URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May...

31
URA Review – May 8, 2006 1 US CMS – RP, FNAL US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006

Transcript of URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May...

Page 1: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 1

US CMS – RP, FNALUS CMS – RP, FNALUS CMS – RP, FNALUS CMS – RP, FNAL

CMS Research Program (FNAL)

Dan Green

US CMS RPM

May 8, 2006

Page 2: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 2

OutlineOutlineOutlineOutline

• LHC Science – EPP2010• Status of CMS Construction – CD4-A, 97% complete

• Magnet• HCAL• ME

• Construction- CD4-B, • SiTrkr• FPix

• Physics Preparation• Computing TDR• Physics TDR• Research Program

• US CMS Collaboration@ FNAL• LPC• ROC/LHC@FNAL• CMS Dept.

Page 3: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 3

LHC w.r.t. EPP2010LHC w.r.t. EPP2010LHC w.r.t. EPP2010LHC w.r.t. EPP2010

Page 4: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 4

CMS MagnetCMS MagnetCMS MagnetCMS Magnet

Cold. Inserted HCAL in April.

Field map and quench studies in summer, 2006.

Page 5: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 5

HCAL Installation ProgressHCAL Installation ProgressHCAL Installation ProgressHCAL Installation Progress

An initial set of calibration constants for all HCAL – HB, HE, HF exists based on test beams in 2004 and radioactive sources to carry over energy taken in 2005. Good to ~ 5%. Check in test beam in 2006 (with ECAL). Expect ~ 15% “brightening” in 4T magnet – to be tested and tracked.

Page 6: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 6

HCAL - ForwardHCAL - ForwardHCAL - ForwardHCAL - Forward

Staged in bldg #186. Calibration is ~ ½ complete. Plan to finish and move to SX5 for July installation in UX

Page 7: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 7

““Slice Tests” – HCAL muonsSlice Tests” – HCAL muons““Slice Tests” – HCAL muonsSlice Tests” – HCAL muons

Page 8: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 8

ME ProgressME ProgressME ProgressME Progress

•YE+ endcap installation finished -- 196 chambers

•YE- endcap finished except for ME-1/3 chambers (36)

•Chamber installation 91% finished

•Cabling now 80% finished

•TMBs starting to be delivered

•Slice test starting on YE+1

Page 9: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 9

• 9 ME2 + 9 ME3 chambers available (600 sector)

• Services in place: LV, gas, and HV

• 9 production TMBs and Peripheral Backplane

• ME+2 station

• Production TMBs arriving at CERN in February.

27

1432

16

ME2

27

32

16

ME3

ME+2ME+3

ME - Slice Test SetupME - Slice Test SetupME - Slice Test SetupME - Slice Test Setup

Page 10: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 10

HCALHCAL

ECALECAL RCTRCT GCTGCT GT/GMTGT/

GMTTTCTTC DTTFDTTF

CSCTFCSCTF

Central Integration RacksCentral Integration RacksCentral Integration RacksCentral Integration RacksMitigation – buy schedule using #904.

Test Trigger, DAQ.

DAQ segment is in SX5 with cosmic ray muon data logging.

Page 11: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 11

TOB - Rod Insertion, Cabling & TOB - Rod Insertion, Cabling & Testing at CERNTesting at CERN

TOB - Rod Insertion, Cabling & TOB - Rod Insertion, Cabling & Testing at CERNTesting at CERN

SiTrkr module production is complete. Will finish rod production at FNAL and UCSB by the end of summer. Installation is ongoing in the Tracker Integration Facility. Plan for 25% “slice” test in TIF before UX installation at end of CY06.

Page 12: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 12

FPix (baseline):

US delivers:

4 ‘disks’

TBM (for CMS Pixels)

• Mechanical support and cooling

• Pixel Sensors

• Assembled pixel detectors

• The required electronics (adapter board, port card) except the: ROC, FEC, FED and OL

½-Disks:12 Blades

Blade:2 Panels

HDI, TBM

Plaquette:Sensors,

ROC, VHDI(picture

later)

Pigtail:Panels to

Adapter BoardFan-in/Fan-out

Extension Cable

Port Card: AOH (2),DOH, ALT, Gate Keeper,

TPLL, DCU

FEC

FED

CMS DAQ

½-ServiceCylinder

O-fibers

Power,Cooling

Full Size Model.

FPIX StatusFPIX StatusFPIX StatusFPIX Status

Page 13: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 13

Jan Jul Jan Jul Jan Jul Jan Jul Jan Jul Jan

ConstructDetector

Assemble detecor

Commission at SIDET

Commission atCERN

Install in IP

Commission/Beam

Operate Exp

Construct '07 det

Commission in SIDET

Commission in CERN

Install at CERNoperate

2008 20092004 2005 2006 2007

Construction M&O

OperationalSpares

MainDetector

’07 Detector

Calendar Year

Schedule: From Construction to Schedule: From Construction to M&OM&O

Schedule: From Construction to Schedule: From Construction to M&OM&O

Schedule for FPIX has completion of installation and switch to M&O in first ¼ of CY08. There is schedule float for CD4-B. All parts are just now in place and construction can begin. Detector Construction for FY06 is ~ 3.5 M$ at FNAL (direct) – used to complete SiTrkr and FPIX. There are ~ 28 FTE in FY06.

Page 14: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 14

Computing TDR CompletedComputing TDR CompletedComputing TDR CompletedComputing TDR Completed

The Computing TDR represents the new paradigm after the problems with DC04.

It is the blueprint for future progress.

Page 15: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 15

CPT OrganizationCPT OrganizationCPT OrganizationCPT Organization

HLT/DQME. Meschi

ReconstructionT. Boccali

Analysis ToolsL. Lista

SimulationM.Stavrianakou

D.Elvira

Calibr/alignmentO. Buchmuller

L. Malgeri

FrameworkL. Sexton

SoftwareL. Silvestris

A. Yagil

Integration Program

I. Fisk/S.Belforte

Facilities and Infrastructure

N. Sinanis

Operations ProgramL. Barone

Technical Program

P.Elmer/S.Lacaprara

ComputingL. Bauerdick

S. Belforte

Project ManagerP.Sphicas

Project OfficeV.Innocente

L.Taylor

Fast SimulationP. Janot

ECAL/e-C. Seez

Y. Sirois

TRACKER/b-I.TomalinF. Palla

HCAL/JetMETJ.RohlfC.Tully

MuonsN. Neumeister

U.Gasparini

PRSD. Acosta

A. Deroeck

Online SelectionS. Dasu

C. Leonidopoulos

HiggsS. Nikitenko

SUSY & BSML. Pape

M. Spiropulu

Standard ModelJ. Mnich

Heavy IonsB. Wyslouch

Generator ToolsF. Moortgat

S. Slabospitsky

ORCA for PTDRW. Adam

SW Devel ToolsS. Argiro

GeometryM. Case

Page 16: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 16

Computing ModelComputing ModelComputing ModelComputing Model

CMS CAF must be constructed. T1 resources pledged to CMS not sufficient for CMS requirements. Also requirements themselves are 2x below those of ATLAS. Much work remains.

Page 17: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 17

Physics TDR Volume 1Physics TDR Volume 1Physics TDR Volume 1Physics TDR Volume 1

Volume I concerns detector performance and models. These items are crucial to predicting Physics performance of the CMS detector.

Page 18: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 18

FY06 – M&O in RPFY06 – M&O in RPFY06 – M&O in RPFY06 – M&O in RP

Commitment Profile

-2

0

2

4

6

8

10

12

14

16

18

FY02 FY03 FY04 FY05 FY06 FY07 FY08

AY

$M

EMU

HCAL

Trigger

DAQ

ECAL

FPix

SiTrk

Com Ops

Prg Mgt

Upg R&D

M&O Mgt Rsv

For FY06 M&O costs are ~ 14 M$. Of that ~ 4.2 M$ goes to university groups, while ~ 9.8 M$ goes to FNAL ( Cat A – PO – LPC - ROC ) - burdened

Page 19: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 19

FY06 - S&C in the RPFY06 - S&C in the RPFY06 - S&C in the RPFY06 - S&C in the RP

FY06 S&C costs are ~ 15 M$. Of that 10.5 M$ goes to FNAL (T1 – LPC CAF – CP), while 3.5 M$ goes to university groups ( 7 T2 centers) - burdened

Page 20: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 20

US CMS DemographicsUS CMS DemographicsUS CMS DemographicsUS CMS Demographics

Expect to grow to ~ 500 FTE physicists at ~ 49 institutions by first beam to CMS. March CMS Week – Rockefeller + Puerto Rico.

Page 21: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 21

Demographic Split of US CMSDemographic Split of US CMSDemographic Split of US CMSDemographic Split of US CMS

CMS Head Count, F+PD, 387 TotalBoston Univ., BostonBrown Univ., ProvidenceUC Davis, DavisUCLA, Los AngelesUC Riverside, RiversideUC San Diego, La J olla

UC Santa Barbara, Santa BarbaraCalifornia Inst. of Tech., PasadenaCarnegie Mellon Univ., PittsburghUniversity of Colorado at Boulder, BoulderCornell University, IthacaFairfield Univ., FairfieldFermi National Accelerator Lab., BataviaUniv. of Florida, GainesvilleFlorida International University, M iamiFlorida State Univ., TallahasseeFlorida Inst. of Tech., MelbourneUniv. of Illinois at Chicago, Chicago

The Univ. of Iowa, Iowa CityIowa State Univ., AmesJ ohns Hopkins Univ., BaltimoreThe Univ. Of Kansas, LawrenceKansas State Univ., ManhattanLLNL, LivermoreUniv. of Maryland, College ParkMassachusetts Inst. of Tech., CambridgeUniv. of M innesota, M inneapolisUniv. of M ississippi, UniversityUniv. of Nebraska-Lincoln, LincolnState Univ. of New York, Buffalo

Northeastern Univ., BostonNorthwestern Univ., EvanstonUniv. of Notre Dame, Notre DameThe Ohio State Univ., ColumbusPrinceton Univ., PrincetonPurdue Univ., West LafayettePurdue Univ. Calumet, HammondRice Univ., HoustonUniv. of Rochester, RochesterRutgers University, PiscatawayTexas A&M Univ., College StationTexas Tech Univ., Lubbock

Vanderbilt University, NashvilleUniversity of Virginia, CharlottesvilleVirginia Polytech. Inst. and State Univ., BlacksburgUniv. of Wisconsin, MadisonYale University, New Haven

Page 22: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 22

FY06 – Core SupportFY06 – Core SupportFY06 – Core SupportFY06 – Core Support

DOE+NSF "Supplementary", 600 k$+111k$

EMU

HCAL

Trig

DAQ

ECAL

Fpix

SiTrk

SWC

PRS/

Each FY, US CMS performs a bottoms up assessment of needs in the core program. The L2 managers set priorities, while the overall priority is defined by the RP management.

Page 23: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 23

FNAL Activities in CMSFNAL Activities in CMSFNAL Activities in CMSFNAL Activities in CMS

Page 24: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 24

LPC at FermilabLPC at FermilabLPC at FermilabLPC at Fermilab

Appears to be successful. WH11 filled and moving onto WH10 and WH1. Note unique open areas for Physics discussions.

Page 25: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 25

LPC WebsiteLPC WebsiteLPC WebsiteLPC Website

Growth continues. WH11 ~ full. Expanding to WH10E

Page 26: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 26

ROC at FermilabROC at FermilabROC at FermilabROC at Fermilab

ROC to provide facilities for Data Quality Monitoring remotely. Improves effectiveness of remote experts and benefit from time difference (night shift). Have achieved good FNAL support. ROC will move to WH1 as a visible symbol of the FNAL commitment to CMS.

Page 27: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 27

WH1E – LHC @ FNALWH1E – LHC @ FNALWH1E – LHC @ FNALWH1E – LHC @ FNAL

First phase has begun. By end of FY06 have the control room and a teleconference center. Office space for shifters and data quality monitoring will come later.

Page 28: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 28

CMS @ FNAL - Dept. in PPDCMS @ FNAL - Dept. in PPDCMS @ FNAL - Dept. in PPDCMS @ FNAL - Dept. in PPD

E892 at FNAL. Core Program budget in PPD is:

210 k$ M&S for M&O

175 k$ G&V

26 k$ SLHC R&D

88 k$ LPC Support (bulk comes from M&O)

------------------------------

~500 k$ in M&S (large travel component)

CMS Dept. in PPD has 43 FTE

FNAL Physicists – 46 on M&O A. For TDR 96 FNAL names – Phys+CP+Eng

SWF is ~ 4 M$ for core support (physicists)

M&O is ~ 8.3 M$ (direct), 7.0 M$ in M&S ( Category A costs, HCAL ) with 1.3 M$ in SWF (RP Project Office, 8 FTE)

Page 29: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 29

CMS @ FNAL – Dept. in CDCMS @ FNAL – Dept. in CDCMS @ FNAL – Dept. in CDCMS @ FNAL – Dept. in CD

S&C in FY06 is costed at 8.8 M$ (direct). Of that 5.3 M$ is in M&S (T1 and LPC CAF), while 3.5 M$ is in SWF (T1 + LPC Ops). There are ~ 30 FTE working on S&C in CD for FY06.

There are 8 FTE in the CD CMS Dept. , with 90 k$ of M&S core support.

Page 30: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 30

WH10E ProposalWH10E ProposalWH10E ProposalWH10E Proposal

LPC is overflowing – especially in the summer. Add slots for LPC. Also, with ROC move, more offices freed up on WH11. Must also accommodate the large “silicon” community arising from Run II + BTeV physicists.

Page 31: URA Review – May 8, 20061 US CMS – RP, FNAL CMS Research Program (FNAL) Dan Green US CMS RPM May 8, 2006.

URA Review – May 8, 2006 31

SummarySummarySummarySummary

• Construction is ~ on schedule – 97% complete at end of FY05.

• CD4-B – SiTrkr is ballistic. FPIX finally has parts in hand.

• Computing TDR and Physics TDR are done. RP is now the central management instrument of US CMS.

• US CMS continues to grow. FNAL is the largest group.

• LPC is forging ahead• ROC is analyzing cosmic ray data. LHC@FNAL will soon

be complete (end FY06).• PPD and CD CMS Dept. hosts the Project/Program office

and supports FNAL physicists working on CMS.