What is the Joint Project ? Sciences with the Joint Project Recent Progress and the Future Project...
-
Upload
rosa-fletcher -
Category
Documents
-
view
216 -
download
1
Transcript of What is the Joint Project ? Sciences with the Joint Project Recent Progress and the Future Project...
What is the Joint Project ? Sciences with the Joint Project Recent Progress and the Future Project Plan Issues for Nuclear and Particle Physics
KEK-JAERI Joint Projecton High Intensity Proton Accelerators
Shoji Nagamiya
Project Team
Site View of the Project
Linac400 MeV normal linac400-600 MeV superconducting linac
50 GeV Synchrotron
Particle Nuclear Physics
NeutrinoNuclear Transmutation
Life & Material Science(Neutron, Muon, RI)
3 GeV Synchrotron
World’s Proton Accelerators
IPNS
1000
10000
100
10
1
0.01
0.1
0.1 1 10 100 1000 10000
Energy (GeV)
AGS
CERN-PSFNAL-MI
U70
SPS
ISISTRIUMF
PSI(CW)
KEK-12GeV PS
Tevatron
This Project3 GeV
ExistingUnderconstruction
Power
KEK-500MeVBooster
SNS
Proposed
-Materials LifeSciences
1 MW
0.1 MW
ESS
-Nuclear ParticlePhysics
This Project50 GeV
Why Do We Need High Intensity Protons?
・ Materials & Life Sciences at 3 GeV・ Nuclear & Particle Physics at 50 GeV・ R&D toward Transmutation at 0.6 GeV
Three Questions about Mass
Concept of the Mass Itself– Higgs Mechanism (LHC, Lepton Collider, etc.)
Neutrino Mass?– Beyond the Standard Model
Generation of the Mass of Matter (= Generation of the Mass of Proton or Neutron)– Spontaneous chiral symmetry breaking
Nuclear/Particle Physics (1)
Neutrino oscillation and neutrino mass (SuperK + K2K)– SuperK’s atmospheric experiment + r
ecent SNO experiment suggests the finite mass for and .
– K2K disappearance experiment also suggests the finite mass of .
From measurement of m to the lepton family mixing (Joint Project)– Flux () at the Planned 50 GeV PS
> 100 x Flux () at KEK 12 GeV PS
Future facility … towards CP violation
ê_â™ ≈ 250 km
τ? νμ
ìåäC≈295 km
Atoms and Neutrinos in the Universe2
m
Proton + ElectronOne each
2m
One billioneach !
Three types of neutrinos(e, , τ)
New Data from K2K
2 year (1999-2001)data observed atSuperKamiokande
No oscillation (expected)
= 64 + 6.1 - 6.6Observed
= 44
97% confident that carries a finite mass.
Nuclear/Particle Physics (2)
NormalNucleus
|<qq>ρ,T|
5ρ0T
300 MeV
TemperatureDensity
ρ
T. Hatsuda and T. Kunihiro, Phys. Rev. Lett. 55 (1985) 158.W. Weise, Nucl. Phys. A443 (1993) 59c.
Hypernucleus
NormalNucleus
Baryon Implantation Meson Implantation
e+
e−
Meson
Hyperon
Methods of how to study the origin of hadron mass– Lattice QCD (theory)– Implantation of a hadron in nuclear matter (Joint Project)– Behavior of hadrons at hot and dense nuclear matter (RHIC)
mu, d-quark (5-10 MeV/c2)
< (1/100) mproton (1000 MeV/c2)
Atoms and Nuclei
r
Electron Bound State
V
r
V
rA
Nucleon Bound State
Atom Nucleus
Electron
Nucleus
Neutron
Proton
Materials/Life Sciences (1)
X-rays interact with electrons. X-rays see high-Z atoms.Neutrons interact with nuclei. Neutrons see low-Z atoms.
Li
O
Mn
Li
O
Material for Li-battery seen by X rays (left) and Neutrons (right)
T. Kamiyama, et al.
Neutron Scattering
Materials/Life Sciences (2)
From structure to function
ÉÉ̂ìÉpÉNéø DNAA protenmoleculemoving alongthe DNA chain
Hen Egg-White Lysozyme
Water moleculesObserved withneutrons
X-rays Neutrons
N. Niimura, et al.
Protein
Materials/Life Sciences (4)
Muon SciencesMuonTwo charge states, +e and -eMuon Mass ≈ (1/10) × ( )proton mass 200 × ( )electron mass
Finite magnetic moment Polarized when produced from pion
Negativemuon
ProtonPositivemuon Electron
Muonic Atom Muonium
1/200 Radius is by smaller than the normal atomix size
World Centers
ESS(under discussion)
SNS
FNAL
CERN
Future neutron sceinces
JointProject
Future neutrino sciences
For Kaons: World’s center.For neutrinos and for neutrons: One of three big centers.For transmutation: A unique facility.
群分離 核変換処理
High-LevelWaste
Atomic PowerStation
Takes 102 yrs to reach the negligible
level
Long-livedNuclei
Short-livedNuclei
Proton Accelerator
Neutron
ProronTarget
With Transmutation ・・・
Without transmutation ・・・ Short-lived Nuclei
Radiation Level( about1 /200)
Takes 〜 104 yrs to reachthe negligible level
Accelerator-Driven Transmutation (ADS)
Transmutation + Energy Production
Superconducting Proton LinacTo GridToAcceletratorProton BeamAbout 1 GeV - a few 10 mA
Power GenerationSpallationTargetçƒèàóùçHèÍHigh- Level WastePartit ioningMA, LLFPShort- lived
Nuclei
ç≈èIèàï™Nuclear transmutaion is an important issue for nuclear power
stations. This project will explore the technical feasibility.
Final GoalSubcrit ical
Core
Final Geographical
Disposal
Reprocessing
Recent Events (1)
August, 1998: Suggestion of a joint effort between Monbu-sho and Science and Tech. Agency (STA)
March, 1999: MoU between JAERI and KEK signed.– New organization for the project was initiated.
April, 1999: International Review: Y. Cho (chair)– Emphasized the importance of the joint effort.
May, 1999: Positive Movement at both Monbu-sho and STA– Monbu-sho: Science Council emphasized the importance of a cooperative
effort between KEK and JAERI.– STA: The Joint Proposal was submitted to the Atomic Energy Council of Ja
pan. Enthusiastic! December, 1999 - June, 2000: Another (& the last) major review of t
he project.– The Review Committee was formed under the Atomic Energy Council of Ja
pan and the Science Council of Japan. – Final report was published in August, 2000.– Encouraged strongly the project. Need to set priorities.
Recent Events (2)
April, 2001: Phase 1 construction started.– Phase 1 + Phase 2 = 1,890 Oku Yen.– Phase 1 = 1,335 Oku Yen for 6 years.– Cash in fund = 30 (JFY00) + 47 (JFY01) Oku Yen. – Construction budget does not include salaries.
May, 2001: Construction Agreement between KEK and JAERI signed. A new construction team initiated.– About 300 people from KEK and JAERI are now working.
June, 2001: Interim Report from the Prefecture Committee, called “Science Frontier 21”.– Connection to industry, Internationalization of Tokai Village,
etc.– Final report will be published in March, 2002.
July, 2001: Approval by the Tokai Village.– Geological studies have been started.
December, 2001: Budget for JFY2002 (+ Supplemental budget for JFY2001).
Phase 1 Items to be Constructed at 50 GeV
Accelerator– Stable operations up to 30 GeV guarenteed. Most
likely, up to 40 GeV is possible.– Magnets and all accelerator elements to be
constructed in Phase 1 are for the 50 GeV operation.– The power storage device is deferred to Phase 2.
Slow Extraction– Very limited experimental areas (see the later talks).
Fast Extraction– Elements that must be installed at the beginning will be constr
ucted.
• The minimum accelerator components + building for the fast extraction from 50 GeV.
• Crossing point between the neutrino line and the 3 GeV BT.
to allow Phase 2 neutrino construction without any major shutdown of the accelerators
Proposed Schedule
Merging betweenMonbusho and STA
1 MW
?
?
?
FY00 FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08
LinacSuperconducting Linac3 GeV Synchrotron50 GeV Synchrotron
Neutron Scattering FacilityMuon FacilityTransmutaion R&DNuclear/Particle Phys. FacilityNeutrino Facility
R&Dbudget
Phase 1 Project Cost ≅ 1,335 Oku Yen( Total Project Cost≅ 1,890 )Oku Yen
& 00 R D Budget for FY ≅ 33 Oku Yen
? indicates 2PhaseConstruction
budget
Now
Organization for Construction
Project Team
JAERI President
K. MurakamiKEK DirectorH. Sugawara
Steering CommitteeY. Kimura & S. Saito
Project HeadquartersDirector: S. Nagamiya
Deputu Director: H. Yokomizo
UsersCommittee
Int. AdvisoryCommittee
Matrerials andLife sciences
Y. Ikeda
CoordinationY. Oyama
M. Takasakisaki
TransmutationExperimentsH. Oigawa
Radiation SafetyN. Sasammoto
T. Shibata
Nuclear ParticlePhysics Experiment
J. Imazato
Accelerator
T. Yamaszaki
Facility and BuildingH. NaruseT. Yamada
AdministrationT. KonashiT. Sawada
Issues for 50 GeV PS
Accelerator– Phase 1: 40 GeV could be possible instead of 30 GeV.– An additional power storage device is needed for 50 GeV
(Phase 2 includes the power storage device). Slow Extraction
– Need to select a few experiments for Phase 1.• Will form PAC-like Committee soon to select possible
experiments for Phase 1 (This point is a discussion item at this Workshop.)
– When do we propose Phase 2 ? Fast Extraction
– Neutrino experiment has a very high priority. KEK will submit Phase 2 neutrino construction budget to the Government soon.
– Need to form a high-level review committee at the Government.
Issues for 50 GeV PS (continued)
Other Issues– What to do about an anti-proton accumulator ring?
• LEAR magnets were shipped from CERN to KEK.• The site has to be saved before the Phase 1 construction.
– Are there any other important areas to be reserved before finalizing the Phase 1 construction design?
• Polarized protons? Experimental Activities until the Completion of
the Project– KEK 12 GeV activities and the experimental activities
outside Japan.
Most likely, the PAC-like Committee will be formed within half a year. Call for LOI will be made at that time. -- Need discussions at this Workshop, though.
Beam Commissioning
Item
Linac Bldg
Linac Accel
3GeV Bldg
3GeV Accel
3GeV Exp Bldg
3GeV Exp Fac
50GeV Bldg
50GeV Accel
50GeV Exp Bldg
50GeV Exp Fac
Power 0.1% 1% 10Åì Å 1̀00Åì
Beam Test
3GeV BT
Installation
10Åì Å 1̀00Åì
Beam Test
Construction
Installation
Beam TestInstallationConstruction
Beam TestConstruction Installation
Power 0.1% 1% 10Åì Å 1̀00Åì
Installation
Beam Test
Beam Test
Construction Installation
Start Usage
Test Periodţ
Open to Users
Year2001 2002 2003 2004 2005 2006 2007 2008 2009
Construction
Power 0.1% 1%
Possible Upgrades
From 1 MW to 5 MW– Strong voice toward 5 MW from neutron scattering
community.– Also, this upgrade is useful for nuclear transmutation.
Nuclear/particle physics– Neutrino factory– Muon factory– Anti-proton accumulator ring– Ultra cold neutrons– Heavy-ion beams at about 20 GeV per nucleon– Polarized protons
Summary
Uniqueness of the Project– Goal: World’s highest intensity for proton beams.– Variety of secondary beams + Variety of frontier sciences.
International Research Center– Would like to create a research center in the Asian/Oceanic regio
n.– Would also like to invite scientists from Europe and the US.
Variety of Possibilities for Future Upgrades First Example of the Joint Project between the Past Two A
gencies, Monbu-sho and STA. Need to Establish “Strategy” for the 50 GeV Experimental
Activities This Workshop