U.S. 50 Bridge Replacement over Tanner Creek
Tuesday, June 25, 2013
5:30 p.m. Presentation
Lawrenceburg Fire Department
Lawrenceburg, Indiana
![Page 2: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/2.jpg)
Welcome Rickie Clark, INDOT Office of Public Involvement Purpose/Explanation of Public Hearing Public Hearing Format Visit our sign-in table Informational Handouts Submitting public comments for hearings transcript Project display area
![Page 3: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/3.jpg)
Welcome Introduction of INDOT Project Officials
Project Management – Danny Pearcy, INDOT Seymour District
Design Public Involvement
City of Lawrenceburg Dearborn County Recognition of Elected Public Officials
![Page 4: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/4.jpg)
Public Hearing Sign-in at attendance table to be added to project
mailing list A public hearing notice was mailed to known
property owners within project area Announcement of this hearing was posted to INDOT
website. A media release was also issued Legal notice of public hearing published in the
Dearborn County Register on 6/6/13 & 6/20/13
![Page 5: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/5.jpg)
Project Stakeholders Indiana Department of Transportation Indiana Division Federal Highways Administration Dearborn County City of Lawrenceburg Local communities Elected Public Officials Community residents and citizens Commuters Trucking industry Schools Emergency Services
![Page 6: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/6.jpg)
Project Development Process
We Are Here
Engineering Assessment
Project purpose &
need
develop project
alternatives
Screen project
alternatives
Additional work on project
alternatives & preliminary
design
Release environmental document & preliminary
design
Public Hearing to
solicit public comment
Right-of-Way Construction
![Page 7: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/7.jpg)
Environmental Document
Requirement of the National Environmental Policy Act (NEPA) Requires INDOT to analyze and evaluate the
impacts of a proposed project to the natural and socio-economic environments
Impacts are described in environmental document Environmental document was released for public
involvement May 2013
![Page 8: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/8.jpg)
Environmental Document Development of document begins once purpose and
need for the project has been clearly identified Develop a number of possible alternatives including a
“Do Nothing” alternative as a baseline for comparison
Screen alternatives to identify a preferred alternative Solicit public comment on environmental document
and preliminary design plan Solicit, address, and fully consider public comments
as part of decision making process
![Page 9: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/9.jpg)
Elements of the Environmental Documentation
Real Estate Community ImpactsAir Quality Wetlands and WaterwaysNoise FloodplainsFarmland Endangered SpeciesHazardous Materials Historic/Archaeological
Cultural Resources
![Page 10: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/10.jpg)
Environmental Document INDOT Seymour District, Planning and
Programming Dept. 185 Agrico Lane, Seymour, Indiana (877) 305-7611
INDOT Office of Public Involvement, Indiana Government Center North, Room N642, 100 North Senate Avenue, Indianapolis (317) 232-6601
Lawrenceburg Public Library, 150 Mary Street, Lawrenceburg, Indiana (812) 537-2775
![Page 11: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/11.jpg)
U.S. 50 Bridge Rehabilitation and Widening
![Page 12: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/12.jpg)
Project Need The existing structure has a deteriorated deck with numerous patched locations
Heavy corrosion is present on the existing steel girders and bearings
Deck joints have deteriorated allowing water to drain onto the steel beams
![Page 13: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/13.jpg)
Project Need Existing railing does not meet INDOT standards Slope walls are eroded and in poor condition Abutments do not have adequate support length based on
AASHTO criterion
![Page 14: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/14.jpg)
Existing U.S. 50 Classified as urban principal arterial Posted speed of 30 mph Design speed of 40 mph Located within Lawrenceburg Adjacent to newly constructed bridge carrying traffic west
Flat level terrain
![Page 15: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/15.jpg)
Existing U.S. 50 Asphalt travel lanes 11ft. wide
Asphalt shoulders 3ft wide Overlay and repair done in 1976 Urban setting, built up, primarily commercial use
Access drives located immediately off both ends of structure
![Page 16: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/16.jpg)
Existing structure over Tanners Creek
Existing piers in good condition Light spalling and deterioration Some rust damage in and around bearings
5 spans: 81’-3”, 105’-7 ½ “, 113’-9”, 105’-7 ½ , and 81’3” Built-up plate girder with reinforced concrete deck Asphalt overlay
![Page 17: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/17.jpg)
Existing structure over Tanners Creek
Damaged bridge deck Multiple patching locations throughout Joint failure at all locations
Bearings at abutments in poor condition Rusted cross bracing Pitting and rust present on steel girders
![Page 18: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/18.jpg)
US 50 Bridge is Historic
Eligible for listing in the National Register of Historic Places for its historical significance
![Page 19: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/19.jpg)
Historic Bridge InventoryUS 50 Bridge is Non-Select
not suitable candidate for preservation
not considered excellent example
![Page 20: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/20.jpg)
Alternatives Analysis Rehabilitation for Continued Vehicular Use One or two-way roadway on historic bridge One-way pair: historic bridge & new bridge each
Bypass (non-vehicular use) Relocate (non-vehicular use) Replacement
Non-Select Bridges
![Page 21: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/21.jpg)
Historic Bridge Process Seek Consulting Party Comment
No opposition to project to date Market Bridge for Re-Use
Has been marketed for over 6 months Identify Preferred Alternative
Replacement (reconstruction) Hold Public Hearing Environmental Document Approval
After hearing comment period
![Page 22: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/22.jpg)
US 50 Bridge Marketing Legal notice in a local newspaper Signs at both approaches
to the bridge INDOT’s historic bridge
marketing website http://www.in.gov/indot/2532.htm
No interested party for re-useto date
![Page 23: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/23.jpg)
Joseph E. Seagrams & Sons Distillery Complex
Other Historic Resources
![Page 24: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/24.jpg)
Newtown Historic District Other Historic Resources
![Page 25: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/25.jpg)
U.S. 50 Plan View
![Page 26: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/26.jpg)
Proposed Structure 5 span pre-stressed concrete bulb-t beam bridge Total bridge width of 72’-2” Total bridge length of 492’-0” Utilize existing piers and widen to retain architectural features Utilize existing abutments and widen Provide locations for future decorative lighting Repair and protect against future scour
![Page 27: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/27.jpg)
Maintenance of Traffic (MOT)
• 2 lanes of traffic at all times• Least disruptive option• New pavement markings• Narrow temporary shoulders during construction• Posted speed limit during construction
![Page 28: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/28.jpg)
![Page 29: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/29.jpg)
East End Improvements Mill and Resurface Terminate prior to railroad crossing
Install curb and gutter New pavement and railroad markings
![Page 30: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/30.jpg)
Real Estate Acquisition Process
![Page 31: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/31.jpg)
Real Estate Acquisition Existing r/w – 0.5 acre Permanent r/w – 1 acre Drive Access
Remain open during construction with possible temporary closure
![Page 32: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/32.jpg)
Permanent Right of Way
![Page 33: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/33.jpg)
Real Estate Acquisition Process
"Uniform Act of 1970" All federal, state, and local governments must
comply Requires an offer for just compensation
Acquisition Process Appraisals Review Appraisals Negotiations
![Page 34: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/34.jpg)
Project Schedule
Public Hearing – June 2013 Environmental Document Finalized: Summer 2013 Preliminary Design Plan refinement: Summer 2013 Real Estate Acquisition Activities: 2013 - 2014
Appraising Negotiations / Buying Utilities coordination
Project Let for bidding: 2014 Construction: 2014 - 2015
![Page 35: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/35.jpg)
INDOT would like to hear from you Talk with INDOT project team members Comment sheet in information packet E-mail or Mail comments to INDOT Sign-in sheet to be added to project mailing list Visit INDOT website at www.in.gov/indot/2366.htm
“Public Involvement” page Visit INDOT Seymour District Page:
http://www.in.gov/indot/2706.htm All comments are very much appreciated and will be
given full consideration by project team
![Page 36: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/36.jpg)
Public Involvement Team
Rickie Clark, INDOT Office of Public Involvement (317) 232-6601 [email protected]
Glenda Seal, INDOT Seymour District Customer Service Center Director (877) 305-7611 [email protected]
![Page 37: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/37.jpg)
Submit Public Comments
Submit public comments using the options described in 1st page of information packet
Public Comment Form Via e-mail Participating during public comment session via microphone Verbal comments recorded and transcribed for inclusion into to public
hearings transcript INDOT respectfully requests comments be submitted by
Friday July 12, 2013 All comments submitted will become part of public record,
entered into transcript, reviewed, evaluated and given full consideration during decision making process
![Page 38: U.S. 50 Bridge Replacement over Tanner Creek Tuesday, June 25, 2013 5:30 p.m. Presentation Lawrenceburg Fire Department Lawrenceburg, Indiana](https://reader035.fdocuments.net/reader035/viewer/2022070500/568168ba550346895ddfa5d2/html5/thumbnails/38.jpg)
THANK YOU
Please visit with INDOT project officials following the public comment session
Project Open House Project maps, displays, real estate acquisition
table, INDOT project officials, informal Q & A Thank you for your attendance this evening