![Page 1: Wheatstone Project Update - Chevron Corporation · Wheatstone; Wheatstone Project; Wheatstone progress; Australia; Chevron Australia; natural gas; LNG; liquified natural gas; Barrow](https://reader036.fdocuments.net/reader036/viewer/2022062507/5fc1f3739572eb6be67667c9/html5/thumbnails/1.jpg)
© 2015 Chevron Corporation. All rights reserved.
Wheatstone Project Update
October 30, 2015
![Page 2: Wheatstone Project Update - Chevron Corporation · Wheatstone; Wheatstone Project; Wheatstone progress; Australia; Chevron Australia; natural gas; LNG; liquified natural gas; Barrow](https://reader036.fdocuments.net/reader036/viewer/2022062507/5fc1f3739572eb6be67667c9/html5/thumbnails/2.jpg)
© 2015 Chevron Corporation. All rights reserved.
Overall Project Progress
We continue to make steady progress against key milestones in the
Wheatstone Project.
2
Train 1 Train 2
![Page 3: Wheatstone Project Update - Chevron Corporation · Wheatstone; Wheatstone Project; Wheatstone progress; Australia; Chevron Australia; natural gas; LNG; liquified natural gas; Barrow](https://reader036.fdocuments.net/reader036/viewer/2022062507/5fc1f3739572eb6be67667c9/html5/thumbnails/3.jpg)
© 2015 Chevron Corporation. All rights reserved.
Wheatstone Offshore Platform Hookup and Commissioning
Hookup and commissioning activities continue and the first permanent systems
have been completed.
3
![Page 4: Wheatstone Project Update - Chevron Corporation · Wheatstone; Wheatstone Project; Wheatstone progress; Australia; Chevron Australia; natural gas; LNG; liquified natural gas; Barrow](https://reader036.fdocuments.net/reader036/viewer/2022062507/5fc1f3739572eb6be67667c9/html5/thumbnails/4.jpg)
© 2015 Chevron Corporation. All rights reserved.
Subsea Activities
All subsea equipment and flowlines are installed. Umbilical fabrication is
complete and offshore installation has commenced.
4
![Page 5: Wheatstone Project Update - Chevron Corporation · Wheatstone; Wheatstone Project; Wheatstone progress; Australia; Chevron Australia; natural gas; LNG; liquified natural gas; Barrow](https://reader036.fdocuments.net/reader036/viewer/2022062507/5fc1f3739572eb6be67667c9/html5/thumbnails/5.jpg)
© 2015 Chevron Corporation. All rights reserved.
LNG Plant Site
17 of 24 Train 1 process modules required for first LNG have been delivered to
the LNG plant site.
5
![Page 6: Wheatstone Project Update - Chevron Corporation · Wheatstone; Wheatstone Project; Wheatstone progress; Australia; Chevron Australia; natural gas; LNG; liquified natural gas; Barrow](https://reader036.fdocuments.net/reader036/viewer/2022062507/5fc1f3739572eb6be67667c9/html5/thumbnails/6.jpg)
© 2015 Chevron Corporation. All rights reserved.
LNG Plant Site
The LNG storage tanks are well advanced with external module installations
under way.
6