Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355...

5
Westinghouse - Water Reactor- - Nucle Trnroiogyo vsion Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230 -April 21, 1983 NS-EPR-2753 Mr. R. C. DeYoung, Director Division of Inspection and Enforcement U.S. Nuclear Regulatory Commission Phillips Building 7920 Norfolk Avenue Betheda, MD 20014 Dear Mr. DeYoung: This is to confirm the telephone conversation of April 20, 1983, between Messrs. D. Rawlins and J. McAdoo of Westinghouse and Mr. Vernon Hodge of the NRC. In that conversation Westinghouse notified NRC of the potential for misoperation of OS-416 reactor trip underveltage devices. This was reported under O1CFR21 for operating plants and under 10OCFR50.55(e) for plants under construction. Westinghouse has advised its NSSS utility customers of this determination. Table 1 is a listing of U.S. plants with DS-416 reactor trip switchgear employing the undervoltage attachments. On March 31, 1983. Westinghouse advised you of the potential for misoperation of these attachments based on reported malfunctions at one plant during testing. At that time, Westinghouse requested information from its utility customers relative to dimensions of several clearances in the attachment to aid in our evaluation. The Westinghouse evaluation has concluded that deviations from the recommended clearances could increase the potential for misoperation of the attachment, thereby creating a condition wherein the reactor trip switchgear might not open on automatic demand from the reactor protection system. Subsequent to the March 31, 1983 notification, Westinghouse advised its operating plant utilities on April 15, 1983, of an additional misoperation of another DS-416 undervoltage attachment. Investigation of this event revealed a missing retaining ring on one of the two undervoltage attachment pivot shafts (shown in Attachment 2). This allowed the pivot shaft to move laterally such that one end came out of its guide hole in the frame of the undervoltage attachment and did not permit the attachment to operate on demand. A missing retaining ring was also identified at another plant. No misoperation of that attachment had been reported. The Westinghouse evaluation of the retaining ring issue revealed a discre pancy in design. The groove in the shaft receiving the retaining ring was not increased in width to be consistent with an earlier (1972) retaining ring 8305110427 830421 PDR ADOCK 05000334 S PDR g /: )

Transcript of Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355...

Page 1: Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230 -April 21, 1983 NS-EPR-2753 Mr. R. C. DeYoung, Director

Westinghouse - Water Reactor- - Nucle Trnroiogyo vsion

Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230

-April 21, 1983

NS-EPR-2753

Mr. R. C. DeYoung, Director Division of Inspection and Enforcement U.S. Nuclear Regulatory Commission Phillips Building 7920 Norfolk Avenue Betheda, MD 20014

Dear Mr. DeYoung:

This is to confirm the telephone conversation of April 20, 1983, between Messrs. D. Rawlins and J. McAdoo of Westinghouse and Mr. Vernon Hodge of the NRC. In that conversation Westinghouse notified NRC of the potential for misoperation of OS-416 reactor trip underveltage devices. This was reported under O1CFR21 for operating plants and under 10OCFR50.55(e) for plants under construction. Westinghouse has advised its NSSS utility customers of this determination. Table 1 is a listing of U.S. plants with DS-416 reactor trip switchgear employing the undervoltage attachments.

On March 31, 1983. Westinghouse advised you of the potential for misoperation of these attachments based on reported malfunctions at one plant during testing. At that time, Westinghouse requested information from its utility customers relative to dimensions of several clearances in the attachment to aid in our evaluation. The Westinghouse evaluation has concluded that deviations from the recommended clearances could increase the potential for misoperation of the attachment, thereby creating a condition wherein the reactor trip switchgear might not open on automatic demand from the reactor protection system.

Subsequent to the March 31, 1983 notification, Westinghouse advised its operating plant utilities on April 15, 1983, of an additional misoperation of another DS-416 undervoltage attachment. Investigation of this event revealed a missing retaining ring on one of the two undervoltage attachment pivot shafts (shown in Attachment 2). This allowed the pivot shaft to move laterally such that one end came out of its guide hole in the frame of the undervoltage attachment and did not permit the attachment to operate on demand. A missing retaining ring was also identified at another plant. No misoperation of that attachment had been reported.

The Westinghouse evaluation of the retaining ring issue revealed a discrepancy in design. The groove in the shaft receiving the retaining ring was not increased in width to be consistent with an earlier (1972) retaining ring

8305110427 830421 PDR ADOCK 05000334 S PDR

g /: )

Page 2: Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230 -April 21, 1983 NS-EPR-2753 Mr. R. C. DeYoung, Director

Mr. R. C. DeYoung -2-- April 21, 1983 NS-EPR-2753

design change. The new retaining ring is wider than the original design and does not seat properly in the existing grooves. This discrepancy increases the potential for misoperation of the DS-416 undervoltage attachment, thereby creating a condition wherein the reactor trip switchgear might not open on automatic demand from the reactor protection system.

Corrective Actions

(1) Westinghouse has committed to its utilities to replace the undervoltage attachments on DS-416 reactor trip switchgear supplied by Westinghouse for its Nuclear Steam Supply Systems. (2) The new attachments have modified (widened) grooves to accommodate the new retaining rings. (3) Manufacturing drawings have been revised and quality control procedures modified so that critical design dimensions are maintained during manufacture. (4) Furthermore, Wef.inghouse is developing and will implement a procedure for installation of the new attachments on DS-416 reactor trip switchgear in the plant. This field installation procedure will provide for proper alignment and interface of the attachment with the breaker trip shaft.

to Justify continued plant operation, until replacement undervoltage attachments can be fabricated, shipped, and properly installed, Westinghouse has recommended that the utilities perform the following:

(a) Assure that control room operators are alerted to the potential for misoperation of the reactor trip switchgear due to possible malfunction of the undervoltage attachments.

(b) Re-emphasize to the control room operators the indications available to detect failure of the rods to insert into the core following a demand signal from the automatic protection system.

(c) Re-emphasize to the control room operators the manual reactor trip options available in the existing emergency operating procedures. These procedures contain diverse methods of tripping the reactor which do not rely on the undervoltage trip attachment.

(d) Visually verify after operation of the reactor trip switchgear that retaining rings are located on the grooved ends of the two undervoltage pivot shafts identified in Attachment 2. This will provide increased confidence that the shaft will not disengage, and that the attachment will be operable for the next trip demand. After installation of the replacement OS-416 undervoltage attachments, the requirement to visually verify the presence of retaining rings after operation of the reactor trip switchgear can be eliminated.

Page 3: Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230 -April 21, 1983 NS-EPR-2753 Mr. R. C. DeYoung, Director

K

Mr. R. C. DeYoung -3- April 21, 1983 NS-EPR-2753

If you require additional information on this, please contact David H. Fjwlins of my Staff at (412) 374-5282.

Very truly yours,

-& jP. Rahe, Jr., Manager Nuclear Safety Department

/bek

Page 4: Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230 -April 21, 1983 NS-EPR-2753 Mr. R. C. DeYoung, Director

0

.

4

Utility

Alabama Power

Carolina Power & Light

Comonwealth Edisor,

Duke Power

Duke Power

Duquesne Light

Georgia Power

Houston Lighting & Power

New Hampshire P.S.

Northeast Utilities

Public Service of Indiana

SNUPPS - Kansas Gas & Electric

SNUPPS - Union Electric

South Carolina Electric & Gas

TVA

Texas Utility Generating Co. Texas Utilities

*Indicates Operating Plants

Plant

Joseph M. Farley 1* Joseph N. Farley #2*

Shearon-Harris #l Shearon-Harris #2

Byron #1 Byron #2 Braidwood l1 Braidwood #2

Catawba #1 Catawba #2

McGuire #1* McGuire #2*

Beaver Valley #2

Alvin W. Vogtle #1 Alvin W. Vogtle #2

South Texas #1 South Texas #2

Seabrook #1 Seabrook 12

Millstone #3

Marble Hill 11 Marble Hill #2

Wolf Creek #1

Calloway #1

Virgil C. Suumer*

Watts Bar #1 Watts Bar #2

Comanche Peak #1 Comanche Peak #2

4063Q

TABLE I

' " Reactor Trip Switchgear - Type DS-416

Page 5: Westinghouse Water Reactor- Nucle Bectric Corporation ... · Bectric Corporation Divisions oa3 355 PittsBUghPennsywana 15230 -April 21, 1983 NS-EPR-2753 Mr. R. C. DeYoung, Director

.1* K . e *

I,

DSAI16 Undervolfaqe Altach-menii

PiVOT B ARlua 4LANT1

RE S~L 6FVlEt 1

ItOLIAR b4"

,0PERATING *00

movoWen COOK

COIL.

STATI@NEVt CoUl

- I I - A IN 20 s 014upw wwwrA -