WASTEWATER AUTOMATION THE DEVELOPMENT OF A LOW … · automation system that is reliable, robust,...
Transcript of WASTEWATER AUTOMATION THE DEVELOPMENT OF A LOW … · automation system that is reliable, robust,...
1
WASTEWATER AUTOMATION – THE DEVELOPMENT OF A
LOW COST DISTRIBUTED AUTOMATION SYSTEM
A Dissertation
Presented to
The Engineering Institute of Technology
by
Tom Davies
In Partial Fulfillment
of the Requirements for the Degree
Master of Engineering in
INDUSTRIAL AUTOMATION
APRIL 2017
COPYRIGHT © 2017 BY TOM DAVIES
2
TABLE OF CONTENTS
List of Tables ................................................................................................................. 7
List of Figures ................................................................................................................ 8
Abstract ........................................................................................................................ 10
Chapter 1. Introduction ................................................................................................ 17
1.1 The Problem Statement ................................................................................... 17
Chapter 2. Background ................................................................................................ 19
2.1 Moora Waste Water Scheme Overview .......................................................... 19
2.1.1 Catchment Areas ...................................................................................... 22
2.1.2 Pump Stations .......................................................................................... 22
2.1.3 Pump Station Components ....................................................................... 24
2.1.3.1 Switchboard ................................................................................ 24
2.1.3.2 Programmable Logic Controller ................................................. 25
2.1.3.3 Alarm Dialler .............................................................................. 25
2.1.4 Wastewater Treatment Plant (WWTP) .................................................... 26
2.2 Scheme Geography ......................................................................................... 26
2.2.1 Topology .................................................................................................. 27
2.2.2 Topography .............................................................................................. 31
Chapter 3. TheProblem ................................................................................................ 35
3.1 The Existing Problem ..................................................................................... 35
3.2 Problem Frequency and Cost .......................................................................... 36
3.2.1 Pump Station 3 Data ................................................................................ 37
3.3 Legislation....................................................................................................... 39
3.3.1 Regulatory Bodies .................................................................................... 39
3.3.1.1 Economic Regulation Authority (ERA) ..................................... 39
3.3.1.2 Department of Water (DoW) ...................................................... 39
3
3.3.1.3 Department of Health (DoH) ...................................................... 39
3.3.1.4 Department of Environmental Regulations (DER) ..................... 39
3.3.2 Prosecutions & Penalties.......................................................................... 40
3.3.3 Sewage Incidents ..................................................................................... 41
Chapter 4. Method ...................................................................................................... 42
4.1 Relevant Scholarship ...................................................................................... 43
4.2 Requirements .................................................................................................. 43
4.2.1 Alarms Proposed ...................................................................................... 43
4.2.2 Parameters ................................................................................................ 44
4.2.3 Pump current ............................................................................................ 44
4.2.4 Constraints / Factors ................................................................................ 44
4.2.5 In-house Installation Considerations........................................................ 44
4.3 Objectives ....................................................................................................... 45
4.3.1 Benefit to public ....................................................................................... 45
4.3.2 Cost savings ............................................................................................. 45
4.3.3 Staff Knowledge ...................................................................................... 45
4.4 Comparison of Possible Solutions .................................................................. 45
4.4.1 Possible Vendors / Suppliers ................................................................... 46
4.4.1.1 External Engineering Contractors ............................................... 46
4.4.1.2 Internet of Things........................................................................ 47
4.4.1.3 ZigBee Mesh Network ................................................................ 48
4.4.1.4 Schneider .................................................................................... 49
4.4.1.5 Automation IT Oleumtech .......................................................... 50
4.4.1.6 Automation IT – ZigBee + 3G Modems ..................................... 51
4.4.1.7 Automation IT – ZigBee RTUs .................................................. 52
4.4.1.8 Auto Control Systems – Burkert ................................................. 52
4.4.1.9 NHP – Ewon ............................................................................... 53
4
4.4.2 Quantitative Comparison ......................................................................... 54
4.4.3 Outcome of Comparison .......................................................................... 58
Chapter 5. ZigBee- Critical Analysis ........................................................................... 59
5.1 The ZigBee Standard ...................................................................................... 59
5.1.1 ZigBee Wireless Network ........................................................................ 60
5.1.1.1 Power Consumption & Data Rate ............................................... 63
5.1.1.2 Factors Degrading RSSI ............................................................. 64
5.1.2 Fresnel Zone............................................................................................. 64
5.1.3 Preliminary ZigBee Security Risk Assessment ....................................... 65
5.1.3.1 Wastewater Security ................................................................... 67
5.1.3.2 Network Security Risk Analysis ................................................. 68
5.1.3.3 Attack Types ............................................................................... 70
5.1.3.4 Results ......................................................................................... 72
5.1.3.5 Conclusion .................................................................................. 74
5.2 Site Surveys .................................................................................................... 75
5.2.1 Signal Strength ........................................................................................ 75
5.2.1.1 Signal Strength Survey Configuration ........................................ 75
5.2.1.2 Site Survey Results ..................................................................... 77
5.2.1.3 Site Survey Conclusion ............................................................... 78
5.2.2 Security Survey ........................................................................................ 78
5.3 Component Configuration .............................................................................. 80
5.3.1 Component List ........................................................................................ 81
5.3.1.1 Central Station Components ....................................................... 81
5.3.1.2 Pump Station Component List .................................................... 81
5.3.2 Component Descriptions .......................................................................... 82
5.3.2.1 Network Controller ..................................................................... 82
5.3.2.2 Modbus Gateway ........................................................................ 83
5
5.3.2.3 Remote End Units ...................................................................... 83
5.3.2.4 Antennas ..................................................................................... 83
5.3.2.5 Current Transformers .................................................................. 84
5.3.2.6 Ultrasonic Level Transducers ..................................................... 84
Chapter 6. Results ........................................................................................................ 85
6.1 Results Analysis Approach ............................................................................. 85
6.2 Summarised Results ........................................................................................ 85
6.3 Quantitative Results ........................................................................................ 90
6.3.1 Communications ...................................................................................... 90
6.3.3.1 Initial setup – low profile switchboard antennas ........................ 90
6.3.3.2 Antenna Modifications ............................................................... 91
6.3.2 Uptime...................................................................................................... 92
6.3.2.1 Weather ....................................................................................... 92
6.3.2.2 Power Loss .................................................................................. 92
6.3.3 User interaction ........................................................................................ 93
6.3.3.1 Device Configuration .................................................................. 93
6.3.3.2 Wiring & Cabling ....................................................................... 93
6.3.4 GUI Setup ................................................................................................ 94
6.3.5 Calibration................................................................................................ 94
6.3.6 Cost .......................................................................................................... 94
6.3.6.1 Network Components ................................................................. 95
6.3.6.2 Transducers ................................................................................. 95
6.3.6.3 Antennas ..................................................................................... 96
6.3.6.4 Extras .......................................................................................... 96
6.3.6.5 Subscription ................................................................................ 96
6.3.7 Effectiveness ............................................................................................ 96
6.3.7.1 Monitoring .................................................................................. 97
6
6.3.7.2 Pump Operation .......................................................................... 99
6.3.7.3 Impact on Response .................................................................. 100
6.3.7.4 Callout Savings ......................................................................... 101
6.3.7.5 Event Mitigation ....................................................................... 102
6.3.7.6 Alarms ....................................................................................... 102
Chapter 7. Further Work ............................................................................................ 103
7.1 Network Expansion ....................................................................................... 103
7.2 Scripting ........................................................................................................ 104
7.2.1 Gradients and flow rate .......................................................................... 104
7.2.2 Pump Current Data ................................................................................ 105
7.3 Other ............................................................................................................. 106
Chapter 8. Conclusion ................................................................................................ 107
Acknowledgments...................................................................................................... 109
References ......................................................................................................... 110
List of Appendices ..................................................................................................... 114
Appendix A. Water Corporation and Shire data 2012-2014 ................................. 115
Appendix B. Customer Complaints and Blockages - Shire of Moora Sewerage
Scheme ...................................................................................................... 116
Appendix C. Sewage Spills and Incidents ............................................................. 117
Appendix D. ZigSense Reference Projects ............................................................ 120
Appendix E. Topographical data between network nodes .................................... 120
Appendix F. Pump Station 1-7 Summary Statistics from archive data ................. 122
Appendix G. Sample archive data Pump Stations 1, 3 & 4 – Water level, pump
current & pump duty (in colour) ............................................................... 123
7
LIST OF TABLES
Table 1 Catchment Area and Pump Station ................................................................. 21
Table 2 Distances between Central Station (C) and each Pump Station ..................... 27
Table 3 ‘Closer’ paths using a mesh network topology ............................................... 29
Table 4 Optimum distances between nodes ................................................................. 31
Table 5 Optimum distances between nodes and corresponding topographical
figure .................................................................................................................... 32
Table 6 Coordinates and Elevation in Pump Stations and the Central Station ............ 33
Table 7 Pump Station 3 alarm log for year 2014–2015 ............................................... 38
Table 8 Quantitative comparison of researched solutions ........................................... 54
Table 9 Meaning of factor scale 1–10 .......................................................................... 55
Table 10 IEEE 802.15.4 characteristics ....................................................................... 62
Table 11 Determining risk severity.............................................................................. 69
Table 12 Summary of Preliminary Security Analysis ................................................. 72
Table 13 Interpretation of Range Tester output ........................................................... 76
Table 14 Site RF Survey results - Range Tester output ............................................... 76
Table 15 Pump Station 7 to 4 & 2 RF Survey results - Range Tester output .............. 78
Table 16 Results Analysis Criteria. ............................................................................. 86
Table 17 Communications reliability to Central Station with low profile antennas.... 91
Table 18 Extract of archived log data with notes excluding alarms ............................ 98
8
LIST OF FIGURES
Figure 1 Shire of Moora Aerial .................................................................................... 19
Figure 2 Scheme Process ............................................................................................. 20
Figure 3 Catchment Areas ........................................................................................... 22
Figure 4 Basic Pump Station Schematic ...................................................................... 23
Figure 5 Pump Station ................................................................................................. 23
Figure 6 Switchboard Electrical Components and PLC .............................................. 25
Figure 7 WWTP Aerial & Sample Locations .............................................................. 26
Figure 8 Positions of each Pump Station and the Central Station ............................... 28
Figure 9 Possible paths using a mesh network topology ............................................. 29
Figure 10 Optimum paths between nodes .................................................................... 30
Figure 11 Elevation Profile between PS1 and PS3 ...................................................... 33
Figure 12 System Configuration .................................................................................. 59
Figure 13 ZigBee Mesh Network and device types ..................................................... 60
Figure 14 Mesh network as applies to Moora Pump Stations ..................................... 61
Figure 15 ZigBee Device Construction ....................................................................... 62
Figure 16 Power consumption and data rate comparison between different wireless
technologies ......................................................................................................... 63
Figure 17 Fresnel Zone calculation using excel spreadsheet ....................................... 65
Figure 18 How ZigBee integrates security with IEEE 802.15.4.................................. 67
Figure 19 Range testing results .................................................................................... 77
Figure 20 Wireshark program displaying ZigBee network data packets ..................... 79
Figure 21 Wireshark data output.................................................................................. 79
Figure 22 Vendor recommended network configuration ............................................. 81
Figure 23 Network controller & cloud application GUI .............................................. 82
Figure 24 Gateway Controller and software interface ................................................. 83
9
Figure 25 GUI with labels for Pump Station 3 ZigSense monitoring system ............. 97
Figure 26 Typical life cycle costs for pumps in a municipal environment ................ 100
Figure 27 The detection of a ragged pump at Pump Station 3 ................................... 101
Figure 28 Example of observed current and water level data in the ZigSense
desktop GUI ....................................................................................................... 106
10
ABSTRACT
Wastewater treatment is essential infrastructure. In order to ensure public
health is not compromised by means of human contact with sewage-borne pathogens,
this is a licensed and regulated industry within Australia. The governing bodies have
and do prosecute for breaches in the required standards. Wastewater treatment can
vary from large, complex systems servicing the needs of large conurbations to small
regional installations with the associated differences in budgets. A regional
wastewater treatment system was analysed and though functional, there was scope for
improvement. For example, though alarms triggered, the source of the problem was
not identifiable. Rather than solve individual problems an alternative, cost effective
upgrade was identified to be the optimum solution. Without any restrictions a wide
range of different solutions were analysis and evaluated. Factors considered included:
cost, security, ease of use etc. A ZigBee based system ranked the highest in addition
to which the data rates and functionality of this standard were deemed best suited to
simple, low-volume data transmissions. Furthermore the data packets are encrypted
thereby providing some cyber-security. The system was installed and tested and either
met or exceeded all requirements. In effect, it proved to be a simple, cost effective
solution ideally suited to small, regional installations.
The work in this thesis has been published through the process of full paper,
blind peer review as follows: Modern Applied Science; Vol. 11, No. 6; 2017, Pages
29 to 34, Wastewater Automation – The Development of a Low Cost, Distributed
Automation System. Authors: Tom Davies, Stanislaw Paul Maj.
11
Keywords: regional, wastewater, sewerage, automation, shire, local
government
I would like to express my gratitude to the Shire of Moora for the financial
backing of the project and training, EIT (Engineering Institute of Technology) for
creating a very positive, supportive and professional academic environment, and
especially to Associate Professor Dr S. P. Maj (Paul) for giving help and support
exactly where and when it was needed.
12
CHAPTER 1. INTRODUCTION
Water Corporation handed over management of the Moora town site
wastewater scheme to the Shire of Moora. The Shire hired staff, organised training,
allocated a budget and took over managing the treatment lagoons, sewerage piping,
pump stations, customer service, legislative reporting and automation systems.
1.1 The Problem Statement
The Shire of Moora took control of the Moora town site wastewater scheme
from the Water Corporation at the end of 2013. The handover from Water
Corporation to the Shire was relatively brief and due to security and/or privacy
policies not all information and software was received by the Shire.
In particular, SCADA software was not received leaving the Shire with
outdated dialling alarms that could only be reprogrammed to Shire staff phone
numbers. If an alarm went off, no status information was conveyed to the staff, only
where the call was coming from.
This system did not meet the needs of successfully managing and operating a
wastewater scheme. An alternative, cost effective solution is sought - ideally one that
utilizes the staff involved rather than external engineering contractors. We propose to
search for a solution that is both suitable and cost effective.
As the need for automated monitoring and control increases and the income
from small municipal wastewater remain limited, there exists a need for an
automation system that is reliable, robust, customizable and cost effective.
13
This study looks at the viability of such a system and continues toward
implementation and successful commissioning. A description of the scheme follows
to better outline the problem. The problem is detailed in Section 3. The Problem.
14
CHAPTER 2. BACKGROUND
2.1 Moora Waste Water Scheme Overview
To understand the importance and context of the problem the scope of the
wastewater scheme must be briefly looked at in figure 1. Figure 1 shows the
Wastewater Treatment Plant and Reuse Scheme in white, The Pump Stations (1-7) in
green and the sewerage gravity fed network (sewer piping) in red.
Figure 1 Shire of Moora Aerial.
The Shire of Moora maintains a wastewater scheme having:
537 connected services – 105 of which are classified as commercial /
industrial
15
Serves a population of approximately 1500
100,000m3 inflow wastewater per year to the Wastewater Treatment Plant
(WWTP)
Recycles 40,000m3 per year to town site parks and gardens (Reuse Scheme)
Figure 2 Scheme Process.
Figure 2 shows the overall sewerage scheme flow process. The wastewater is
collected in the catchment areas via piping. It then flows to the catchment areas
respective pump station, shown in table 1. From there it flows to the WWTP through
four lagoons, to a Reuse Scheme with one lagoon where it is disinfected, then finally
it waters parks and ovals.
16
Table 1 Catchment Area and Pump Station.
Catchment Area Pump Station
A 1
B 2
C 3
D 4
E 5
F 6
G 7
The Scheme consists of:
17km of piping with cut-ins for each connection
216 access chambers
7 Catchment areas
7 Pump Stations
WWTP (4 lagoons)
Reuse scheme (1 lagoon, chlorine disinfection system)
17
2.1.1 Catchment Areas
Figure 3 Catchment Areas.
Figure 3 illustrates how the catchment areas are related and in what order they
flow. The piping in red belongs to a particular Catchment Area and therefore flows to
a particular Pump Station as described in table 1. The pump station pumps the water
through the network as above and finally from Catchment Area A (Pump Station 1) to
the WWTP (Waste Water Treatment Plant).
2.1.2 Pump Stations
Pump stations are 5-7m deep. The wet well (Figure 4 & 5 Left) contains two
pumps (alternating duty and standby), four floats and other various items. The
switchboard (Figure 4 & 5 right) contains electrical components, a PLC and an alarm
18
dialler. There is one phone connection for each pump station (7 phone lines) that
connects directly to the alarm dialler. The Pump Stations raise the water to the
required level for the next process. Moora is very flat, hence the need for seven pump
stations. The Pump Stations are identical for the purposes of this study.
Figure 4 Basic Pump Station Schematic.
Figure 5 Pump Station (left: wet well inside, right: surface surrounds).
19
2.1.3 Pump Station Components
The system being looked at is control of water levels and pump function at the
pump station wet wells. Each Pump Station has one wet well approximately 3m
diameter and 6m deep. Two pumps are located around 10 -15 cm from the well
bottom and are lowered and raised via rails. In the old system, mercury switch floats
provide the PLC and alarm dialler with water level heights. These have been budgeted
to be upgraded to ultrasonic transducers. The PLC operates the automated functioning
of the pumps. The alarm dialler connects to a phone line and makes a call when the
alarm inputs are triggered. Each pump station has a near identical configuration
conforming to the Water Corporation standards when they were installed. This
includes components within the switchboard and wet well e.g. seven PLCs are all the
same model.
The main components are (also in figure 4):
Switchboard & electrical components
Floats (low, medium, high, extra high) & pumps – in wet well
PLC controlling 2 pumps (PLC in switchboard, pumps in wet well)
Dialler with 3 Digital Inputs (alarms that were previously interpreted by Water
Corporation software)
2.1.3.1 Switchboard
The switchboard contains electrical components, alarm dialler and PLC.
20
Figure 6 Switchboard Electrical Components and PLC.
The plan has components inserted that make up the manual and automated
control of the pumps (figure 6). All seven Pump Stations have the same configuration
as in figure 6. They transport waste water from the catchment Areas to the WWTP
lagoons.
Refer to table 1 to see which Catchment Area feeds to which Pump Station.
Refer to figure 3 to see where each Pump Station pumps.
Refer to figure 1 to see the location of each Pump Station.
2.1.3.2 Programmable Logic Controller
The model is a Koyo Direct Logic 205 with software making viewing, editing
and backing up of the ladder logic program possible.
2.1.3.3 Alarm Dialler
Each of these units has its own dedicated phone line. This hardware is
outdated (pre 2000) has 3 inputs: Extra high water level, power loss and pump fail.
21
Before the Shire took control of the Scheme, Water Corporation (located offsite in
Geraldton) received a readout showing which alarms were triggered with their Citect
software. This software was not provided to the Shire during the handover.
2.1.4 Wastewater Treatment Plant (WWTP)
The water runs through four lagoons in series. Figure 7 shows the sampling
points for each lagoon. The primary is seen top right in figure 7 (sample 1), then the
Secondary (sample 2), third and fourth. Various treatment processes are in play,
though the lagoons can be categorized as ‘Facultative’ lagoons – allowing both
anaerobic and aerobic processes to occur. Sampling is carried out to comply with
legislative requirements. Automation is proposed for the pump stations only, not the
WWTP systems.
Figure 7 WWTP Aerial & Sample Locations.
2.2 Scheme Geography
The layout between Pump Stations and the Central Station was studied in
order to determine if there were any major obstacles that would impact the project,
and what types of technologies could possibly be employed. This section relates to
22
distances, elevations, obstacles in the wireless network context. If mobile carriers,
landlines or cabled internet were to be used, no physical constraints prevent these
from being employed (except for costs).
2.2.1 Topology
A preliminary study shows the positions of the Pump Stations and Central
Station with relation to each other. ‘Topology’ has been used to term the ‘network’
relationship, ‘topography’ more terrain and elevation.
Table 2 Distances between Central Station (C) and each Pump Station.
Path Distance (m)
C-PS1 585
C-PS2 571
C-PS3 214
C-PS4 375
C-PS5 337
C-PS6 650
C-PS7 852
The distances between the Central Station and each Pump Station are shown
in table 2. In table 2, green indicates a distance that is already the shortest possible
path (in a mesh network scenario).
23
Figure 8 Positions of each Pump Station and the Central Station.
When using a mesh network, the REUs can use each other as a relay to pass
the signal on. Taking this into account, the distances not highlighted in Table 2 can be
reduced by relaying off another Pump Station between it and the Central Station. All
possible paths are illustrated in figure 9. The path distances are listed in table 4.
24
Figure 9 Possible paths using a mesh network topology.
Table 3 ‘Closer’ paths using a mesh network topology.
Closer Paths Distance (m)
PS1-PS2 525
PS1-PS3 414
PS2-PS4 334
PS6-PS3 558
PS7-PS4 482
25
Figure 10 Optimum paths between nodes.
Figure 10 shows the closest or optimum distances between Pump Stations and
the Central Station. The Pump Stations will contain Remote End Units and the
Central Station will contain the Gateway and Cloud Controllers. Therefore, each
Pump Station must communicate with the Central Station.
26
Table 4 Optimum distances between nodes.
Best Paths Distance (m) Rank
PS1-PS3 414 5
PS2-PS4 334 2
PS3-C 214 1
PS4-C 375 4
PS5-C 337 3
PS6-PS3 558 7
PS7-PS4 482 6
The optimum paths using a mesh network topology shown in figure 11 has
distances tabulated in table 4. The greatest distance is between PS6 and PS3 (558m).
Not using a mesh network the greatest distance would have been between PS7 and
Central (852m) – table 2.
2.2.2 Topography
Topographical features are of concern for radio communications and are
factored into Fresnel Zone calculations when trying to establish required antenna
27
characteristics and mast heights. Moora town site is particularly flat with a node
elevation range of about 5m. Figures 12 and Appendix E show the elevation profile
for each of the optimum paths between Pump Stations and the Central Station. These
paths are listed in tables 4 & 5.
Table 5 Optimum distances between nodes and corresponding topographical
figure.
Best Paths Distance (m) Figure
PS1-PS3 414 9
PS2-PS4 334 Appendix E
PS3-C 214 Appendix E
PS4-C 375 Appendix E
PS5-C 337 Appendix E
PS6-PS3 558 Appendix E
PS7-PS4 482 Appendix E
28
Figure 11 Elevation Profile between PS1 and PS3.
A preliminary study shows the distances and elevations between the Central
Station and the Seven Pump Stations. The Coordinates and elevations are given in
table 6. AHD stands for Australian Height Datum.
Table 6 Coordinates and Elevation in Pump Stations and the Central Station.
Latitude Longitude
Elevation
AHD
Central 30°38'29.85"S 116° 0'27.26"E 209
PS1 30°38'40.23"S 116° 0'9.48"E 206
PS2 30°38'23.42"S 116° 0'7.23"E 210
29
PS3 30°38'36.31"S 116° 0'24.42"E 209
PS4 30°38'19.94"S 116° 0'19.21"E 209
PS5 30°38'23.59"S 116° 0'37.64"E 211
PS6 30°38'46.90"S 116° 0'41.55"E 210
PS7 30°38'8.30"S 116° 0'7.38"E 208
Figure 9 shows the positions on a satellite image of each Pump Station relative
to the Central Station. Further elevation profiles between nodes are compiled in
Appendix E. Due to the flatness and lack of notable topographical features around the
whole town site; it is assumed that distance will be the greatest factor when
determining signal strength and communication ability.
30
CHAPTER 3. THE PROBLEM
The problem, its cost and relevant legislation are covered in this section.
3.1 The Existing Problem
The hardware was reprogrammed to call Shire mobile numbers when an alarm
was triggered. No information was sent – only the origin phone number – making the
alarm impossible to prioritize.
The Shire purchased Honeywell numerical key panels but that only served to
program the alarm dialler. The alarm dialler is an Ademco Advantage Series built in
the 1990s and was designed to send different analogue tone patterns for each alarm
triggered. These ‘obsolete’ analogue protocols are not interpreted by the Shire. The
Shire has gone as far as to reprogram the Sewerage Staff mobile numbers into the
alarm diallers – this allows notification of ‘an’ alarm from a specific Pump Station
location (the Pump Station ID could be programmed into a mobile phone as a caller
ID). However, when the call is received, only a garbled analogue tone is received –
similar to that of a fax machine or phone modem. Therefore, no further information
about which alarm was triggered is provided.
In the previous system three possible states could trigger the alarm:
Power Loss,
Extra High Float,
Pump Fault
If one of the above were triggered, a call was made to a staff member’s mobile
phone. The staff would see the call came from, for example, Pump Station 3 but no
31
further information was available. A staff member then had to go out on-site and to
determine which of the alarms had gone off. After either resolving the problem or
determining that there was no problem, the issue had to be recorded and logged. The
reason for this situation was the fact that the Shire inherited equipment (but no
software) from the Water Corporation during the handover of the Sewerage Scheme
in the end of 2013.
The problems:
no information is sent– it is not known what triggered the alarm - no
immediate planning possible. This has cost implications as staff are sent on
call outs possibly unnecessarily.
no trending is possible – no information means no trending is possible apart
from number of alarms - level height and pump current is needed. The lack of
trending prevents proper asset management of pump system occurring, also
having cost implications.
Seven phone lines are being utilised (approx. $350 / month) – this could
potentially be improved. In fact, the only trending possible is that manually collected
by a technician on a bi-weekly basis (level height and pump current). Although
effective and useful, this also has manpower cost. Additionally, the system does not
allow for pumps running dry (if the low float fails). The pump could run dry for days
without setting an alarm.
3.2 Problem Frequency and Cost
The existing problem is the limited functionality of the installed SCADA
system – primarily being the lack of information available during an alarm
32
notification. This lack of information doesn’t allow for adequate interpretation,
assessment and prioritization of the alarm event. This in itself leads to a non-optimal
use of staff budget as callouts occur when they are not necessary.
In the financial year 2014 – 2015, at all seven pump stations,110 alarm events
occurred; only 34 had to be acted upon, of these, only 5 had to be acted immediately.
This equates to 110 alarms being potential breaches of governmental
requirements. If correct information was presented, only 5 had to be responded to. In
monetary terms, a savings of callout wages in the order of $3675 could have been
saved (105 events X $35/hr).
3.2.1 Pump Station 3 Data
For 2014-2015, Pump Station 3 had 31 alarms which are itemised in table 7.
Information from table 7 combined with dates of each alarm constitutes the extent of
the monitoring and logging available with the old system.
33
Table 7 Pump Station 3 alarm log for year 2014-2015.
Alarm Status shown on panel
Times called
Reason recorded after callout
Power Loss 19 6 X POWER LOSS - were due to loss of power – Electric Utility works
13 X were due to fluctuations (faults, electrical storms etc.)
Extra High Float
4 2 X required attention
2 X were due to incorrect float heights
Pump Fault 8 5 X required a pump to be pulled up and de-ragged
3 X Actual fault not found
Total 31 Staff received 31 identical alarms
Out of the 31 alarms shown coloured in table 7;
2 had to be responded to within 10 hours (red)
5 had to be responded to within 4 days (orange)
8 had to be monitored (yellow)
16 required no action or monitoring (green)
A potential improvement of reducing the number callouts to 23% (7 callouts /
31 alarms) will also have a potential corresponding financial benefit.
34
3.3 Legislation
3.3.1 Regulatory Bodies
Within Australia, Wastewater is regulated by state governmental bodies and
guidelines are issued nationally.
Aspects of the scheme must be reported to the state authorizing bodies:
3.3.1.1 Economic Regulation Authority (ERA)
Asset Management System and Policies audit. They will place fines of up to
$100,000 if it appears that the assets are not being managed properly according to 3rd
party audit. They also monitor customer complaints and number of blockages.
3.3.1.2 Department of Water (DoW)
oversees all matters water related. A license is required from the DoW to
operate as a Sewerage Scheme Operator.
3.3.1.3 Department of Health (DoH)
health issues especially pathogens coming into contact with public. The DoH
monitors the recycled water pathogen level on a monthly basis. Any deviation results
in the scheme being closed. They can conduct investigations of issues that are health
related and can shut down the scheme or faulty parts thereof if considered unsafe for
the public. A license is required from the DoH to operate the Reuse Scheme.
3.3.1.4 Department of Environmental Regulations (DER)
Cover spills, overflows and odours affecting the environment. They can also
conduct an audit, investigation of incident and can hand out penalties and fines. A
35
license is required from the DER to operate the WWTP. They can limit quantities and
types of waste water accepted by the scheme. The DER monitors spills and the
quarterly wastewater quality sampling. Breaches can result in license suspension /
loss.
Breach of any of these authority’s regulations will have a significant financial
impact on any Shire. The audits are expensive and costs are born by the Shire. The
system in place steers Local Government management toward a proactive, not
reactive, approach to Wastewater Scheme management. The most thorough authority
would be the ERA. They will conduct an audit, create to list of items to be completed,
follow up, and clear the items or issues fines and penalties.
The DER and DoH can simply close the scheme leaving the Shire to dispose
of its wastewater to a WWTP belonging to another Shire. The logistics and costs
simply rule this option out – disposal of one truck in another WWTP costs approx.
$500 and over 50 trucks would be needed each day. The only sensible solution is
compliance.
3.3.2 Prosecutions & Penalties
The DER has a Summary of Prosecutions found at [15] listing offences and
penalties charged over the last several years. The ERA has a listing of Wastewater
license holders and the status of each license and whether penalties have been charged
[16]. The DoW has an information page on Compliance and Enforcement for license
holders [17]. Worksafe WA are the responsible body for regulating onsite safety
conditions, tickets and permits. Summaries of successful prosecutions can be found at
[18]. The Health Department maintain an online ‘convictions register’ [19]
publicising offenders details and business premises.
36
3.3.3 Sewage Incidents
According to [14], ‘Sewage spills can have extreme consequences releasing
pathogens into natural water bodies, swimming areas and sometimes even
contaminating drinking water’. Sewage spills receive a lot of public attention and
invite heavy criticism for the parties’ responsible and authorising bodies.
Some illnesses caused by sewage spills may include [14]:
gastroenteritis (diarrhoea, vomiting)
viral infections such as hepatitis
infections of the skin or eyes.
Sewage incidents can happen for various reasons, but the risk of occurrences
can be minimised by good asset management practises and monitoring systems.
Therefore, the need for an effective automation system customised for the particular
plant must be realistically cost effective and obtainable for smaller regional
communities. The results can range from closure of public areas to multiple deaths
and destruction of communities. Appendix C contains a summarised list of sewage
related incidents.
37
CHAPTER 4. METHOD
In this section, a literature search is covered. Requirements and objectives
along with the primary problem contain the content which will make up the
assessment criteria when results are analysed in section 6. A quantitative vendor
comparison is carried out.
4.1 Relevant Scholarship
The proposal is to search for a cost effective and reliable solution based on
research of existing solutions and custom made possibilities. Studies have been made
on the implementation of automation in wastewater schemes [1], [5]. Also, some
accepted solutions have been developed for urban WWTPs [1], [4], [6], [7] and
smaller scale plants [3]. These studies looked at well-known automation brands and
the implementation of a more expensive installation by engineering staff. They also
dealt mostly with automation within a WWTP.
The implementation of customized low-cost yet reliable automation in a
municipal wastewater scheme managed and installed by specialised staff hasn’t been
so thoroughly documented. The literature search did not reveal a wastewater scheme
implementing:
1. a low-cost reliable, non-specialist installation and
2. the usage of a wireless radio based network in a rural wastewater environment.
In this way, the study has some originality. It is also a situation applicable to
many regional Local Government Shires. The historical data used for the study is
from the Shire of Moora (2013 – present) and Water Corporation alarms and costings
38
(2012-2013) – Appendix A. Various standards and communications have been
considered such as the Ethernet, Modbus protocols, ZigBee radio and internet of
things (IoT) [8], [9], [10], [11] and [12]. It is even possible to keep the current phone
lines in place – but due to running costs and other communication methods (e.g.
ZigBEE [11]), it doesn’t seem likely as a cost effective solution.
UnityWater have procured the services of IT Automation Pty. Ltd. [13] using
Schneider components to implement a similar project. IT Automation Pty. Ltd. are
familiar with working with Government installations but are relatively expensive - the Shire
will look toward carrying out its own installation to keep costs minimal.
4.2 Requirements
The goal of successfully installing and implementing a reliable solution that
meets the needs of the scheme at a reasonable cost is primary. Preferably, an in-house
installation will be carried out to further minimise costs and increase staff
participation and integration.
The following needs have been identified:
4.2.1 Alarms Proposed
Pump fail (existing)
Pump 1 fault
Pump 2 fault
Extra High Water level (existing)
Abnormal current
Power loss (existing)
39
4.2.2 Parameters
The following parameters are to be monitored:
Extra High Water level
4.2.3 Pump current
System operational / non-operational
Trending both pump current and water level would be beneficial
4.2.4 Constraints / Factors
Only a low bit rate is necessary
It is not time critical
Cost is a major factor
Friendly setup and GUI suitable for non-specialised staff
Modular installation and commission – so thorough testing one by one is
possible
4.2.5 In-house Installation Considerations
Project management plan including budgeting
Individual Pump Station requirements
Configuration of remote units
Network configuration
Testing and commissioning
Drawings and documentation
40
4.3 Objectives
Objectives include:
4.3.1 Benefit to public
decreasing the number of related incidents and events before and during the
study
faster response to catchment area blockages due to monitoring of pump
operating hours
4.3.2 Cost savings
calculating the cost benefit of being proactive thanks to the trending data
pump stoppages minimized by monitoring pump current and performance
overtime saved on prioritizing and monitoring the alarms remotely
alarms can immediately be prioritized and planned for
studying the savings of not having to manually collect data
4.3.3 Staff Knowledge
Increased understanding of the scheme – due to information being available
continuously rather than only from inspection, a better understanding of
scheme characteristics will follow.
4.4 Comparison of Possible Solutions
The following is a comparison between different vendors and their solutions.
This section is not just a comparison between competing vendors offering similar
41
products. Diversity is important to remain open to different solution designs as the
best solution to fit the task is being sought, not necessarily the most usual or expected.
The vendors were approached by contacting the most local ones first (Perth,
WA) then proceeding to the vendors based in the other States in Australia. It is a
policy of local government to attempt to use local available business when possible.
No international companies were contacted though some of the local vendors were
agents for products.
4.4.1 Possible Vendors / Suppliers
Nine products are examined with the headings; description, cost, advantages
and disadvantages
4.4.1.1 External Engineering Contractors (Kapp Engineering Pty Ltd) [20]
Description
Modbus system to connect to existing PLC and radio modems at each station,
connected to a central station with SCADA software.
Cost
$50,000+ similarly quoted by KAPP Engineering and other Perth Engineering
companies specializing in this work. The cost of travel for Engineering staff keep the
project cost quite high.
Advantages
Professionally certified work
Sophisticated, secure and many features
42
Disadvantages
Customization can be costly
Ongoing service and maintenance expensive
Expensive
4.4.1.2 Internet of Things Kit (Texas Instruments) [21], [22]
Description
Kit solution configured to match the needs of the scheme. Seven units
deployed at each pump station with appropriate transducers.
Cost
$15,000.
Advantages
Cheap
Information and components readily available
Customizable
Once installed modular and replaceable
Website available – cloud monitoring
Disadvantages
Requires a ‘kit professional’ to successfully install and configure
43
Items are not reliable for wastewater purpose – not fit for purpose
Requires onsite internet connections
Limited trending
This installation may show negligence in a government context – not fit for
purpose
4.4.1.3 ZigBee Mesh Network [23], [24]
Description
Customized ZigBee wireless mesh network
Cost
$19,000.
Advantages
Full in-house installation possible
Inputs are customisable suited to the schemes process and operability
Reliable and fit for this purpose
Communication antennas and other features can be tweaked until staff are
satisfied
Most repairs done in-house
Cheap
44
Information and components readily available
Customizable
Once installed modular and replaceable
Mesh network requires smaller, cheaper antennas than other topologies
Disadvantages
Security, sophistication – not required as control not necessary – only
monitoring
4.4.1.4 Schneider [40]
Description
ScadaPack RTUs, Trio radio units and central HMI unit
Cost
$29,505.
Advantages
Not designed for in-house install
Inputs are customisable suited to the schemes process and operability
Possibly the most reliable and fit for this purpose
Information and components readily available
Customizable
45
Company with the most comprehensive track record
Disadvantages
Price
External install adds on $36,000
4.4.1.5 Automation IT Oleumtech [40]
Description
Oleumtech RTUs, radio units and central HMI unit – cheaper alternative to
Schneider
Cost
$15,744
Advantages
Price
Not designed for in-house install
Inputs are customisable suited to the schemes process and operability
Quite reliable and fit for this purpose
Information and components readily available
Customizable
46
Disadvantages
Price
External install adds on $36,000
4.4.1.6 Automation IT – ZigBee + 3G Modems [40]
Description
Zigbee RTUs, 3G modems when necessary to assist communications
Cost
$11,950 + $2,000/yr
Advantages
In-house install possible
Inputs are customisable suited to the schemes process and operability
Information and components readily available
Customizable
Disadvantages
Ongoing costs
No track record
External install adds on $36,000
47
4.4.1.7 Automation IT – ZigBee RTUs [40]
Description
Chinese imported ZigBee RTUs plus central unit
Cost
Cheaper than 4.4.1.6
Advantages
Price?
Unknown product – no track record
Inputs are customisable suited to the schemes process and operability
Not known whether it is reliable and fit for this purpose
Disadvantages
Unknown product – no track record
Not known whether it is reliable and fit for this purpose
External install adds on $36,000
4.4.1.8 Auto Control Systems – Burkert [41]
Description
Burkert MXConnect and uMesh
48
Cost
$16,950
Advantages
In-house install possible
Inputs are customisable suited to the schemes process and operability
Information and components readily available
Customizable
Price reasonable
Disadvantages
No track record with wastewater
4.4.1.9 NHP – Ewon [42]
Description
Ewon Flexy Routers and modems
Cost
$10,500 + $2,000/yr
Advantages
In-house install possible
Inputs are customisable suited to the schemes process and operability
49
Information and components readily available
Customizable
Disadvantages
Ongoing costs
No track record
GUI
4.4.2 Quantitative Comparison
Table 8 shows a comparison of possible solutions. The measures chosen were
eight factors that were deemed important by the Shire. The scale is 1 -10 giving a
minimum score of 8 and a maximum of 90. The factors and their scale rationale are
explained in table 9.
Table 8 Quantitative comparison of researched solutions.
Score out of 90
Per
th
Eng.
com
pan
y
(Kap
p
Engin
eeri
ng)
Inte
rnet
of
Thin
gs
(Tex
as
Inst
rum
ents
)
Zig
Bee
Zig
Sen
se
Dig
imes
h
net
work
Sch
nei
der
Sca
daP
ack
&
Tri
o
Auto
mat
ion I
T
Ole
um
tech
A
uto
mat
ion I
T
Zig
Bee
+ 3
G
Auto
mat
ion I
T
Zig
Bee
RT
U
Auto
Contr
ol
Syst
ems
Burk
et
NH
P
Fle
xy
Reliable & reputable
10 4 8 10 8 8 5 8 6
Cost 3 10 10 2 7 8 9 8 7
Staff setup difficulty
5 7 9 6 6 6 6 8 7
Local supplier
10 10 10 10 9 9 5 8 8
GUI suitability
10 6 9 10 7 6 6 6 6
Features 10 6 8 10 8 7 5 6 6
Support 10 8 10 10 7 6 4 6 5
50
Security 9 4 6 10 8 6 4 6 6
Operating & servicing costs
3 7 8 4 7 5 8 8 6
Total 70 62 78 72 67 61 52 64 57
Rank 3 6 1 2 4 7 9 5 8
Table 9 Meaning of factor scale 1–10.
Factors Scale 1-10 Meaning
Reliable & reputable 10 great track record and reputation.
5 Average track record and reputation
1 no known information.
Cost - 10 within budget for the complete product e.g.
$25,000
5 Over budget 50%
1 completely inappropriate price range e.g.
$100,000
Staff setup difficulty 10 external engineer / specialized contractor
required
51
5 Complex installation
1 simple setup by untrained staff
Local supplier 10 WA based company / agent
5 Australian / NZ company / agent
1 Overseas company / agent
GUI suitability 10 Clear GUI displaying desired trends with
history and logging
5 Basic symbols
1 Just numbers / raw data
Features 10 Many features to select from
5 Some features
1 No extra features
Support 10 Easy, free information and help
5 Cumbersome, paid support
52
1 No support
Security 10 Many high quality security features
5 Option of some security features
1 Limited or no security
Operating & servicing
costs
10 Cost free connectivity and minimal servicing
5 Some paid components
1 Paid connection at every site and expensive
servicing
The factors selected for the comparison were those deemed to be significantly
valuable to the Shire.
Reliable & reputable: local government does not typically take business risks
with unknown entities.
Cost: everything is decided upon with budget in mind.
Setup: The ability to setup gives enhanced understanding, training and cost
effectiveness to the project.
Local: There is an obligation to use local vendors whenever possible.
GUI: Must be for layman.
53
Features: Can be useful for clarity and future development.
Support: Support is required as a means of keeping the system online must be
maintained.
Security: It is a public utility and therefore could become a target.
Operating costs: A cheap product with high running costs is not viable long
term.
4.4.3 Outcome of Comparison
According to the comparison outlined in table 8, the optimal choice is the
ZigBee based network. ZigSense is the vendor - some of their projects using this
product can be found in Appendix D. It scored 8-10 for all factors except security
(where it scored a 6). Security is a significant issue for public utilities and must be
addressed. Therefore, a preliminary risk assessment has been carried out in Section
5.1.3 ZigBee Security Risk Assessment.
The most reputable and well known vendors supply a product solution not
economically suitable for the Shire – they ranked second and third with cost factors of
two and three respectively. Therefore, the most well priced, reliable, robust solution is
the ZigBee based network. The cloud based GUI is sufficient for Shire needs and does
not require training to be used.
54
CHAPTER 5. ZIGBEE – CRITICAL ANALYSIS
The proposed system was installed in a modular fashion, one by one. The
system is comprised of two Remote End Units, one Antenna, one Current transformer
and one Level Transducer at each Pump Station, and the Central Station has a
network controller, gateway and antenna.
The system is configured as in figure 12.
Figure 12 System Configuration.
5.1 The ZigBee Standard
In 2003 the IEEE 802.15.4 standard was ratified [12]. According to the author
[12], this standard represented a significant break from the “bigger and faster”
55
standards that the IEEE 802 organization continues to develop [12]: “instead of higher
data rates and more functionality, this standard was to address the simple, low-data
volume universe of control and sensor networks, which existed without global
standardization through a miasma of proprietary methods and protocols.” [12]. The
lack of a standard approach was a major impediment to mass manufacturing of
inexpensive silicon radios that could drive down the cost of these devices [12].
5.1.1 ZigBee Wireless Network
Peer-to-peer networking allows each device to communicate directly with
each other. A mesh network may be used if configured by the higher layer entity.
ZigBee networking is natively mesh-based.
Figure 13 indicates routes that requires other radios to “relay” the information
[12].
Figure 13 ZigBee Mesh Network and Device Types [12].
56
The IEEE 802.15.4 standard defines device types as in figure 13.
Figure 14 Mesh network as applies to Moora Pump Stations.
Each ZigBee mesh network node can relay data for the neighbouring nodes
within their transmit range as well providing a self-healing function by re-routing
with other contacted nodes [43]. This also serves to improve energy efficiency.
Figure 14 shows the depiction of a mesh network for the Shire of Moora
Central Stations and Pump Stations. The modulation mode used by 802.15.4 is phase-
shift-key based. It was selected due to its ability to be restored even in low signal to
interference environments [12]. The ZigBee standard employs several frequencies and
they have been designed for minimal interference with other well-known networks
such as WIFI. Three frequencies that are provided by the vendor are shown in table
10.
57
Table 10 IEEE 802.15.4 characteristics [32].
Frequency Range urban
Range outdoors
Tx power Data rate Rx Sensitivity
2.4GHz 100m 2km 63mW 256Kbps – 102dBm
900MHz 600m 14km 250mW 10K / 200Kbps
– 101dBm / – 110dBm
868MHz 600m 14km 250mW 10K / 200Kbps
– 101dBm / – 110dBm
This application will use the 900MHz as longer distances are required with a
low data rate (table 10). The range is sufficient as are the data rate and power
requirements. The relationship between 802.15.4 ZigBee products and the OSI
network model layer is shown in figure 15.
Figure 15 ZigBee Device Construction [12].
58
The emergence of ZigBee as a standard for accepted low-power, low
maintenance, smart devices are summarised in the following extract [44]: “The
wireless technologies are becoming an important asset in the smart grid, particularly
the ZigBee devices. These smart devices are gaining increased acceptance, not only
for building and home automation, but also for energy management, efficiency
optimization and metering services, being able to operate for long periods of time
without maintenance needs. “
5.1.1.1 Power Consumption & Data Rate
ZigBee is a technology that is often employed for its low power consumption
making it suitable for remote sites [47]. Figure 16 shows the power consumption and
data rate comparison between different wireless technologies.
Figure 16 Power consumption and data rate comparison between different
wireless technologies [47].
59
5.1.1.2 Factors Degrading RSSI
Factors that degrade and impact the Received Signal Strength Indicator (RSSI)
values in ZigBee wireless networks [48]:
Reflections on metallic objects
Superposition of electro-magnetic fields
Diffraction at edges
Refraction by media with different propagation velocity
Polarisation of electro-magnetic fields
Unadapted MAC protocols
The Shire of Moora has a mobile cellular network tower located at the centre
of town – which is somewhat central to the Pump Stations. There are also a number of
five metre high tin workshops.
5.1.2 Fresnel Zone
A Fresnel zone calculation from [36] was carried out using mast heights of 6m
(Central Station) and 2.4m (Switchboard height). This simulates the communication
path between the Central Station and a Pump Station. The frequency used was 900
MHz and link to link distance was 500m. The results are shown in figure 17.
60
Figure 17 Fresnel Zone calculation using excel spreadsheet from [36].
The closer obstacles are to the line of sight between two antennas, the more
interference will be experienced due to reflections of the original signal out of its
phase angle. In figure 17, it can be seen that there may be some phase shifting of
signals at the set parameters. It is not yet clear whether this makes this antenna
configuration viable or not. It is not a perfect Fresnel zone, that is, clear, and obstacles
such as buildings have not been taken into account. It is a useful tool for determining
how close an obstacle can occur to a link – The 6m antenna can shoot over close
obstacles 1 or 2m high. It is a preliminary study that is followed by a signal strength
survey (Section 5.2.1) conducted at the appropriate frequency on-site.
5.1.3 Preliminary ZigBee Security Risk Assessment
As discussed, a security assessment looking at ZigBee’s vulnerabilities has
been carried to determine overall suitability for public utilities. Examples of industrial
control systems being vulnerable and victims of cyber-attacks as extracted from [45]:
61
March 2007, Idaho National Laboratory conducted an experiment in which
physical damage was caused to a diesel generator through the exploitation of a
security flaw in its control system.
During the Russian- Georgian war in 2008, cyber-attacks brought down the
Georgian electric grid during the Russian army’s advance through the country.
In April 2009, the Wall Street Journal reported that cyber spies had penetrated
the U.S. electrical grid and left behind software programs that could be used to disrupt
the system.
In 2010, Stuxnet, a large complex piece of malware with many different
components and functionalities, targeted Siemens industrial control systems and
exploited four zero-day vulnerabilities running Windows operating systems. As a
result, 60 percent of Iranian nuclear infrastructure was targeted.
These example were based around electrical supply grids, however the
importance of other utilities such as water and wastewater also make them a potential
target for widespread public disruption and attention.
62
Figure 18 How ZigBee integrates security with IEEE 802.15.4 [49].
ZigBee has its own security features such as 128-bit Advanced Encryption
Standard cryptography and trust centred authentication layered on top of the IEEE
802.15.4 standard having physical and media access control layers as shown in figure
18 [49].
5.1.3.1 Wastewater Security
Industrial network security is a major issue as productivity and profitability
can be compromised. Classified information and compliance can also become
expensive issues when ‘secure’ operations are infiltrated. For the Shire’s application,
security is not as a critical issue as it could be if control was used. Only monitoring is
used and the outputs on the Network Controller and the Remote Units are not
connected. Each of the Pump Stations exist within the Moora town site and this is
63
where the majority of employees also reside. Therefore, after diagnosing a problem
online, a staff member can be sent on site to make a change.
The other issue was that functions such as emergency pump downs are used. If
communication was somehow lost after initiating an emergency pump down online, it
would pump out all of the water and continue to run, heating up the pumps which can
cause damage.
The 802.15.4 does have encryption inbuilt [11] According to the 802.15.4
standard (7.2), “A device may optionally implement security” [11]. This is done by
setting the attribute macSecurityEnabled. Further research must be done to determine
what setting has been implemented. To this end, the Shire has purchased a wireless
interface that can read all transmission sent via 802.15.4. It is called Open Sniffer [31]
and works with the well-known network sniffing software ‘Wireshark’ [33].
5.1.3.2 Network Security Risk Analysis
The risk of an intruder having an impact on the wastewater services is looked
at. In particular, the effect of the introduction of a wireless ZigBee network to monitor
the scheme is analysed. The main defence against all wireless attacks or disturbances
in this situation is the fact that the network is used only for monitor and alarm
purposes, not for control. Therefore, security is much less an issue than it would be if
control (e.g. switching on/off of pumps) was employed.
In one security based study [37], the author looks at techniques for launching a
variety of security attacks on an 802.15.4/ZigBee wireless network [37]. Specifically,
the link layer was attacked using jamming techniques to intercept and corrupt traffic.
64
The following extract illustrates the type of damage that insecure utilities can sustain
when control is executed remotely [38]:
“During March and April 2000, Vitek Boden made 46 attempts using wireless
connections to hack into Maroochy Shire Council's computerised waste management
system. He had lost his job in developing the wireless network that controlled the
sewage and drinking water system. During the attack his laptop identified itself as
Pumping Station 4 and sent commands leading to the release of millions of litres of
raw sewage into rivers and parks, with considerable environmental costs. In October
2001, Boden was found guilty on various charges involving computer hacking, theft
and causing environmental damage, and sentenced to two years imprisonment. On
appeal, convictions on two of the charges were set aside but the sentence was left
unchanged: R v Boden [2002] QCA 164 (10 May 2002). A subsequent special leave
application to the High Court of Australia was dismissed on 25 June 2003.”
A preliminary security risk analysis of the ‘read-only’ wireless 802.15.4
network has been conducted using the factors shown in table 9.
Table 11 Determining risk severity [39].
65
5.1.3.3 Attack Types
The author analysed typical attacks and looked at possible attacks in the Shires
‘read only’ system:
A. Falsifying a network address – hacking in and pretending to be node in the
network.
1) Creating false alarms
False alarms could potentially be created from any node address. This
would be costly as staff would have to go onsite to verify situation. It
would require an individual with the correct transmission equipment and
an understanding of how ZigBee Packets are structured. It would also
require knowledge of what registers belong to what alarms – this would be
more difficult to acquire.
Likelihood: Low
Impact: High
Risk Severity: MEDIUM
2) Corrupting data
Changing packet data would require an understanding of dissecting
ZigBee packets. In many cases the data would be rejected.
Likelihood: Low
Impact: Medium
Risk Severity: LOW
66
3) Giving false readings
Creation of false readings would require an understanding of packet
structure plus the meaning of data in each register. The impact would be
limited by alarm event triggering.
Likelihood: Low
Impact: Medium
Risk Severity: LOW
4) Masking real alarms
Masking real alarms would require an understanding of packet structure
plus the meaning of data in each register.
Likelihood: Low
Impact: High
Risk Severity: MEDIUM
B. Recording and storing data for other purposes – industrial espionage
1) Creating a profile for future attacks
This translates into future events so is difficult to assess. Nevertheless, this
type of vulnerability should be minimised.
Likelihood: Low
Impact: Med
Risk Severity: LOW
2) Attempting exploitation by use of gathered data
The information transmitted has limited use to any third party. Also, there
is only basic operating data – nothing that could be exploited.
Likelihood: Low
Impact: Low
67
Risk Severity: LOW
C. Jamming the airwaves by transmitting on the same frequency.
1) Jamming all monitoring and alarms
A basic understanding of what frequency the network operates on and a
transmitter is all that is required. Continuous jamming would be relatively
easy to locate.
Likelihood: Medium
Impact: Low
Risk Severity: LOW
D. Selective jamming of the airwaves by transmitting on the same frequency at
specific times
1) Jamming all monitoring and alarms at key times
This could be more of a disturbance as it would be difficult to physically
trace. The disturbance would have a cost.
Likelihood: Medium
Impact: Medium
Risk Severity: MEDIUM
5.1.3.4 Results
Table 12 Summary of Preliminary Security Analysis.
Attack Likelihood Impact Severity
A i Low High MEDIUM
68
A summary of the preliminary security analysis is shown in table 12. The
outcome is that the most likely attack (D i) to do damage is a selective jamming attack
which requires motive and only some technical knowledge. Encrypting data will not
treat this problem as it would others. The consequence is a block of information
which could potentially mask an alarm. The jamming action would be observable by
the monitoring system – once the jamming characteristics are measured, an alarm can
be configured to be triggered when jamming occurs. In this way, the impact will be
minimised. A change of frequency (which may prove difficult) or an effort to
apprehend the offender by use of frequency monitors and loggers may be a possible
treatment.
A ii Low Medium LOW
A iii Low Medium LOW
A iv Low High MEDIUM
B i Low Medium LOW
B ii Low Low LOW
C i Medium Low LOW
D i Medium Medium MEDIUM
69
The other two attacks (A i and A iv) require motive and technical expertise –
and considerable research / inside information. This attack may be motivated by a
disgruntled employee. The consequence could be false alarms requiring staff callouts
or an attempt of completely masking an alarm which could, in the worst case
scenario, result in a sewage overflow. This mitigated by having staff physically do
inspections at least twice per week. As it would take about 4-5 days for the system to
go from alarm state (extra high level) to an overflow, it would require a combination
of staff negligence and effective hacking for this to occur. Even in this scenario,
stopped sewerage services prior to an overflow would undoubtedly result in
customers phoning in and complaining that their drains aren’t flowing.
As stated earlier, encryption can be enabled in the ZigBee protocol by
checking a security flag. Once hacking is suspected, security measures can be put into
place such as encryption and changing of node IDs and resetting register address
locations. This means that the hacker would have to start their research all over again.
The regime of changing addresses may be a good security practise to adopt akin to
changing passwords.
5.1.3.5 Conclusion
According to the Preliminary Security Analysis in Section 5.1.3, it has been
found that ZigBee security issues are within acceptable risk limits relevant to the
application. If control was being used, that is if the system was ‘read / write’, then the
risk assessment would have much different results. As a follow up to the Preliminary
ZigBee Security Analysis, which was essentially a desktop exercise, a field network
ZigBee security analysis will be carried out to validate and verify the desktop
findings. This assessment is found in Section 5.2.2 Security Survey.
70
5.2 Site Surveys
Equipment was purchased; a 900MHz range tester and a 900MHz packet
sniffer to assess the viability of communications ability and quality of security
implemented in the wireless network.
5.2.1 Signal Strength
5.2.1.1 Signal Strength Survey Configuration
A signal strength survey was carried out using a ZigSense Range Tester. The
device was designed to help conduct an RF site survey in order to optimise wireless
communications paths of identify problem locations. The test was carried out using
900MHz frequency and at 250mW transmission power. Two units communicate with
each other across a site a give a signal strength output. The outputs are interpreted by
the manufacturer as shown in table 12.
71
Table 13 Interpretation of Range Tester output adapted from [34].
Range Tester output Manufactures Interpretation
-53 dBm Hi
-54 dBm Very good
-62 dBm Good
-69 dBm Somewhat good
-73 dBm OK – Acceptable strength
-82 dBm Slightly weak
-85 dBm Weak
-90 dBm Low
-95 dBm Too Low – refrain from using at this strength
One unit was based at the Shire of Moora office (Central Station), where the
gateway & network controllers will be based and the other unit was transported
around the town site where readings were taken. The test was done using the units at
1.7m height which is less than the 2.4m switchboard height – minimum height of
proposed antennas. Key results are shown in table 14. An estimate radius from results
has been constructed in figure 19.
Table 14 Site RF Survey results - Range Tester output.
Between Central Station and:
Reading Interpretation
Pump Station 1 -82 dBm Slightly weak
Pump Station 2 -82 dBm Slightly weak
72
Pump Station 3 -62 dBm Good
Pump Station 4 -73 dBm OK
Pump Station 5 -85 dBm Weak
Pump Station 6 -85 dBm Weak
Pump Station 7 -95 dBm Too Low
Figure 19 Range testing results.
5.2.1.2 Site Survey Results
The one signal path that is clearly too low is from Central Station to Pump
Station 7. Refer to table 5 and figure 10 – the preliminary site study illustrates the fact
that Pump Station 7 will use Pump Station 4 as a relay in a mesh network. Failing
that, Pump Station 7 may then use Pump Station 2. The results are shown in table 15.
73
Table 15 Pump Station 7 to PS 4 & PS 7 to PS 2 RF Survey results - Range
Tester output.
Between Pump Station 7 and:
Reading Interpretation
Pump Station 2 -82 dBm Slightly weak
Pump Station 4 -73 dBm OK
5.2.1.3 Site Survey Conclusion
Although some results are slightly weak, it must be noted that the antennas
used were the original ZigSense module antennas. Larger, higher gain antennas will
therefore be purchased that are designed for outdoor conditions and are vandal proof.
The Dome Antenna from Rojone Pty Ltd [35] looks to be a product with these
characteristics. The low profile antenna mounts directly onto the top of the
switchboard with 4 fixings making it secure against vandalism. It operates at 800-900
MHz and has transmission power of 50W [35].
5.2.2 Security Survey
OpenSniffer is a device that can read the 802.15.4 wireless network data
packets. Use of Wireshark software, relevant protocol plugins (ZEP and ZigBee)
combined with the OpenSniffer hardware confirmed that the packets were indeed
encrypted. A concept diagram is shown in figure 20. The output displays the
encryption status of each packet confirming whether encryption has been enabled or
not. It also gives details on the authentication process.
74
Figure 20 Wireshark program displaying ZigBee network data packets.
Wireshark [33] and the OpenSniffer [31] hardware produces output verifying
that the authentication process is indeed encrypted.
Figure 21 Wireshark data output.
75
Figure 21 gives some of the data output of this particular network. The bottom
right of the diagram (….T…8…E. etc) indicates that the data packets are
encapsulated and encrypted. The protocols observed were UDP (User Datagram
Protocol), ZEP (ZigBee Encapsulation Protocol), ZigBee (IEEE 802.15.4) sent over
Ethernet II.
5.3 Component Configuration
The ZigBee network requires remote units to pick up analogue and digital
information at each Pump Station. They communicate to a Modbus Gateway and
Cloud Controller facilitating the cloud applications. An over view is given in figure
22.
Figure 22 Vendor recommended network configuration [28].
76
5.3.1 Component List
The components will have the following quantities
5.3.1.1 Central Station Components
The Central Station can be linked to an existing computer, the internet, and
will have the highest antenna mast. The items include:
1 X Network Controller
1 X Modbus Gateway
1 X Antenna
5.3.1.2 Pump Station Component List
This is the item list for all seven Pump Stations:
14 X Remote End Units
7 X Antennas
7 X Current transformers
7 X Ultrasonic level meters
77
5.3.2 Component Descriptions
5.3.2.1 Network Controller
Figure 23 Network controller & cloud application GUI.
The Cloud Controller (Figure 23 left) provides information for the cloud
application and is physically located at the Central Station. A Modbus cable connects
it to the Gateway Controller. The connection uses the ModBus protocol. An Ethernet
cable connects the Cloud Controller to the internet via TCP/IP protocol where
connection to the cloud application server can take place. The Cloud Application
requires a paid registration ($40/month) and each device must be added. Alarms and
unit calibration takes place using access via a web page. An example of the web
application is shown in figure 23 (right).
78
5.3.2.2 Modbus Gateway
Figure 24 Gateway Controller and software interface.
The ModBus Gateway in figure 24 (left) wirelessly connects via ZigBee
protocol to the remote units and is physically located at the Central Station. It also
connects via USB cable to PC running the ZigSoft software shown in figure 22
(right). The ModBus Gateway holds all register data for all connected devices. This
register data is passed to the Cloud Controller where it will be interpreted and
displayed.
5.3.2.3 Remote End Units
The Remote Units will collect the analogue and digital data from the outputs
and transducers in the Pump Stations. The type used has two digital inputs and two
analogue inputs.
5.3.2.4 Antennas
Antennas were selected after testing. The most important factor is
communication ability. Other factors include form factor, durability and cost.
79
5.3.2.5 Current Transformers
A current transformer measures pump current (0-20 Amps) and delivers it as
4-20mA to the analogue input of the Remote End Unit. One at each pump station
reads the current drawn and combined with the Digital Input ‘PumpDuty1 or
PumpDuty 2’, it can be determined which pump is running and what current is being
drawn.
5.3.2.6 Ultrasonic Level Transducers
The ultrasonic level meter outputs 4-20mA for reading water level at each
pump station. This output connects to the analogue input of the ZigBee Remote End
Unit. The ultrasonic sensor hangs approximately 0.5 metre from the top of the wet
well and bounces an audible signal of the surface of the water.
80
CHAPTER 6. RESULTS
6.1 Results Analysis Approach
The results are compared to the objectives previously covered in this project.
These problems, requirements and objectives will make up the criteria of the
effectiveness of the given solution. They have been drawn from different sections
(listed below) and are tabulated in section 6.2.
The main problems were outlined in section 3:
No alarm information is sent
No trending is possible
Requirements were outlined in section 4.2 which covered the following main
components:
Alarms to be set
Parameters to be monitored
Factors to be considered
In-house installation factors
Objectives were outlined in section 4.3:
Benefit to public (effectiveness of scheme)
Cost Savings
Staff Knowledge
6.2 Summarised Results
From section 6.1, criteria were determined that form the basis of the results
evaluation. This, and the outcomes (Items 1-5), have been tabulated in table 16. There
are 33 items which are derived from the following:
81
Items 1-5 Section 3 Problem – Primary
Items 6-15 Section 4.2 Problem – Requirements
Items 16-22 Section 4.3 Problem – Objectives
This links the problem directly to the results and additional supporting items
were added (Items 22-33).
Table 16 Results Analysis Criteria.
Item
# Section Item
1
Never
0%
2
Seldom
<50%
3
Often
>50%
4
Mostly
>70%
5
Always
1 3
Is the alarm status
accurately sent?
2 3
Alarms triggered
reliably?
3 3
Alarms communicated
effectively?
4 3 Is trending functioning?
5 3 Is archiving possible?
6 4.2.1 Alarm pump fail
82
working?
7 4.2.1
Alarm extra high water
level?
8 4.2.1
Alarm pump current
deviation?
9 4.2.1 Alarm power loss?
10 4.2.2 Water level trending?
11 4.2.2 Pump current trending?
12 4.2.2 System status trending?
13 4.2.3
Within budget
expectations?
14 4.2.3
Friendly GUI and
suitable for untrained
staff?
15 4.2.3
Modular and easy
installation?
83
16 4.3.1
Can mitigate events?
E.g. overflow
17 4.3.1 Improves response?
18 4.3.1
Improves asset
management?
19 4.3.2
Results in more cost
efficient scheme?
20 4.3.2
Reduces callouts and
overtime?
21 4.3.2
Replaces manual data
collection?
22 4.3.3
Increases knowledge of
pump station
characteristics?
23 General
Communications
functioning?
24 General Wiring simple?
84
25 General Antennas adequate?
26 General Uptime continuous?
27 General
Reliability during
weather events?
28 General
Reliability during
power loss events?
29 General
Ease of user
interaction?
30 General
Device configuration
simple?
31 General
GUI configuration
simple?
32 General
Parameter calibration
simple?
33 General
Ongoing costs as
expected?
85
According to the criteria in table 16, the ZigBee solution fulfilled the
requirements. The antennas did not always meet up to expectations and some had to
be replaced with more powerful designs that had a negligible adverse effect on start-
up costs as antennas are a relatively inexpensive component of the system. Such
issues and other details of the results are elaborated further in section 6.3
6.3 Quantitative Results
6.3.1 Communications
Communications in this context refers to the successful two way exchange of
data between Pump Station nodes and Central Station node.
6.3.3.1 Initial setup – low profile switchboard antennas
The units were deployed at all pump stations with a small, low profile antenna.
After installation it was found that this antenna was not sufficient for the outlying
stations. The low profile antenna was selected as it was the most physically robust and
was difficult to damage / vandalise. Results of communications reliability to Central
Station with low profile antenna mounted on switchboard is shown in table 17.
Two conclusions can be drawn. Firstly, the signal survey gave positive results
for all Pump Stations except number Seven. Therefore, the survey was not accurate
for the low profile antenna type. Secondly, the low profile antenna type has a
maximum practical range of about 500m (PS1 is 585m from the Central Station.
Signal quality may be affected by a mobile phone transmitter in the town site which
operates at a similar frequency. Certain directions may have more interference. The
units at Pump Stations 1, 2, 3, 4 were configured to act as routers to facilitate the
86
mesh network topology. With the low profile antennas, this did not seem to improve
signal quality.
6.3.3.2 Antenna Modifications
The Central Station was replaced with a higher gain omni-directional antenna.
Pump Stations 2, 5, 6, 7 had Higher gain (14dBi) Yagi direction antennas installed.
These changes enabled communications to take place from all Pump Stations to the
Central Station. There was little difference in the price of each antenna type.
Table 17 Communications reliability to Central Station with low profile
antennas.
Pump Station Signal reliability After
modifications
1 YES YES
2 NO YES
3 YES YES
4 YES YES
5 NO YES
6 NO YES
7 NO YES
87
6.3.2 Uptime
Since the first week of setting up the system at the first Pump Station, the
communication has stayed online for three full months. The antennas were set up as
suggested, Central Station 4m high, Pump Station 3 2.4m high. It was found that a
small antenna inside a closed switchboard will not be able to communicate; the
antenna must be mounted outside of the switchboard. Connection can ‘break’ quite
often but the local unit stores the data and sends on next available signal. This was
sufficient to capture all necessary data for this application. Therefore, it can be stated
that the uptime for a 3 month period was 100%.
6.3.2.1 Weather
Once effective communications had been established, there was no significant
down time. During weather events (high winds – late February, 2017). Some stations
would drop out occasionally (up to 30% of the time during these events) as detected
by direct connection to the Gateway Controller. However, the sampling continued
(and saved locally) at the Pump Station and when communications was re-established,
the online cloud application database was populated. There was no significant
disturbance to data collection due to weather conditions.
6.3.2.2 Power Loss
It was observed that when power loss was experienced (e.g. 2nd
March, 2017),
the ZigBee module operated on its backup battery. An alarm was configured to notify
lost power. However, the ultrasonic level transducer that is used to measure the pump
station water level was offline. Although not completely essential, knowing the water
levels during a widespread blackout could be useful.
88
Two ways of achieving this would be to:
install a UPS type backup for the transducer
install a non-powered mercury switch float connected directly to a digital
input of the ZigBee module sending an alarm when a certain water level was
reached.
Seven UPS’s would have some cost involved but would continue to provide
online monitoring. The float switches would be cheaper but only alert at a set height.
Given the low frequency of blackouts and a stockroom full of float switches, the Shire
of Moora is considering installing these to mitigate such an event. Another scheme
may consider the battery backup as a better solution, for example in the case of more
extended blackouts, more Pump Stations to monitor, less staff resources etc.
6.3.3 User Interaction
User refers to the person not only using the system but also installing the
hardware and configuring the equipment.
6.3.3.1 Device Configuration
The connectivity of network devices was assisted by instruction manuals and
guidebooks but wasn’t completely without issue. In particular the link between the
network controller and the gateway controller was not clear. The process is simple
enough – the support is not yet fully established in Australia. Having done it once, the
process is straightforward.
6.3.3.2 Wiring & Cabling
The ZigBee modules were connected to
89
DC power supply
A powered current transformer (analogue input)
An ultrasonic level transducer (analogue input)
Antenna (sma coax)
Data cable from PLC – 3 wires (2 digital inputs)
6.3.4 GUI Setup
The device configuration was intuitive. Some addressing concepts were
needed, Modbus was used but understanding of the protocol was not necessary.
Alarm setting was also simple.
Each parameter could be displayed in a limited set of display methods such as
graphs, bar charts, gauges etc. The data could easily be exported in excel format (as
well as other formats).
Scripting is possible in the PAWN language and will be looked at to further
quantify some information such as Pump Station Operating Hours, or accumulated
time that current is above a specified threshold.
6.3.5 Calibration
Calibration was carried out by two people comparing actual amps and levels
to the raw data. A formula can be determined (these cases were linear y=ax+b) and
then adjusted until the online output matches the actual local data.
6.3.6 Cost
The total cost amounted to $11,355 with an optional extra of $14,350 for
ultrasonic transducers.
90
The ongoing subscription amounted to $432 / year.
6.3.6.1 Network Components
Item Price (circa) Quantity Total
Network Controller $910 1 $910
Gateway Controller $900 1 $900
ZigBee modules $795 7 $5565
Sum $7375
6.3.6.2 Transducers
Ultrasonic Transducer
These were purchased previously and are outside the scope of the project.
Existing float switches / alternative level transducers could be used.
Item Price (circa) Quantity Total
Ultrasonic
Transducer
$2050 7 $14,350
Current Transformers
Not necessary if the pump system has an analogue output for current drawn. In
most cases these would be required.
91
Item Price (circa) Quantity Total
Current Transformer $340 7 $2,380
6.3.6.3 Antennas
Item Price (circa) Quantity Total
Antenna $150 8 $1,200
6.3.6.4 Extras & Modifications
Data cabling and fixings were about $400. Antennas had to be changed twice
for outer Pump Stations (PS 2, 6 & 7).
An interesting bonus and significant cost reduction was the fact that one
ZigSense module was used at each Pump Station instead of the proposed two. This
saved $5565 and it was found that one unit would provide all necessary operational
parameters.
6.3.6.5 Subscription
The online subscription giving access to data, GUI and trending amounted to
$432 / year.
6.3.7 Effectiveness
This section covers the critical items such as monitoring parameters, savings
realised, alarm reliability and possible event mitigation.
92
6.3.7.1 Monitoring
Some variables that had not previously been monitored continuously were
now available. This gave the staff an opportunity to get to know the patterns and
characteristic behaviour of pump currents, pump run times and water level shifts.
Examples of the parameters monitored are shown in figure 25. The first unit
monitored was Pump Station 3 which was installed on 3rd
November, 2016. The
remaining units were installed in January, 2017.
See Appendix F for summarised Pump Station 1-7 data and Appendix G for
raw data.
Figure 25 GUI with labels for Pump Station 3 ZigSense monitoring.
It can be seen in figure 25 when water levels are rising and falling and a more
rapid increase when an upstream pump station is pumping (first rise in water level in
figure 25). Also, the pump current and operating duration can be noted.
93
Table 18 Extract of archived log data with notes excluding alarms.
Time
PS3
LEVEL
(metres) Note
PS3
Pump
Current
(Amps) Note
PS3
Duty
Select Note
PS3
Fault
Code Note
2/12/2016
11:06 1.1 MID 0 Pump off 2
Pump 1
selected 15 No fault
2/12/2016
11:07 1.1 4.5
Operating
normally 2
Pump 1
selected 15 No fault
2/12/2016
11:16 1 4.5
Operating
normally 2
Pump 1
selected 15 No fault
2/12/2016
11:24 0.9 4.4
Operating
normally 2
Pump 1
selected 15 No fault
2/12/2016
11:29 0.8 4.4
Operating
normally 2
Pump 1
selected 15 No fault
2/12/2016
11:30 0.7 4.4
Operating
normally 2
Pump 1
selected 15 No fault
2/12/2016 0.6 LOW 0 Pump off 1
Pump 2 15 No fault
94
11:31 selected
Table 18 shows extracts of an archive log data file that can be extracted from
the cloud based online system. Two months of data takes up about five megabytes of
disk storage. In table 18, Pump unit 1 pumps the water level down from 1.1m to 0.6m
respectively from MID level to LOW level as designed. The ability to log so much
information makes dealing with audits and compliance easier and more transparent.
Alarm states have been omitted as no alarms were triggered in this period.
6.3.7.2 Pump Operation
Previously, the current was checked weekly, if a deviation was observed it
was acted upon that day. This means if the pump did not completely fail it could run
with a high current drawn for 1-6 days. We can say 4 days on average as weekends
come into play. Using the ‘old’ system, it was impossible to determine exactly when
the problem began.
With the new system, over a period of two months, 7 observations of high
currents were observed and were acted on the same day (3 times), the next day (3
times) and once two days later due a weekend. This averages out to a 1 day response
from detection to treatment. This saves about 3 days for each event, equivalent to 126
days of high current pumping which can be assumed is damaging to the pumps. How
damaging each event is, is difficult to measure as each situation is different
Making the assumption that a pump running out of its normal current range for
6 months will develop a major problem, it can be calculated that the new system saves
95
one pump every one and a half years. For the Shire of Moora, the average cost of the
pumps are around $7500. This equates to a savings of approximately $5,000 per year.
Figure 26 Typical life cycle costs for pumps in a municipal environment [46].
According to [46] as shown in figure 26, electrical energy costs make up the
largest cost portion in a pumps life cycle. When pumping current is monitored (and
responded to) effectively, this improves the pumps overall efficiency reducing
electrical costs.
6.3.7.3 Impact on Response
Once the characteristic behaviour of the pumps and water levels had been
determined (as in figure 27), meaningful deviations were recognised. An example of
this occurring is shown in figure 27 when the pump current deviated outside normal
96
ranges. Staff decided to pull the pump immediately and it was ragged. From such
occurrences an accurate understanding of the system is obtained and limits can be set
to provide staff with warnings. The history can be viewed as far back as 2 months so
behaviour over a previous period can be studied. During working hours, problems can
be identified and treated within an hour. Without monitoring, these situations can
linger for weeks putting unnecessary strain on the pumps and their power
consumption. In figure 27, the deviation can be seen on the first half of the curve, the
bumpy region at about 07:59am.
Figure 27 The detection of a ragged pump at Pump Station 3.
6.3.7.4 Callout Savings
36 alarms would have been triggered under the ‘old’ system over the two
month period as opposed to 7 callouts (none critical) with the ‘new’ system. This has
97
saved 29 callouts over 2 months, at 1 hour per callout ($40 / hour) equated to $1160
over the two month period or $6960 per year.
6.3.7.5 Event Mitigation
The online water level monitoring was useful during a high rainfall week in
February – all monitoring was possible online rather than onsite leaving time for other
tasks.
6.3.7.6 Alarms
The previous’ systems alarms (outlined in section 3) were replaced with
configurable SMS alarms that texted specific alarm parameters. Once the alarm had
been received, the staff member could then log on remotely and read all measured
parameters. The history could also be viewed (as in figure 25). This allowed for an
accurate and rapid diagnosis of the problems without moving location (via mobile
device). An example of an alarm that was avoided is given in figure 27. Setting alarm
parameters will be different for each pump and each Pump Station – each having their
own particular behaviour. Unusually long pump running times can now be alarmed
which wasn’t previously possible. Also, low water levels (under pump inlet) are now
alarmed.
98
CHAPTER 7. FURTHER WORK
7.1 Network Expansion
Extension of the network into other services is possible and expands the size
and therefore usability of the network. A recycled water scheme will have one of
these units installed as will the town swimming pool. The recycled water quality and
chlorine levels will be monitored. From the swimming pool, chlorine gas leaks will be
monitored and alarms set. Other future station may include natural water way levels
and meteorological stations.
Once the network is established, it is relatively simple and cost effective to
add nodes. Most of the problems have been ironed out, there are no extra ongoing
costs, just the hardware cost and installation. Additional nodes configured to act as
routers should increase the stability of the network.
A study has been conducted by [50] that couples ZigBee radio modules with
external power amplifiers and low noise amplifiers. It was shown that with an
external power amplifier and a low-noise amplifier the outdoor radio range can reach
up to 1600 m with a negligible packet error rate [50]. This indicates that the extension
of the mesh network is physically possible. However, care should be taken to comply
with legislation changes found at [51]. Currently the restrictions of this band (in
Australia) are no longer in force [51]. Cellular networks in Australia operate in this
frequency range.
99
7.2 Scripting
Scripting using the PAWN language in the online GUI allows parameters to
be included as variables into functions. These functions can also be allocated
acceptable ranges of operation and alarmed accordingly.
Small data - optimum processing.
Using a minimal number sensors, data is carefully chosen to extract the
maximum amount of operational information. Rather than continual expansion and
collection of more and more data and then figuring out how to handle it, an alternative
approach could be to use a minimal number of sensors and from that, infer maximal
information. Figuring out more ways to extract information from a minimal data set
keeps costs and maintenance low. The handling of this data does not add extra
running costs to the system once the scripting is established. If the correct sensors are
in place then scripts can be written – the result is cost effective optimisation of the
system.
7.2.1 Gradients and flow rate
Once enough data has been analysed, pump characteristics can be determined
for each pump station. Some pump stations have a relatively uniform inflow from the
local catchment area, some have a combination of inflows from catchment area and
one or two adjacent pump stations flowing in. Therefore, the characteristics, although
individual for each pump station, are able to be analysed in terms of when a particular
pump station is pumping and possibly even which pump unit is running from the
incoming station.
An example of the total inflow to say Pump Station 2 would be:
100
The catchment area inflow rate + inflow from PS4 (pump unit 1 or 2) + inflow
from PS7 (pump unit 1 or 2)
Or PS2 = Catchment B + PS4 + PS7
Once the inflow rates have been determined for each of the 4 pump units from
PS 4 & 7 including multiple pump units running simultaneously (one from PS4 and
one from PS7 – 4 combinations). The catchment area inflow is added on as a
‘tolerance’ as these flows are relatively low and more variable. The scripting could
additionally link the operation of each pump (PS4 & 7) unit to the PS2 inflow. When
this has been established and acceptable limits have been determined, exceedances
can be used to trigger warnings. In particular:
No local catchment area flow – local blockage
Low flow rate from a pump station – PS problem or pressure main pipe
obstruction
Low flow from a pump unit – pump problem (blockage, bearings, rags…)
7.2.2 Pump Current Data
The pump current can be analysed. Refer to Appendix F for summary statistics
including accumulated pump current which can be used for overall power
consumption over a given period of time. Deviation from the set range can be caused
by a blockage in the impellor. Moving increase in range of data could be an
accumulated blockage, bearings or seals deteriorating. Decrease of data could be a
burst line or pumps not delivering water effectively. Current deviation can be directly
related to poor pump operating conditions and maintenance requirements:
Gradual rise of current – accumulated ragging of pump, bearings
Rapid rise – foreign object in impellor, blockage
101
Erratic current – objects around impellor
Low current – water not being moved (burst line)
Long pumping times – low pump performance – damaged impellor,
obstruction
Figure 28 Example of observed current and water level data in the ZigSense
desktop GUI.
7.3 Other
An uninterruptable power supply (UPS) may be installed to keep the water
level data coming in during a power loss. Eight units would be required; seven for the
pump station level transducers and one for the Central Station gateway controller.
102
CHAPTER 8. CONCLUSION
The implementation of ZigBee technology to the Shire of Moora’s town site
wastewater has proven to be successful. The cost effectiveness, reliability and
relatively easy install have made it possible for Local Municipalities to adopt such a
system. The ZigBee solution certainly seems to meet the requirements for low cost. It
has the benefit of having a standardized platform, reliability and well developed
products. The cases are thick, strong moulded plastic and are easy to open and work
on when necessary.
The ZigSense cloud based applications are easy to configure (though some
connection issues were experienced early on) and the graphs and gauges are simple to
set up. It is missing some on / off graphical; buttons for DI states and at this stage no
graphics are available with the mobile version. Using a desktop browser on the
mobile device is one work-around but not a very friendly one. Scripting is an option
that will be pursued to further customize the cloud app and to calculate and log further
diagnostic data such as total pump operating hours. Currently, logs are downloaded
(up to one months’ worth) and calculations are made on the excel file. This operation
should be automated at the cloud level as well as more streamlined and relevant data
monitoring, logging and alarm settings. All staff members (not specifically trained for
using this system) were satisfied with the GUI and the skills required to monitor
relevant parameter was acquired within a few hours.
One unexpected outcome is that members of staff have determined is that after
getting to know the system, only one remote end unit is required. The analogue
parameters must be measured as well as which pump is running, but the other fault
103
codes can be inferred directly from the analogue parameters exceeding normal
operating ranges. For example, nearly all problems have an impact on water level, so
if water level goes beyond its limits and is alarmed then other fault codes are not
necessary. Likewise, if pump current and duration are monitored and deviations are
alarmed, then the additional pump fault code is not needed. The removal of one unit
greatly simplifies installation and reduces cost. This significant cost reduction equates
to $900 times 7 units which is a total savings of $6300.
The greatest underestimation was the range of the ZigBee modules. A
literature study revealed potential ranges as did specific advertising material.
However, the distance with the selected antennas seemed to be around 350-450m and
nodes beyond this required individual consideration. It is an important note that a
node requiring 850m communication distance may require a physically large antenna
(say, one meter in length). This may not be viable and should be considered in early
planning phases. Selecting the best antenna was the task that proved to be most
difficult as desktop studies did not equate to actual local conditions perfectly.
A benefit of the low cost mesh network is that it can be expanded to other
utility types. An expansion of the network results in more routable paths that
communication can take place in, increasing the overall effectiveness of the network.
The network is being expanded to cover the online chlorine analyser at the Shire of
Moora’s recycled wastewater scheme. The data will be incorporated into the current
system at the cost of just the extra hardware and installation.
104
ACKNOWLEDGMENTS
Acknowledgement and thanks to the Shire of Moora and EIT for support of
the project.
105
REFERENCES
[1] Haimi. H., Mulas. M., Vahala, R. Process Automation in Wastewater
Treatment Plants: the Finnish Experience. (2010). E-Water.
[2] Symphony Plus: The Total Automation Solution for Water and Wastewater.
(2012). ABB
[3] Automation Within Reach Even for Small Water, Wastewater Facilities.
(2011). General Electric.
[4] How Automated Real-Time Controls Can Provide More Consistency in
Wastewater Treatment Operations. (2015). HACH.
[5] Olsson, G., Rosen, C. Automation in Wastewater Treatment. (2011). Lund
University, Lund, Sweden..
[6] Solutions for the Water & Wastewater Industry. (2011).NHP Electrical
Engineering Products Pty Ltd.
[7] Wastewater treatment plant: automation of floc filtration. (2009). FESTO.
[8] The Internet of Things: Opportunities & Challenges. (2015). Texas
Instruments.
[9] Wireless connectivity for the Internet of Things (IoT) with MSP430™
microcontrollers (MCUs). (2014). Texas Instruments.
[10] IEEE 802.15.4 - 2003
[11] IEEE 802.15.4 – 2011 IEEE Standard 802.15.4 for local and metropolitan area
networks— Part 15.4: Low-Rate Wireless Personal Area Networks (LR-
WPANs) LAN/MAN Standards Committee of the IEEE Computer Society
IEEE-SA Standards Board, 2011.
106
[12] Adams, J. T. An Introduction to IEEE STD 802.15.4. (2006) Freescale
Semiconductor. Inc.
[13] Munday, P. Automation IT awarded contract to upgrade SCADA system for
Unitywater Sewage Pump Stations. (2015). Automation IT Pty. Ltd.
[14] http://healthywa.wa.gov.au/Articles/S_T/Sewage-spills
[15] https://www.der.wa.gov.au/our-work/enforcement/summary-of-prosecutions
[16] https://www.erawa.com.au/water1/water-licensing/licence-holders
[17] http://www.water.wa.gov.au/licensing/water-licensing/compliance-and-
enforcement
[18] http://prosecutions.commerce.wa.gov.au/
[19] http://ww2.health.wa.gov.au/Articles/F_I/Food-offenders/Publication-of-
names-of-offenders-list
[20] http://www.kapp.com.au/
[21] The Evolution of the Internet of Things. Texas Instruments, 2013.
[22] The Internet of Things: Opportunities & Challenges. Texas Instruments, 2013.
[23] http://www.zigsense.com.au/
[24] http://www.zigbee.org/
[25] Your solution for water and wastewater pumping stations. Schneider Electric,
2007.
[26] Water Wastewater Solutions Guide. Schneider Electric, 2009.
[27] www.der.wa.gov.au
[28] https://www.erawa.com.au
[29] http://www.water.wa.gov.au
[30] Ww2.health.wa.gov.au
[31] www.sewio.net
107
[32] ZigSense brochure, 2013. www.zigsense.com
[33] www.wireshark.org
[34] ZigBee (TM) RANGE TESTER. User Manual. Revision E. ZigSense, 2010.
[35] Rojone A-490-18F 838 MHz Next G Antenna. Rojone Pty Ltd. 2009.
[36] www.extronics.com extronics rf calculator.
[37] Melgares, R. A. 802.15.4 / ZigBee Analysis and Security: Tools for Practical
Exploration of the Attack Surface. Dartmouth College, 2011.
[38] http://www.aic.gov.au/publications/current%20series/tandi/321-
340/tandi329.html
[39] https://www.owasp.org/index.php/OWASP_Risk_Rating_Methodology
[40] Offer Document. Automation IT. 2016.
[41] www.burkert.com.au
[42] www.ewon.biz
[43] Jin Zhu and Recayi Pecen. Paper #086, IT 303 A Novel Automatic Utility
Data Collection System using IEEE 802.15.4- Compliant Wireless Mesh
Networks. Department of Industrial Technology University of Northern Iowa,
2008.
[44] N.C. Batista, R. Melício, J.C.O. Matias, J.P.S. Catalão. Photovoltaic and wind
energy systems monitoring and building/home energy management using
ZigBee devices within a smart grid. Universtiy of Beira Interior, University of
Evora, Technical Universtiy of Lisbon, 2012.
[45] Elias Bou-Harb, Claude Fachkha, Makan Pourzandi, Mourad Debbabi, and
Chadi Assi, Communication Security for Smart Grid Distribution Networks.
IEEE Communications Magazine • January 2013.
108
[46] T. Augustyn. ENERGY EFFICIENCY AND SAVINGS IN PUMPING
SYSTEMS – THE HOLISTIC APPROACH. Southern African Energy
Efficiency Convention, 2012.
[47] Mohamed Samra, Shiemaa Sidahmed, Stephen Greedy, Armando Mndez.
Feasibility Analysis of Wireless Technologies for Railway Signalling
Systems. Birmingham Center for Railway Research and Education, University
of Birmingham, UK, 2016.
[48] R, Mardeni. Othman, Shaifull Nizam. Node Positioning in ZigBee Network
Using Trilateration Method Based on the Received Signal Strength Indicator
(RSSI). European Journal of Scientific Research ISSN 1450-216X Vol.46
No.1 (2010).
[49] David Geer. Users Make a Beeline for ZigBee Sensor Technology, 2005.
[50] Allan HUYNH, Jingcheng ZHANG, Qin-Zhong YE and Shaofang GONG.
ZigBee Radio with External Power Amplifier and Low-Noise Amplifier.
Sensors & Transducers, 2010.
[51] https://www.legislation.gov.au/Details/F2005B01395
109
LIST OF APPENDICES
Appendix A Water Corporation data 2012 / 2013
Table A1. Water Corporation costs 2012-13
Table A2. Shire of Moora costs 2013-14
Appendix B Customer Performance History
Table B2. Customer Complaints & Blockages History
Appendix C Sewage Spills & Incidents
Appendix D ZigSense Reference Projects
Table D1. ZigSense past projects [23]
Appendix E Elevation profiles between nodes
Figure E1. Elevation Profile between PS2 and PS4.
Figure E2. Elevation Profile between PS3 and Central Station.
Figure E3. Elevation Profile between PS4 and Central Station.
Figure E4. Elevation Profile between PS5 and Central Station.
Figure E5. Elevation Profile between PS6 and PS3.
Figure E6. Elevation Profile between PS7 and PS4
Appendix F Pump Station 1-7 Summary Statistics from archive data
Table F1 – Average water height and accumulated pump current from PS 1-7.
Appendix G – Sample archive data Pump Stations 1,3 & 4 – Water level, pump current
& pump duty (in colour)
Table G1 – Sample Archive data PS1, 3 & 4 – Water height and pump
current.
61
61
61
62
62
63
64
64
65
65
65
65
65
66
66
66
66
67
67
110
Appendix A Water Corporation and Shire data 2012-2014
Water Corporation data 2012 / 2013
Table A1 Water Corporation costs 2012–13.
Reactive Maintenance - Immediately Dispatched $ 16,696.06
Reactive Maintenance - Not Immediately Dispatched $ 32,805.78
Planned Maintenance $ 25,024.63
Water Corporation annual management fee $ 150,000.00
Total $ 224,526.47
Blockages for this year and the preceding 10 ranged from 9-24. The most
suitable KPI to be minimised is reactive maintenance $49,501.84.
Shire of Moora data 2013 / 2014
Table A2 Shire of Moora costs 2013–14.
Reactive Maintenance - Immediately Dispatched $ 5,000
Reactive Maintenance - Not Immediately Dispatched $ 2,000
Planned Maintenance & upgrades $
111
81,000
Total $
224,526.47
Appendix B Customer Complaints and Blockages - Shire of Moora Sewerage
Scheme
Another commonly accepted KPI is the number of blockages / customer
complaints experience in a year. According to the ERA, compliance was based on 40
events / 100km of piping as being acceptable. Therefore, the Shire of Moora can have
up to 6 (but not 7) events per year and still be compliant.
Table B1 Customer Complaints & Blockages History.
Customer Performance History
Note: fewer than 40 blockages per 100km per year
Year
Allowed per
year Actual Compliant?
2009-10 6.64 24 No
2010-11 6.64 9 No
112
2011-12 6.64 11 No
2012-13 6.64 15 No
2013-14 6.64 3 Yes
2014 6.64 2 Yes
2015 6.64 1 Yes
2016 6.64 2 Yes
With this KPI having already dropped to quite a low level, it may not be the
most suitable as an indicator for this study but nevertheless cannot be ignored.
Appendix C Sewage Spills and Incidents
Sewage Spills & Incidents
Location: Australia, Perth, Swan River, Caversham
Size: 400,000 L
Date: Oct 2004
Impact: Water sports, swimming, fishing stopped
Source: http://www.abc.net.au/news/2004-10-17/health-warning-after-swan-river-sewage-spill/569762
Location: Australia, Bendigo
Size: 600,000 L
Date: Nov 2009
Impact: Required full cleanup
113
Source: http://www.abc.net.au/news/2009-11-30/sewage-spill-raises-health-concerns/1162544
Location: New Zealand, Palmerston
Size: North Ambulatory Unit ‘soaked’ in sewage
Date: May 2008
Impact: Disturbance of patients
Source: http://www.stuff.co.nz/manawatu-standard/news/409667/Sewage-spill-a-massive-disaster
Location: South Africa Johannesburg
Size: heavy contamination of Hartbeespoort Dam
Date: Nov 2016
Impact: Required full clean up
Source: http://ewn.co.za/2016/11/07/sewage-spill-hits-hartbeespoort-dam
Location: USA, Long Beach
Size: 2.4M Gallons
Date: July 2016
Impact: Polluted waterway
Source: http://www.surfermag.com/features/two-and-a-half-million-gallons-of-sewage-spills-into-los-angeles-river/#A0BWb5S2Pseic3h1.97
Location: Hawaii, Waikiki
Size: 48 million Gallons
Date: 2006
Impact: beaches closed
Source: http://www.mnn.com/green-tech/research-innovations/stories/when-waste-attacks-5-big-sewage-disasters
114
Location: Gaza
Size: sewage basin collapse
Date: 2007
Impact: 4 dead 20 injured, village flooded
Source: http://www.mnn.com/green-tech/research-innovations/stories/when-waste-attacks-5-big-sewage-disasters
Location: Scotland , Edinburgh
Size: Treatment Plant failure
Date: 2007
Impact: 100 million litres into waterway
Source: http://www.mnn.com/green-tech/research-innovations/stories/when-waste-attacks-5-big-sewage-disasters
Location: San Isidro, Mexico
Size: 6000 cubic metres per second flooding into a residential area
Date: 2011
Impact: 200 homes flooded
Source: http://www.mnn.com/green-tech/research-innovations/stories/when-waste-attacks-5-big-sewage-disasters
115
Appendix D ZigSense Reference Projects
Table D1 ZigSense past projects [23].
Appendix E Topographical data between network nodes
Elevation profiles between nodes
Figure E1 Elevation Profile between PS2 and PS4.
116
Figure E2 Elevation Profile between PS3 and Central Station.
Figure E3 Elevation Profile between PS4 and Central Station.
Figure E4 Elevation Profile between PS5 and Central Station.
117
Figure E5 Elevation Profile between PS6 and PS3.
Figure E6 Elevation Profile between PS7 and PS4.
Appendix F Pump Station 1-7 Summary Statistics from archive data
Table F1 Average water height and accumulated pump current from PS 1-7.
PS1 PS2 PS3 PS4 PS5 PS6 PS7
Average water height 1.65 1.34 1.02 1.07 1.83 1.02 1.32
Sum of pump current 2089 1854 1676 655 1937 702 754
118
The length of data collection was 44.2 days. The sample rate was 30 seconds.
The water height is distance from the bottom of the wet well. The sum of
current is indicative of the total power used by each pump station.
Appendix G Sample archive data Pump Stations 1, 3 & 4 – Water level, pump
current & pump duty (in colour)
Table G1 Sample Archive data PS1, 3 & 4 – Water height and pump current.
Time PS1_
LEV
EL
(Met
res)
PS1_AM
PS
(Amps)
PS3_LE
VEL
(metres)
PS3_AM
PS
(Amps)
PS4_L
EVEL
(Metr
es)
PS4_AM
PS
(Amps)
Pump unit 1
Pump unit 2
24/02/2017 3:53 1.96 0 1.13 0 0.59 0
24/02/2017 3:53 2.07 0 1.13 0 0.6 0
24/02/2017 3:54 2.15 0 1.13 0 0.6 0
24/02/2017 3:54 2.22 7 1.13 0 0.6 0
24/02/2017 3:55 2.17 9 1.13 0 0.6 0
24/02/2017 3:55 2.04 9 1.13 0 0.61 0
119
24/02/2017 3:56 1.92 9 1.13 0 0.61 0
24/02/2017 3:56 1.8 9 1.13 0 0.62 0
24/02/2017 3:57 1.67 9 1.13 0 0.62 0
24/02/2017 3:57 1.53 9 1.13 0 0.62 0
24/02/2017 3:58 1.39 9 1.13 0 0.63 0
24/02/2017 3:58 1.27 1 1.13 0 0.63 0
24/02/2017 3:59 1.26 0 1.13 0 0.63 0
24/02/2017 3:59 1.27 0 1.13 0 0.64 0
24/02/2017 5:00 2.23 0 0.76 0 0.7 0
24/02/2017 5:01 2.24 0 0.76 0 0.7 0
24/02/2017 5:01 2.23 3 0.76 0 0.71 0
24/02/2017 5:02 2.15 9 0.76 0 0.72 0
24/02/2017 5:02 2.06 9 0.76 0 0.72 0
120
24/02/2017 5:03 1.83 9 0.76 0 0.72 0
24/02/2017 5:03 1.66 9 0.77 0 0.73 0
24/02/2017 5:04 1.52 9 0.77 0 0.74 0
24/02/2017 5:04 1.34 7 0.77 0 0.74 0
24/02/2017 5:05 1.26 0 0.77 0 0.74 0
24/02/2017 5:05 1.26 0 0.77 0 0.75 0
24/02/2017 5:32 2.11 0 0.85 0 0.59 0
24/02/2017 5:32 2.19 0 0.85 0 0.59 0
24/02/2017 5:33 2.21 9 0.85 0 0.6 0
24/02/2017 5:33 2.11 9 0.85 0 0.6 0
24/02/2017 5:34 2 9 0.85 0 0.61 0
24/02/2017 5:34 1.87 9 0.85 0 0.61 0
24/02/2017 5:35 1.73 9 0.86 0 0.62 0
121
24/02/2017 5:35 1.6 9 0.86 0 0.62 0
24/02/2017 5:36 1.45 9 0.86 0 0.63 0
24/02/2017 5:36 1.32 5 0.86 0 0.64 0
24/02/2017 5:37 1.26 0 0.86 0 0.64 0
24/02/2017 5:37 1.26 0 0.86 0 0.65 0
24/02/2017 6:49 1.42 0 1.13 0 0.57 0
24/02/2017 6:49 1.43 0 1.14 0 0.58 0
24/02/2017 6:50 1.43 0 1.14 1.3 0.58 0
24/02/2017 6:50 1.44 0 1.16 3.7 0.58 0
24/02/2017 6:51 1.45 0 1.18 3.7 0.59 0
24/02/2017 6:51 1.46 0 1.19 3.6 0.59 0
24/02/2017 6:52 1.46 0 1.21 3.6 0.61 0
24/02/2017 6:52 1.47 0 1.22 3.6 0.63 0
122
24/02/2017 6:53 1.47 0 1.23 3.6 0.65 0
24/02/2017 6:53 1.48 0 1.25 3.6 0.66 0
24/02/2017 6:54 1.49 0 1.26 3.6 0.67 0
24/02/2017 6:54 1.49 0 1.27 3.7 0.69 0
24/02/2017 6:55 1.5 0 1.29 3.7 0.7 0
24/02/2017 6:55 1.51 0 1.3 3.6 0.72 0
24/02/2017 6:56 1.51 0 1.31 3.7 0.73 0
24/02/2017 6:56 1.51 0 1.32 3.7 0.73 0
24/02/2017 6:57 1.54 0 1.33 3.7 0.75 0
24/02/2017 6:57 1.57 0 1.34 3.7 0.76 0
24/02/2017 6:58 1.57 0 1.35 3.7 0.77 0
24/02/2017 6:58 1.57 0 1.36 3.6 0.78 0
24/02/2017 6:59 1.77 0 1.37 3.6 0.78 0
123
24/02/2017 6:59 1.95 0 1.39 3.7 0.79 0
24/02/2017 7:00 1.97 0 1.4 3.7 0.8 0
24/02/2017 7:00 2.1 1 1.41 3.7 0.81 0
24/02/2017 7:01 2.21 9 1.42 3.6 0.81 0
24/02/2017 7:01 2.14 9 1.43 3.6 0.82 0
24/02/2017 7:02 2.13 9 1.44 3.7 0.83 0
24/02/2017 7:02 2.01 10 1.45 3.7 0.83 0
24/02/2017 7:03 1.9 10 1.45 3.7 0.84 0
24/02/2017 7:03 1.8 10 1.46 3.6 0.84 0
24/02/2017 7:04 1.68 10 1.47 3.6 0.85 0
24/02/2017 7:04 1.59 10 1.48 3.7 0.86 0.72
24/02/2017 7:05 1.57 10 1.49 3.7 0.84 5.13
24/02/2017 7:05 1.34 8 1.5 3.6 0.77 5.16
124
24/02/2017 7:06 1.28 0 1.5 3.7 0.7 5.15
24/02/2017 7:06 1.32 0 1.51 3.6 0.63 5.11
24/02/2017 7:07 1.35 0 1.52 3.6 0.56 5.15
24/02/2017 7:07 1.39 0 1.53 3.6 0.51 0.43
24/02/2017 7:08 1.46 0 1.53 3.6 0.5 0
24/02/2017 7:08 1.49 0 1.54 3.6 0.51 0
24/02/2017 7:09 1.5 0 1.55 3.7 0.52 0
24/02/2017 7:09 1.5 0 1.55 3.6 0.52 0
24/02/2017 7:10 1.51 0 1.55 3.6 0.52 0
24/02/2017 7:10 1.66 0 1.55 3.6 0.53 0
24/02/2017 7:11 1.69 0 1.54 3.6 0.54 0
24/02/2017 7:11 1.75 0 1.54 3.6 0.54 0
24/02/2017 7:12 1.77 0 1.53 3.6 0.54 0
125
24/02/2017 7:12 1.79 0 1.53 3.6 0.55 0
24/02/2017 7:13 1.89 0 1.52 3.6 0.55 0
24/02/2017 7:13 1.92 0 1.52 3.6 0.56 0
24/02/2017 7:14 1.94 0 1.51 3.6 0.56 0
24/02/2017 7:14 1.94 0 1.51 3.6 0.57 0
24/02/2017 7:15 2.05 0 1.5 3.7 0.57 0
24/02/2017 7:15 2.09 0 1.5 3.7 0.57 0
24/02/2017 7:16 2.13 0 1.49 3.7 0.58 0
24/02/2017 7:16 2.17 0 1.49 3.7 0.58 0
24/02/2017 7:17 2.21 0 1.48 3.7 0.59 0
24/02/2017 7:17 2.2 4 1.48 3.6 0.6 0
24/02/2017 7:18 2.11 10 1.47 3.6 0.61 0
24/02/2017 7:18 1.97 9 1.47 3.6 0.61 0
126
24/02/2017 7:19 1.86 9 1.46 3.6 0.62 0
24/02/2017 7:19 1.78 10 1.46 3.7 0.63 0
24/02/2017 7:20 1.66 10 1.45 3.7 0.64 0
24/02/2017 7:20 1.48 9 1.45 3.7 0.65 0
24/02/2017 7:21 1.36 9 1.45 3.6 0.65 0
24/02/2017 7:21 1.28 2 1.44 3.6 0.67 0
24/02/2017 7:22 1.29 0 1.43 3.6 0.68 0
24/02/2017 7:22 1.33 0 1.43 3.7 0.68 0
24/02/2017 7:23 1.37 0 1.43 3.7 0.69 0
24/02/2017 7:23 1.39 0 1.42 3.7 0.7 0
24/02/2017 7:24 1.46 0 1.41 3.7 0.71 0
24/02/2017 7:24 1.51 0 1.41 3.7 0.71 0
24/02/2017 7:25 1.6 0 1.4 3.7 0.72 0
127
24/02/2017 7:25 1.68 0 1.4 3.7 0.72 0
24/02/2017 7:26 1.76 0 1.39 3.7 0.73 0
24/02/2017 7:26 1.93 0 1.39 3.7 0.73 0
24/02/2017 7:27 2.01 0 1.38 3.7 0.74 0
24/02/2017 7:27 2.14 1 1.38 3.6 0.75 0
24/02/2017 7:28 2.21 9 1.37 3.6 0.75 0
24/02/2017 7:28 2.15 10 1.36 3.6 0.76 0
24/02/2017 7:29 2.11 10 1.36 3.6 0.77 0
24/02/2017 7:29 2.03 9 1.35 3.6 0.79 0
24/02/2017 7:30 1.95 9 1.35 3.6 0.8 0
24/02/2017 7:30 1.81 9 1.35 3.7 0.8 0
24/02/2017 7:31 1.76 9 1.34 3.6 0.81 0
24/02/2017 7:31 1.58 9 1.33 3.6 0.82 0
128
24/02/2017 7:32 1.42 9 1.33 3.6 0.83 0
24/02/2017 7:32 1.32 4 1.32 3.6 0.84 0
24/02/2017 7:33 1.28 0 1.32 3.6 0.85 0
24/02/2017 7:33 1.33 0 1.31 3.6 0.85 0.49
24/02/2017 7:34 1.34 0 1.31 3.6 0.85 3.87
24/02/2017 7:34 1.41 0 1.3 3.6 0.82 3.88
24/02/2017 7:35 1.46 0 1.29 3.6 0.8 3.93
24/02/2017 7:35 1.5 0 1.29 3.6 0.78 3.93
24/02/2017 7:36 1.56 0 1.28 3.6 0.75 3.92
24/02/2017 7:36 1.6 0 1.27 3.6 0.72 3.94
24/02/2017 7:37 1.62 0 1.27 3.7 0.71 3.95
24/02/2017 7:37 1.69 0 1.27 3.6 0.67 3.91
24/02/2017 7:38 1.73 0 1.26 3.6 0.64 3.92
129
24/02/2017 7:38 1.76 0 1.25 3.7 0.62 3.94
24/02/2017 7:39 1.78 0 1.25 3.6 0.6 3.96
24/02/2017 7:39 1.83 0 1.24 3.6 0.57 3.89
24/02/2017 7:40 1.89 0 1.23 3.6 0.55 3.9
24/02/2017 7:40 1.91 0 1.23 3.7 0.53 0.24
24/02/2017 7:41 1.98 0 1.22 3.7 0.53 0
24/02/2017 7:41 2.01 0 1.22 3.6 0.54 0
24/02/2017 7:42 2.05 0 1.21 3.6 0.55 0
24/02/2017 7:42 2.1 0 1.2 3.6 0.56 0
24/02/2017 7:43 2.15 0 1.2 3.6 0.57 0
24/02/2017 7:43 2.17 0 1.19 3.6 0.58 0
24/02/2017 7:44 2.18 0 1.18 3.5 0.6 0
24/02/2017 7:44 2.18 0 1.18 3.6 0.61 0
130
24/02/2017 7:45 2.12 8 1.17 3.6 0.62 0
24/02/2017 7:45 2.04 9 1.16 3.7 0.63 0
24/02/2017 7:46 1.93 10 1.15 3.7 0.64 0
24/02/2017 7:46 1.83 9 1.14 3.7 0.66 0
24/02/2017 7:47 1.7 9 1.14 3.7 0.68 0
24/02/2017 7:47 1.56 9 1.13 3.7 0.69 0
24/02/2017 7:48 1.4 9 1.12 3.7 0.7 0
24/02/2017 7:48 1.34 8 1.1 3.7 0.72 0
24/02/2017 7:49 1.31 0 1.09 3.7 0.73 0
24/02/2017 7:49 1.33 0 1.08 3.7 0.75 0
24/02/2017 7:50 1.5 0 1.06 3.7 0.76 0
24/02/2017 7:50 1.62 0 1.04 3.7 0.77 0
24/02/2017 7:51 1.7 0 1.02 3.7 0.78 0
131
24/02/2017 7:51 1.7 0 1 3.6 0.79 0
24/02/2017 7:52 1.7 0 0.99 3.7 0.81 0
24/02/2017 7:52 1.97 0 0.97 3.6 0.81 0
24/02/2017 7:53 2.22 6 0.95 3.7 0.82 0
24/02/2017 7:53 2.21 8 0.93 3.7 0.82 0
24/02/2017 7:54 2.16 9 0.91 3.7 0.84 0
24/02/2017 7:54 2.12 9 0.91 3.6 0.85 0
24/02/2017 7:55 2.07 9 0.93 3.6 0.85 3.06
24/02/2017 7:55 1.96 9 0.96 3.7 0.8 5.21
24/02/2017 7:56 1.86 9 0.99 3.7 0.73 5.24
24/02/2017 7:56 1.78 9 1.02 3.7 0.67 5.23
24/02/2017 7:57 1.7 9 1.05 3.7 0.6 5.19
24/02/2017 7:57 1.61 9 1.09 3.7 0.54 3.51
132
24/02/2017 7:58 1.45 9 1.12 3.7 0.51 0
24/02/2017 7:58 1.37 9 1.14 3.7 0.51 0
24/02/2017 7:59 1.3 2 1.16 3.7 0.52 0
24/02/2017 7:59 1.3 0 1.18 3.7 0.52 0
24/02/2017 8:00 1.36 0 1.19 3.7 0.53 0
24/02/2017 8:00 1.4 0 1.2 3.7 0.53 0
24/02/2017 8:01 1.44 0 1.21 3.7 0.54 0
24/02/2017 8:01 1.48 0 1.22 3.8 0.54 0
24/02/2017 8:02 1.51 0 1.23 3.7 0.55 0
24/02/2017 8:02 1.56 0 1.24 3.7 0.55 0
24/02/2017 8:03 1.59 0 1.25 3.7 0.56 0
24/02/2017 8:03 1.62 0 1.26 3.7 0.56 0
24/02/2017 8:04 1.65 0 1.27 3.7 0.57 0
133
24/02/2017 8:04 1.65 0 1.27 3.7 0.58 0
24/02/2017 8:05 1.72 0 1.28 3.7 0.58 0
24/02/2017 8:05 1.77 0 1.29 3.7 0.58 0
24/02/2017 8:06 1.84 0 1.3 3.7 0.59 0
24/02/2017 8:06 1.84 0 1.31 3.7 0.6 0
24/02/2017 8:07 1.84 0 1.32 3.7 0.6 0
24/02/2017 8:07 1.84 0 1.32 3.7 0.6 0
24/02/2017 8:08 1.84 0 1.33 3.7 0.61 0
24/02/2017 8:08 1.84 0 1.34 3.7 0.62 0
24/02/2017 8:09 1.84 0 1.35 3.7 0.62 0
24/02/2017 8:09 1.95 0 1.35 3.7 0.62 0
24/02/2017 8:10 2.13 0 1.36 3.7 0.64 0
24/02/2017 8:10 2.19 0 1.37 3.7 0.67 0
134
24/02/2017 8:11 2.19 0 1.38 3.7 0.69 0
24/02/2017 8:11 2.19 0 1.38 3.6 0.71 0
24/02/2017 8:12 2.15 5 1.39 3.6 0.73 0
24/02/2017 8:12 2.11 10 1.4 3.6 0.73 0
24/02/2017 8:13 2.11 10 1.41 3.6 0.73 0
24/02/2017 8:13 2.11 10 1.41 3.6 0.75 0
24/02/2017 8:14 2.11 10 1.42 3.6 0.77 0
24/02/2017 8:14 2.11 10 1.43 3.6 0.77 0
24/02/2017 8:15 1.96 10 1.43 3.6 0.79 0
24/02/2017 8:15 1.72 9 1.44 3.6 0.8 0
24/02/2017 8:16 1.72 9 1.45 3.6 0.81 0
24/02/2017 8:16 1.72 9 1.45 3.6 0.82 0
24/02/2017 8:17 1.72 9 1.46 3.6 0.83 0
135
24/02/2017 8:17 1.48 3 1.46 3.6 0.84 0
24/02/2017 8:18 1.3 0 1.47 3.6 0.84 0
24/02/2017 8:18 1.3 0 1.48 3.6 0.85 0
24/02/2017 8:19 1.4 0 1.48 3.6 0.86 0.66
24/02/2017 8:19 1.4 0 1.48 3.6 0.83 3.78
24/02/2017 8:20 1.4 0 1.47 3.6 0.8 3.83
24/02/2017 8:20 1.4 0 1.47 3.6 0.78 3.81
24/02/2017 8:21 1.58 0 1.46 3.6 0.76 3.79
24/02/2017 8:21 1.62 0 1.46 3.6 0.73 3.79
24/02/2017 8:22 1.65 0 1.46 3.6 0.7 3.82
24/02/2017 8:22 1.69 0 1.45 3.6 0.68 3.8
24/02/2017 8:23 1.69 0 1.45 3.6 0.67 3.8
24/02/2017 8:23 1.69 0 1.44 3.6 0.62 3.81
136
24/02/2017 8:24 1.69 0 1.44 3.6 0.6 3.8
24/02/2017 8:24 1.83 0 1.43 3.6 0.57 3.77
24/02/2017 8:25 1.88 0 1.43 3.6 0.55 3.76
24/02/2017 8:25 1.9 0 1.42 3.6 0.54 3.76
24/02/2017 8:26 1.97 0 1.42 3.6 0.53 1.54
24/02/2017 8:26 1.99 0 1.41 3.6 0.54 0
24/02/2017 8:27 2.04 0 1.41 3.6 0.55 0
24/02/2017 8:27 2.07 0 1.4 3.6 0.55 0
24/02/2017 8:28 2.11 0 1.39 3.6 0.57 0
24/02/2017 8:28 2.15 0 1.39 3.6 0.58 0
24/02/2017 8:28 2.16 0 1.38 3.6 0.59 0
24/02/2017 8:29 2.2 0 1.38 3.6 0.6 0
24/02/2017 8:29 2.2 4 1.37 3.6 0.61 0
137
24/02/2017 8:30 2.2 9 1.37 3.6 0.62 0
24/02/2017 8:30 2.2 9 1.36 3.7 0.63 0
24/02/2017 8:31 2.03 9 1.36 3.7 0.64 0
24/02/2017 8:31 1.75 9 1.35 3.7 0.65 0
24/02/2017 8:32 1.68 9 1.34 3.8 0.66 0
24/02/2017 8:32 1.54 9 1.34 3.7 0.66 0
24/02/2017 8:33 1.44 9 1.33 3.7 0.68 0
24/02/2017 8:33 1.39 9 1.33 3.7 0.69 0
24/02/2017 8:34 1.38 9 1.32 3.7 0.7 0
24/02/2017 8:34 1.31 1 1.32 3.8 0.71 0
24/02/2017 8:35 1.37 0 1.31 3.8 0.72 0
24/02/2017 8:35 1.49 0 1.31 3.7 0.73 0
24/02/2017 8:36 1.6 0 1.3 3.7 0.74 0
138
24/02/2017 8:36 1.71 0 1.3 3.7 0.75 0
24/02/2017 8:37 1.81 0 1.29 3.7 0.75 0
24/02/2017 8:37 1.81 0 1.28 3.7 0.76 0
24/02/2017 8:38 2.06 0 1.28 3.7 0.77 0
24/02/2017 8:38 2.21 6 1.27 3.7 0.78 0
24/02/2017 8:39 2.18 10 1.27 3.7 0.78 0
24/02/2017 8:39 2.15 10 1.26 3.7 0.79 0
24/02/2017 8:40 2.05 10 1.26 3.7 0.79 0
24/02/2017 8:40 1.94 10 1.25 3.7 0.8 0
24/02/2017 8:41 1.83 10 1.25 3.7 0.81 0
24/02/2017 8:41 1.73 10 1.24 3.7 0.81 0
24/02/2017 8:42 1.66 10 1.23 3.7 0.83 0
24/02/2017 8:42 1.51 10 1.23 3.7 0.83 0
139
24/02/2017 8:43 1.36 8 1.22 3.7 0.84 0
24/02/2017 8:44 1.28 0 1.21 3.7 0.85 0
24/02/2017 8:44 1.3 0 1.21 3.7 0.85 5.49
24/02/2017 8:45 1.33 0 1.2 3.7 0.79 5.16
24/02/2017 8:45 1.39 0 1.19 3.7 0.73 5.21
24/02/2017 8:46 1.43 0 1.19 3.7 0.65 5.23
24/02/2017 8:46 1.45 0 1.18 3.7 0.58 5.21
24/02/2017 8:47 1.48 0 1.17 3.7 0.53 2.48
24/02/2017 8:47 1.54 0 1.17 3.7 0.51 0
24/02/2017 8:48 1.58 0 1.16 3.7 0.52 0
24/02/2017 8:48 1.61 0 1.15 3.7 0.53 0
24/02/2017 8:49 1.65 0 1.14 3.7 0.54 0
24/02/2017 8:49 1.68 0 1.13 3.7 0.55 0
140
24/02/2017 8:50 1.73 0 1.12 3.7 0.57 0
24/02/2017 8:50 1.77 0 1.11 3.7 0.57 0
24/02/2017 8:51 1.8 0 1.09 3.7 0.57 0
24/02/2017 8:51 1.83 0 1.08 3.7 0.58 0
24/02/2017 8:52 1.84 0 1.06 3.6 0.6 0
24/02/2017 8:52 1.91 0 1.04 3.6 0.61 0
24/02/2017 8:53 1.94 0 1.02 3.6 0.61 0
24/02/2017 8:53 1.97 0 1 3.6 0.62 0
24/02/2017 8:54 2.01 0 0.98 3.6 0.63 0
24/02/2017 8:54 2.06 0 0.96 3.6 0.63 0
24/02/2017 8:55 2.09 0 0.94 3.6 0.64 0
24/02/2017 8:55 2.11 0 0.93 3.6 0.65 0
24/02/2017 8:56 2.15 0 0.91 3.6 0.65 0
141
24/02/2017 8:56 2.15 0 0.89 3.6 0.67 0
24/02/2017 8:57 2.15 0 0.87 3.6 0.67 0
24/02/2017 8:57 2.15 0 0.86 3.6 0.67 0
24/02/2017 8:58 2.16 2 0.84 3.6 0.67 0
24/02/2017 8:58 2.15 10 0.82 3.6 0.68 0
24/02/2017 8:59 2.02 10 0.8 3.6 0.68 0
24/02/2017 8:59 1.95 9 0.78 3.6 0.68 0
24/02/2017 9:00 1.94 9 0.77 3.6 0.69 0
24/02/2017 9:00 1.85 9 0.75 3.6 0.7 0
24/02/2017 9:01 1.82 9 0.73 3.6 0.7 0
24/02/2017 9:01 1.82 9 0.72 3.6 0.7 0
24/02/2017 9:02 1.66 9 0.7 3.6 0.71 0
24/02/2017 9:02 1.66 9 0.69 3.6 0.71 0
142
24/02/2017 9:03 1.52 9 0.67 3.6 0.71 0
24/02/2017 9:03 1.5 9 0.66 3.6 0.72 0
24/02/2017 9:04 1.5 9 0.64 3.1 0.72 0
24/02/2017 9:04 1.39 4 0.63 0 0.72 0
24/02/2017 9:05 1.32 0 0.64 0 0.73 0
24/02/2017 9:05 1.36 0 0.64 0 0.73 0