Vedasandur 19.05.15

10
INSPECTION REPORT OF EXECUTIVE ENGINEER (RD) DINDIGUL ON THE WORKS INSPECTED ON VEDASANDUR PANCHAYAT UNION Date: 19.05.2015 1) Scheme : MLACDS –2014-2015 Name of Block : Vedasandur Name of Panchayat : Kovilur Name of work : Construction of Drama stage at Ramanathapuram government higher.sec. school Estimate Amount : Rs.3.05 lakhs Stage of work : White / Colour washing progress Observation: At the time of inspection , all item of the work completed including pressed tiles laying work also completed. The colour washing was about to start. The basement height of the stage was 0.75m. Ramp was constructed, but the hand rails were not fixed. The flooring plastering work was not started. Instructed the AE(RD) to complete the flooring work thenonly colour washing work should be started. Instructed the AE(RD), to procure the good quality of paint and to maintain the uniform colour code. AE(RD) was further instructed to speed up the work and complete it in all aspects before 31.05.2015.

description

Vedasandur 19.05.15

Transcript of Vedasandur 19.05.15

  • INSPECTION REPORT OF EXECUTIVE ENGINEER (RD) DINDIGUL ON THE WORKS INSPECTED ON VEDASANDUR

    PANCHAYAT UNION

    Date: 19.05.2015

    1) Scheme : MLACDS 2014-2015

    Name of Block : Vedasandur

    Name of Panchayat : Kovilur

    Name of work : Construction of Drama stage at

    Ramanathapuram government

    higher.sec. school

    Estimate Amount : Rs.3.05 lakhs

    Stage of work : White / Colour washing progress

    Observation:

    At the time of inspection , all item of the work completed

    including pressed tiles laying work also completed.

    The colour washing was about to start.

    The basement height of the stage was 0.75m.

    Ramp was constructed, but the hand rails were not fixed.

    The flooring plastering work was not started.

    Instructed the AE(RD) to complete the flooring work thenonly

    colour washing work should be started.

    Instructed the AE(RD), to procure the good quality of paint and

    to maintain the uniform colour code.

    AE(RD) was further instructed to speed up the work and

    complete it in all aspects before 31.05.2015.

  • 2) Scheme : VPSC 14-15

    Name of Block : Vedasandur

    Name of Panchayat : Koovakkapatti

    Name of work : Construction of Village Panchayat Service

    centre at Koovakkapatti

    Estimate Amount : Rs.14.43 lakhs

    Stage of work : Roof laid

    Observation:

    At the time of inspection the building was roof laid.

    The thickness of the roof slab was measured and found as

    12.50cm.

    The inner measurement of the building is verified and found as

    Training room 7.10m x 12.09m.

    Passage room 15.81m x 2.55m.

    Room for MIS 6.20m x 3.95m.

    Hall for work station 6.20m x 7.91m.

    Staircase area 6.20m x 3.96m.

    The basement height is 1.00 m and from basement to roof

    height is 3.05m.

    The outer toilet work was not started and The centering was not

    removed.

    Instructed the AE(RD) to start the outer toilet work and to

    ensure the proper curing for roof slab.

    The doors and windows fixing work completed and tiles was

    procured not yet laid.

    There are no materials for further work, instructed the AE(RD) &

    Contractor to collect the all materials immediately and to start

    the toilet work.

    Instructed the Assistant Engineer(RD) to construct ramp at

    proper gradient as per the standard specifications of 1 in 12 ratio

    of minimum length 12.00m.

  • Rain water harvesting structure should be constructed as per

    specification .

    Instructed the AE(RD) to speed up the work and complete the

    work as per time schedule.

    3) Name of Scheme : MGNREGS 2014-2015

    Name of Block : Vedasanthoor

    Name of Panchayat : Koovakkapatty

    Name of work : Deepening strengthening the

    Chettikulam

    Estimate Amount : Rs. 7.90 lakhs

    Observation:

    Time of inspection 12.20 PM. Verified the NMR Nos 323080 to

    323087. At the time of inspection male 22 nos, and female

    114 nos, total no.of 136 nos were working on the field.

    Pre marking of site has been done by Panchayat Secretary for

    one week. One pit measurement for 20 workers group was

    verified and found it is correct.

    Top painted pegs (Timber/Steel) were used for pre marking.

    All entries made in NMR form and job cards were cross verified

    with workers. The details were noted below.

    Pre-measurement was properly marked. It was observed that 3rd

    group workers pit size was 11m x 9m x 0.90were taken 15cm

    depth of earth work. Beneficiaries were instructed that 30cm

    depth should be taken for full payment.

    Panchayat Secretary was instructed to

    All the entries in NMR and Job Card should be made

    properly.

    All the MGNREGS instructions should be strictly

    implemented in the field.

    Panchayat secretary instructed to carefully enter the

    payment details at relevant box in the Job Card.

    At the time of inspection sufficient medicine were not

    available in First Aid Box, Panchayat Secretary was

  • advised to do the needful and also to provide rest

    shed for children with tar palia and local available

    materials.

    Job Card Verifications

    NMR no : Nos 323080 to 323087 of 20 nos used. Verified the Job

    card as below

    Sl No Name of workers Job Card No

    1 Kanniammal W/o Paramasivam 7A

    2 Maruthayee W/o Perumal 210A

    3 Kengammal W/o Veerasamy 734A

    4 Ponnuthai W/o Muniandi 481A

    4) Scheme : RRMS 2014-2015

    Name of Block : Vedasandur

    Name of Panchayat : Athurpillaiyur

    Name of work : Providing 2 layer WBM + BT

    AthurPillaiyur to Valluvannagar road

    km 0/0-2/0

    Estimate Amount : Rs.20.70 lakhs

    Stage of work : BT Chips collection completed

    Observation:

    The actual length of the road is 2000m and width of the road is

    3.75m.

    At the time of inspection, The patch works were completely and

    evenly.

    The jungle clearance and earth work also completed entire

    length of the road.

    The BT chips collection completed.

    Instructions given to the contractor to clean the surface with

    wire brushes and apply prime coat before 24 hours of B.T laying.

    Bituminous primer shall not be applied to a surface or during a

    dust storm or when the weather is foggy, rainy or windy or when

  • the temperature in the shade is less than 100C. Surfaces which

    are to receive emulsion primer should be damp, but no free or

    standing water shall be present.

    Instruction given to the contractor side berm work should be

    done simultaneously during the time of laying BT work.

    Instructions given to Assistant Engineer (RD) to start BT laying

    work and complete the work as per time schedule.

    5) Scheme : VPSC 14-15

    Name of Block : Vedasandur

    Name of Panchayat : Marambadi

    Name of work : Construction of Village Panchayat Service

    centre at Marambadi

    Estimate Amount : Rs.14.43 lakhs

    Stage of work : Flooring tiles laying

    Observation:

    At the time of inspection, the building was at plastering

    completed stage.

    The basement the building was measured and found as 0.80m.

    Ramp was constructed, the length of the ramp was 6.00 and

    width of the ramp was 1.20m.

    The toilet laying work and flooring tiles laying work progress.

    The weathering course and pressed tiles laying work also

    completed.

    The wall tiles was laid around the toilet wall 1m height from the

    floor level.

    The doors and windows were fixed.

    The doors edges was brokend and steps corners also brokened.

    Instructed the AE(RD) to rectify the above defects before

    starting the colour washing work.

    Rain water harvesting structure should be constructed as per

    specification.

    Instructed to the AE(RD) that to speed up the laying work and to

    start the color washing work immediately.

  • 6) Scheme : Anganwadi 2014-2015

    Name of Block : Vedasandur

    Name of Panchayat : Marambadi

    Name of work : Construction of Anganwadi building at

    Marambadi

    Estimate Amount : Rs.6.50 lakhs

    Stage of work : Lintel level

    Observation:

    At the time of inspection the lintel level brick work

    completed.

    The basement height of the building was measured and

    found as 0.50m.

    The inner measurement of the building was measured and

    found as hall 6.00 x4.00m , kitchen 3.00 x 1.50m and store

    room 3.00 x 2.38m.

    Instructed the AE(RD) to start the lintel centering work

    immediately.

    The flooring concrete was not laid , instructed to lay the

    flooring concrete, thenonly the lintel concrete should be laid.

    At the procured metals for lintel concrete, some over size

    metal and soft metal were found.

    It should be removed from the site immediately and correct

    size of metal should be collected.

    AE(RD) was instructed to start the bar bending work for

    lintel concrete.

    Instructed to Assistant Engineer (RD) to expedite the work

    and all item of works should completed up to roof laid stage

    before 10.06.2015.

  • 7) Scheme : BPRIS - 2014-2015

    Name of Block : Vedasandur

    Name of Panchayat : Thattarapatty

    Name of work : Improvements to Ariyapithanpatty

    km 0/0-1/670

    Estimate Amount : Rs.57.78 lakhs

    Stage of work : BT Chips collection progress

    Observation:

    This work was inspected with reference to the estimate.

    The total length of the road is 1670m, the formation width of

    the road is 7.00m and the carriage way width is 3.75m as per

    the estimate provision.

    At the time of inspection, jungle clearance and earth work for

    the entire length of the road was completed.

    The WBM Grade II & III metal spreading work completed.

    The thickness the the Grade II and III was verified at chainage

    1/210m and found as 0.15m.

    Instructions given to the contractor the BT chips collection to

    speed up immediately,

    The side berms work has not done properly to do the side berms

    works simultaneously to a width of 1.00m on both side.

    Instructed the AE(RD) to expedite the work and complete the

    all item of work before 10.06.2015.

    8) Scheme : NABARD XX - 2014-2015

    Name of Block : Vedasandur

    Name of Panchayat : Nagaiyakottai

    Name of work : Improvements to the road from

    Kallukottai to Rajapuram km 0/0 1/0

    Estimate Amount : Rs. 22.80 lakhs

    Stage of work : WBM Gr- III Metal collection

    progress

  • Observation:

    The name board was fixed to the entrance of the road.

    The KM and HM stones were fixed.

    The total length of the road is 1000m, the carriage width of the

    road is 3.75m.

    At ch 990m, RCC slab culvert was completed.

    Instructed to AE (RD) to maintain correct gauge length of 1.92m

    for every stock.

    The Gr.II metal sieve analysis was done at 0/710 and results are

    as follows.

    Sl.

    No.

    Sieve

    Size

    Wt.

    Retained

    % of

    Retained

    %

    Passing

    Cumulative

    retained

    Permissible

    value

    1 90 0 0 0 0 100

    2 63 2120 21.20 21.20 78.80 90-100

    3 53 3535 35.35 56.55 43.45 25-75

    4 45 3886 38.86 95.41 4.59 0-15

    5 22.40 459 4.59 100 0 0-5

    Instructions given to Assistant Engineer (RD) to maintain the

    proper camber and consolidation.

    Instructed the AE(RD) to expedite the work and complete the

    work as per time schedule.

    9) Scheme : NABARD - 2014-2015

    Name of Block : Vedasandur

    Name of Panchayat : Nagaiyakottai

    Name of work : Providing and laying two layer WBM with

    BT from Ariyapithampatti road

    km 0/0

    Estimate Amount : Rs. 26.79 lakhs

    Stage of work : CD works completed

  • Observation:

    The work was inspected with reference to the estimate provision.

    The name board was fixed and KM and HM stones were fixed.

    The actual length of the road is 1000m, carriage way width

    3.75m.

    The jungle clearance work and earth work were completed to the

    entire length of the road.

    The gravel soling work completed to the entire length of the road

    and thickness was verified and found as 0.15m as per estimate

    provision.

    The CD works are completed in chainage 0/6 km to a vent of 3m

    span RCC slap culvert and and 2m span at chainage 5m.

    The sieve analysis Grade III is conducted and the result is under

    (chainage @ 1/135m)

    I.S.Sieve designation

    Weight of sample retained (gm)

    Percent of Wt. retained

    (%)

    Cumulative percent of Wt. retained (%)

    Percentage of Wt.

    Passing (%)

    Permissible Value in %

    63 0 0 0 100 100

    53 545 5.45 5.45 94.55 95-100

    45 1816 18.16 23.61 76.39 65-95

    22.40 7128 71.28 94.89 5.11 0-10

    11.20 511 5.11 100 0 0-5

    Instructed to the AE(RD) that the 4% camber should be properly

    maintained to the entire length of the road.

    Instructed to the AE(RD) & Contractor that to start the grade II

    metal collection work and to expedite the work as per time

    schedule.

  • 10) Scheme : General Fund (DP) 14-15

    Name of Block : Vedasandur

    Name of Panchayat : Velampatti

    Name of work : Providing new Drainage in Vellampatti

    AD colony to Beerakkal house near at

    Vellampatti

    Estimate Amount : Rs.1.85 lakhs

    Stage of work : RR Masonary progress

    Observation:

    The above work was inspected with reference to the estimate.

    The length of the drainage was measured and found as 105m

    and vent of the drainage was 0.45m.

    The width of the drainage wall was 0.30m and height of the wall

    was 0.60m.

    Instructed the AE(RD) to do the simultaneous pointing should be

    done in RR masonry.

    Instructed the AE(RD), to provide the proper gradient to the

    drain portion for free flow of drain water.

    Instructed the AE(RD), to speed up the work and complete the

    work before 31.05.2015.

    Executive Engineer (RD), DRDA, Dindigul.

    To

    1. The Block Development Officer (B.P. & V.P.), Vedasandur

    2. The Assistant Engineer (RD)/Block Engineer, Vedasandur

    3. The Assistant Executive Engineer (RD), Vedasandur Sub Division

    for necessary follow up action.

    Copy Submitted to

    1. The District Collector/Chairman, DRDA, Dindigul.

    2. The Project Director, DRDA, Dindigul.