Erwin Siesling BE-OP-ISO
87th ISCC meeting 20 Feb 2020, CERN
Update on the Low Energy part, REX and HIE ISOLDE
Plans for 2020 Beam Commissioning & Machine Studies
Outline
• Status report- Low Energy part
- REX / HIE ISOLDE
• Early start-up schedule and planning
• Hardware, Beam commissioning & Machine
studies- Low Energy part
- REX/HIE ISOLDE
• ISOLDE 3D integration
• Conclusions
Status ISOLDE Low Energy
3
HT modulators:
- High Precision 60kV power
supplies, Target Modulators
& HT fast recovery systems
installed on HT 1 & 2
- FESA3 compliant control
system deployed
- On site test load and HT
calibration tools installed
- Ready for commissioning at
start-up in 2020 and 2021
with protons
GLM & GHM area:
- Refurbishment to comply to
modern legislation for the
manipulation of open
sources
- Ready for RIBs in 2021
- Addressed in Karl’s talk
Cooling & Ventilation:
- Maintenance on the
different cooling water and
ventilation systems
finishing: All cooling water
back end February 2020
New fast Tape-Station:
- Installed in the CAO
beamline
- FESA classes done
- Application to be (re)written
- Operational at start-up in
2020
Beam Instrumentation
consolidation and upgrades
Low E beamlines:
- New scanners and FCs at
all Low E beamlines as well
as new separator area
scanners and spares
- Installation ongoing, Low E
beamlines done, Separator
zone to be done.
Operational at start-up in
2020
All Low E LS2 tasks are on track
Bottleneck for beam commissioning the readiness of FE10 and
vacuum maintenance on the primary oil pumps (May, possibly April)
Vacuum maintenance:
- All TPs done. Leak test to
be performed
- Separators and Target
area oil pumps: oil change
and consolidation in May
(LS2 availability) (possibly
April)
Beam Instrumentation consolidation and upgrades
William Andreazza, Michel Duraffourg, Paulo Martins. BE-BI team
Status REX & HIE ISOLDE
SEC
ISS
Miniball
5
Cooling & Ventilation:
- HIE ISOLDE CV building
199 modification finished.
Beneficial for both the 199
cryo plant as well as the
508 user labs
- 508 CV/airco upgrade
finished and labs are up to
user specs
- All cooling water back end
February 2020
All REX / HIE ISOLDE LS2 tasks are on track
Minor delay for cryo end-of-cooldown date (1wk)
REX TRAP & EBIS:
- TRAP maintenance and
electrodes repair done. To
be tested 2020
- TRAP ion source working
- TRAP RF hardware
replaced – to be tested
- EBIS new electron gun
under fabrication. To be
ready for tests 2020
REX NC LINAC:
- REX RF consolidation and
maintenance done. First RF
tests carried out. Ready for
2020 re-commissioning
- 7 Gap water hoses to be
replaced
- IHS water hoses to be
replaced (still in LS2?)
- BI: 3 additional HIE ISOLDE
type Diagnostic Boxes
assembled and vacuum
tested. Installation mid-
March, operational for 2020
- REX vacuum maintenance
finished. Ready for 2020 re-
commissioning
Three new diagnostic
boxes and steerers
New EBIS electron gun
CM4 repaired
HIE SC LINAC:
- HIE ISOLDE Cryo plant
maintenance done. Ready
for re-commissioning and
cooldown in 2020 (18th May)
- CM4 re-installed
- Intertank sectors reinstalled
and vacuum connections
done
- CM4 infrastructure and cryo
connections ongoing
- Re-commissioning CM1-4
with stable beam from EBIS
foreseen as of July 2020
Miniball
Additional silicon detectors:
- Installation March 2020
6
Courtesy Candy Capelli EN-MME, Nicolas Chritin EN-MME,
Simon Mataguez BE-OP, William Andreazza BE-BI, Jose
Ferreira Somoza TE-VSC
REX 3 new diagnostic boxes + additional steererDboxes assembled and vacuum tested, installation mid-March. Infrastructure and supports are adapted.
Transport Cryo Module 4 from SM18 back to ISOLDE:
21st January 2020
HIE ISOLDE installation work: CM4, intertank sectors
& infrastructure
Tuner plate stepping motors
RF patch panels
XLN6 intertank
BCAM alignment system
Many thanks to all the groups
involved for keeping the
schedule with the heavy LS2
load
Points of attention:
Cryo:
- An issue was found with the
Cryostat He release safety
valve which needs repair.
Installation later in parallel
with continuing activities
- All other CM Cryostat He
release safety valves will be
inspected
To do:
- Current leads and cooling
solenoids
- DC and BI connections
Intertank sectors XLN5 & 6
Cryostat He release safety valve
XLN5 intertank
CM4 vacuum infrastructure
CM4 instrumentation cabling
Outline
• Status report- Low Energy part
- REX / HIE ISOLDE
• Early start-up schedule and planning
• Hardware, Beam commissioning & Machine
studies- Low Energy part
- REX/HIE ISOLDE
• ISOLDE 3D integration
• Conclusions
Early start-up in 2020: As requested LS2 Schedule 2.4:
Early start-up 2020:
Approved by the CERN Research Board, LS2 Committee and IEFC
Low E Beam commissioning and development tests with stable beam as of end-Aug 2020
For Hardware commissioning we hope to have beam from FE10 (GPS) as of April (depending
on FE readiness and vacuum maintenance (primary pumps) (scheduled May, possibly April)
HIE-ISOLDE Beam commissioning and development tests with stable beam as of July 2020
Physics 2021:
Low E Physics start end April 2021
HIE-ISOLDE Physics start mid-May 2021
Gain:
~ 4 months HIE ISOLDE Physics, ~1 month Low Energy Physics
Better performing machine, better understanding of the machine
parameters resulting in higher quality beams and shorter set-up times
ISOLDE low energy
Physics start
HIE-ISOLDE
Physics start
Necessary main CERN electrical interventions, manoeuvres and safety tests planned in the first half of 2020
would cause serious perturbation for the HIE ISOLDE cryo plant
Mitigation:
AUG (Arret d’Urgence) tests weekend 23/24th May have been moved forward to weekend 16/17th May to
minimize the impact on HIE ISOLDE Cryo
Within the HIE ISOLDE Cryo cooldown process the critical period of sending cold gas and He into the
CMs will be postponed to 18th May to avoid any critical situation
Effect on the overall HIE ISOLDE planning will be a delay of 1 wk for the end-of-cooldown date (from 29th
May to 8th June). The delay will be absorbed in the planning since parts of the 2wks RF tests at cold take
place during the cooldown process
Back-up network tests set for the 26th May will be moved to Monday 25th May to accommodate LINAC4
commissioning
Planning issues:
+1 wk to 08/06/20
EN-EL interventions planning HIE ISOLDE installation and recommissioning planning
Outline
• Status report- Low Energy part
- REX / HIE ISOLDE
• Early start-up schedule and planning
• Hardware, Beam commissioning &
Machine studies- Low Energy part
- REX/HIE ISOLDE
• ISOLDE 3D integration
• Conclusions
Low Energy hardware & beam commissioning
13
Hardware commissioning (ISOLDE machine supervisor on duty as of March (weekdays, working hours):
Apart from the usual machine checkout and hardware tests:
New Front-Ends hardware commissioning
Functional verification of all HT electrostatic power supplies (CCV/AQN), the connections to the different
elements and the capacitance of the plates inside via the HT connector
Verification voltage ripple on the electrostatic power supplies
Test of all applications for operations
New diagnostic boxes: all new FCs and scanners hardware tests (applications, controls and movement)
New beam-gates hardware tests
New Fast Tapestation tests (with simulated proton timing)
Beam commissioning:
Beam characteristics from the new Front-Ends
Beam onto the new beam instrumentation: all new FCs and
scanners tests with stable beam (signals and applications)
New beam-gates tests with stable beam
Work on beam optics model: first for GPS separator and central
beamline followed by HRS separator and ISCOOL
Test beam to RCX line in preparation for MIRACLS (emittance,
transmission and optics) (ex-NICOLE line)
Bottleneck to avoid parallel Low E
and REX/HIE beam commissioning:
Start beam commissioning asap
Readiness of FE10 and vacuum
maintenance on the primary
pumps (separator areas and
target area. Foreseen May,
possibly April)
New Front-Ends
New beam
instrumentation
New beam-
gates controls
Beam Commissioning 2020:
J.A. Rodriguez, BE-OP-ISO
SEC / OTPCISS
Miniball Experimental stations:
Stable beams (wks. 37, 38, 45, 46)
Three new diagnostic
boxes and steerers
New electron gun
CM4
repaired
Additional
silicon detectors
New software or major upgrades:
Beam instrumentation applications suite (wks. 28-30, 34)
New slow extraction application (wk. 30)
Fast Beam Investigation tool (wks. 31, 32)
Beam optimizer for injection into experiments (wks. 37, 38)
Energy / energy spread application (wk. 31)
Automatic SRF phasing (wk. 33)
New or heavily refurbished hardware:
New steerers and diagnostic boxes: FCs, slits, attenuators, collimators and silicon detectors (wks. 28, 29, 30)
New electron gun in the REX-EBIS charge breeder (contaminant characterization: wks. 29, 31)
REX RF amplifiers (wks. 30-32)
Phasing of refurbished cryomodule 4 (CM4) (wk. 33)
Two additional silicon detectors (wk. 34)
Machine Studies 2020:
New REX
separator optics
J.A. Rodriguez, BE-OP-ISO
SEC / OTPCISS
Miniball
Stability REX RF
for low A/q beams
Bunch length stretching
Energy spread minimization
Beam size minimization
Preparation for potential future upgrades:
Alternative REX separator optics with beam waist
before RFQ (wk. 28)
Development of train extraction from the REX-EBIS
charge breeder (wks. 28, 38)
Bunch length stretching at secondary target (wk. 43)
Beam improvements requested by users of the facility:
Charge breeder slow extraction to 1.8 ms (wk. 30)
Feasibility study for low A/q beams. Stability of REX RF (wk. 36)
Energy spread minimization at secondary target (wk. 44)
Slit-based emittance reduction with limited beam losses (wk. 44)
Slow extraction (1.8 ms)
Train extraction
Machine development:
Energy and energy spread measurement in three HEBT lines (wk. 34)
Transverse and longitudinal phase space characterization and validation of optics models (wks. 35, 43)
Machine A/q scalability studies (wk. 41)
Development of beam-based energy gain measurement (wk. 42)
Outline
• Status report- Low Energy part
- REX / HIE ISOLDE
• Early start-up schedule and planning
• Hardware, Beam commissioning & Machine
studies- Low Energy part
- REX/HIE ISOLDE
• ISOLDE 3D integration
• Conclusions
Full ISOLDE 3D integration:
The Low Energy, REX/HIE ISOLDE post-accelerator, Target Area and all infrastructure
have now been merged into one 3D CATIA model.
The ISOLDE 3D CATIA model has been converted to 3DXML and is available in EDMS EDMS CERN-0000000088 to CERN-0000205967
EDMS 2324292 2020/02/04 ISOLDE INTEGRATION BEAM MACHINE & EXPERIMENTS
EDMS 2324319 2020/01/31 ST1234846_01 ISOLDE INTEGRATION BLDS 170 197 508
(Work by: Vincent Barozier EN-MME, Made available by: Simon Mataguez BE-OP, Miguel Lozano Benito BE-OP (CATIA course)
Visualisation and basic viewing:
You will need to load 3D XML:
https://www.3ds.com/fr/produits-et-
services/3d-xml/telechargements/
Visualisation and measurements:
You will need an access and
SmarTeam account (request by
Ticket) and load from CMF SpinFire
("read only")
18
Conclusions: All Low Energy and REX / HIE ISOLDE LS2 tasks are on track
Highlights since last ISCC:
New scanners and FC units have been installed in all Low E beamlines
Separator zones will follow. Operational for 2020. A new Semgrid target will be
built, ready for the 2021 proton beam
REX 3 new Diagnostic boxes have been assembled and vacuum tested.
Supports have been adapted. Ready for installation mid-March
HIE ISOLDE Cryo Module 4 is back in position after repair and tests in SM18
(Walter Venturini & BE-RF team). Reinstallation and connection of infrastructure
on schedule. Point of attention: Crystat He release safety valve(s): Under repair.
No effect on schedule to be expected.
Early start-up 2020 approved by CERN Research Board, IEFC and LS2C
Aiming for REX/HIE ISOLDE HW tests as of April, cooldown May 2020 followed
by Beam Commissioning and Test & Development run as of July 2020.
For the Low E part hoping for early HW tests as of April and Beam
Commissioning as soon as FE10 comes online and vacuum maintenance has
finished (due to LS2 load this is scheduled for May but possibly April to finish)
Well defined Hardware tests-, Beam Commissioning- and Machine Studies plan
by BE-OP