URA Review – May 8, 2006 1
US CMS – RP, FNALUS CMS – RP, FNALUS CMS – RP, FNALUS CMS – RP, FNAL
CMS Research Program (FNAL)
Dan Green
US CMS RPM
May 8, 2006
URA Review – May 8, 2006 2
OutlineOutlineOutlineOutline
• LHC Science – EPP2010• Status of CMS Construction – CD4-A, 97% complete
• Magnet• HCAL• ME
• Construction- CD4-B, • SiTrkr• FPix
• Physics Preparation• Computing TDR• Physics TDR• Research Program
• US CMS Collaboration@ FNAL• LPC• ROC/LHC@FNAL• CMS Dept.
URA Review – May 8, 2006 3
LHC w.r.t. EPP2010LHC w.r.t. EPP2010LHC w.r.t. EPP2010LHC w.r.t. EPP2010
URA Review – May 8, 2006 4
CMS MagnetCMS MagnetCMS MagnetCMS Magnet
Cold. Inserted HCAL in April.
Field map and quench studies in summer, 2006.
URA Review – May 8, 2006 5
HCAL Installation ProgressHCAL Installation ProgressHCAL Installation ProgressHCAL Installation Progress
An initial set of calibration constants for all HCAL – HB, HE, HF exists based on test beams in 2004 and radioactive sources to carry over energy taken in 2005. Good to ~ 5%. Check in test beam in 2006 (with ECAL). Expect ~ 15% “brightening” in 4T magnet – to be tested and tracked.
URA Review – May 8, 2006 6
HCAL - ForwardHCAL - ForwardHCAL - ForwardHCAL - Forward
Staged in bldg #186. Calibration is ~ ½ complete. Plan to finish and move to SX5 for July installation in UX
URA Review – May 8, 2006 7
““Slice Tests” – HCAL muonsSlice Tests” – HCAL muons““Slice Tests” – HCAL muonsSlice Tests” – HCAL muons
URA Review – May 8, 2006 8
ME ProgressME ProgressME ProgressME Progress
•YE+ endcap installation finished -- 196 chambers
•YE- endcap finished except for ME-1/3 chambers (36)
•Chamber installation 91% finished
•Cabling now 80% finished
•TMBs starting to be delivered
•Slice test starting on YE+1
URA Review – May 8, 2006 9
• 9 ME2 + 9 ME3 chambers available (600 sector)
• Services in place: LV, gas, and HV
• 9 production TMBs and Peripheral Backplane
• ME+2 station
• Production TMBs arriving at CERN in February.
27
1432
16
ME2
27
32
16
ME3
ME+2ME+3
ME - Slice Test SetupME - Slice Test SetupME - Slice Test SetupME - Slice Test Setup
URA Review – May 8, 2006 10
HCALHCAL
ECALECAL RCTRCT GCTGCT GT/GMTGT/
GMTTTCTTC DTTFDTTF
CSCTFCSCTF
Central Integration RacksCentral Integration RacksCentral Integration RacksCentral Integration RacksMitigation – buy schedule using #904.
Test Trigger, DAQ.
DAQ segment is in SX5 with cosmic ray muon data logging.
URA Review – May 8, 2006 11
TOB - Rod Insertion, Cabling & TOB - Rod Insertion, Cabling & Testing at CERNTesting at CERN
TOB - Rod Insertion, Cabling & TOB - Rod Insertion, Cabling & Testing at CERNTesting at CERN
SiTrkr module production is complete. Will finish rod production at FNAL and UCSB by the end of summer. Installation is ongoing in the Tracker Integration Facility. Plan for 25% “slice” test in TIF before UX installation at end of CY06.
URA Review – May 8, 2006 12
FPix (baseline):
US delivers:
4 ‘disks’
TBM (for CMS Pixels)
• Mechanical support and cooling
• Pixel Sensors
• Assembled pixel detectors
• The required electronics (adapter board, port card) except the: ROC, FEC, FED and OL
½-Disks:12 Blades
Blade:2 Panels
HDI, TBM
Plaquette:Sensors,
ROC, VHDI(picture
later)
Pigtail:Panels to
Adapter BoardFan-in/Fan-out
Extension Cable
Port Card: AOH (2),DOH, ALT, Gate Keeper,
TPLL, DCU
FEC
FED
CMS DAQ
½-ServiceCylinder
O-fibers
Power,Cooling
Full Size Model.
FPIX StatusFPIX StatusFPIX StatusFPIX Status
URA Review – May 8, 2006 13
Jan Jul Jan Jul Jan Jul Jan Jul Jan Jul Jan
ConstructDetector
Assemble detecor
Commission at SIDET
Commission atCERN
Install in IP
Commission/Beam
Operate Exp
Construct '07 det
Commission in SIDET
Commission in CERN
Install at CERNoperate
2008 20092004 2005 2006 2007
Construction M&O
OperationalSpares
MainDetector
’07 Detector
Calendar Year
Schedule: From Construction to Schedule: From Construction to M&OM&O
Schedule: From Construction to Schedule: From Construction to M&OM&O
Schedule for FPIX has completion of installation and switch to M&O in first ¼ of CY08. There is schedule float for CD4-B. All parts are just now in place and construction can begin. Detector Construction for FY06 is ~ 3.5 M$ at FNAL (direct) – used to complete SiTrkr and FPIX. There are ~ 28 FTE in FY06.
URA Review – May 8, 2006 14
Computing TDR CompletedComputing TDR CompletedComputing TDR CompletedComputing TDR Completed
The Computing TDR represents the new paradigm after the problems with DC04.
It is the blueprint for future progress.
URA Review – May 8, 2006 15
CPT OrganizationCPT OrganizationCPT OrganizationCPT Organization
HLT/DQME. Meschi
ReconstructionT. Boccali
Analysis ToolsL. Lista
SimulationM.Stavrianakou
D.Elvira
Calibr/alignmentO. Buchmuller
L. Malgeri
FrameworkL. Sexton
SoftwareL. Silvestris
A. Yagil
Integration Program
I. Fisk/S.Belforte
Facilities and Infrastructure
N. Sinanis
Operations ProgramL. Barone
Technical Program
P.Elmer/S.Lacaprara
ComputingL. Bauerdick
S. Belforte
Project ManagerP.Sphicas
Project OfficeV.Innocente
L.Taylor
Fast SimulationP. Janot
ECAL/e-C. Seez
Y. Sirois
TRACKER/b-I.TomalinF. Palla
HCAL/JetMETJ.RohlfC.Tully
MuonsN. Neumeister
U.Gasparini
PRSD. Acosta
A. Deroeck
Online SelectionS. Dasu
C. Leonidopoulos
HiggsS. Nikitenko
SUSY & BSML. Pape
M. Spiropulu
Standard ModelJ. Mnich
Heavy IonsB. Wyslouch
Generator ToolsF. Moortgat
S. Slabospitsky
ORCA for PTDRW. Adam
SW Devel ToolsS. Argiro
GeometryM. Case
URA Review – May 8, 2006 16
Computing ModelComputing ModelComputing ModelComputing Model
CMS CAF must be constructed. T1 resources pledged to CMS not sufficient for CMS requirements. Also requirements themselves are 2x below those of ATLAS. Much work remains.
URA Review – May 8, 2006 17
Physics TDR Volume 1Physics TDR Volume 1Physics TDR Volume 1Physics TDR Volume 1
Volume I concerns detector performance and models. These items are crucial to predicting Physics performance of the CMS detector.
URA Review – May 8, 2006 18
FY06 – M&O in RPFY06 – M&O in RPFY06 – M&O in RPFY06 – M&O in RP
Commitment Profile
-2
0
2
4
6
8
10
12
14
16
18
FY02 FY03 FY04 FY05 FY06 FY07 FY08
AY
$M
EMU
HCAL
Trigger
DAQ
ECAL
FPix
SiTrk
Com Ops
Prg Mgt
Upg R&D
M&O Mgt Rsv
For FY06 M&O costs are ~ 14 M$. Of that ~ 4.2 M$ goes to university groups, while ~ 9.8 M$ goes to FNAL ( Cat A – PO – LPC - ROC ) - burdened
URA Review – May 8, 2006 19
FY06 - S&C in the RPFY06 - S&C in the RPFY06 - S&C in the RPFY06 - S&C in the RP
FY06 S&C costs are ~ 15 M$. Of that 10.5 M$ goes to FNAL (T1 – LPC CAF – CP), while 3.5 M$ goes to university groups ( 7 T2 centers) - burdened
URA Review – May 8, 2006 20
US CMS DemographicsUS CMS DemographicsUS CMS DemographicsUS CMS Demographics
Expect to grow to ~ 500 FTE physicists at ~ 49 institutions by first beam to CMS. March CMS Week – Rockefeller + Puerto Rico.
URA Review – May 8, 2006 21
Demographic Split of US CMSDemographic Split of US CMSDemographic Split of US CMSDemographic Split of US CMS
CMS Head Count, F+PD, 387 TotalBoston Univ., BostonBrown Univ., ProvidenceUC Davis, DavisUCLA, Los AngelesUC Riverside, RiversideUC San Diego, La J olla
UC Santa Barbara, Santa BarbaraCalifornia Inst. of Tech., PasadenaCarnegie Mellon Univ., PittsburghUniversity of Colorado at Boulder, BoulderCornell University, IthacaFairfield Univ., FairfieldFermi National Accelerator Lab., BataviaUniv. of Florida, GainesvilleFlorida International University, M iamiFlorida State Univ., TallahasseeFlorida Inst. of Tech., MelbourneUniv. of Illinois at Chicago, Chicago
The Univ. of Iowa, Iowa CityIowa State Univ., AmesJ ohns Hopkins Univ., BaltimoreThe Univ. Of Kansas, LawrenceKansas State Univ., ManhattanLLNL, LivermoreUniv. of Maryland, College ParkMassachusetts Inst. of Tech., CambridgeUniv. of M innesota, M inneapolisUniv. of M ississippi, UniversityUniv. of Nebraska-Lincoln, LincolnState Univ. of New York, Buffalo
Northeastern Univ., BostonNorthwestern Univ., EvanstonUniv. of Notre Dame, Notre DameThe Ohio State Univ., ColumbusPrinceton Univ., PrincetonPurdue Univ., West LafayettePurdue Univ. Calumet, HammondRice Univ., HoustonUniv. of Rochester, RochesterRutgers University, PiscatawayTexas A&M Univ., College StationTexas Tech Univ., Lubbock
Vanderbilt University, NashvilleUniversity of Virginia, CharlottesvilleVirginia Polytech. Inst. and State Univ., BlacksburgUniv. of Wisconsin, MadisonYale University, New Haven
URA Review – May 8, 2006 22
FY06 – Core SupportFY06 – Core SupportFY06 – Core SupportFY06 – Core Support
DOE+NSF "Supplementary", 600 k$+111k$
EMU
HCAL
Trig
DAQ
ECAL
Fpix
SiTrk
SWC
PRS/
Each FY, US CMS performs a bottoms up assessment of needs in the core program. The L2 managers set priorities, while the overall priority is defined by the RP management.
URA Review – May 8, 2006 23
FNAL Activities in CMSFNAL Activities in CMSFNAL Activities in CMSFNAL Activities in CMS
URA Review – May 8, 2006 24
LPC at FermilabLPC at FermilabLPC at FermilabLPC at Fermilab
Appears to be successful. WH11 filled and moving onto WH10 and WH1. Note unique open areas for Physics discussions.
URA Review – May 8, 2006 25
LPC WebsiteLPC WebsiteLPC WebsiteLPC Website
Growth continues. WH11 ~ full. Expanding to WH10E
URA Review – May 8, 2006 26
ROC at FermilabROC at FermilabROC at FermilabROC at Fermilab
ROC to provide facilities for Data Quality Monitoring remotely. Improves effectiveness of remote experts and benefit from time difference (night shift). Have achieved good FNAL support. ROC will move to WH1 as a visible symbol of the FNAL commitment to CMS.
URA Review – May 8, 2006 27
WH1E – LHC @ FNALWH1E – LHC @ FNALWH1E – LHC @ FNALWH1E – LHC @ FNAL
First phase has begun. By end of FY06 have the control room and a teleconference center. Office space for shifters and data quality monitoring will come later.
URA Review – May 8, 2006 28
CMS @ FNAL - Dept. in PPDCMS @ FNAL - Dept. in PPDCMS @ FNAL - Dept. in PPDCMS @ FNAL - Dept. in PPD
E892 at FNAL. Core Program budget in PPD is:
210 k$ M&S for M&O
175 k$ G&V
26 k$ SLHC R&D
88 k$ LPC Support (bulk comes from M&O)
------------------------------
~500 k$ in M&S (large travel component)
CMS Dept. in PPD has 43 FTE
FNAL Physicists – 46 on M&O A. For TDR 96 FNAL names – Phys+CP+Eng
SWF is ~ 4 M$ for core support (physicists)
M&O is ~ 8.3 M$ (direct), 7.0 M$ in M&S ( Category A costs, HCAL ) with 1.3 M$ in SWF (RP Project Office, 8 FTE)
URA Review – May 8, 2006 29
CMS @ FNAL – Dept. in CDCMS @ FNAL – Dept. in CDCMS @ FNAL – Dept. in CDCMS @ FNAL – Dept. in CD
S&C in FY06 is costed at 8.8 M$ (direct). Of that 5.3 M$ is in M&S (T1 and LPC CAF), while 3.5 M$ is in SWF (T1 + LPC Ops). There are ~ 30 FTE working on S&C in CD for FY06.
There are 8 FTE in the CD CMS Dept. , with 90 k$ of M&S core support.
URA Review – May 8, 2006 30
WH10E ProposalWH10E ProposalWH10E ProposalWH10E Proposal
LPC is overflowing – especially in the summer. Add slots for LPC. Also, with ROC move, more offices freed up on WH11. Must also accommodate the large “silicon” community arising from Run II + BTeV physicists.
URA Review – May 8, 2006 31
SummarySummarySummarySummary
• Construction is ~ on schedule – 97% complete at end of FY05.
• CD4-B – SiTrkr is ballistic. FPIX finally has parts in hand.
• Computing TDR and Physics TDR are done. RP is now the central management instrument of US CMS.
• US CMS continues to grow. FNAL is the largest group.
• LPC is forging ahead• ROC is analyzing cosmic ray data. LHC@FNAL will soon
be complete (end FY06).• PPD and CD CMS Dept. hosts the Project/Program office
and supports FNAL physicists working on CMS.