WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview...

61
WEST DEPTFORD TOWNSHIP PUBLIC SCHOOL DISTRICT OAKVIEW ELEMENTARY SCHOOL 350 DUBOIS AVENUE WOODBURY, NJ 08096 FACILITY ENERGY REPORT

Transcript of WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview...

Page 1: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

WEST DEPTFORD TOWNSHIP PUBLIC SCHOOL DISTRICT

OAKVIEW ELEMENTARY SCHOOL

350 DUBOIS AVENUE

WOODBURY, NJ 08096

FACILITY ENERGY REPORT

Page 2: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 1 of 30

TABLE OF CONTENTS

I. HISTORIC ENERGY CONSUMPTION/COST ................................................................. 2

II. FACILITY DESCRIPTION ................................................................................................ 7

III. MAJOR EQUIPMENT LIST .............................................................................................. 9

IV. ENERGY CONSERVATION MEASURES ..................................................................... 10

V. ADDITIONAL RECOMMENDATIONS ......................................................................... 30

Appendix A – ECM Cost & Savings Breakdown

Appendix B – New Jersey Smart Start® Program Incentives

Appendix C – Portfolio Manager “Statement of Energy Performance”

Appendix D – Major Equipment List

Appendix E – Investment Grade Lighting Audit

Appendix F – Renewable / Distributed Energy Measures Calculations

Page 3: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 2 of 30

I. HISTORIC ENERGY CONSUMPTION/COST The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. Electric Utility Provider: Public Service Electric & Gas Electric Utility Rate Structure: Large Power & Lighting Service (LPLS) Third Party Supplier: N/A Natural Gas Utility Provider: Public Service Electric & Gas Utility Rate Structure: Large Volume Gas (LVG) Third Party Supplier: Hess The electric usage profile represents the actual electrical usage for the facility. The electric utility measures consumption in kilowatt-hours (KWH) and maximum demand in kilowatts (KW). One KWH usage is equivalent to 1000 watts running for one hour. One KW of electric demand is equivalent to 1000 watts running at any given time. The basic usage charges are shown as generation service and delivery charges along with several non-utility generation charges. Rates used in this report reflect the historical data received for the facility. The gas usage profile within each facility report shows the actual natural gas energy usage for the facility. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy.

Page 4: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 3 of 30

Table 1 Electricity Billing Data

Utility Provider: PSE&GRate: LPLS

Meter No: 778020889Account # 42 171 503 18

Third Party Utility Provider: N/ATPS Meter / Acct No: N/A

MONTH OF USE CONSUMPTION KWH TOTAL BILL

Dec-10 111,349 $16,766 Jan-11 111,387 $17,092 Feb-11 111,324 $16,827 Mar-11 103,504 $17,136 Apr-11 112,811 $18,256 May-11 122,118 $19,377 Jun-11 191,075 $29,693 Jul-11 260,032 $40,008

Aug-11 185,546 $32,148 Sep-11 185,512 $31,382 Oct-11 156,602 $27,862 Nov-11 167,036 $29,167

Totals 1,818,296 617 Max $295,713

AVERAGE DEMAND 398.7 KW averageAVERAGE RATE $0.163 $/kWh

499

273300315

420

324400536617501

ELECTRIC USAGE SUMMARY

DEMAND KW

281357

Page 5: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 4 of 30

Figure 1 Electricity Usage Profile

Page 6: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 5 of 30

Table 4 Natural Gas Billing Data

*Note: The gas rate for this facility is far below the average rate for similar facilities and the bills for the third party supplier which cover supply to this facility could not be acquired. In order to more accurately reflect the average rate per unit, third party supplier billing data from the other district buildings was used to estimate the third party supply charges.

Utility Provider: PSE&GRate: LVG

Meter No: 2750770Account Number 42 171 503 18

Third Party Utility Provider: HessTPS Account No:

MONTH OF USECONSUMPTION

(THERMS) TOTAL BILL

Nov-10 547 $549Dec-10 808 $811Jan-11 910 $912Feb-11 815 $818Mar-11 538 $541Apr-11 337 $314May-11 219 $208Jun-11 66 $70Jul-11 0 $11

Aug-11 68 $78Sep-11 136 $145Oct-11 411 $383Nov-11 596 $599

TOTALS 4,904 $4,888

AVERAGE RATE: $1.00 $/THERM

-

NATURAL GAS USAGE SUMMARY

Page 7: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 6 of 30

Figure 2 Natural Gas Usage Profile

Page 8: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 7 of 30

II. FACILITY DESCRIPTION

The Oakview Elementary School is located at 350 DuBois Avenue in Woodbury, New Jersey. The 41,905 SF Oakview Elementary School was built in 1956. The building is a single-story structure and consists of office space for administrative use, all-purpose room, classrooms, kitchen and mechanical rooms.

Occupancy Profile

The typical hours of operation for Oakview Elementary School are Monday through Friday between 8:00 am and 4:30 pm, with custodial services running until 11:00 pm. The elementary school has a 12 month administrative occupancy of 56 people and 10 month occupancy with students of 320. Also, during the summer months summer recreation programs utilize available space to conduct their programs until approximately 4:30 pm.

Building Envelope

Exterior walls for the Oakview Elementary School are brick faced with a concrete block construction. The amount of insulation within the walls is unknown. The windows throughout the elementary school are in average condition. The roof is a flat, built up rubber roof that appears to be in good condition. The amount of insulation below the roof is unknown. Exterior doors had air gaps ranging in size of 1/16” to 1/8” in some areas and should be addressed with either re-aligning the doors or replacing the weather stripping entirely.

Heating Plant

Heating is provided to the facility from the Mechanical Room housing three natural gas fired, cast iron sectional hot water boilers made by Weil McLain. All three boilers have equivalent heating capacity characteristics having an input capacity of 1,527 MBH and output of 1,250 MBH for a combined output of 3,750 MBH. All three boilers appear to be well maintained and in good condition. Combustion tests were not available for review but based on age the assumption is the overall fuel-to-thermal efficiency for the boilers is approximately 75%, based on radiation losses and inefficiencies in operation inherent to the older technology. Both boilers are approximately 15 years old with a projected 20 years of their ASHRAE service life remaining. At this time, the boilers are not recommended for replacement. The heating hot water is circulated throughout the building via a constant speed end-suction pump set located in the Mechanical Room. The pumps are driven with standard efficiency motors that are recommended to be replaced with NEMA premium efficient motors. The hot water heating system provides heating hot water to the unit ventilators, hot water fin-tube radiators and heating and ventilation units throughout the facility.

Cooling Plant

Cooling is provided to the facility from an outdoor, air-cooled chiller as manufactured by Trane. The chiller has a cooling capacity equal to approximately 125 tons and is approximately 14 years old. Based on the chiller’s age, it has a projected six years remaining on its ASHRAE service life. The chiller appears to be well maintained and in good condition. At this time, the chiller is

Page 9: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 8 of 30

not recommended for replacement. The chilled water is circulated throughout the building via a constant speed end-suction pump set located in the Mechanical Room. The pumps are driven with high efficiency motors. However a replacement is recommended in order to provide inverter-duty motors capable of operating via variable speed drive as recommended in another ECM included within this audit. The chilled water cooling system provides chilled water to the unit ventilators and any other air-handling systems with chilled water coils throughout the facility.

HVAC Systems

The Library is conditioned via a packaged air-to-air heat pump rooftop unit as manufactured by Trane. This unit provides approximately 7.5 cooling tons and 88 MBH of heating. The unit is relatively new, being installed in 2011 and is in great condition.

The All-Purpose Room is conditioned via indoor air-handling units that are of an older vintage but appear to be functioning. The units are not recommended for replacement based on energy savings alone at this time.

The classrooms within the facility are conditioned via unit ventilators with chilled water and hot water coils as manufactured by Nesbitt. The units appear to have been replacement units and are not recommended for upgrades at this time.

Exhaust System

Air is exhausted from the toilet rooms and other areas of the facility through the roof exhaust fans.

HVAC System Controls

The HVAC systems within the Oakview Elementary School are controlled by various electronic controls systems. There are Tracer Summit Controls, Siebe Environmental Controls and Barber Coleman controls. There is a modem installed in the control panel that provides supervisory control and monitoring to the Facilities Director.

Domestic Hot Water

The main source of domestic hot water for Oakview Elementary School is an AO Smith 250 MBH gas fired water heater with an integrated storage capacity of 100 gallons. The hot water heater is passed its ASHRAE service life of 12 years but appears to be in working condition. The hot water heater is recommended for replacement in the near future.

Lighting

Refer to the Investment Grade Lighting Audit Appendix for a detailed list of the lighting throughout the facility and estimated operating hours per space.

Page 10: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 9 of 30

III. MAJOR EQUIPMENT LIST

The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment’s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix.

Refer to the Major Equipment List Appendix for this facility.

Page 11: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 10 of 30

IV. ENERGY CONSERVATION MEASURES Energy Conservation Measures are developed specifically for this facility. The energy savings and calculations are highly dependent on the information received from the site survey and interviews with operations personnel. The assumptions and calculations should be reviewed by the owner to ensure accurate representation of this facility. The following ECMs were analyzed:

Table 1 ECM Financial Summary

ECM #1 Lighting Upgrade (CFL's) $429 $59 7.2 107.7%

ECM #2 Lighting Upgrade Gymnasium $5,064 $233 21.8 -31.1%

ECM #3 Lighting Controls Upgrade $8,505 $1,987 4.3 250.5%

ECM #4 Domestic Hot Water Heater Upgrade

$15,202 $682 22.3 -46.2%

ECM #5 NEMA Premium Motor Replacement

$12,782 $570 22.4 -19.7%

ECM #6 VFD on Chilled Water Pumps

$119,609 $1,913 62.5 -76.0%

ECM #7 Computer Standby or Hibernate

$767 $1,157 0.7 2162.7%

REM #1 77.08 KW PV System $475,926 $32,235 14.8 1.6%

Notes:

ECM NO. DESCRIPTION

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

ENERGY CONSERVATION MEASURES (ECM's)

NET INSTALLATION

COSTA

RENEWABLE ENERGY MEASURES (REM's)

ECM NO. DESCRIPTION

NET INSTALLATION

COST

ANNUAL SAVINGSB

ANNUAL SAVINGS

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

A. Cost takes into consideration applicable NJ Smart StartTM incentives.B. Savings takes into consideration applicable maintenance savings.

Page 12: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 11 of 30

Table 2 ECM Energy Summary

ECM #1 Lighting Upgrade (CFL's) 0.6 367 0

ECM #2 Lighting Upgrade Gymnasium 1 1,435 0

ECM #3 Lighting Controls Upgrade 0.0 12,267 0

ECM #4 Domestic Hot Water Heater Upgrade

0.0 0 682

ECM #5 NEMA Premium Motor Replacement

1.9 6,360 0

ECM #6 VFD on Chilled Water Pumps

0.0 11,808 0

ECM #7 Computer Standby or Hibernate

0.0 7,100 0

REM #1 77.08 KW PV System 77.1 91,296 0

ENERGY CONSERVATION MEASURES (ECM's)

ELECTRIC DEMAND

(KW)

ELECTRIC CONSUMPTION

(KWH)

ECM NO. DESCRIPTION

ANNUAL UTILITY REDUCTION

ECM NO. DESCRIPTION

ANNUAL UTILITY REDUCTIONRENEWABLE ENERGY MEASURES (REM's)

NATURAL GAS (THERMS)

ELECTRIC DEMAND

(KW)

NATURAL GAS (THERMS)

ELECTRIC CONSUMPTION

(KWH)

Page 13: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 12 of 30

Table 3 Facility Project Summary

Design / Construction Extras is shown as an additional cost for the facility project summary. This cost is included to estimate the costs associated with construction management fees for a larger combined project.

Lighting Upgrade (CFL's) $59 $429 $0 $429 7.2

Lighting Upgrade Gymnasium

$233 $5,064 $0 $5,064 21.8

Lighting Controls Upgrade $1,987 $9,450 $945 $8,505 4.3

Domestic Hot Water Heater Upgrade

$682 $15,600 $398 $15,202 22.3

NEMA Premium Motor Replacement

$570 $13,212 $430 $12,782 22.4

VFD on Chilled Water Pumps

$1,913 $119,859 $250 $119,609 62.5

Computer Standby or Hibernate

$1,157 $767 $0 $767 0.7

Design / Construction Extras (15%)

$0 $24,657 $0 $24,657

Total Project $6,601 $189,038 $2,023 $187,015 28

ENERGY SAVINGS IMPROVEMENT PROGRAM - POTENTIAL PROJECT

SIMPLE PAYBACK

ENERGY CONSERVATION

MEASURES

ANNUAL ENERGY

SAVINGS ($)

PROJECT COST ($)

SMART START

INCENTIVES

CUSTOMER COST

Page 14: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 13 of 30

ECM #1: Lighting Upgrade – General Description: The majority of the interior lighting throughout Oakview Elementary School is provided with fluorescent fixtures with older generation, 700 series and 741/ECO 32W T8 lamps and electronic ballasts. Although these T8 lamps are considered fairly efficient, further energy savings can be achieved by replacing the existing T8 lamps with new generation, 800 series 28W T8 lamps without compromising light output. Concord Engineering recommends that these fixtures remain unmodified due to the extensive costs which will be incurred if these fixtures are to be re-lamped and re-ballasted, which results in a long payback period. The ECM includes replacement of any incandescent lamps with compact fluorescent lamps. Compact fluorescent lamps (CFL’s) were designed to be direct replacements for the standard incandescent lamps which are common to table lamps, spot lights, hi-hats, bathroom vanity lighting, etc. The light output of the CFL has been designed to resemble the incandescent lamp. The color rendering index (CRI) of the CFL is much higher than standard fluorescent lighting, and therefore provides a much “truer” light. The CFL is available in a myriad of shapes and sizes depending on the specific application. Typical replacements are: a 13-Watt CFL for a 60-Watt incandescent lamp, an 18-Watt CFL for a 75-Watt incandescent lamp, and a 26-Watt CFL for a 100-Watt incandescent lamp. The CFL is also available for a number of “brightness colors” that is indicated by the Kelvin rating. A 2700K CFL is the “warmest” color available and is closest in color to the incandescent lamp. CFL’s are also available in 3000K, 3500K, and 4100K. The 4100K would be the “brightest” or “coolest” output. A CFL can be chosen to screw right into your existing fixtures, or hardwired into your existing fixtures. Where the existing fixture is controlled by a dimmer switch, the CFL bulb must be compatible with a dimmer switch. In some locations the bulb replacement will need to be tested to make sure the larger base of the CFL will fit into the existing fixture. The energy usage of an incandescent compared to a compact fluorescent approximately 3 to 4 times greater. In addition to the energy savings, compact fluorescent fixtures burn-hours are 8 to 15 times longer than incandescent fixtures ranging from 6,000 to 15,000 burn-hours compared to incandescent fixtures ranging from 750 to 1000 burn-hours. However, the maintenance savings due to reduced lamp replacement is offset by the higher cost of the CFL’s compared to the incandescent lamps. Energy Savings Calculations: The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building.

Page 15: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 14 of 30

Energy Savings Summary:

Installation Cost ($): $429NJ Smart Start Equipment Incentive ($): $0Net Installation Cost ($): $429Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $59Total Yearly Savings ($/Yr): $59Estimated ECM Lifetime (Yr): 15Simple Payback 7.2Simple Lifetime ROI 107.7%Simple Lifetime Maintenance Savings $0Simple Lifetime Savings $891Internal Rate of Return (IRR) 11%Net Present Value (NPV) $279.98

ECM #1 - ENERGY SAVINGS SUMMARY

Page 16: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 15 of 30

ECM #2: Lighting Upgrade – Gymnasium Description: The gymnasium at Oakview Elementary School is currently lit via 400 watt Metal Halide HID fixtures. The space would be better served with a more efficient, fluorescent lighting system. Concord Engineering recommends upgrading the lighting to an energy-efficient T5 high output system that includes new six lamp, 54 watt high output fixtures. This measure replaces all the HID, 400 watt HID MH fixtures with a well-designed T5 high output (HO) system. T5 High output fixtures with reflectors and wire guards will be required in order to meet the mandated 50 foot-candle average within the spaces. Energy Savings Calculations: A detailed Investment Grade Lighting Audit can be found in Investment Grade Lighting Audit Appendix that outlines the proposed retrofits, costs, savings, and payback periods. Energy Savings Summary:

Installation Cost ($): $5,064NJ Smart Start Equipment Incentive ($): $0Net Installation Cost ($): $5,064Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $233Total Yearly Savings ($/Yr): $233Estimated ECM Lifetime (Yr): 15Simple Payback 21.8Simple Lifetime ROI -31.1%Simple Lifetime Maintenance Savings $0Simple Lifetime Savings $3,488Internal Rate of Return (IRR) -4%Net Present Value (NPV) ($2,288.40)

ECM #2 - ENERGY SAVINGS SUMMARY

Page 17: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 16 of 30

ECM #3: Lighting Controls Upgrade – Occupancy Sensors Description: Some of the lights in the Oakview Elementary School are left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off.

Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report:

• Occupancy Sensors for Lighting Control 20% - 28% energy savings.

Savings resulting from the implementation of this ECM for energy management controls are estimated to be 20% of the total light energy controlled by occupancy sensors (The majority of the savings is expected to be after school hours when rooms are left with lights on) This ECM includes installation of ceiling or switch mount sensors for individual offices, classrooms, large bathrooms, and Media Centers. Sensors shall be manufactured by Sensorswitch, Watt Stopper or equivalent. The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls. Energy Savings Calculations:

( )( )kWh/YrEnergyLightControlledSavings%SavingsEnergy ×=

( )

×=

kWh$CostElecAvekWhSavingsEnergySavings.

Page 18: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 17 of 30

Rebates and Incentives:

From the NJ Smart Start® Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: Smart Start Incentive

= (# Wall mount sensors × $20 per sensor)+ (# Ceiling mount sensors × $35 per sensor)

Energy Savings Summary:

Installation Cost ($): $9,450NJ Smart Start Equipment Incentive ($): $945Net Installation Cost ($): $8,505Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $1,987Total Yearly Savings ($/Yr): $1,987Estimated ECM Lifetime (Yr): 15Simple Payback 4.3Simple Lifetime ROI 250.5%Simple Lifetime Maintenance Savings $0Simple Lifetime Savings $29,809Internal Rate of Return (IRR) 22%Net Present Value (NPV) $15,218.62

ECM #3 - ENERGY SAVINGS SUMMARY

Page 19: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 18 of 30

ECM #4: High Efficiency Gas Hot Water Heater

Description: The Oakview Elementary School has one A.O. Smith gas-fired hot water heater that serves the entirety of the original building. The gas fired heater has surpassed its life expectancy of a typical hot water heater. This ECM will replace the original gas fired domestic water heaters with Natural Gas fired 98.5% thermal efficient Bradford White eF Series. The unit will be replaced with a 199 MBH and 100 gallon heater. Energy Savings Calculations:

Energy Density for “Education” type building = 5.2 kBtu / SF / year

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS Existing Gas Hot Water Heater

High Efficiency Heater

Building Type Education

Building Square-foot 41,905 41,905

Domestic Water Usage, kBtu 217,906.00 217,906.00

DHW Heating Fuel Type Gas Gas

Heating Efficiency 75% 98% 23%

Total Usage (kBTU) 290,541 222,353 68,188

Nat Gas Cost ($/Therm) $ 1.000 $ 1.000

ECM RESULTS EXISTING PROPOSED SAVINGS

Natural Gas Usage (Therms) 2,905 2,224 682

Energy Cost ($) $2,905 $2,224 $682

COMMENTS:

DOM. HOT WATER HEATER CALCULATIONS

Savings are based on Energy Information Administration Commercial Building Energy Consumption Survey 2003 Information

ENERGY SAVINGS CALCULATIONS

Page 20: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 19 of 30

)(SFFootageSquareBuildingSF

yrkBtuDensityEnergyUsageHeatDHW ×

=

( )

( )

×

=

UnitFuelBTUValueHeatFuelEffHeating

BtuConsHeatHWDomUsageTotalDHW%.

.

( )

×=

UnitFuelCostFuelAveUnitsFuelUsageFuelHeatingCostEnergy $

Energy Savings Summary:

Installation Cost ($): $15,600NJ Smart Start Equipment Incentive ($): $398Net Installation Cost ($): $15,202Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $682Total Yearly Savings ($/Yr): $682Estimated ECM Lifetime (Yr): 12Simple Payback 22.3Simple Lifetime ROI -46.2%Simple Lifetime Maintenance Savings $0Simple Lifetime Savings $8,184Internal Rate of Return (IRR) -8%Net Present Value (NPV) ($8,413.37)

ECM #4 - ENERGY SAVINGS SUMMARY

Page 21: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 20 of 30

ECM #5: Install NEMA Premium® Efficiency Motors Description: The improved efficiency of the NEMA Premium® efficient motors is primarily due to better designs with use of better materials to reduce losses. Surprisingly, the electricity used to power a motor represents 95 % of its total lifetime operating cost. Because many motors operate continuously 24 hours a day, even small increases in efficiency can yield substantial energy and dollar savings. The electric motors driving the hot and cold water pumps are candidates for replacing with premium efficiency motors. These standard efficiency motors run considerable amount of time over a year. This energy conservation measure replaces existing inefficient electric motors with NEMA Premium® efficiency motors. NEMA Premium® is the most efficient motor designation in the marketplace today.

Energy Savings Calculations: Error! Bookmark not defined.

Electric usage, kWh =HP × LF × 0.746 × Hours of Operation

Motor Efficiency

where, HP = Motor Nameplate Horsepower Rating LF = Load Factor Motor Efficiency = Motor Nameplate Efficiency

ProposedExisting UsageElectricUsageElectrickWhSavings,UsageElectric −= Electric Usage Savings, kWh = Electric UsageExisting − Electric UsageProposed

Electric cost savings = Electric Usage Savings × Electric Rate �$

kWh�

EQMTID FUNCTION

MOTOR HP

HOURS OF OPERATION

EXISTING EFFICIENCY

NEMA PREMIUM

EFFICIENCYHWP-1 Hot Water Pump 7.5 3,391 88.5% 91.7%HWP-2 Hot Water Pump 7.5 3,391 88.5% 91.7%CHWP-1 Chilled Water Pump 20 3,391 91.0% 93.0%CHWP-2 Chilled Water Pump 20 3,391 91.0% 93.0%

IMPLEMENTATION SUMMARY

Page 22: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 21 of 30

The calculations were carried out and the results are tabulated in the table below:

Equipment Cost and Incentives

Below is a summary of SmartStart Building® incentives for premium efficiency motors:

The following table outlines the summary of motor replacement costs and incentives:

EQMTID

MOTOR HP

LOAD FACTOR

EXISTING EFFICIENCY

NEMA PREMIUM

EFFICIENCY

POWER SAVINGS

kW

ENERGY SAVINGS

kWH

COST SAVINGS

HWP-1 7.5 90% 88.5% 91.7% 0.20 677 $110HWP-2 7.5 90% 88.5% 91.7% 0.20 677 $110

CHWP-1 20 90% 91.0% 93.0% 0.32 1,082 $175CHWP-2 20 90% 91.0% 93.0% 0.32 1,082 $175

TOTAL 1.0 3,518 $570

PREMIUM EFFICIENCY MOTOR CALCULATIONS

HORSE POWER

NJ SMART START

INCENTIVE5 $60

7.5 $9010 $10015 $11520 $12525 $13030 $15040 $180

INCENTIVES

EQMTID

MOTOR POWER

HP

INSTALLED COST

SMART START

INCENTIVENET COST

TOTAL SAVINGS

SIMPLE PAYBACK

HWP-1 7.5 $1,971 $90 $1,881 $110 17.2HWP-2 7.5 $1,971 $90 $1,881 $110 17.2CHWP-1 20 $4,635 $125 $4,510 $175 25.7CHWP-2 20 $4,635 $125 $4,510 $175 25.7TOTAL Totals: $13,212 $430 $12,782 $570 22.4

MOTOR REPLACEMENT SUMMARY

Page 23: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 22 of 30

Energy Savings Summary:

Installation Cost ($): $13,212NJ Smart Start Equipment Incentive ($): $430Net Installation Cost ($): $12,782Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $570Total Yearly Savings ($/Yr): $570Estimated ECM Lifetime (Yr): 18Simple Payback 22.4Simple Lifetime ROI -19.7%Simple Lifetime Maintenance Savings $0Simple Lifetime Savings $10,260Internal Rate of Return (IRR) -2%Net Present Value (NPV) ($4,942.50)

ECM #5 - ENERGY SAVINGS SUMMARY

Page 24: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 23 of 30

ECM # 6: Install VFD on Chilled Water Pumps Description: The chilled water system at the Oakview Elementary School utilizes two constant speed pumps to circulate chilled water from the air cooled chiller at the mechanical room throughout the building. Based on the survey of the existing equipment it appears that the chilled water air handlers have 3-way control valves for flow control. 3-way control valves allow constant flow of the water loop, requiring full pumping energy continuously, unlike 2-way control valves that provide flow through the heat exchanger equipment only when there is a call for cooling, and allow the system to reduce flow when it is not needed. This ECM includes the installation of Variable Frequency Drives on the two (2) 20 horsepower existing chilled water pumps. The VFD control is based on a differential pressure sensor in the water loop to measure demand for water. This ECM also includes replacement of the existing 3-way valves with 2-way valves which enable the system to operate correctly. Energy Savings Calculations:

Pump Power HP =FlowGPM × Headft−hd.

3650 × ηPump × ηmotor

Energy Consumption (kWh) = Motor HP × 0.746kWHP

× Hours of operation (Hr) ×1

ηmotor

Total Energy Consumption (kWh) = �Energy Consumption of Each Motor

Energy Cost ($) = Total Comsumption(kWh) × Average Cost of Electric �$

kWh�

Affinity Laws are used in order to calculate energy savings by calculating the reduced power consumption requirement based a reduction in flow. Affinity laws, are as following: Q = Flow, n = RPM, p = total pressure Q2

Q1=

n2n1

p2p1

= �n2n1�2

HP2HP1

= �n2n1�3

Page 25: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 24 of 30

Estimated Operating Profile with VFD

0%

5%

10%

15%

20%

25%

100% 90% 80% 70% 60% 50% 40% 30% 20%

PERC

ENT

HOUR

S

PERCENT FLOW

OPERATING PROFILE

ECM INPUTS EXISTING PROPOSED SAVINGSECM INPUTS CV Pumps VFD Pumps

Flow Control Throttle VFD -

Motor Nameplate HP 20.0 20.0

Flow* (GPM) 300 300 -

Head* (Ft) 140 140 -

Pump Efficiency (%) 75.0% 75.0% -

Motor Efficiency (%) 91.0% 94.1% 3.1%

Operating Hrs 1600 1600 -

Estimated Power (HP) 15.5 15.0 0.51

Elec Cost ($/kWh) 0.162 0.162 -

ECM RESULTS EXISTING PROPOSED SAVINGS

Electric Energy (kWh) 20,383 8,575 11,808

Electric Energy Cost ($) $3,302 $1,389 $1,913

CHILLER PUMPS VFD CALULATION

ENERGY SAVINGS CALCULATIONS

COMMENTS:

Page 26: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 25 of 30

Energy Savings Summary:

Installation Cost ($): $119,859NJ Smart Start Equipment Incentive ($): $250Net Installation Cost ($): $119,609Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $1,913Total Yearly Savings ($/Yr): $1,913Estimated ECM Lifetime (Yr): 15Simple Payback 62.5Simple Lifetime ROI -76.0%Simple Lifetime Maintenance Savings 0Simple Lifetime Savings $28,695Internal Rate of Return (IRR) -14%Net Present Value (NPV) ($96,771.31)

ECM #6 - ENERGY SAVINGS SUMMARY

Page 27: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 26 of 30

ECM #7: Set Computers to Automatic Stand-by or Hibernate Modes Description: During the survey, it was noticed that the majority of the computers were left at ON position with the monitors at Screen Saver or OFF positions. Many personal computers (PC) came equipped with automatic Sleep Mode or Hibernate (power down) mode features. Normally computers boot up from Sleep Mode or Hibernate mode much faster than powering up from Shut Down position. Based on an independent study by the U.S. Department of Energy, Energy star® rated computers use approximately 70% less power during Sleep Mode. It is recommended to set up the PCs at this facility to switch into Sleep Mode after a short period of inactivity and Hibernate mode after a long period of inactivity. This ECM includes configuring the computers in the classrooms and the offices such that they automatically switch into:

- Sleep Mode after 15 minutes of inactivity - Hibernate after 60 minutes of inactivity

The inactivity times above can be adjusted based on experience or preference. Even though this ECM can be implemented easily in house, the calculations assume an independent computer technician performing the task at a typical market rate. Energy Savings Calculations: No. of Computers: 46 Operating Weeks per Year: 42 Estimated percentage of computers left ON overnight: 75%

( ) ( )

××=

KWW1000

HrsOperationWPowerComputerComputersof#UsageElectric

( )

×=

kWh$CostElecAvekWhUsageElectricCostEnergy

The cost of configuring the computers to automatically sleep or hibernate is based on 10 minutes per computer per technician at an hourly rate indicated below.

Page 28: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 27 of 30

Implementation Costs: = # Computers X Configuration Time X Cost per Hour = 46 Computers X 10 Minutes/Computer X $100 per Hour

= $767

ECM INPUTS EXISTING PROPOSED SAVINGSECM INPUTS Manual Operation Auto Power Save -

# of Computers 46 46 -

% Computers left ON 75% 75% -

Power when left ON (Watt) 50 50 -

Power at Stand-by (Watt) 5 5 -

Power at Hibernate (Watt) 4 4 -

Power when OFF (Watt) 0 0 -

Operating Weeks per Yr 42 42 -

Operating Hours per Week 168 168 -

Hours/Wk Computers ON 120 20 -

Hours/Wk at Sleep Mode 0 20 -

Hours/Wk at Hibernate Mode 0 80 -

Hours/Wk at Power Down 48 48 -

Elec Cost ($/kWh) 0.163 0.163 -

ECM RESULTS EXISTING PROPOSED SAVINGS

Electric Usage (kWh) 8,694 1,594 7,100

Energy Cost ($) $1,417 $260 $1,157

COMMENTS:

ENERGY SAVINGS CALCULATIONS

Calculation assumes computers currently run throughout work week and get shut down over the weekend.

AUTOMATIC SLEEP OR HIBERNATE MODES FOR COMPUTERS

Page 29: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 28 of 30

Energy Savings Summary:

Installation Cost ($): $767NJ Smart Start Equipment Incentive ($): $0Net Installation Cost ($): $767Maintenance Savings ($/Yr): $0Energy Savings ($/Yr): $1,157Total Yearly Savings ($/Yr): $1,157Estimated ECM Lifetime (Yr): 15Simple Payback 0.7Simple Lifetime ROI 2162.7%Simple Lifetime Maintenance Savings $0Simple Lifetime Savings $17,355Internal Rate of Return (IRR) 151%Net Present Value (NPV) $13,045.19

ECM #7 - ENERGY SAVINGS SUMMARY

Page 30: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 29 of 30

REM #1: 77.08 kW Solar System Description: The Oakview Elementary School has available roof and parking lot space that could accommodate a significant amount of solar generation. Based on the available areas a 77.08 kilowatt solar array could be installed, assuming the existing roof structure is capable of supporting an array. The array will produce approximately 91,296 kilowatt-hours annually that will reduce the overall electric usage of the facility by 4.7%. Energy Savings Calculations: See Renewable / Distributed Energy Measures Calculations Appendix for detailed financial summary and proposed solar layout areas. Financial results in table below are based on 100% financing of the system over a fifteen year period. Energy Savings Summary:

System Size (KWDC): 77.08Electric Generation (KWH/Yr): 91,296Installation Cost ($): $475,926SREC Revenue ($/Yr): $17,445Energy Savings ($/Yr): $14,790Total Yearly Savings ($/Yr): $32,235ECM Analysis Period (Yr): 15Simple Payback (Yrs): 14.8

Analysis Period Electric Savings ($): $275,077

Analysis Period SREC Revenue ($): $252,716Net Present Value (NPV) ($149,866.98)

REM #1 - ENERGY SAVINGS SUMMARY

Page 31: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit

Concord Engineering Group, Inc. 9C12051 January 17, 2013 FINAL Page 30 of 30

V. ADDITIONAL RECOMMENDATIONS The following recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the office of Clean Energy but save energy none the less.

A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency. Poorly maintained heat transfer surfaces can reduce efficiency 5-10%.

B. Maintain all weather stripping on windows and doors.

C. Clean all light fixtures to maximize light output.

D. Provide more frequent air filter changes to decrease overall system power usage and maintain better IAQ.

E. Turn off computers when not in use. Ensure computers are not running in screen saver mode.

F. Ensure outside air dampers are functioning properly and only open during occupied mode.

Page 32: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX A

Page 33: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

APPENDIX A1 of 1

LIFETIME ENERGY SAVINGS

LIFETIME MAINTENANCE

SAVINGSLIFETIME ROI SIMPLE PAYBACK INTERNAL RATE OF

RETURN (IRR)NET PRESENT VALUE

(NPV)

MATERIAL LABOR REBATES, INCENTIVES

NET INSTALLATION

COSTENERGY MAINT. / SREC TOTAL (Yearly Saving * ECM Lifetime) (Yearly Maint Svaing * ECM

Lifetime)(Lifetime Savings - Net Cost) /

(Net Cost) (Net cost / Yearly Savings)

($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($)

ECM #1 Lighting Upgrade (CFL's) $78 $351 $0 $429 $59 $0 $59 15 $891 $0 107.7% 7.2 10.92% $279.98

ECM #2 Lighting Upgrade Gymnasium $2,844 $2,220 $0 $5,064 $233 $0 $233 15 $3,488 $0 -31.1% 21.8 -4.34% ($2,288.40)

ECM #3 Lighting Controls Upgrade $7,950 $1,500 $945 $8,505 $1,987 $0 $1,987 15 $29,809 $0 250.5% 4.3 22.21% $15,218.62

ECM #4 Domestic Hot Water Heater Upgrade $12,600 $3,000 $398 $15,202 $682 $0 $682 12 $8,184 $0 -46.2% 22.3 -8.44% ($8,413.37)

ECM #5 NEMA Premium Motor Replacement $6,942 $6,270 $430 $12,782 $570 $0 $570 18 $10,260 $0 -19.7% 22.4 -2.22% ($4,942.50)

ECM #6 VFD on Chilled Water Pumps $44,398 $75,461 $250 $119,609 $1,913 $0 $1,913 15 $28,695 $0 -76.0% 62.5 -14.14% ($96,771.31)

ECM #7 Computer Standby or Hibernate $0 $767 $0 $767 $1,157 $0 $1,157 15 $17,355 $0 2162.7% 0.7 150.85% $13,045.19

REM #1 77.08 KW PV System $475,926 $0 $0 $475,926 $14,790 $17,445 $32,235 15 $483,528 $261,679 1.6% 14.8 0.20% ($91,104.57)

Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period.2) The variable DR in the NPV equation stands for Discount Rate3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period .

REM RENEWABLE ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

ECM COST & SAVINGS BREAKDOWNCONCORD ENGINEERING GROUP

West Deptford BOE - Oakview Elementary School

INSTALLATION COST YEARLY SAVINGSECM

LIFETIMEDESCRIPTIONECM NO.

ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

Page 34: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX B

Page 35: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix B Page 1 of 4

Concord Engineering Group, Inc. 520 BURNT MILL ROAD VOORHEES, NEW JERSEY 08043 PHONE: (856) 427-0200 FAX: (856) 427-6508

SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives as of February 15, 2011:

Electric Chillers Water-Cooled Chillers $12 - $170 per ton

Air-Cooled Chillers $8 - $52 per ton

Energy Efficiency must comply with ASHRAE 90.1-2007

Gas Cooling Gas Absorption Chillers $185 - $400 per ton

Gas Engine-Driven Chillers Calculated through custom measure

path)

Desiccant Systems $1.00 per cfm – gas or electric

Electric Unitary HVAC Unitary AC and Split Systems $73 - $92 per ton

Air-to-Air Heat Pumps $73 - $92 per ton Water-Source Heat Pumps $81 per ton

Packaged Terminal AC & HP $65 per ton Central DX AC Systems $40- $72 per ton

Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat

(Hospitality & Institutional Facility) $75 per thermostat

Energy Efficiency must comply with ASHRAE 90.1-2007

Gas Heating Gas Fired Boilers < 300 MBH $300 per unit

Gas Fired Boilers ≥ 300 - 1500 MBH $1.75 per MBH

Gas Fired Boilers ≥1500 - ≤ 4000 MBH $1.00 per MBH

Gas Fired Boilers > 4000 MBH (Calculated through Custom Measure

Path)

Gas Furnaces $300 - $400 per unit, AFUE ≥ 92%

Page 36: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix B Page 2 of 4

Ground Source Heat Pumps

Closed Loop $450 per ton, EER ≥ 16 $600 per ton, EER ≥ 18 $750 per ton, EER ≥ 20

Energy Efficiency must comply with ASHRAE 90.1-2007

Variable Frequency Drives Variable Air Volume $65 - $155 per hp

Chilled-Water Pumps $60 per VFD rated hp

Compressors $5,250 to $12,500 per drive

Cooling Towers ≥ 10 hp $60 per VFD rated hp

Natural Gas Water Heating

Gas Water Heaters ≤ 50 gallons, 0.67 energy factor or better

$50 per unit

Gas-Fired Water Heaters > 50 gallons $1.00 - $2.00 per MBH

Gas-Fired Booster Water Heaters $17 - $35 per MBH

Gas Fired Tankless Water Heaters $300 per unit

Prescriptive Lighting Retro fit of T12 to T-5 or T-8 Lamps

w/Electronic Ballast in Existing Facilities

$10 per fixture (1-4 lamps)

Replacement of T12 with new T-5 or T-8 Lamps w/Electronic Ballast in

Existing Facilities $25 per fixture (1-4 lamps)

Replacement of incandescent with screw-in PAR 38 or PAR 30 (CFL)

bulb $7 per bulb

T-8 reduced Wattage (28w/25w 4’, 1-4 lamps)

Lamp & ballast replacement $10 per fixture

Hard-Wired Compact Fluorescent $25 - $30 per fixture

Metal Halide w/Pulse Start Including Parking Lot

$25 per fixture

T-5 and T-8 High Bay Fixtures $16 - $200 per fixture

HID ≥ 100w Retrofit with induction lamp, power coupler and generator

(must be 30% less watts/fixture than HID system)

$50 per fixture

HID ≥ 100w Replacement with new HID ≥ 100w

$70 per fixture

Page 37: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix B Page 3 of 4

Prescriptive Lighting - LED

LED New Exit Sign Fixture Existing Facility < 75 kw Existing Facility > 75 kw

$20 per fixture $10 per fixture

LED Display Case Lighting $30 per display case

LED Shelf-Mtd. Display & Task Lights $15 per linear foot

LED Portable Desk Lamp $20 per fixture

LED Wall-wash Lights $30 per fixture

LED Recessed Down Lights $35 per fixture LED Outdoor Pole/Arm-Mounted Area

and Roadway Luminaries $175 per fixture

LED Outdoor Pole/Arm-Mounted Decorative Luminaries

$175 per fixture

LED Outdoor Wall-Mounted Area Luminaries

$100 per fixture

LED Parking Garage Luminaries $100 per fixture

LED Track or Mono-Point Directional Lighting Fixtures

$50 per fixture

LED High-Bay and Low-Bay Fixtures for Commercial & Industrial Bldgs.

$150 per fixture

LED High-Bay-Aisle Lighting $150 per fixture

LED Bollard Fixtures $50 per fixture

LED Linear Panels (2x2 Troffers only) $100 per fixture

LED Fuel Pump Canopy $100 per fixture

LED Refrigerator/Freezer case lighting replacement of fluorescent in medium

and low temperature display case

$42 per 5 foot $65 per 6 foot

Page 38: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix B Page 4 of 4

Lighting Controls – Occupancy Sensors

Wall Mounted $20 per control Remote Mounted $35 per control

Daylight Dimmers $25 per fixture

Occupancy Controlled hi-low Fluorescent Controls

$25 per fixture controlled

Lighting Controls – HID or Fluorescent Hi-Bay Controls Occupancy hi-low $75 per fixture controlled Daylight Dimming $75 per fixture controlled

Daylight Dimming - office $50 per fixture controlled

Premium Motors Three-Phase Motors $45 - $700 per motor

Fractional HP Motors Electronic Communicated Motors (replacing shaded pole motors in

refrigerator/freezer cases)

$40 per electronic communicated motor

Other Equipment Incentives

Performance Lighting

$1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE 90.1-

2007 for New Construction and Complete Renovation

Custom Electric and Gas Equipment Incentives

not prescriptive

Custom Measures

$0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year

payback on estimated savings. Minimum required savings of 75,000 KWh or 1,500 Therms and a IRR of at

least 10%. Multi Measures Bonus 15%

Page 39: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX C

Page 40: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

OMB No. 2060-0347

STATEMENT OF ENERGY PERFORMANCEWest Deptford School District - Oakview ElementarySchool

Building ID: 3278820 For 12-month Period Ending: November 30, 20111

Date SEP becomes ineligible: N/A Date SEP Generated: October 19, 2012

FacilityWest Deptford School District - OakviewElementary School350 DuBois AvenueWoodbury, NJ 08096

Facility OwnerWest Deptford Township Public SchoolDistrict675 Grove Road West Deptford, NJ 08066

Primary Contact for this FacilityWilliam Thompson675 Grove Road West Deptford, NJ 08066

Year Built: 1956Gross Floor Area (ft2): 41,905

Energy Performance Rating2 (1-100) 1

Site Energy Use Summary3

Electricity - Grid Purchase(kBtu) 6,204,026 Natural Gas (kBtu)4 490,400 Total Energy (kBtu) 6,694,426

Energy Intensity4 Site (kBtu/ft2/yr) 160 Source (kBtu/ft2/yr) 507 Emissions (based on site energy use) Greenhouse Gas Emissions (MtCO2e/year) 905 Electric Distribution Utility Public Service Electric & Gas Co National Median Comparison National Median Site EUI 44 National Median Source EUI 138 % Difference from National Median Source EUI 267% Building Type K-12

School

Stamp of Certifying Professional

Based on the conditions observed at thetime of my visit to this building, I certify that

the information contained within thisstatement is accurate.

Meets Industry Standards5 for Indoor EnvironmentalConditions:Ventilation for Acceptable Indoor Air Quality N/A Acceptable Thermal Environmental Conditions N/A Adequate Illumination N/A

Certifying ProfessionalMichael Fischette520 South Burnt Mill Road Voorhees, NJ 08043

Notes: 1. Application for the ENERGY STAR must be submitted to EPA within 4 months of the Period Ending date. Award of the ENERGY STAR is not final until approval is received from EPA.2. The EPA Energy Performance Rating is based on total source energy. A rating of 75 is the minimum to be eligible for the ENERGY STAR.3. Values represent energy consumption, annualized to a 12-month period.4. Values represent energy intensity, annualized to a 12-month period.5. Based on Meeting ASHRAE Standard 62 for ventilation for acceptable indoor air quality, ASHRAE Standard 55 for thermal comfort, and IESNA Lighting Handbook for lighting quality.

The government estimates the average time needed to fill out this form is 6 hours (includes the time for entering energy data, Licensed Professional facility inspection, and notarizing the SEP) andwelcomes suggestions for reducing this level of effort. Send comments (referencing OMB control number) to the Director, Collection Strategies Division, U.S., EPA (2822T), 1200 Pennsylvania Ave.,NW, Washington, D.C. 20460.

EPA Form 5900-16

Page 41: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

ENERGY STAR®

Data Checklistfor Commercial Buildings

In order for a building to qualify for the ENERGY STAR, a Professional Engineer (PE) or a Registered Architect (RA) must validate the accuracy of the data underlyingthe building's energy performance rating. This checklist is designed to provide an at-a-glance summary of a property's physical and operating characteristics, as well asits total energy consumption, to assist the PE or RA in double-checking the information that the building owner or operator has entered into Portfolio Manager.

Please complete and sign this checklist and include it with the stamped, signed Statement of Energy Performance.NOTE: You must check each box to indicate that each value is correct, OR include a note.

CRITERION VALUE AS ENTERED INPORTFOLIO MANAGER VERIFICATION QUESTIONS NOTES

Building Name West Deptford School

District - OakviewElementary School

Is this the official building name to be displayed inthe ENERGY STAR Registry of LabeledBuildings?

Type K-12 School Is this an accurate description of the space inquestion?

Location 350 DuBois Avenue,Woodbury, NJ 08096

Is this address accurate and complete? Correctweather normalization requires an accurate zipcode.

Single Structure Single Facility

Does this SEP represent a single structure? SEPscannot be submitted for multiple-buildingcampuses (with the exception of a hospital, k-12school, hotel and senior care facility) nor can theybe submitted as representing only a portion of abuilding.

Oakview Elementary School (K-12 School)

CRITERION VALUE AS ENTERED INPORTFOLIO MANAGER VERIFICATION QUESTIONS NOTES

Gross Floor Area 41,905 Sq. Ft.

Does this square footage include all supportingfunctions such as kitchens and break rooms usedby staff, storage areas, administrative areas,elevators, stairwells, atria, vent shafts, etc. Alsonote that existing atriums should only include thebase floor area that it occupies. Interstitial(plenum) space between floors should not beincluded in the total. Finally gross floor area is notthe same as leasable space. Leasable space is asubset of gross floor area.

Open Weekends? No

Is this building normally open at all on theweekends? This includes activities beyond thework conducted by maintenance, cleaning, andsecurity personnel. Weekend activity could includeany time when the space is used for classes,performances or other school or communityactivities. If the building is open on the weekend aspart of the standard schedule during one or moreseasons, the building should select ?yes? for openweekends. The ?yes? response should applywhether the building is open for one or both of theweekend days.

Number of PCs 46 Is this the number of personal computers in theK12 School?

Number of walk-inrefrigeration/freezer

units 0

Is this the total number of commercial walk-in typefreezers and coolers? These units are typicallyfound in storage and receiving areas.

Presence ofcooking facilities Yes

Does this school have a dedicated space in whichfood is prepared and served to students? If theschool has space in which food for students is onlykept warm and/or served to students, or has only agalley that is used by teachers and staff then theanswer is "no".

Percent Cooled 70 % Is this the percentage of the total floor space withinthe facility that is served by mechanical coolingequipment?

Percent Heated 100 % Is this the percentage of the total floor space withinthe facility that is served by mechanical heatingequipment?

Months 10(Optional) Is this school in operation for at least 8 months ofthe year?

Page 1 of 4

Page 42: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

High School? No

Is this building a high school (teaching grades 10,11, and/or 12)? If the building teaches to highschool students at all, the user should check 'yes'to 'high school'. For example, if the school teachesto grades K-12 (elementary/middle and highschool), the user should check 'yes' to 'highschool'.

Page 2 of 4

Page 43: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

ENERGY STAR®

Data Checklistfor Commercial Buildings

Energy ConsumptionPower Generation Plant or Distribution Utility: Public Service Electric & Gas Co

Fuel Type: Electricity

Meter: electric (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2011 11/30/2011 167,036.00

10/01/2011 10/31/2011 156,602.00

09/01/2011 09/30/2011 185,512.00

08/01/2011 08/31/2011 185,546.00

07/01/2011 07/31/2011 260,032.00

06/01/2011 06/30/2011 191,075.00

05/01/2011 05/31/2011 122,118.00

04/01/2011 04/30/2011 112,811.00

03/01/2011 03/31/2011 103,504.00

02/01/2011 02/28/2011 111,324.00

01/01/2011 01/31/2011 111,387.00

12/01/2010 12/31/2010 111,349.00

electric Consumption (kWh (thousand Watt-hours)) 1,818,296.00

electric Consumption (kBtu (thousand Btu)) 6,204,025.95

Total Electricity (Grid Purchase) Consumption (kBtu (thousand Btu)) 6,204,025.95

Is this the total Electricity (Grid Purchase) consumption at this building including allElectricity meters?

Fuel Type: Natural Gas

Meter: gas (therms)Space(s): Entire Facility

Start Date End Date Energy Use (therms)

11/01/2011 11/30/2011 596.00

10/01/2011 10/31/2011 411.00

09/01/2011 09/30/2011 136.00

08/01/2011 08/31/2011 68.00

07/01/2011 07/31/2011 0.00

06/01/2011 06/30/2011 66.00

05/01/2011 05/31/2011 219.00

04/01/2011 04/30/2011 337.00

03/01/2011 03/31/2011 538.00

02/01/2011 02/28/2011 815.00

Page 3 of 4

Page 44: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

01/01/2011 01/31/2011 910.00

12/01/2010 12/31/2010 808.00

gas Consumption (therms) 4,904.00

gas Consumption (kBtu (thousand Btu)) 490,400.00

Total Natural Gas Consumption (kBtu (thousand Btu)) 490,400.00

Is this the total Natural Gas consumption at this building including all Natural Gas meters?

Additional FuelsDo the fuel consumption totals shown above represent the total energy use of this building?Please confirm there are no additional fuels (district energy, generator fuel oil) used in this facility.

On-Site Solar and Wind EnergyDo the fuel consumption totals shown above include all on-site solar and/or wind power located atyour facility? Please confirm that no on-site solar or wind installations have been omitted from thislist. All on-site systems must be reported.

Certifying Professional (When applying for the ENERGY STAR, the Certifying Professional must be the same PE or RA that signed and stamped the SEP.)

Name: _____________________________________________ Date: _____________

Signature: ______________________________________ Signature is required when applying for the ENERGY STAR.

Page 4 of 4

Page 45: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

FOR YOUR RECORDS ONLY. DO NOT SUBMIT TO EPA.

Please keep this Facility Summary for your own records; do not submit it to EPA. Only the Statement of Energy Performance(SEP), Data Checklist and Letter of Agreement need to be submitted to EPA when applying for the ENERGY STAR.

FacilityWest Deptford School District - OakviewElementary School350 DuBois AvenueWoodbury, NJ 08096

Facility OwnerWest Deptford Township Public SchoolDistrict675 Grove Road West Deptford, NJ 08066

Primary Contact for this FacilityWilliam Thompson675 Grove Road West Deptford, NJ 08066

General InformationWest Deptford School District - Oakview Elementary School

Gross Floor Area Excluding Parking: (ft2) 41,905 Year Built 1956 For 12-month Evaluation Period Ending Date: November 30, 2011

Facility Space Use SummaryOakview Elementary School

Space Type K-12 School

Gross Floor Area (ft2) 41,905

Open Weekends? No

Number of PCs 46

Number of walk-in refrigeration/freezerunits 0

Presence of cooking facilities Yes

Percent Cooled 70

Percent Heated 100

Months o 10

High School? No

School District o West Deptford

Energy Performance ComparisonEvaluation Periods Comparisons

Performance Metrics Current(Ending Date 11/30/2011)

Baseline(Ending Date 11/30/2011) Rating of 75 Target National Median

Energy Performance Rating 1 1 75 N/A 50

Energy Intensity

Site (kBtu/ft2) 160 160 34 N/A 44

Source (kBtu/ft2) 507 507 108 N/A 138

Energy Cost

$/year N/A N/A N/A N/A N/A

$/ft2/year N/A N/A N/A N/A N/A

Greenhouse Gas Emissions

MtCO2e/year 905 905 193 N/A 246

kgCO2e/ft2/year 22 22 5 N/A 6

More than 50% of your building is defined as K-12 School. Please note that your rating accounts for all of the spaces listed. The National Median column presentsenergy performance data your building would have if your building had a median rating of 50. Notes:o - This attribute is optional.d - A default value has been supplied by Portfolio Manager.

Page 46: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

2011West Deptford School District - OakviewElementary School350 DuBois AvenueWoodbury, NJ 08096

Portfolio Manager Building ID: 3278820

The energy use of this building has been measured and compared to other similar buildings using theEnvironmental Protection Agency’s (EPA’s) Energy Performance Scale of 1–100, with 1 being the least energyefficient and 100 the most energy efficient. For more information, visit energystar.gov/benchmark.

This building’sscore

1

100

Most Efficient

This building uses 507 kBtu per square foot per year.*

*Based on source energy intensity for the 12 month period ending November 2011

Date of certification

Date Generated: 10/19/2012

Statement ofEnergy Performance

1

Least Efficient

50

Median

Buildings with a score of75 or higher may qualifyfor EPA’s ENERGY STAR.

I certify that the information contained within this statement is accurate and in accordance with U.S.Environmental Protection Agency’s measurement standards, found at energystar.gov

Page 47: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX D

Page 48: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix DPage 1 of 5

AC UnitsTag

Unit Type Packaged Heat Pump

Qty 1

Location Roof

Area Served Library

Manufacturer Trane

Model # WSC090E3R0A0

Serial # 114510571L

Cooling Type DX, R410A

Cooling Capacity (Tons) 7.5 Tons

Cooling Efficiency (SEER/EER)

13 SEER/ 10.1 EER

Heating Type Heat Pump

Heating Input (MBH) 88 MBH

Efficiency 3.2 COP

Fuel Heat Pump

Approx Age 1

ASHRAE Service Life 15

Remaining Life 14

Comments

Note:

MAJOR EQUIPMENT LISTConcord Engineering Group

Oakview Elementary School

"N/A" = Not Applicable. "-" = Info Not Available

Page 49: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix DPage 2 of 5

BoilersTag

Unit Type Cast Iron Sectional Boiler

Cast Iron Sectional Boiler

Cast Iron Sectional Boiler

Qty 1 1 1

Location Mechanical Room Mechanical Room Mechanical Room

Area Served Hot Water Boiler Loop Hot Water Boiler Loop Hot Water Boiler Loop

Manufacturer Weil McLain Weil McLain Weil McLain

Model # P-1178-W P-1178-W P-1178-W

Serial # 98-11011-H 98-11013-H 98-11015-H

Input Capacity (Btu/Hr) 1,527 1,527 1,527

Rated Output Capacity (Btu/Hr) 1,250 1,250 1,250

Approx. Efficiency % 75.0% 75.0% 75.0%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 14 14 14

ASHRAE Service Life 35 35 35

Remaining Life 21 21 21

Comments Power Flame Burner MN: WCR2-G-15 SN: 59804698

Note:

MAJOR EQUIPMENT LISTConcord Engineering Group

Oakview Elementary School

"N/A" = Not Applicable. "-" = Info Not Available

Page 50: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix DPage 3 of 5

Domestic Water HeatersTag

Unit Type Commercial Domestic Hot Water Heater

Qty 1

Location Mechanical Room

Area Served Domestic Loop

Manufacturer AO Smith

Model # BTC 250 970

Serial # MG98-0756247-970

Size (Gallons) 100

Input Capacity (MBH/KW) 250

Recovery (Gal/Hr) 227.3

Efficiency % 80%

Fuel Natural Gas

Approx Age 14

ASHRAE Service Life 12

Remaining Life (2)

Comments

Note:

MAJOR EQUIPMENT LISTConcord Engineering Group

Oakview Elementary School

"N/A" = Not Applicable. "-" = Info Not Available

Page 51: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix DPage 4 of 5

PumpsTag

Unit Type Base Mounted End Suction Pumps

Base Mounted End Suction Pumps

Qty 2 2

Location Mechanical Room Mechanical Room

Area Served Chilled Water Loop Hot Water Boiler Loop

Manufacturer Bell & Gossett Bell & Gossett

Model # 1510 Series 1510 Series

Serial # 2138534 2089036

Horse Power 20 7.5

Flow 300 GPM @ 140 FTHD 120 GPM @ 110 FTHD

Motor Info US Motors Marathon Motors

Electrical Power 208-230/460/3/60 230/460/3/60

RPM 1765 1760

Motor Efficiency % 88.5 88.5

Approx Age 14 14

ASHRAE Service Life 20 20

Remaining Life 6 6

Comments

Note:

MAJOR EQUIPMENT LISTConcord Engineering Group

Oakview Elementary School

"N/A" = Not Applicable. "-" = Info Not Available

Page 52: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix DPage 5 of 5

Cooling TowerTag

Unit Type Air Cooled Rotary Chiller

Qty 1

Location Outside of Mech Room

Area Served Chilled Water Loop

Manufacturer Trane

Model # RTAA125AYJ01A0D1BDFMN

Serial # U98G01971

Refrigerant R-22

Cooling Capacity (Tons) 125 Tons

Cooling Efficiency (KW/Ton)

9.8 EER

Volts / Phase / Hz 200/60/3

Fuel Electric

Chilled Water GPM / ΔT 300 GPM / 10°∆T

Condenser Water GPM / ΔT

N/A

Approx Age 14

ASHRAE Service Life 20

Remaining Life 6

Comments Only Evaporator GPM

Note:

MAJOR EQUIPMENT LISTConcord Engineering Group

Oakview Elementary School

"N/A" = Not Applicable. "-" = Info Not Available

Page 53: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX E

Page 54: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix E - Lighting Audit - Oakview Elementary School new.xlsx Page 1

CEG Project #:Facility Name: Address:City, State, Zip

Fixture Reference # Location

Average Burn Hours

Description Lamps per Fixture

Watts per Fixture

Qty of Fixtures

Total kW

Usage kWh/Yr Work Description Equipment Description Lamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Energy Savings,

kW

Energy Savings,

kWh

Energy Savings, $ Material Total Labor Total All Rebate

EstimateSimple

PaybackControl

Ref # Controls Description Qty of Controls

Hour Reduction

%

Energy Savings,

kWh

Energy Savings, $

1 Room 1 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

4 Room 1 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

9 Room 1 1200 1x4, 2 Lamp, 32w, T8, Wall Mnt, Prismatic Lens 2 62 1 0.06 74 Existing to Remain Existing to Remain 2 62 0 0.06 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 2 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

4 Room 2 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

8 Room 2 600 1 Lamp, 26w CFL 1 26 1 0.03 16 Existing to Remain Existing to Remain 1 26 0 0.03 16 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Room 2 600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 64 Existing to Remain Existing to Remain 4 106.7 0 0.11 64 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 3 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

5 Room 3 600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 64 Existing to Remain Existing to Remain 4 106.7 0 0.11 64 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

7 Room 3 600 2 Lamp, 7w CFL Globe, Surface Mnt. 2 14 1 0.01 8 Existing to Remain Existing to Remain 2 14 0 0.01 8 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

8 Room 3 600 1 Lamp, 26w CFL 1 26 1 0.03 16 Existing to Remain Existing to Remain 1 26 0 0.03 16 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 4 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 22 1.36 3,546 Existing to Remain Existing to Remain 2 62 0 1.36 3,546 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 709 $115

4 Room 4 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

7 Room 4 600 2 Lamp, 7w CFL Globe, Surface Mnt. 2 14 1 0.01 8 Existing to Remain Existing to Remain 2 14 0 0.01 8 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

7 Room 4 600 2 Lamp, 7w CFL Globe, Surface Mnt. 2 14 1 0.01 8 Existing to Remain Existing to Remain 2 14 0 0.01 8 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 5 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

1 Office 1 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 7 0.43 1,128 Existing to Remain Existing to Remain 2 62 0 0.43 1,128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 226 $37

2 Office 1 6002x2, 2 Lamp, 17w F017, Surface Mnt, Prismatic

Lens2 33 1 0.03 20 Existing to Remain Existing to Remain 2 33 0 0.03 20 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Office 2 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 6 0.37 967 Existing to Remain Existing to Remain 2 62 0 0.37 967 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 193 $31

4 Office 2 600 60w Incandescent 1 60 5 0.30 180 Relamp 13w CFL 1 13 5 0.07 39 0.24 141 $23 $30.00 $135.00 $165.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

3 Main Entrance 3000 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 1 0.06 186 Existing to Remain Existing to Remain 2 62 0 0.06 186 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Front Hallway 3000 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 13 0.81 2,418 Existing to Remain Existing to Remain 2 62 0 0.81 2,418 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 East Hallway 3000 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 7 0.43 1,302 Existing to Remain Existing to Remain 2 62 0 0.43 1,302 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 All-purpose room Hallway 3000 2x4, 2 Lamp, 32w, T8,

Recessed, Prismatic Lens 2 62 10 0.62 1,860 Existing to Remain Existing to Remain 2 62 0 0.62 1,860 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 6 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

Retrofit Energy Savings Proposed Lighting ControlsLighting Retrofit CostsExisting Fixtures Proposed Fixtures Retrofit

9C12051Oakview Elementary School

Woodbury, NJ 08096350 Dubois Avenue

Page 55: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix E - Lighting Audit - Oakview Elementary School new.xlsx Page 2

Fixture Reference # Location

Average Burn Hours

Description Lamps per Fixture

Watts per Fixture

Qty of Fixtures

Total kW

Usage kWh/Yr Work Description Equipment Description Lamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Energy Savings,

kW

Energy Savings,

kWh

Energy Savings, $ Material Total Labor Total All Rebate

EstimateSimple

PaybackControl

Ref # Controls Description Qty of Controls

Hour Reduction

%

Energy Savings,

kWh

Energy Savings, $

Retrofit Energy Savings Proposed Lighting ControlsLighting Retrofit CostsExisting Fixtures Proposed Fixtures Retrofit

1 Room 7 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

1 Room 8 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

1 Room 9 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 16 0.99 2,579 Existing to Remain Existing to Remain 2 62 0 0.99 2,579 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 516 $84

1 Room 10 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 16 0.99 2,579 Existing to Remain Existing to Remain 2 62 0 0.99 2,579 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 516 $84

1 Boys RR 12001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 3 0.19 223 Existing to Remain Existing to Remain 2 62 0 0.19 223 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Girls RR 12001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 3 0.19 223 Existing to Remain Existing to Remain 2 62 0 0.19 223 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

4 Hallway Storage 1 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

4 Hallway Storage 2 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

4 Hallway Storage 3 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

1 Small Group 1 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 6 0.37 967 Existing to Remain Existing to Remain 2 62 0 0.37 967 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 193 $31

1 Small Group 2 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 6 0.37 967 Existing to Remain Existing to Remain 2 62 0 0.37 967 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 193 $31

10 Hall Storage 6001x4, 2 Lamp, 32w, T8, Pendant Mnt, Prismatic

Lens2 62 4 0.25 149 Existing to Remain Existing to Remain 2 62 0 0.25 149 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Middle Hallway 3000 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 7 0.43 1,302 Existing to Remain Existing to Remain 2 62 0 0.43 1,302 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Library 2600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 27 2.88 7,490 Existing to Remain Existing to Remain 4 106.7 0 2.88 7,490 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Room 11A 2600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 7 0.75 1,942 Existing to Remain Existing to Remain 4 106.7 0 0.75 1,942 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 388 $63

1 Computer Lab 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

3 Health Suite 2600 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 4 0.25 645 Existing to Remain Existing to Remain 2 62 0 0.25 645 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

6 Health Suite Bathroom 1200 3', 1 Lamp, 25w, T8,

Surface Mnt, No lens 1 25.9 1 0.03 31 Existing to Remain Existing to Remain 1 25.9 0 0.03 31 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Health Suite 1 2600 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 1 0.06 161 Existing to Remain Existing to Remain 2 62 0 0.06 161 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Health Suite 2 2600 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 2 0.12 322 Existing to Remain Existing to Remain 2 62 0 0.12 322 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Storage 600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 3 0.32 192 Existing to Remain Existing to Remain 4 106.7 0 0.32 192 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

4 Storage 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

1 Room 12 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 14 0.87 2,257 Existing to Remain Existing to Remain 2 62 0 0.87 2,257 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 451 $73

9 Room 12 1200 1x4, 2 Lamp, 32w, T8, Wall Mnt, Prismatic Lens 2 62 1 0.06 74 Existing to Remain Existing to Remain 2 62 0 0.06 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Hallway Storage 6001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 1 0.06 37 Existing to Remain Existing to Remain 2 62 0 0.06 37 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 13 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 12 0.74 1,934 Existing to Remain Existing to Remain 2 62 0 0.74 1,934 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 387 $63

Page 56: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix E - Lighting Audit - Oakview Elementary School new.xlsx Page 3

Fixture Reference # Location

Average Burn Hours

Description Lamps per Fixture

Watts per Fixture

Qty of Fixtures

Total kW

Usage kWh/Yr Work Description Equipment Description Lamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Energy Savings,

kW

Energy Savings,

kWh

Energy Savings, $ Material Total Labor Total All Rebate

EstimateSimple

PaybackControl

Ref # Controls Description Qty of Controls

Hour Reduction

%

Energy Savings,

kWh

Energy Savings, $

Retrofit Energy Savings Proposed Lighting ControlsLighting Retrofit CostsExisting Fixtures Proposed Fixtures Retrofit

4 Room 13 600 60w Incandescent 1 60 1 0.06 36 Relamp 13w CFL 1 13 1 0.01 8 0.05 28 $5 $6.00 $27.00 $33.00 $0.00 7.2235356 0 No New Controls 0 0.0% 0 $0

9 Room 13 1200 1x4, 2 Lamp, 32w, T8, Wall Mnt, Prismatic Lens 2 62 1 0.06 74 Existing to Remain Existing to Remain 2 62 0 0.06 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 14 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 16 0.99 2,579 Existing to Remain Existing to Remain 2 62 0 0.99 2,579 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 516 $84

1 Room 14 6001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 2 0.12 74 Existing to Remain Existing to Remain 2 62 0 0.12 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Room 14 6001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 2 0.12 74 Existing to Remain Existing to Remain 2 62 0 0.12 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Small Group 2600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 2 0.21 555 Existing to Remain Existing to Remain 4 106.7 0 0.21 555 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 111 $18

10 Stage 26001x4, 2 Lamp, 32w, T8, Pendant Mnt, Prismatic

Lens2 62 10 0.62 1,612 Existing to Remain Existing to Remain 2 62 0 0.62 1,612 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

11 Stage 2600 26w CFL Pendant Mnt 1 26 8 0.21 541 Existing to Remain Existing to Remain 1 26 0 0.21 541 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

10 Stage Storage 6001x4, 2 Lamp, 32w, T8, Pendant Mnt, Prismatic

Lens2 62 2 0.12 74 Existing to Remain Existing to Remain 2 62 0 0.12 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Kitchen 2600 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 4 0.25 645 Existing to Remain Existing to Remain 2 62 0 0.25 645 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

10 Kitchen Storage 6001x4, 2 Lamp, 32w, T8, Pendant Mnt, Prismatic

Lens2 62 6 0.37 223 Existing to Remain Existing to Remain 2 62 0 0.37 223 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Faculty Dining 2600 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 4 0.25 645 Existing to Remain Existing to Remain 2 62 0 0.25 645 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 129 $21

1 Faculty Dining 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 1 0.06 161 Existing to Remain Existing to Remain 2 62 0 0.06 161 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Faculty Dining RR 12001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 1 0.06 74 Existing to Remain Existing to Remain 2 62 0 0.06 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

9 Faculty Dining RR 1200 1x4, 2 Lamp, 32w, T8, Wall Mnt, Prismatic Lens 2 62 1 0.06 74 Existing to Remain Existing to Remain 2 62 0 0.06 74 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

10 Receiving 6001x4, 2 Lamp, 32w, T8, Pendant Mnt, Prismatic

Lens2 62 8 0.50 298 Existing to Remain Existing to Remain 2 62 0 0.50 298 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Teacher RR 1200 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 128 Existing to Remain Existing to Remain 4 106.7 0 0.11 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Teacher RR 1200 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 128 Existing to Remain Existing to Remain 4 106.7 0 0.11 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 Janitor closet 600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 64 Existing to Remain Existing to Remain 4 106.7 0 0.11 64 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Faculty Work Room 2600 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 4 0.25 645 Existing to Remain Existing to Remain 2 62 0 0.25 645 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 5

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 129 $21

5 Rear Hallway 3000 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 8 0.85 2,561 Existing to Remain Existing to Remain 4 106.7 0 0.85 2,561 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Kindergarten 1 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 18 1.12 2,902 Existing to Remain Existing to Remain 2 62 0 1.12 2,902 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 580 $94

5 K1-k2 storage 1 600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 4 0.43 256 Existing to Remain Existing to Remain 4 106.7 0 0.43 256 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 K1-k2 storage 2 600 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 2 0.21 128 Existing to Remain Existing to Remain 4 106.7 0 0.21 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Kindergarten 2 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 18 1.12 2,902 Existing to Remain Existing to Remain 2 62 0 1.12 2,902 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 580 $94

1 HC Pre-School 1 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 18 1.12 2,902 Existing to Remain Existing to Remain 2 62 0 1.12 2,902 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 580 $94

Page 57: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix E - Lighting Audit - Oakview Elementary School new.xlsx Page 4

Fixture Reference # Location

Average Burn Hours

Description Lamps per Fixture

Watts per Fixture

Qty of Fixtures

Total kW

Usage kWh/Yr Work Description Equipment Description Lamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Energy Savings,

kW

Energy Savings,

kWh

Energy Savings, $ Material Total Labor Total All Rebate

EstimateSimple

PaybackControl

Ref # Controls Description Qty of Controls

Hour Reduction

%

Energy Savings,

kWh

Energy Savings, $

Retrofit Energy Savings Proposed Lighting ControlsLighting Retrofit CostsExisting Fixtures Proposed Fixtures Retrofit

5 HC Pre-School Storage 1 600 2x4, 4 Lamp, 32w, T8,

Recessed, Prismatic Lens 4 106.7 2 0.21 128 Existing to Remain Existing to Remain 4 106.7 0 0.21 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 HC Pre-School RR 1 1200 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 128 Existing to Remain Existing to Remain 4 106.7 0 0.11 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 HC Pre-School 2 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 18 1.12 2,902 Existing to Remain Existing to Remain 2 62 0 1.12 2,902 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 580 $94

5 HC Pre-School Storage 2 600 2x4, 4 Lamp, 32w, T8,

Recessed, Prismatic Lens 4 106.7 2 0.21 128 Existing to Remain Existing to Remain 4 106.7 0 0.21 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

5 HC Pre-School RR 2 1200 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 1 0.11 128 Existing to Remain Existing to Remain 4 106.7 0 0.11 128 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Classsroom 14 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 16 0.99 2,579 Existing to Remain Existing to Remain 2 62 0 0.99 2,579 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 516 $84

1 Classroom 15 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 12 0.74 1,934 Existing to Remain Existing to Remain 2 62 0 0.74 1,934 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 387 $63

1 Classroom 16 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 12 0.74 1,934 Existing to Remain Existing to Remain 2 62 0 0.74 1,934 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 387 $63

1 Classroom 17 26001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 12 0.74 1,934 Existing to Remain Existing to Remain 2 62 0 0.74 1,934 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 4

Dual Technology Occupancy Sensor -

Remote Mnt.1 20.0% 387 $63

5 Hallway 3000 2x4, 4 Lamp, 32w, T8, Recessed, Prismatic Lens 4 106.7 6 0.64 1,921 Existing to Remain Existing to Remain 4 106.7 0 0.64 1,921 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

1 Boiler room 6001x4, 2 Lamp, 32w, T8, Surface Mnt, Prismatic

Lens2 62 7 0.43 260 Existing to Remain Existing to Remain 2 62 0 0.43 260 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

3 Hall Near Boiler room 3000 2x4, 2 Lamp, 32w, T8, Recessed, Prismatic Lens 2 62 2 0.12 372 Existing to Remain Existing to Remain 2 62 0 0.12 372 0.00 0 $0 $0.00 $0.00 $0.00 $0.00 - 0 No New Controls 0 0.0% 0 $0

TOTAL 199 5942.8 568 38 88,954 13 37 88,588 1 367 59 78 351 429 0 30 6 12,267 1,987

Page 58: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix E - Lighting Audit - Oakview Elementary School new.xlsx Page 5

CEG Project #:Facility Name: Address:City, State, Zip

Fixture Reference # Location

Average Burn Hours

Description Lamps per Fixture

Watts per Fixture

Qty of Fixtures

Total kW

Usage kWh/Yr Work Description Equipment Description Lamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Energy Savings,

kW

Energy Savings,

kWh

Energy Savings, $ Material Total Labor Total All Rebate

EstimateSimple

PaybackControl

Ref # Controls Description Qty of Controls

Hour Reduction

%

Energy Savings,

kWh

Energy Savings, $

12 All Purpose Room 2600 400w Metal Halide 1 400 12 4.80 12,480 New Fixture 2x4 54w T5HO 6 Lamp w/Prismatic Lens 6 354 12 4.25 11,045 0.55 1,435 $233 $2,844.00 $2,220.00 $5,064.00 $0.00 21.78042 0 No New Controls 0 0.0% 0 $0

TOTAL 12 5 12,480 12 4 11,045 1 1,435 233 2,844 2,220 5,064 0 0 0 0 0

Retrofit Energy Savings Lighting Retrofit Costs Proposed Lighting ControlsProposed Fixtures Retrofit

9C12051Oakview Elementary School

350 Dubois AvenueWoodbury, NJ 08096

Existing Fixtures

Page 59: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX F

Page 60: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix FPage 1 of 2

Location Description

Area (Sq FT) Panel Qty

Panel Sq Ft

Panel Total Sq

FtTotal KWDC

Total Annual kWh

Total KWAC

Panel Weight

(41.9 lbs) W/SQFTOakview

Elementary8050 SHARP

NU-U235F2328 17.5 5,753 77.08 91,296 62.4 13,743 13.40

.= Proposed PV LayoutNotes:

1. Estimated kWH based on the National Renewable Energy Laboratory PVWatts Version 1 Calculator Program.

Page 61: WEST DEPTFORD TOWNSHIP PUBLIC S D · 1/17/2013  · West Deptford Twp. Public Schools – Oakview Elementary School Energy Audit Concord Engineering Group, Inc. 9C12051 January 17,

Appendix FPage 2 of 2

Project Name: LGEA Solar PV Project - Oakview ElementaryLocation: West Deptford, NJ

Description: Photovoltaic System 100% Financing - 15 year

Simple Payback Analysis

Total Construction Cost $475,926Annual kWh Production 91,296

Annual Energy Cost Reduction $14,790Average Annual SREC Revenue $17,445

Simple Payback: Years

Life Cycle Cost AnalysisAnalysis Period (years): 15 Financing %: 100%

Discount Rate: 3% Maintenance Escalation Rate: 3.0%Average Energy Cost ($/kWh) $0.162 Energy Cost Escalation Rate: 3.0%

Financing Rate: 6.00% Average SREC Value ($/kWh) $0.191Period Additional Energy kWh Energy Cost Additional SREC Interest Loan Net Cash Cumulative

Cash Outlay Production Savings Maint Costs Revenue Expense Principal Flow Cash Flow0 $0 0 0 0 $0 0 0 0 01 $0 91,296 $14,790 $0 $22,824 $28,006 $20,187 ($10,580) ($10,580)2 $0 90,840 $15,234 $0 $22,710 $26,761 $21,432 ($10,250) ($20,830)3 $0 90,385 $15,691 $0 $22,596 $25,439 $22,754 ($9,907) ($30,736)4 $0 89,933 $16,161 $0 $22,483 $24,036 $24,158 ($9,549) ($40,285)5 $0 89,484 $16,646 $922 $22,371 $22,546 $25,648 ($10,098) ($50,384)6 $0 89,036 $17,146 $917 $17,807 $20,964 $27,230 ($14,158) ($64,541)7 $0 88,591 $17,660 $912 $17,718 $19,285 $28,909 ($13,728) ($78,269)8 $0 88,148 $18,190 $908 $17,630 $17,502 $30,692 ($13,282) ($91,552)9 $0 87,707 $18,735 $903 $17,541 $15,609 $32,585 ($12,820) ($104,372)

10 $0 87,269 $19,298 $899 $13,090 $13,599 $34,595 ($16,705) ($121,076)11 $0 86,833 $19,876 $894 $13,025 $11,465 $36,729 ($16,187) ($137,263)12 $0 86,398 $20,473 $890 $12,960 $9,200 $38,994 ($15,651) ($152,914)13 $0 85,966 $21,087 $885 $12,895 $6,795 $41,399 ($15,097) ($168,011)14 $0 85,537 $21,720 $881 $8,554 $4,241 $43,952 ($18,801) ($186,813)15 $0 85,109 $22,371 $877 $8,511 $1,530 $46,663 ($18,188) ($205,001)

Totals: 1,322,533 $275,077 $9,889 $252,716 $246,978 $475,926 ($205,001) ($1,462,627)Net Present Value (NPV)

Photovoltaic System 100% Financing - 15 year

14.76

($149,867)