Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete...
Transcript of Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete...
![Page 1: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/1.jpg)
1
Welcome!We Will Begin Momentarily
Please submit all questions and comments via the chat room.
If you have called into this meeting and wish to submit questions or comments please
email [email protected].
If we do not respond to your question/comments tonight,
it will be responded to within 30 days of receipt.
Your question and answer will then be posted on www.DART.org/SilverLine
Thank You
![Page 2: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/2.jpg)
2
City of Plano – Betterments Workshop #4July 1, 2020
Dallas Area Rapid Transit (DART)Silver Line Regional Rail Project
![Page 3: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/3.jpg)
DART Community Engagement
Representative
3
![Page 4: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/4.jpg)
COVID-19 Update
4
Due to the current pandemic, all public involvement
sessions will take place via video conference.
DART urges you to follow the guidelines from the Centers
for Disease Control and Prevention (CDC) to keep your
family healthy and safe.
Stay up to date by attending public involvement sessions
online, signing up for construction alerts, visiting
DART.org/SilverLine or calling 214-749-2543.
![Page 5: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/5.jpg)
How To Stay Informed
5
Attend meetings virtually
![Page 6: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/6.jpg)
Questions and Answers
6
Please submit all questions and comments
via the chat room.
If you have called into this meeting and wish to submit
questions or comments please email
If we do not respond to your question/comments tonight,
it will be responded to within 30 days of receipt.
Your question and answer will then be posted on www.DART.org/SilverLine
Thank You
![Page 7: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/7.jpg)
Silver Line Project Update
7
• The design-build status for Silver Line is 59% complete as of June 30, 2020.
• The Silver Line vehicle design is 85% complete as of June 30, 2020.
• The Equipment Maintenance Facility design is at 65% complete as of June 30, 2020.
• As of July 1, 2020 active construction in DFW, Coppell, Addison and Carrollton.
• Currently in Plano you will see surveying, some excavation and light construction work happening. Heavy construction is currently scheduled to begin late July/August.
![Page 8: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/8.jpg)
Purpose of the Meeting
8
1. Review Results of the Previous Betterments
Workshops
2. Review Recommendations from DART for Color and
Finish of Betterment Walls
3. Obtain Input from Residential Adjacent Property
Owners on Color and Finish of Betterment Walls
![Page 9: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/9.jpg)
Betterments Consensus Results - Plano
9
Consensus Results are as follows:
• AuraOne 90 Plano• 1 out of 1 Votes Received
• 15' Betterment Wall
• Ezekial Way
• 1 out of 14 Votes Received
• 15' Betterment Wall
Previous Betterment Workshops were held on the following dates:
• Workshop #1 –March 28, 2019
• Workshop #2 – September 26, 2019
• Workshop #3a –October 10, 2019
• Workshop #3b –November 7, 2019
• Workshop #4 – July 1, 2020
![Page 10: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/10.jpg)
Betterments Consensus Results
10
![Page 11: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/11.jpg)
Aura One90 Plano – South
15’ Betterment Wall
11
![Page 12: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/12.jpg)
Aura One90 Plano – North
15’ Betterment Wall
12
![Page 13: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/13.jpg)
Betterments Consensus Results
13
![Page 14: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/14.jpg)
Ezekial Way – 15' Betterment Wall
14
![Page 15: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/15.jpg)
Ezekial Way – 15' Betterment Wall
15
![Page 16: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/16.jpg)
Ezekial Way – 15' Betterment Wall
16
![Page 17: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/17.jpg)
Durisol Wall Color Options
17
(DEFAULT)
![Page 18: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/18.jpg)
Durisol Finish Options
BUSH HAMMER (DEFAULT)
ROLLED BRICKROLLED DRYSTACK
ROLLED ASHLAR
18
![Page 19: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/19.jpg)
Surface Treatment and Finish
19
![Page 20: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/20.jpg)
Bush Hammer Finish
20
* Posts will not be painted or have cladding.
![Page 21: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/21.jpg)
Rolled Ashlar Finish
21
* Posts will not be painted or have cladding.
![Page 22: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/22.jpg)
Rolled Drystack Finish
22
* Posts will not be painted or have cladding.
![Page 23: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/23.jpg)
Rolled Brick Finish
23
* Posts will not be painted or have cladding.
![Page 24: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/24.jpg)
1082D Tan (Default)
24
* Posts will not be painted or have cladding.
![Page 25: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/25.jpg)
Bush Hammer Finish (Default)
25
* Posts will not be painted or have cladding.
![Page 26: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/26.jpg)
What To Expect Next
26
You will be receiving a letter confirming consensus for
your area along with a ballot to choose
Betterment wall color and finish.
We ask that you complete the ballot and submit it by the
enclosed date specified.
As we continue to progress with the project, DART will
contact you for any further needs to complete the project.
We strongly encourage you to sign up online to get project
and construction updates at www.DART.org/SilverLine.
![Page 27: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/27.jpg)
27
27Thank You For Joining Us!
If you still have questions or comments, please submit them to
We will respond to you question or comment within 30 days of receipt.
Your question and answer will then be
posted on www.DART.org/SilverLine
![Page 28: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/28.jpg)
28
28
![Page 29: Welcome! We Will Begin Momentarily · • The design-build status for Silver Line is 59% complete as of June 30, 2020. • The Silver Line vehicle design is 85% complete as of June](https://reader033.fdocuments.net/reader033/viewer/2022042416/5f31bc972335d5366a024552/html5/thumbnails/29.jpg)
Silver Line Project Map
29
Silver Line Regional Rail Project
Silver Line Station