Virginia Beach Transit Extension StudyDraft Environmental Impact Statement
Town Center Alignment Alternative BriefingVirginia Beach City CouncilVirginia Beach City Council
September 9, 2014
Presentation
1. Project Background
2. Town Center Alternative
3. Town Center Capital Costs, O&M Costs, and Ridership Forecasts
4. Study Schedule
Page 2
9/9/2014
2
VIRGINIA BEACH TRANSIT EXTENSION STUDY
PROJECT BACKGROUND
Page 3
Project Goals• Provide additional mobility opportunities in the east‐west corridor
• Expand multi‐modal transportation system that supports local land use plans and initiatives (Strategic Growth Areas)p ( g )
• Develop transportation infrastructure that supports the regional tourism industry
Page 4Page 4
9/9/2014
3
Virginia Beach Transit Extension StudyThe Virginia Beach Transit Extension Study (VBTES) is examining the best transit options for a former freight rail right of way that runs from Newtown Road to Birdneck Road in Virginia Beach. The study area extends from Newtown Road to the Oceanfront area on 19th Street.
• Four Fixed Guideway Alignment Alternatives from Newtown Road
– Alternative 1a: ~3 miles to the Town Center Area
– Alternative 1b: 4.8 miles to the Rosemont Area
– Alternative 2: 12.2 miles to the Oceanfront along the NSRR corridor (with Maintenance Facility)
– Alternative 3: 13.5 miles to the Oceanfront through the Hilltop Area (with Maintenance Facility)
Page 5
Alternative 1b:
Alternative 1a: Newtown to Town Center (Town Center Alternative)
Newtown to Rosemont (Rosemont Alternative)
Alternative 2: Newtown to Oceanfront via NSRR ROW (NSRR Alternative)
Page 6
Alternative 3: Newtown to Oceanfront via Laskin Road (Hilltop Alternative)
9/9/2014
4
DEIS Technology Alternatives• Light Rail Transit (LRT)
• Bus Rapid Transit (BRT)
7
Feeder Bus Routes
Page 8
9/9/2014
5
VIRGINIA BEACH TRANSIT EXTENSION STUDY
TOWN CENTER ALTERNATIVE
Page 9
Alternatives 1b, 2, and 3: Newtown to Rosemont and theOceanfront
Page 10
9/9/2014
6
Alternative 1a: Newtown to Town Center (Town Center Alternative)
Page 11
Alternative 1a: Newtown to Town Center (Town Center Alternative)
Page 12
9/9/2014
7
Page 13
Page 14
9/9/2014
8
Page 15
Page 16
9/9/2014
9
Page 17
Page 18
9/9/2014
10
Page 19
Page 20
9/9/2014
11
Page 21
Page 22
9/9/2014
12
Page 23
Page 24
9/9/2014
13
Page 25
Alternative 1a: Newtown to Town Center (Town Center Alternative)
Page 26
9/9/2014
14
TOWN CENTER ALIGNMENT ALTERNATIVE
CAPITAL COSTS, O&M COSTS, AND RIDERSHIP FORECASTS
Page 27
Capital Cost Estimating
Costs Contingency Escalation
Page 28
9/9/2014
15
Capital Cost Assumptions
Assumptions for the Town Center Light Rail Alternative
• Escalation
• Contingencies
• Real Estate
• Vehicle Costs
• Soft Costs
Page 29
Capital Cost Assumptions
• Escalation
Year IHS Global Insight Highway and Street Index
ENR Construction Cost Index VBTES Rate VBTES Cost
Index
2013 BASE Base Cost Plus
2014 1.4% 4.7% 4.70% 4.7%
2015 2.5% 3.4% 3.40% 8.3%
2016 2.9% 2.2% 2.90% 11.4%
2017 2.5% 2.4% 2.50% 14.2%
2018 2.2% 2.4% 2.40% 16.9%
Page 30
% %
2019 2% 2.7% 2.70% 20.1%
2020 2% 2.6% 2.60% 23.2%
9/9/2014
16
Capital Cost Assumptions
• Contingencies by major project element
Major Project Element ContingencyTrack 35%Stations 30%Modifications to Maintenance Facility 30%Site Work 35%Utilities 40%Rail Systems (Traction Power, Signals) 35%Real Estate (excluding NSRR ROW) 50%
Page 31
Vehicles 20%Unallocated 2% of total
• Real Estate Costs– Based on City assessed values for 2013
– Includes
Capital Cost Assumptions
• Partial property takes
• Whole property takes
• Costs to relocate businesses, where required
• Legal fees and transfer costs
– Does not include• Costs of Kempsville Lumber, NSRR ROW (prorated), and Circuit p , (p ),City (all properties already owned by the City)
• Temporary construction easements
Page 32
9/9/2014
17
• Vehicles– Four Light Rail Vehicles required for service to Town Center
Capital Cost Assumptions
– Twelve additional transit buses are required to support LRT Service to support• Three additional bus routes
• Extended AM and PM hours
• Additional service days (weekends)
• Increased frequency of service
Page 33
Capital Cost Assumptions
• Soft Costs (% of construction)
Soft Costs % of Construction
Project Development (DEIS/Concept Design) 2.5%Engineering 12%Project Management 5%Construction Management 8%Insurance 2%Legal/Permit Fees 2%
Page 34
Survey/Testing/Inspection 2%System Startup 1.5%
9/9/2014
18
Capital Costs
Opinion of Probable Capital Cost Current Year*(2013)
YOE* (2018)
Construction Cost $ 161 $ 188Other Project Costsj
Existing Tide System Improvements $ 5 $ 6
Light Rail Vehicles (4) $ 21 $ 25
Bus Vehicles (12) $ 9 $ 11
“New” Real Estate Required** $ 19 $ 24
Project Development and Engineering $ 24 $ 27
Other Soft Costs (PM/CM/Legal/Startup) $ 34 $ 39
Unallocated Contingencies $ 6 $ 7
Total Probable Capital Cost $ 279 $ 327
Page 35
Reflects Constitution Station End of Line Option – 3.1 Miles* In Millions of Dollars** Does not include real estate purchased to date of $28M
OCC Modifications
Page 36
9/9/2014
19
Capital Cost Comparison
Project Length Capital Cost Cost per MileVBTES LRT to Constitution Drive 3.1 $279 million* $90 million*
VBTES compared to significant LRT projects under construction in FY13
Virginia Beach, VA$ $
Central Corridor LRTMinneapolis, MN
9.8 $956 million $97 million
North Corridor LRTHouston, TX
5.28 $756 million $143 million
Southeast Corridor LRTHouston, TX
6.56 $822 million $125 million
Dulles Metrorail Extension Northern Virginia**
11.7 $3.1 billion $269 million
Page 37
* FY 13 Dollars** Heavy Rail Project in VA
Local Share of O&M Costs*
Comparison of Bus and LRT Service CostsO&M Costs
in 2012 Service Levels and Dollars
Virginia Beach Projected Bus and LRT Service $ 11.0 MVirginia Beach Bus Service Costs in 2012** $ 3.0 M
Expanded Bus Service for LRT $ 6.0 M
Light Rail Service in Virginia Beach to Town Center $ 2.0 M
Norfolk Bus and LRT Service $ 14.2 MNorfolk Bus Service Costs in 2012 $ 8.5 M
Light Rail Service in Norfolk in 2012 $ 5.7 M
Page 38
* Not Including Paratransit Costs** FY14 Virginia Beach local share for bus service costs is $4.4 M
9/9/2014
20
Ridership Forecast
Ridership Forecasting for Light Rail to Town Center
• Results of FTA approved ridership model• Home-Based Work Model produces conservative ridership numbers
Tide Forecast(FY 2011)
Actual Tide(FY 2014)
Projected Norfolk (2034)
Projected Virginia Beach
(2034)
Total ProjectedTide LRT(2034)
AverageWeekday
2,900 5,300 7,050 2, 250 9,300
• Does not include Tourism or Special Events
Page 39
Annual Trips
870,000 1.4 million 2.8 million
Tide Ridership
Tide Average Monthly Ridership Since Opening
140,000
160,000
40,000
60,000
80,000
100,000
120,000
Page 40
-
20,000
FY12 FY13 FY14 FY15
9/9/2014
21
VIRGINIA BEACH TRANSIT EXTENSION STUDY
STUDY SCHEDULE
Page 41
September Public Meetings ‐ Town Center Alternative
• September 22, 2014Renaissance AcademyWit hd k R dWitchduck Road6:00 to 7:30 PM
• September 24, 2014Westin HotelTown Center
Page 42
o Ce te6:00 to 7:30 PM
9/9/2014
22
Public Comment
• Comments are welcome at any time during the VBTES process.
• You are encouraged to participate throughout the entire study g p p g yprocess.
• Formal Comments on the DEIS will be accepted after the release of the document (the beginning of 2015) during the Formal Public Comment Period at the Formal DEIS Public Hearings.
HRT ill dd ll “ b t ti ” itt t• HRT will address all “substantive” written comments.
Page 43
VBTES DEIS Remaining Milestones
• Early Submittal of DEIS Chapters to FTA (September 2014)
• Full Submittal of DEIS to FTA (October 2014)Full Submittal of DEIS to FTA (October 2014)
• Formal DEIS Public Comment Period and Formal DEIS Public Hearings (Early 2015)
• Locally Preferred Alternative Selected by City Council (Early 2015)
Page 44
9/9/2014
23
2014 2015 2016J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
DEIS Completion
Update DEIS ‐ New Alternative
FTA Review/Approval of DEIS
Town Center Schedule under State – City Funding
pp
DEIS Circulation and Public Hearings
Locally Preferred Alternative (LPA)
LPA to HRTPO Fiscally Constrained LRTPHRT Request to Enter FTA "Project Development"
Preparation of Final EIS/ROD
HRT Request to Enter FTAHRT Request to Enter FTA “Engineering"
Design Build
FFGA/ Final Engineering /Construction
Operations
Page 45
Thank You
Page 46
9/9/2014
24
Public Comment
Visit the VBTES Website or leave a message on the VBTES project hotline
• Website: www.gohrt.com/about/development/vbtes
• Study Hotline: 757‐222‐6098• Study Hotline: 757 222 6098
Share your comments directly with HRT and the City of Virginia Beach
HAMPTON ROADS TRANSITJulie Timm
Transit Development OfficerDepartment of Planning and Development
CITY OF VIRGINIA BEACHBrian Solis
Transportation and Transit ManagerStrategic Growth Area Office
47
509 East 18th StreetNorfolk, VA 23504
757‐222‐6000 ext. [email protected]
4525 Main Street, Suite 710Virginia Beach, VA 23462
757‐385‐[email protected]