst the grey shadow ones show the keywords referred
to the other contributors.
Why Social Infrastructure Projects Experience Cost Overrun?
88
elements so that they disregarded the feasibility of completing the project within a short
time depending on the existing construction technology and planned resources (Miranda
Sarmento & Renneboog, 2017). This happens in China when the government announces
a project at an early stage with no qualified feasibility study or a detailed design plan,
only to rectify the situation once as the project progresses and more information is
available. Moreover, according to Hirschman (2014) and his “Hiding Hand” theory,
people are usually over optimistic at the beginning when they have little knowledge about
the project and later when the full picture of possible problems unfolds, they will strive to
overcome them. Hence, people may reserve less construction time for a certain project in
the preliminary design stage than in the later stage when the design is completed (Love,
Zhou, et al., 2017).
After the construction inception of the construction, the delivery time frequently gets
postponed regardless of all the effort to deliver the project in line with the schedule
initially announced as it was far from the reality. Nevertheless, the public is not informed
with the whole process. All they hear from the media is that the social infrastructure
project suffers schedule overrun, which draws pressure on the project manager. CASE
#4clearly shows the dilemma of this situation: it creates favorable impression among the
public but criticism later towards the government when the project fails to fulfill its
commitment on time.
Sometimes a project could not postpone but adapt to the impractical timeline in order
to keep pace with other projects in the same portfolio. CASE #1 is a good example. Part
of an array of projects within a portfolio to deliver as early as possible, the museum
project there was limited time left for the design company to detail the drawing. The
project team in CASE #2 also had to deal with a tight schedule but for a different reason:
to reduce the negative impact of construction work in the vicinity.
Why Social Infrastructure Projects Experience Cost Overrun?
89
Idle Time
The notion of idle time refers to the time that a labor or machine is unproductive
during the duration of a project (Hapka, 1997). Various reasons include management
actions and the factors beyond their control (Christian & Hachey, 1995).
Idle time can emerge simply because the project team does not know what to do
next. In the story of CASE #1, when the contractor responsible for the foundation
excavation accomplished their work, the design company was still struggling with the
detailed drawing of the upper part. As a result, the contractor assigned to the construction
of the upper part of the museum had nothing to do except wait for the design company to
clarify the next step. As for CASE #2, the government urged the project team to begin the
construction work by May 1st, 2011, when the design company was still working on the
preliminary design documents. Regardless, the project was forced to go prematurely into
excavation. The unplanned and messy procedures may account for much of the delay.
Idle time is thus an unavoidable consequence of the unrealistic schedule discussed above.
If the design company had been given adequate time to complete their work, there would
not have been much idle time.
Factors beyond management control may include the delay of transporting materials
due to insufficient supply as in CASE #3 and weather disruption such as typhoon
(typhoon is prevailing in Xiamen city especially from August to October) as in CASE #4.
However, these factors had comparatively less influence on delaying the schedule
compared to management related factors.
Idle time is both a trigger of time pressure as well as a consequence of trying to
compensate for the lost time. The construction team has to “innovate” in some ways to
reduce the time, which may increase cost or creates a vicious circle.
Why Social Infrastructure Projects Experience Cost Overrun?
90
Utilization of Incomplete Design
To relieve time pressure and deliver the project on time, the project teams in three
out of four cases resorted to the same solution, which is using the incomplete design in
budget estimation and tendering process to accelerate the project progress. In CASE #1
and #2, the government and project manager deal with time pressure by entering the
bidding process regardless of incomplete design. The miscalculated workloads on the
bidding documents prepared on the preliminary design mislead the bidders. Along with
the process, the design company gradually modified and detailed the design, hence the
“additional workload”. Contractors finally found it impossible to finish the project in
accordance with the original budget.
Love, Smith, and Li (1999) in their study imply that the downstream quality costs of
the on-site construction will be cut significantly if more work is put on upstream design.
At the meantime, it has been pointed out by previous research that the budget overrun can
be traced back in the early stage, especially during the design process of the project
(Cantarelli, Flyvbjerg, van Wee, & Molin, 2010; Love, Ahiaga-Dagbui, et al., 2017). Our
findings are consistent with them, the main reason for cost overrun was the use of
incomplete design document in the tendering process. A qualified and integral design
plan should be able to provide precise information for the project, so that the budget
estimator can come up with a reliable budget figure. Unfortunately, in all cases, the
design plan used in estimating the conceptual budget did not fulfill that obligation.
While nowadays the RCF approach becomes popular in assisting the budget
estimation, without including the unique features of each project, this estimation may still
lacks credibility (Darwish, 2005; Jarkas, 2014; Minato, 2003). Without the support of
qualified design documents, the “guesstimating” occurs (Sing et al., 2012). Furthermore,
the “guesstimating” is systematically underestimated due to optimistic bias (Flyvbjerg,
Why Social Infrastructure Projects Experience Cost Overrun?
91
2018). When the design document is completed and the actual workload revealed, the
required cost of resources skyrockets consequently.
Long Period of Ex Ante Preparation
In general, social infrastructure projects experience prolonged preparation. During
this long-time preparation, the project is refined progressively. As pointed out by
evolutional theorists like Peter Love, cost overrun accumulates because of the
“evolution” of the project in term of the design, resources, requirements and scope.
During the evolution process, some events occur out of the blue and ultimately influence
the project and raise the cost (Van Wee, 2007). Among these factors, we note changes in
scope, change orders and inflation, which we discuss below.
Table 12 Keywords related to changes of orders/scope 21
21 This table assembles the keywords for the four cases. In this table the bold cell shows the keywords extracted from
documents related to change order/scopes, whilst the grey shadowed ones show the keywords referring to other
contributors.
Why Social Infrastructure Projects Experience Cost Overrun?
92
Changes in Scope
A social infrastructure project is initiated in order to satisfy a public need (A guide to
the project management body of knowledge (PMBOK® Guide).5th ed., 2013). For
example, a park provides an open space for exercising, a library an environment for
educating, and a low-cost housing program a shelter for people with low incomes. For
most social infrastructure projects, the scope is not always simple and straightforward to
determine. The scope of some projects evolves from time to time and covers more than
one social need (Atkinson, Crawford, & Ward, 2006). As witnessed in several studies
focusing on cost overrun in infrastructure projects, the change of scope accounts for the
amendment of the budget to a certain degree (Love, Zhou, et al., 2017). Take CASE #4
for example. During three years of preparation, the “Sponge City” strategy kicked in
which brought workload escalation and subsequently caused cost overrun.
Changes of Orders
A change of orders is a modification of workload that is added to or deleted from the
original contract of a project (Hanna, Russell, Nordheim, & Bruggink, 1999). According
to Love, Irani, et al. (2017), change of orders is one of the predominant cost overrun
factors. The evidence can be found in CASES #1 & 3.
In CASE #1, a change to upgrade the elevator system generate an extra 6.62 million.
Also, the change to add the outdoor landscaping work into the project counted for 5.92
million in budget adjustment. In the construction of the incineration plant (CASE #3), the
government modified the construction standards after the project inception. To adapt to
the new regulations, the project team had to upgrade the technology and materials. The
adjustment led to an increased investment of 7.07 million.
Inflation
Due to the long preparation time, the market price of labor and materials were
different from the time when the original conceptual budget was estimated. Love, Sing,
Why Social Infrastructure Projects Experience Cost Overrun?
93
Wang, et al. (2014) suggest that inflation should be excluded from cost overrun, because
it is hard to anticipate the escalation caused by inflation. However, in this study, inflation
is still considered as overrun as the taxpayers needed to pay more money than they were
told before the construction of the project.
The inflation problem haunted the museum construction in CASE #1. The inflation
of manpower and materials translated into a total of extra 6.21 million. The price of the
materials and equipment also increased by 100 million in the CASE #3.
Coordination among Stakeholders
It takes more than one party to accomplish a project. The figure below shows what
stakeholders were involved at different stages of the four case projects. The figure shows
six most important time nodes of the project, and each bar show the involvement period
of each stakeholder.
Figure 7 Stakeholders and involvements
As shown in the figure, besides the Reformation and Development Department and the
representative company, other stakeholders only took part in the project when they were
needed. The design company, construction contractor and the company who was in
charge of the future operations might overlap in their involvement, but they work
separately in general. Tasks conducted by different stakeholders needed to maintain a
certain degree of continuity. The drawing developed by the design company was used as
guidance for construction work carried out by the construction company, and the future
Why Social Infrastructure Projects Experience Cost Overrun?
94
operations company acted as the end-user, whose concerns should be fulfilled by the
design company. Love (2011), based on the examination of two social infrastructure
projects in Australia, suggested that the reason laid behind the omissions and errors of the
construction is the deficient communication between the design company and the
construction contractor (Love, 2011). It has also been shown in previous literature that
the overrun problem can be mitigated by close coordination between design and
construction parties (Minato, 2003).
As documented in the post-evaluation report of Case #1, the operations company did
not participate at the design stage was the reason why the museum experienced a massive
change of internal decoration. When the operations company was finally picked by the
government, the construction of the main building had already been completed. Though
the operations company was not satisfied with the design, there is little they could do. At
last, the government agreed to separate the internal decoration and exhibition fees from
the whole project, the operations company helped the design company revise the plan
with the extra budget. If the operations company were able to express their demand and
request at the beginning of the project, the overrun might not occur. As stated by
Loosemore (2016), the early involvement of the construction and operation teams at the
design stage will positively impact the project. Adopting the PPP procurement may also
help (Atmo, Duffield, Zhang, & Wilson, 2017; Ismail, 2013; Olusola Babatunde,
Opawole, & Emmanuel Akinsiku, 2012; Osei-Kyei & Chan, 2015; Rangel & Galende,
2010; Zhang, Gao, Feng, & Sun, 2015).
4.3. Stakeholders
In this section, we address the question of which stakeholders should take the
responsibility for cost overrun. In order to achieve this goal, we integrate the contributors,
the timeline and stakeholders together to see the relationship in between. Figure 7-10
exhibit CASE #1-4 respectively. In the figure, the white cell shows the stakeholders and
Why Social Infrastructure Projects Experience Cost Overrun?
95
the responsibility they carried in the project, on the other hand, the grey cell show
contributions caused the overrun.
Figure 8 CASE#1
Why Social Infrastructure Projects Experience Cost Overrun?
96
Figure 9 CASE#2
Why Social Infrastructure Projects Experience Cost Overrun?
97
Figure 10 CASE#3
Why Social Infrastructure Projects Experience Cost Overrun?
98
Figure 11 CASE#4
The table below maps cost overrun contributors and the role stakeholders play.
Table 13 the Cross-case analysis of contributors and stakeholders
CASE#1 CASE#2 CASE#3 CASE#4 Time pressure-unrealistic time schedule-premature announcement (CASE1,3&4)/ reduce
The ED company (planner); the Reformation and Development
The hospital (request); the Reformation and Development Department
The EE company (planner); the Reformation and Development
The Reformation and Development Department (planner/announcer)
Why Social Infrastructure Projects Experience Cost Overrun?
99
Disturbance (CASE#2)
Department (announcer)
(decision maker)
Department (announcer)
Idling time Inadequate detail in drawings (the design company)
Lack of proper solution for fire preventing system (the design company)
Sequence of design stage and construction stage
The ED company (proposer); the Reformation and Development Department (decision maker)
The Reformation and Development Department (decision maker)
The EE company (proposer); the Reformation and Development Department (decision maker)
Change orders Change in national standard; the Reformation and Development Department (decision maker)
Change in national standard; the Reformation and Development Department (decision maker)
Scope changes The provincial government (request)
Inflation of labor/material
External factor External factors
Coordination The design company & construction contractor; late involvement of the future operation company
Why Social Infrastructure Projects Experience Cost Overrun?
100
The initial schedule was planned in the feasibility report by different stakeholders
based on each case. According to the meeting memo, these initial schedules were then
used as a referencing timeline through the project lifecycle regardless of the fact that the
schedule planned on this stage was highly unreliable. This problem is quite obvious in
CASE#1 & 2. This schedule was unrealistic and unachievable, yet it was treated as an
ideal schedule that could be followed. As a result, pressure emerged to deliver the project
as early as possible. It can thus be argued that the decision maker, namely, the
Reformation and Development Department who insisted to stick with the unachievable
schedule, should take the major responsibility even though the schedule was planned by
various parties in different cases, rather than the planner.
Another problem causing the tight schedule is the idle time during construction. It
might seem that the problem was caused by lack of detailed drawing from the design
company, and that the design company should be responsible for it. The design company
did get criticized for failing to hand in the detailed drawing on time according to the
memo of CASE#1 &3. In reality, however, as shown in post-project evaluation report of
CASE #1, after the delivery of first stage design, the project manager only gave the
design company 25 days to detail the design. According to the author’s personal work
experience in architecture industry, it is impossible to accomplish this mission within 25
days. Hence, once again, the decision maker who set up the unachievable delivery
deadline should take the responsibility.
Other cost overrun contributors which concern the decision maker include its
decision to reverse the sequence of design and bidding for the construction and the
changed orders. These two contributors were both derived from the decision made by the
Reformation and Development Department, nevertheless, there was a slight difference
between them. The use of incomplete design for bidding was proposed by the agency
company in CASE#1 &3. On the other hand, the changed orders emerged from the
Why Social Infrastructure Projects Experience Cost Overrun?
101
modification of the national standard which was not in the control of the city government.
It was clearly stated in the red line documents distributed by the national government, so
the change of order to adapt to the new standard must be implemented. This was
unforeseen event, in other words, an external factor. Another sudden event that
negatively influenced CASE#4 was the forced change of the scope of the project to carry
out the “Sponge City” strategy. This scope change was not a deliberate act taken by the
Reformation and Development Department, but instead an environmental-friendly
strategy promoted nationally, so the Xiamen government had to comply with it.
The inflation problem was another external cost overrun contributor, though the
budget estimator was supposed to foresee the inflation and be prepared (Rothballer,
2012). The inflation, in most cases, stems from the turbulence of the marketplace (Buffie,
1995). Since the project usually goes through a long period of preparation, adding up to
the chance to be affected by such external environment as the market constantly changes.
In reality, the inflation accounts for a large portion of cost overrun.
As stated in the meeting memos, the design company and construction contractors
hardly had the opportunity to discuss about the project face to face. They participated in
the project during different stages. Although their involvement periods sometimes
overlapped each other, their communication was mainly through a third party: the project
manager. The project manager from the agency company handled the transition from the
design stage to construction stage, and thus it was the manager’s obligation to make sure
that the transition went smoothly, avoiding misunderstanding between the parties and
expanding coordination (Ford, 1995).
Why Social Infrastructure Projects Experience Cost Overrun?
102
5. Discussion
As noted earlier in this thesis, there are two main theoretical schools that prevail in
the literature to explain the cost overrun phenomenon: evolution and psycho theories. In
this section, we discuss the findings in light of these two schools of thought.
5.1. Evolution Theories
Evolution theorists advance that modification along the project lifecycle constitutes
the overarching reason for cost overrun (Ahiaga-Dagbui et al., 2017). As the word
“evolution” suggests, scholars from this school focus more on accumulating outcomes
resulted from a series of events within the duration of the project. In their opinion, even
with the most advanced forecasting technology, the budget and duration estimated in the
early stage are inherently unreliable and unstable due to a lack of adequate information
(Love et al., 2019). The project gradually becomes more well-defined as time goes by
and the final design is different from the conceptual design. Therefore, the budget
estimation in the late stage that covers all work costs is bound to be closer to the reality,
different from the budget estimated in the early stage using the sketchy design. The
differences in workload, design, definition and orders between the budget estimation at
the two stages of the project lifecycle are key reasons causing cost overrun (Ahiaga-
Dagbui & Smith, 2014b). The case analysis in this study suggests evolution theory fits
well in the context of the four social infrastructure projects in China.
First, changes of orders and scope occurred in all four cases and explained cost
overrun to a certain extent. Changes of orders and changes of scope result in the
increase/decrease of the workload of the project and are ultimately reflected in the final
cost.
In the table below, changes of orders and changes of scope are listed. The figure of
the overrun caused by changes of orders used below to calculate the portion is collected
Why Social Infrastructure Projects Experience Cost Overrun?
103
from the documents. By reviewing the documents, the study adds up figures which are
clearly described as the overrun caused by changes of orders or scope.
Table 14 Overrun caused by increased workload (change order/scope)
Type of change order or scope
Portion (overrun caused by change of orders divided by
total overrun) unit: thousand (RMB)
CASE#1 § added fire suppression gaseous systems
§ upgrade of the elevator equipment and the supporting electricity system
§ outdoor landscaping design § additional investment in interior
decoration (this part has been removed from the budget of the project and the city government decided to set the budget indecently for the interior decoration)
!"#$"&'(()*!+)#',-.!ℎ+*0'"1"(,'(#$"$+2!"#$"&'(()*
= 9755.71114108.82 = 8.55%
CASE#2 § upgrade of the fire preventing system § upgrade of technique of excavating
work § additional fees to accelerate the pile
foundation construction
!"#$"&'(()*!+)#',-.!ℎ+*0'"1"(,'(#$"$+2!"#$"&'(()*
=1266.142305.71 = 54.91%
CASE#3 § excavating standard improvement § upgrade of incineration technique
(towards eco-friendly)
!"#$"&'(()*!+)#',-.!ℎ+*0'"1"(,'(#$"$+2!"#$"&'(()*
=107.42515.16 = 20.85% CASE#3 § including the “sponge city” strategy
into the project scope § additional design fee and workload
for the change in outdoor landscaping (in order to cope with “sponge city” strategy)
§ additional fee in changing the paving material (in order to cope with “sponge city” strategy)
!"#$+,@)#$A'*$!+)#',-.!ℎ+*0'"1#!"B'
$"$+2!"#$+,@)#$A'*$
= 100%
Another cost overrun contributor which results in an extremely massive increase of
the workload is the utilization of incomplete design in the early budget estimation and
duration. This phenomenon can also be explained through the evolution theory. The
Why Social Infrastructure Projects Experience Cost Overrun?
104
essential argument in evolution theory is that the budget and duration will get modified as
the project is defined more and more precisely through the project lifecycle (Ahiaga-
Dagbui et al., 2017). Actually, as reiterated by Love and Ahiaga-Dagbui (2018), it is hard
and even unrealistic to forecast what will happen to a project at the initial stage when
nothing has been settled down. The fundamental root of the cost overrun and schedule
delay is the lack of complete information in the early project phase.
As found in the documentary analysis, when estimating the conceptual budget, the
budget estimation committee, based on the workload calculated by the fragmentary
documents, came up with a conceptual budget as early as possible and proceeded further
even though against a time pressure. At the meantime, with the anxiety to further shorten
the time, the agency company and city government tended to just grab the sketchy
drawing and used it in the bidding process rather than waiting for the design company to
offer a set of complete drawings qualified for tendering. However, the reality was that,
the workload calculated from the sketchy drawing which had been provided to the
competing contractors inevitably had errors and omissions. Therefore, once the design
company finished the design in which the real workload was taken into fuller
consideration, the workload calculated based on the detailed drawing was bound to
increase considerably compared to that which had been estimated previously. The
increased workload would definitely generate escalation on cost. Sometimes,
construction contractors were even forced to start the on-site work way ahead before the
detailed drawing (which is supposed to lead the construction work) was completed to
save time. This rashness in some cases even resulted in reworks (CASE#1) and idle time
(CASE#1 &2). Besides the additional labor and material fees derived from the increase of
workload, the design fees for the design company and the on-site management fees also
skyrocketed.
Why Social Infrastructure Projects Experience Cost Overrun?
105
Table 15 Overrun caused by increased workload (omission)
Increase of the workload
Portion (overrun caused by omission of workload divided by
total overrun) unit: thousand (RMB)
CASE#1
§ additional design fees for the design company
§ additional labor and material fees
§ additional on-site management
!"#$"&'(()*!+)#',-."AC##C"*
$"$+2!"#$"&'(()*
= 63442.01114108.82 = 55.60% CASE#2 !"#$"&'(()*!+)#',
-."AC##C"*$"$+2!"#$"&'(()*
= 395.882305.71 = 17.17% CASE#3 !"#$"&'(()*!+)#',
-."AC##C"*$"$+2!"#$"&'(()*
=291.07515.16 = 56.50%
The two contributors engendered cost overrun in the same way, that is, generating a
growth in work costs in addition to the existing workload. However, there is a subtle
difference. The increase of workload stemmed from changes of orders/scope driven by
unforeseen events/changes. On the other hand, the growth of workload originated from
the utilization of sketchy drawing or in essence an omission. This “additional” workload
was a part of the project from the very beginning, yet was not noticed by the project team
until the design had been completed.
5.1.1. The paradox of narrowing down the budget
Although evolution theory works for explaining cost overrun in social infrastructure
projects in China, there is a small paradox this study would like to point out.
In China, there are three stages of budget – the preliminary budget, the design budget
and the conceptual budget. To ensure a sound investment of the money from taxpayers,
the Chinese government enforces strict management system on the budget estimation of
Why Social Infrastructure Projects Experience Cost Overrun?
106
the infrastructure project. The Chinese government requires that the budget estimation
committee and the agency company narrow down the budget stage by stage. In other
words, the budget should be less than or equal to the figure in the last stage during the
“evolution”. Whenever the budget increases, the project promoter is required to file a
report explaining about the increment. This budget management system intends to
prevent the project budget from increasing without a compelling reason.
Nevertheless, according to evolutional theorists, however, as more detailed project
information come into light, the budget is supposed to increase rather than decrease
(Love, Smith, Simpson, Regan, & Olatunji, 2015). Interestingly, at the same time, the
situation found in the practical cases in this study shows the same development path as
pointed out by evolution theorists. Indeed, with the increase in workload induced by
changes of scope and changes of orders, cost exceeded the original conceptual budget in
all four cases. Hence, the following paradox emerged: the government’s requirement
contradicted the academic theory and reality. The intension to prevent the budget
escalation turns out to be in vain in these four cases.
5.2. Psycho theories
Psycho theorists hold that cost-overrun is due to budget underestimation (Flyvbjerg,
2007b). Optimistic bias and strategic misrepresentation are commonly mentioned in the
literature on cost overrun in social infrastructure projects. Optimistic bias is a cognitive
bias that makes people believe that the task they are taken is less likely to experience a
negative event or end up with a negative outcome (Flyvbjerg, 2007a). Strategic
misrepresentation is an unethical action undertaken by some project planners to promote
a project. Similar to optimistic bias, strategic misrepresentation is also related to budget
underestimation. Their difference is that the optimistic bias is unconscious, while
strategic misrepresentation is deliberate deception to make the project profitable and
favorable on paper (Flyvbjerg, 2007a).
Why Social Infrastructure Projects Experience Cost Overrun?
107
No direct evidence can be found in the documentary analysis that suggests the
existence of optimistic bias (delusion) and strategic misrepresentation (deception) in the
four cases. That is also a limitation which can be found in most studies that try to verify
the psycho theories, since it is common that people refuse to admit that they tell a lie.
However, the tendency of consistent overrun in social infrastructure projects in China
seems in line with the pattern revealed by psycho theorists like Bent Flyvbjerg. Also,
during the case study, a few discoveries indicate that some action taken by the project
promoters is questionable and worth considering.
First, even the previous evidence clearly shows that an action has a tendency to cause
the cost overrun, the project team insists to adopt it again and again without any
amendment and consequently leads to overrun without exception. From the documentary
analysis and this discussion of the contributors, it is inferred from that the government
frequently resorted to a solution, which involved a sketchy design in the bidding of
construction contractors to save as much time as possible. However, in three cases, this
measure not only failed to reduce the time but also caused massive omission of workload
when signing the construction contract, from which severe cost escalation stemmed. It is
clear that an early start of bidding before having a fully-prepared design document will
do more harm than good. It is worth pondering why the government sticks to this
“solution”. As described in the section about the responsibility of stakeholders, it is
known that this “solution” was proposed by the agency company and was approved by
the Reformation and Development Department. Nevertheless, as evidence showed that
the “solution” was ineffective, the project promoter insisted that the project could save
more time regardless of the idle time which would emerge later.
Second, the paradox in the rules set by the Chinese government to narrow down the
budget stage by stage also reflects the possible existence of strategic misrepresentation or
deception. In order to fulfill the mission of narrowing down the budget, the budget
Why Social Infrastructure Projects Experience Cost Overrun?
108
estimation committee tended to overestimate the conceptual budget slightly in the early
phase. CASE#4 witnessed a surprising cost underrun despite a massive increase of
workload due to the changes of scope. The question then is: was the original conceptual
budget realistic? Did the budget estimation committee excessively overestimate budget to
reserve more room for the narrowing down of the budget? This remains to be ascertained.
Furthermore, previous studies on strategic misrepresentation focus mostly on
deception in budget estimation at the proposal stage in an attempt to increase the chance
of the project approval (Flyvbjerg, 2007b). However, due to the unique budget adjusting
mechanism, the two findings discussed above could happen at any phase of the project
lifecycle.
Still, as shared by many studies about psycho theorists, scholars are unable to force
project stakeholders to acknowledge whether there is delusion or deception, or optimistic
bias or strategic misrepresentation or to deny their existence (Flyvbjerg, 2013). It is not
easy to find direct evidence of strategic misrepresentation, so this study is only able to
catch some signals of the existence of it.
Table 16 the Comparison Between Two Schools of Thought
Evolution Theorist Psycho Theorist
§ changes of order
§ changes of scope
§ unrealistic schedule arrangement
§ utilization of incomplete design
§ overestimation of the budget at the
early stage
§ Evidence unavailable
Why Social Infrastructure Projects Experience Cost Overrun?
109
6. Conclusion
This study sought to understand why social infrastructure projects experience cost
overrun in the context of China. To answer this question, a literature review about the
causes of cost overrun was conducted. From the literature review, it was concluded that
there are two main schools of thought, namely, evolution and psycho theories.
Second, this study undertook a case study, using documentary analysis to explore the
causes of cost overrun for four social infrastructure projects that were completed in the
city of Xiamen in China. Case documentation includes feasibility study reports,
application and approval of preliminary budget, application and approval of the
conceptual budget, application and approval of the adjustment of the conceptual budget,
meeting memos, post-evaluation reports and final audit reports. This study coded the
documents, highlighted and counted the keywords related to cost overrun, and identified
contributors that increased the cost of projects. Three cases (#1, 2 & 3) out of four
experienced severe cost overrun (cases #1, 2 & 3). Case # 4, though delivered within
budget, witnessed dramatic budget adjustment and re-allocation.
Last, taking a cue from the existing two schools of thought, this study concluded
with key explanations for cost overrun in the four social infrastructure projects examined
in China. Besides the main research question, this study also analyzed the responsibilities
of different stakeholders with regards to cost overrun. This section reviews and discusses
the findings and limitations of the case study and offers suggestions for future research as
well as practical implications.
Why Social Infrastructure Projects Experience Cost Overrun?
110
6.1. The causes of cost overrun
This study identified four reasons why cost overrun occurred in the four cases: time
pressure, changes during the long duration, inflation and coordination. But keywords
counting revealed that the first two are the major reasons for the overrun.
6.1.1. Time pressure
Time pressure and equivalent keywords have been frequently mentioned in the
documents. The obligation to stick to prematurely announced delivery dates and the
complexity of on-site management are the root causes of the time pressure. In order to
relieve the pressure, the workload was increased due to the utilization of an incomplete
design for estimation and tendering process and finally more time was idled away. The
figure below shows the how time pressure, premature announcement, idle time and
change of order interacting with each other.
Figure 12 Time Pressure
Why Social Infrastructure Projects Experience Cost Overrun?
111
6.1.2. Changes of orders and project scope
Change of orders/scope happened in all four cases and caused a dramatic workload
increase. Those changes led to additional investments in labor, material and equipment
which intensified the cost overrun. Also, in China, every change of orders/scope needs to
be examined through a lengthy approval procedure by many administrations. The red
tape induced idle time which was an aggravation to time pressure and ultimately further
eroded the project performance.
6.1.3. Theoretical contribution
The literature on the reasons of cost overrun can be divided into three categories:
evolution theories, psycho theories and other non-mainstream theories. Evolution theories
and psycho theories differ not only in the way they calculate overrun and their respective
points of reference (Invernizzi et al., 2018), but also in the framework of causes of
overrun they consider. The evolution theorists, as the word “evolution” suggests, believe
that change along the project lifecycle is the main influencing factor in causing overrun
(Ahiaga-Dagbui & Smith, 2014a). Nevertheless, the psycho theorists put the blame on the
behavioral factors such as optimistic bias and strategic misrepresentation (Cantarelli,
Flybjerg, Molin, & Van Wee, 2013a).
In this study, it is found that evolution theory fits better the data than its counterpart
psycho theory in explaining cost overrun in Chinese social infrastructure projects.
Documentary evidence suggests cost overrun can be explained by evolution theory, while
only a faint trace of psycho theory could possibly be related to strategic misrepresentation
and optimistic bias. Indeed, the study found that the two main reasons explaining cost
overrun are time pressure and changes of orders/scope, which can be traced back to
evolution theory (Hanna et al., 1999; Love, Irani, et al., 2017).
Why Social Infrastructure Projects Experience Cost Overrun?
112
6.2. Practical Implications
§ Avoid the premature announcement of the delivery date
Premature announcement was the main reason why the project team was always
under enormous time pressure. In most cases, time pressure forced the project team to
speed up procedure in spite of a poor work quality and therefore exerted negative impact
on the project. Therefore, in order to guarantee the project’s quality and mitigate cost
overrun, the government should not release the deadline to the public before the project
planner is equipped with adequate information to forecast a reliable and steady delivery
date.
§ Leave the design company enough time to complete their work before rush into next
stage.
A well-organized project schedule should leave enough time for each stakeholder to
carry out their own work and thus form a solid foundation for next step. In the case study
analysis, it is found that the government did not wait for the design company to finish the
detailed drawings in order to cut the time. They instead brought the sketchy drawing to
the budget estimation committee and the construction contractor. This reckless action
caused errors in workload determination. Moreover, the government might even force the
construction team to start their work without a clear instruction from the drawings, which
resulted in reworks and much time being idled, intensifying time pressure. Therefore, this
study appeals to the government to leave adequate time, so that the budget estimator can
be capable of coming up with a correct estimation and the construction contractor can be
fully prepared for the project.
§ The end-user should be involved at an early stage
In social infrastructure contexts, the end-user is the future operator of the facility. For
example, the end-user of the science museum in case #1 is the curator; the garage and
reception building construction work in case #2 is the hospital; the incineration plant in
Why Social Infrastructure Projects Experience Cost Overrun?
113
case #3 is the EE company; the campus construction project in case #4 is the president.
The end-user has all the expertise required for operating the facility and therefore they
have a good knowledge of what the project should fulfill. The project planner and
designer have to take their input into consideration. The case study in this report clearly
stated the benefit of early involvement of the end-user. The science museum experienced
massive interior space transformation, which was both costly and time-consuming, just
because the operation company was picked by the government after the construction
phase and the operator was unable to share their opinions and make change requests in
the design phase. In the case of the incineration plant, it was managed and constructed by
its end-user. Although this project also suffered from changes of orders, none of the
change was issued by the end-users.
§ Be prepared for unexpected events
It is vital for project planners to identify that a change in the project lifecycle is
inevitable, so it is important to integrate a change management plan to prepare for
unexpected changes that can potentially lead to subsequent cost overrun. The
management plan can include an independent contingency fund that would cater to
changes especially the sudden ones. A contingency preparation means that the project can
have some breathing space when encountering “black swan” incidence (Love, Sing,
Carey, & Kim, 2014).
§ The specialty of conceptual budget overrun
Through the research, we found that, the scale of the overrun that took place in the
Chinese social infrastructure projects appears smaller than that in the West, and the
conceptual budget system in Chinese projects might be the main reason. The Chinese
authority puts much emphasis on the conceptual budget and takes it as a warning line for
the budget management, so to guard against cost increases. It comes from the third
Why Social Infrastructure Projects Experience Cost Overrun?
114
budget estimation stage, which is based on the construction blueprint and the workload
calculation. Therefore, this budget is supposed to reflect the reality accurately. During the
project lifecycle, once the cost exceeds the conceptual budget, the government authority
needs to figure out reasons for the cost escalation and adjusts the conceptual budget
according to the situation so as to have the adjusted conceptual budget closer to the final
cost. This explains why, the cost overrun calculated using the adjusted figure might be
less than that in existing studies using data from the West.
6.3. Limitations of the study
This research conducted a case study through documentary analysis approach.
Although the documents used in the case study helped to address the reasons for cost
overrun to a great extent, it still has its own limitations. Data collection techniques like
interviews might generate new insights through a direct and face to face contact with
diverse interviewees. Thus, the validity of the study’s findings can be further
strengthened by interviews with stakeholders involved in the four social infrastructure
projects. Another limitation is that documents are likely to reflect the issues that their
authors seek to highlight, not the ones they choose to avoid. In this regard, both the
documentary and interview analysis may fall short when it comes to revealing strategic
misrepresentation in infrastructure projects, which remain a key empirical challenge.
Secondary, the research limited the case sample to four projects from one city due to
data accessibility. Increasing the number of projects across broader geographical regions
would lead to a more robust representativeness of the Chinese social infrastructure
industry.
Why Social Infrastructure Projects Experience Cost Overrun?
115
Next, the research focused on cases with massive budget adjustment. A comparative
study on social infrastructure projects with small budget adjustment and those with a
sound budget execution will add more insight into this research question.
Finally, this thesis adopted merely qualitative approach (case study) in addressing the
research question, while the existing literature on cost overrun focused more on
quantitative approaches, which makes the analysis approach of this thesis less informed.
In the future study, literatures discussed relevant topics which put an emphasis on
conducting case study like works from Nuno Gil should be taken into consideration.
6.4. Suggestions for future research
Besides the four cases introduced before, the author also examined 10 more social
infrastructure projects of Xiamen city. During the study, an interesting pattern emerged.
The project type with more previous experience normally yielded a better cost
performance. This conjecture is proposed based on two observations.
§ In the 2007-2017 decade in Xiamen city, there have been 53 projects related to campus
construction, yet the figures for museum-related projects and incineration plant
projects were only four and five respectively ("Annual Report for Infrastruction
Project," 2017). The number of campus construction projects is ten times that of
museum-related projects.
§ Within the ten cases, four campus construction projects (including CASE #4)
experienced budget underrun, while the museum construction project overrun (CASE
#1) its budget dramatically.
It seems that the projects with unique characteristics are more likely to encounter
cost overrun because of their higher levels of complexity or uncertainty compared to the
projects which are more general (Love, Ika, Sing, & Newton, 2019; Love, Ika, & Ahiaga-
Dagbui, 2019; Love, Ika, & Sing, 2020). While it has been long been argued that
Why Social Infrastructure Projects Experience Cost Overrun?
116
Reference Class Forecasting (hereinafter RCF) can be useful to capture the previous
experience of as-built projects and have positive influence on cost estimation (Flyvbjerg,
2007a; Flyvbjerg et al., 2017), it does not account for complexity. These observations
suggest a possibility to connect the two schools together to further explore the
relationship between complexity, cost overrun and RCF estimation approach.
Why Social Infrastructure Projects Experience Cost Overrun?
117
Appendix: CRS Code of Social Infrastructure Facility
Why Social Infrastructure Projects Experience Cost Overrun?
118
Why Social Infrastructure Projects Experience Cost Overrun?
119
Why Social Infrastructure Projects Experience Cost Overrun?
120
Why Social Infrastructure Projects Experience Cost Overrun?
121
Why Social Infrastructure Projects Experience Cost Overrun?
122
Why Social Infrastructure Projects Experience Cost Overrun?
123
Why Social Infrastructure Projects Experience Cost Overrun?
124
Why Social Infrastructure Projects Experience Cost Overrun?
125
Why Social Infrastructure Projects Experience Cost Overrun?
126
Why Social Infrastructure Projects Experience Cost Overrun?
127
Why Social Infrastructure Projects Experience Cost Overrun?
128
Reference
2018 Central Construction Expenditure Budget Table. (2018). In M. o. F. o. t. P. s. R. o. China (Ed.).
About the OECD. Retrieved from http://www.oecd.org/about/ Adafin, J., Rotimi, J. O., & Wilkinson, S. (2015). Why do the design stage elemental cost
plan and final tender sum differ in New Zealand? Journal of financial Management of property
Construction Economics, 20(2), 116-131. Ahiaga-Dagbui, D. D., Love, P. E., Smith, S. D., & Ackermann, F. (2017). Toward a
systemic view to cost overrun causation in infrastructure projects: A review and implications for research. Project management journal, 48(2), 88-98.
Ahiaga-Dagbui, D. D., & Smith, S. D. (2014a). Dealing with construction cost overruns using data mining. Construction Management
Economics, Management and Financial Markets, 32(7-8), 682-694. Ahiaga-Dagbui, D. D., & Smith, S. D. (2014b). Exploring escalation of commitment in
construction project management: case study of the Scottish Parliament project. Ahiaga-Dagbui, D. D., & Smith, S. D. (2014c). Rethinking construction cost overruns:
cognition, learning and estimation. Journal of Financial Management of Property Construction Economics, 19(1), 38-54. Al-Hazim, N., & Salem, Z. A. (2015). Delay and cost overrun in road construction
projects in Jordan. International Journal of Engineering Technology, 4(2), 288. Ameyaw, E. E., Chan, A. P., Owusu-Manu, D.-G., & Coleman, E. (2015). A fuzzy model
for evaluating risk impacts on variability between contract sum and final account in government-funded construction projects. Journal of facilities management, 13(1), 45-69.
Anbari, F. T., Carayannis, E. G., & Voetsch, R. J. (2008). Post-project reviews as a key project management competence. Technovation, 28(10), 633-643.
Andrić, J. M., Mahamadu, A.-M., Wang, J., Zou, P. X., & Zhong, R. (2019). The cost performance and causes of overruns in infrastructure development projects in Asia. Journal of Civil Engineering
Management, 25(3), 203-214. Annual Report for Infrastruction Project. (2017). Retrieved from
http://dpc.xm.gov.cn/xxgk/wzndbg/201801/t20180130_1844820.htm Atkinson, R., Crawford, L., & Ward, S. (2006). Fundamental uncertainties in projects and
the scope of project management. International journal of project management, 24(8), 687-698.
Why Social Infrastructure Projects Experience Cost Overrun?
129
Atmo, G. U., Duffield, C., Zhang, L., & Wilson, D. I. (2017). Comparative performance of PPPs and traditional procurement projects in Indonesia. International Journal of Public Sector Management, 30(2), 118-136.
Auditor General of Western Australia. (2012). Retrieved from https://audit.wa.gov.au/wp-content/uploads/2013/05/report2012_121.pdf
Australia, C. I. D. A. a. M. B. (1995). Measuring up or muddling through: best practice in the Australian non-residential construction industry. Sydney,
Australia Baccarini, D., & Love, P. E. (2013). Statistical characteristics of cost contingency in
water infrastructure projects. Journal of Construction Engineering Management, 140(3), 04013063. Bordat, C., McCullouch, B., & Sinha, K. (2004). An analysis of cost overruns and time
delays of INDOT projects. Joint Transportation Research Program, 11. Budget 2018: Annual infrastructure spending hiked to Rs 6 lakh crore. (2018). Hindustan
Time. Retrieved from https://www.hindustantimes.com/india-news/budget-2018-annual-infrastructure-spending-hiked-to-rs-6-lakh-crore/story-qzLWaH9Ipdvy8FYe48MCkP.html
Buffie, E. F. (1995). Public investment, private investment, and inflation. Journal of Economic Dynamics and Control, 19(5-7), 1223-1247.
Calderón, C., Moral‐Benito, E., & Servén, L. (2015). Is infrastructure capital productive? A dynamic heterogeneous approach. Journal of Applied Econometrics, 30(2), 177-198.
Calia, M. (2018). Trump pushes infrastructure plan, but says it will likely have to wait until after the midterms. CNBC. Retrieved from https://www.cnbc.com/2018/03/29/trump-infrastructure-plan-will-likely-wait-until-after-the-midterms.html
Cantarelli, C. C., Flybjerg, B., Molin, E. J., & Van Wee, B. (2013a). Cost overruns in large-scale transportation infrastructure projects: explanations and their theoretical embeddedness. arXiv preprint arXiv:1307.2176.
Cantarelli, C. C., Flybjerg, B., Molin, E. J., & Van Wee, B. (2013b). Cost overruns in large-scale transportation infrastructure projects: Explanations and their theoretical embeddedness.
Cantarelli, C. C., Flyvbjerg, B., & Buhl, S. L. (2012). Geographical variation in project cost performance: the Netherlands versus worldwide. Journal of Transport Geography, 24, 324-331.
Cantarelli, C. C., Flyvbjerg, B., van Wee, B., & Molin, E. J. (2010). Lock-in and its influence on the project performance of large-scale transportation infrastructure projects: investigating the way in which lock-in can emerge and affect cost overruns. Environment and planning B: planning and design, 37(5), 792-807.
Why Social Infrastructure Projects Experience Cost Overrun?
130
Cantarelli, C. C., Molin, E. J., van Wee, B., & Flyvbjerg, B. (2012). Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases. Transport policy, 22, 49-56.
Cantarelli, C. C., van Wee, B., Molin, E. J., & Flyvbjerg, B. (2012). Different cost performance: different determinants?: The case of cost overruns in Dutch transport infrastructure projects. Transport policy, 22, 88-95.
Capital Budgeting Group. (1984). Infrastructure Budget: China Financial and Economic Publishing House.
Casey, D., & Houghton, C. J. N. R. (2010). Clarifying case study research: examples from practice. 17(3).
China Statistical Yearbook. (2016). Retrieved from National Bureau of Statistics: http://www.stats.gov.cn/tjsj/ndsj/
Christian, J., & Hachey, D. (1995). Effects of delay times on production rates in construction. Journal of Construction Engineering and Management, 121(1), 20-26.
Council, L. (2012). Rail infrastructure project costing in New South Wales. Inquiry of the General Purpose Standing Committee(3).
Curry, B. (2019). City of Ottawa increases transit funding by $7.5-million in face of public anger over problems with new LRT system. The Globe and Mail. Retrieved from https://www.theglobeandmail.com/canada/article-city-of-ottawa-increases-transit-funding-by-75-million-in-face-of/
Darwish, M. I. (2005). Factors affecting design documentation quality in construction industry.
De Marco, A., Rafele, C., & Thaheem, M. J. (2015). Dynamic management of risk contingency in complex design-build projects. Journal of Construction Engineering Management, 142(2), 04015080.
Devi, A. C., & Ananthanarayanan, K. (2017). Factors influencing cost over-run in Indian construction projects. Paper presented at the MATEC Web of Conferences.
Dong, G. (2009). Strengthen budget management and effectively control project cost. Technology Information, 28.
Eberts, R. W. (1990). Public infrastructure and regional economic development. Economic Review, 26(1), 15-27.
Eliasson, J., & Fosgerau, M. (2013). Cost overruns and demand shortfalls–deception or selection? Transportation Research Part B: Methodological, 57, 105-113.
Fazekas, M., & Tóth, B. (2018). The extent and cost of corruption in transport infrastructure. New evidence from Europe. Transportation Research Part A: Policy Practice, 113, 35-54.
Feasibility Study. (2020). Retrieved from http://dpc.xm.gov.cn/xxgk/xxgkzn/
Why Social Infrastructure Projects Experience Cost Overrun?
131
Fereday, J., & Muir-Cochrane, E. (2006). Demonstrating rigor using thematic analysis: A hybrid approach of inductive and deductive coding and theme development. International journal of qualitative methods, 5(1), 80-92.
Flyvbjerg, B. (2007a). Eliminating bias in early project development through reference class forecasting and good governance. KJ Sunnev rag, ed. Beslutninger pa svakt informasjonsgrunnlag. Trondheim, Norway, 90-110.
Flyvbjerg, B. (2007b). Policy and planning for large-infrastructure projects: problems, causes, cures. Environment Planning B: planning
design, 34(4), 578-597. Flyvbjerg, B. (2009). Survival of the unfittest: why the worst infrastructure gets built—
and what we can do about it. Oxford review of economic policy, 25(3), 344-367. Flyvbjerg, B. (2013). How planners deal with uncomfortable knowledge: The dubious
ethics of the American Planning Association. Cities, 32, 157-163. Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview.
Project management journal, 45(2), 6-19. Flyvbjerg, B. (2018). Planning Fallacy or Hiding Hand: which is the better explanation?
arXiv preprint arXiv:1802.09999. Flyvbjerg, B., Ansar, A., Budzier, A., Buhl, S., Cantarelli, C., Garbuio, M., . . . Lunn, D.
(2018). Five things you should know about cost overrun. Transportation Research Part A: Policy Practice, 118, 174-190.
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American planning association, 68(3), 279-295.
Flyvbjerg, B., Hon, C.-k., & Fok, W. H. (2017). Reference class forecasting for Hong Kong's major roadworks projects.
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2003). How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), 71-88.
Flyvbjerg, B., Skamris Holm, M. K., & Buhl, S. L. (2004). What causes cost overrun in transport infrastructure projects? Transport Reviews, 24(1), 3-18.
Foote, A. (2019). Woe-train: Ottawa's LRT troubles, by the numbers. CBC News. Retrieved from https://www.cbc.ca/news/canada/ottawa/ottawa-otrain-problem-issue-graph-numbers-1.5348331
Ford, D. N. (1995). The dynamics of project management: an investigation of the impacts of projects process and coordination on performance: Massachusetts Institute of Technology Cambridge, MA.
Gil, N. (2016). A collective-action perspective on the planning of megaprojects. In The Oxford handbook of megaproject management (pp. 259-286): Oxford University Press Oxford.
Why Social Infrastructure Projects Experience Cost Overrun?
132
Gil, N., & Lundrigan, C. (2012). The leadership and governance of megaprojects. Manchester: Manchester University.
Gilovich, T., Griffin, D., & Kahneman, D. (2002). Heuristics and biases: The psychology of intuitive judgment: Cambridge university press.
A guide to the project management body of knowledge (PMBOK® Guide).5th ed. (2013). Newtown Square: Project Management Institute, Inc.
Hanna, A. S., Russell, J. S., Nordheim, E. V., & Bruggink, M. J. (1999). Impact of change orders on labor efficiency for electrical construction. Journal of Construction Engineering and Management, 125(4), 224-232.
Hansen, N. M. (1965). Unbalanced growth and regional development. Economic inquiry, 4(1), 3-14.
Hapka, R. J. (1997). Remote control of engine idling time. In: Google Patents. Heckman, J. (1979). Sample selection bias as a specification error. Econometrica:
Journal of the econometric society, 153-161. Hegazy, T. (2002). Computer-based construction project management: Prentice Hall
Upper Saddle River, NJ. Houghton, C., Casey, D., Shaw, D., & Murphy, K. (2013). Rigour in qualitative case-
study research. Nurse researcher, 20(4). Hrushka, A. (2017). A Year in Review: Honolulu Rail Project. In: Pacific Business
News, 27th December, Available at: http://www. bizjournals …. Hu, K. (2017). Characteristics, Contributions and Trends of China's Express Industry
Development. China Development Observation. Retrieved from http://www.chinado.cn/?p=5485
Hwang, B.-G., Zhu, L., Wang, Y., & Cheong, X. (2017). Green building construction projects in Singapore: Cost premiums and cost performance. Project Management Journal, 48(4), 67-79.
Invernizzi, D. C., Locatelli, G., & Brookes, N. (2018). Cost overruns–helping to define what they really mean.
Investing in Canada plan Bilateral Agreements. (2018). Retrieved from https://www.infrastructure.gc.ca/prog/programs-infc-summary-eng.html#icip
Investing in Social Infrastructure. (2018). Retrieved from https://www.infrastructure.gc.ca/plan/si-is-eng.html
Ismail, S. (2013). Critical success factors of public private partnership (PPP) implementation in Malaysia. Asia-Pacific Journal of Business Administration, 5(1), 6-19.
ISTAT. (2006). Rome Jarkas, A. M. (2014). Factors impacting design documents quality of construction
projects. International Journal of Design Engineering, 5(4), 323-343.
Why Social Infrastructure Projects Experience Cost Overrun?
133
Kahneman, D., & Egan, P. (2011). Thinking, fast and slow (Vol. 1): Farrar, Straus and Giroux New York.
Ke, Y., Wang, S., Chan, A. P., & Cheung, E. (2011). Understanding the risks in China's PPP projects: ranking of their probability and consequence. Engineering, Construction and Architectural Management, 18(5), 481-496.
Khan, S., & VanWynsberghe, R. (2008). Cultivating the under-mined: Cross-case analysis as knowledge mobilization. Paper presented at the Forum qualitative Sozialforschung/forum: Qualitative social research.
Koch, C. (2014). The more the better? Investigating performance of the Danish and Swedish offshore wind farm cluster. Journal of Financial Management of Property, 19(1), 24-37.
Liao, P.-C., Lei, G., Fang, D., & Liu, W. (2014). The relationship between communication and construction safety climate in China. KSCE Journal of Civil Engineering, 18(4), 887-897.
Lind, H., & Brunes, F. (2015). Explaining cost overruns in infrastructure projects: a new framework with applications to Sweden. Construction management
Economics, Management and Financial Markets, 33(7), 554-568. Liu, L., & Napier, Z. (2010). The accuracy of risk‐based cost estimation for water
infrastructure projects: preliminary evidence from Australian projects. Construction Management
Economics, Management and Financial Markets, 28(1), 89-100. Liu, L., Wehbe, G., & Sisovic, J. (2010). The accuracy of hybrid estimating approaches:
a case study of an Australian state road & traffic authority. The Engineering Economist, 55(3), 225-245.
Loosemore, M. (2016). Social procurement in UK construction projects. International journal of project management, 34(2), 133-144.
Love, P. E. (2002). Influence of project type and procurement method on rework costs in building construction projects. Journal of construction engineering
management, 128(1), 18-29. Love, P. E. (2011). Plugging the gaps’ between optimum bias and strategic
misrepresentation and infrastructure cost overruns. Procedia engineering, 14, 1197-1204.
Love, P. E., Ahiaga-Dagbui, D., Welde, M., & Odeck, J. (2017). Light rail transit cost performance: Opportunities for future-proofing. Transportation Research Part A: Policy
Practice, 100, 27-39. Love, P. E., & Ahiaga-Dagbui, D. D. (2018). Debunking fake news in a post-truth era:
The plausible untruths of cost underestimation in transport infrastructure projects. Transportation Research Part A: Policy Practice, 113, 357-368.
Why Social Infrastructure Projects Experience Cost Overrun?
134
Love, P. E., Ahiaga-Dagbui, D. D., & Irani, Z. (2016). Cost overruns in transportation infrastructure projects: Sowing the seeds for a probabilistic theory of causation. Transportation Research Part A: Policy Practice, 92, 184-194.
Love, P. E., Edwards, D. J., & Irani, Z. (2012). Moving beyond optimism bias and strategic misrepresentation: An explanation for social infrastructure project cost overruns. IEEE Transactions on Engineering Management, 59(4), 560-571.
Love, P. E., Edwards, D. J., & Smith, J. (2005). Contract documentation and the incidence of rework in projects. Architectural Engineering
Design Management, 1(4), 247-259. Love, P. E., Irani, Z., Smith, J., Regan, M., & Liu, J. (2017). Cost performance of public
infrastructure projects: the nemesis and nirvana of change-orders. Production Planning Control, 28(13), 1081-1092.
Love, P. E., & Li, H. (2000). Overcoming the problems associated with quality certification. Construction Management
Economics, 18(2), 139-149. Love, P. E., & Li, H. (2000). Quantifying the causes and costs of rework in construction.
Construction Management Economics, Management and Financial Markets, 18(4), 479-490. Love, P. E., Mandal, P., & Li, H. (1999). Determining the casual structure of rework in
construction projects. Constr. Manage. Econ, 17(4), 505-517. Love, P. E., Sing, C.-P., Carey, B., & Kim, J. T. (2014). Estimating construction
contingency: Accommodating the potential for cost overruns in road construction projects. Journal of Infrastructure Systems, 21(2), 04014035.
Love, P. E., Sing, C.-P., Wang, X., Irani, Z., & Thwala, D. W. (2014). Overruns in transportation infrastructure projects. Structure Infrastructure Engineering, 10(2), 141-159.
Love, P. E., Sing, M. C., Ika, L. A., & Newton, S. (2019). The cost performance of transportation projects: The fallacy of the Planning Fallacy account. Transportation Research Part A: Policy Practice, 122, 1-20.
Love, P. E., Smith, J., & Li, H. (1999). The propagation of rework benchmark metrics for construction. International Journal of Quality & Reliability Management.
Love, P. E., Smith, J., Simpson, I., Regan, M., & Olatunji, O. (2015). Understanding the landscape of overruns in transport infrastructure projects. Environment and planning B: planning and design, 42(3), 490-509.
Love, P. E., Zhou, J., Edwards, D. J., Irani, Z., & Sing, C.-P. (2017). Off the rails: The cost performance of infrastructure rail projects. Transportation Research Part A: Policy Practice, 99, 14-29.
Why Social Infrastructure Projects Experience Cost Overrun?
135
Mansfield, N. R., Ugwu, O., & Doran, T. (1994). Causes of delay and cost overruns in Nigerian construction projects. nternational journal of project Management, 12(4), 254-260.
Minato, T. (2003). Design documents quality in the Japanese construction industry: factors influencing and impacts on construction process. International journal of project management, 21(7), 537-546.
Miranda Sarmento, J., & Renneboog, L. (2017). Cost overruns in public sector investment projects. Public Works Management
Policy, 22(2), 140-164. Miranda Sarmento, J., Renneboog, L. J. P. W. M., & Policy. (2017). Cost overruns in
public sector investment projects. 22(2), 140-164. Moteff, J., & Parfomak, P. (2004). Critical infrastructure and key assets: definition and
identification. Myers, B., Fisher, R., Pickering, S., & Garnett, S. (2014). Post-project evaluation of the
sustainability of development project outcomes: a case study in eastern Indonesia. Development in Practice, 24(3), 379-389.
Odeck, J. (2004). Cost overruns in road construction—what are their sizes and determinants? Transport policy, 11(1), 43-53.
Odeyinka, H., Larkin, K., Weatherup, R., Cunningham, G., McKane, M., & Bogle, G. (2012). Modelling risk impacts on the variability between contract sum and final account. Royal Institution of Chartered Surveyors, London, 1-19.
Ökmen, Ö., & Öztaş, A. (2010). Construction cost analysis under uncertainty with correlated cost risk analysis model. Construction management and economics, 28(2), 203-212.
Olusola Babatunde, S., Opawole, A., & Emmanuel Akinsiku, O. (2012). Critical success factors in public-private partnership (PPP) on infrastructure delivery in Nigeria. Journal of facilities management, 10(3), 212-225.
Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International journal of project management, 33(6), 1335-1346.
Pickrell, D. H. (1990). Urban Rail Transit Projects: Forecast Versus Actual Ridership and Costs.
Pickrell, D. H. (1992). A desire named streetcar fantasy and fact in rail transit planning. ournal of the American Planning Association, 58(2), 158-176.
Pitsis, T. S., Clegg, S. R., Marosszeky, M., & Rura-Polley, T. (2003). Constructing the Olympic dream: A future perfect strategy of project management. Organization Science, 14(5), 574-590.
Prevedouros, P. (2016). Hart Rail: A Megaproject Failure in the Making. New Geography, 27th January. In.
Why Social Infrastructure Projects Experience Cost Overrun?
136
Puentes, R. (2015). Why Infrastructure Matters: Rotten Roads, Bum Economy. Retrieved from Brookings: https://www.brookings.edu/opinions/why-infrastructure-matters-rotten-roads-bum-economy/
Rangel, T., & Galende, J. (2010). Innovation in public–private partnerships (PPPs): the Spanish case of highway concessions. Public money & management, 30(1), 49-54.
Rosenfeld, Y. (2013). Root-cause analysis of construction-cost overruns. Journal of Construction Engineering
Management, 140(1), 04013039. Rothballer, C. (2012). Infrastructure Investment Characteristics: Risk, Regulation, and
Inflation Hedging. Technische Universität München, Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014). Cost overrun in the
Malaysian construction industry projects: A deeper insight. International journal of project management, 32(8), 1471-1480.
Sing, C.-p., Love, P. E., & Tam, C. M. (2011). Stock-flow model for forecasting labor supply. Journal of Construction Engineering Management, 138(6), 707-715.
Sing, C.-p., Love, P. E., & Tam, C. M. (2012). Multiplier model for forecasting manpower demand. Journal of Construction Engineering Management, 138(10), 1161-1168.
State Council's Opinions on Strengthening Urban Infrastructure Construction. (2013). Retrieved from http://www.gov.cn/zwgk/2013-09/16/content_2489070.htm
Terrill, M., & Danks, L. (2016). Cost overruns in transport infrastructure: Grattan Institute Carlton, Victoria, Australia.
Terrill, M., & Danks, L. (2016). Cost Overruns in Transportation Infrastructure Projects. Melbourne: A Grattan Institute, 12(2016), 184-194.
Torrisi, G. (2009). Public infrastructure: definition, classification and measurement issues. Economics, Management and Financial Markets, 4(3), 100.
Tversky, A., & Kahneman, D. (1974). Judgment under uncertainty: Heuristics and biases. science, 185(4157), 1124-1131.
Ubani, E., Okorocha, K., & Emeribe, S. (2013). Analysis of factors influencing time and cost overruns on construction projects in South Eastern Nigeria. International Journal of Management Sciences
Business Research, 2(2). Van Wee, B. (2007). Large infrastructure projects: a review of the quality of demand
forecasts and cost estimations. Environment Planning, 34(4), 611-625. Wachs, M. (1989). When planners lie with numbers. American Planning Association.
Journal of the American Planning Association, 55(4), 476.
Why Social Infrastructure Projects Experience Cost Overrun?
137
Wan, N. (2007). On the basic construction of enterprise comprehensive budget management. Financial supervision(2), 22.
Wang. (2006). Risks and precautions of auditing the final report of capital construction projects. China Internal Audit, 000(008), 57-58.
Wang, X. (2017). This year's double 11 express is faster than in previous years. Is your parcel arrived? People’s Daily. Retrieved from http://finance.people.com.cn/n1/2017/1113/c1004-29642448.html
Whan, C. (2019a). Ottawa city council approves funding for stage 2 of LRT. Global News. Retrieved from https://globalnews.ca/news/5026177/ottawa-city-council-approves-funding-stage-2-lrt/
Whan, C. (2019b). Ottawa LRT delays cost city almost $33 million: treasurer memo. Golabl News. Retrieved from https://globalnews.ca/news/5413856/ottawa-lrt-delays-treasurer-memo/
Why infrastructure matters. (2017). Retrieved from https://www.ebrd.com/infrastructure/infrastructure-matters.com
Wild, C. (2015). 1957-1973 Building the Sydney Opera House. Retrieved from https://mashable.com/2015/07/11/building-sydney-opera-house/
Wilson, D. I., Pelham, N., & Duffield, C. F. (2010). A review of Australian PPP governance structures. Journal of Financial Management of Property
Construction Economics, 15(3), 198-215. Wood, P. S. (2010). Comparing cost uplift in infrastructure delivery methods: a case
based approach. Queensland University of Technology, Xiaolong, W. (2012). Xiamen First Hospital parking building under construction,
providing 798 parking spaces. Xiamen Daily. Retrieved from http://house.fjsen.com/2012-03/28/content_8095482.htm
Yin, R. K. (2017). Case study research and applications: Design and methods: Sage publications.
Yin, R. K., & Davis, D. (2007). Adding new dimensions to case study evaluations: The case of evaluating comprehensive reforms. New directions for evaluation, 2007(113), 75-93.
Zhang, S., Gao, Y., Feng, Z., & Sun, W. (2015). PPP application in infrastructure development in China: Institutional analysis and implications. International journal of project management, 33(3), 497-509.
Zheng, R. (2011). Analysis on the development trend of high-speed railways in China and the use of steel.