Outline• Status and plans for 2012 experiments
• Shifts and schedule• RILIS and REX operation• New experiments for post accelerated beams 2012
• HIE-ISOLDE status and plans• Reports and recommendations from the IAP• Cavity design and tests• Civil engineering and installation work LS1
• Foreseen activities for LS1• Target area activities• Modifications in the experimental hall• Other plans
![Page 3: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/3.jpg)
Injector schedule 2012
35 weeks of physics(vs 29 in 2010,2011)
Protons for ISOLDE restart in spring 2014
Guaranteed protons (46% requested):
(Possible increase at next research board)
![Page 4: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/4.jpg)
ISOLDE schedule 2012
Status today:9 IS experiments and 2 LOIs CLOSED this month79 IS experiments and 9 LOIs OPEN (711 + 30 requested shifts)+ 14 IS experiments and 5 LOIs SUBMITTED to this INTC (193 + 17 requested shifts)1059 remaining shifts for proposals and LOIs904 + 47 (LOIs) shifts requested so far (66 more might be still requested)
Reasonable number of shifts that can be scheduled in 2012: 590
![Page 5: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/5.jpg)
5
Beam Sm Ga Mg At Pb Dy Nd Pr Ag Tl Cd Mn Ni Yb ZnPlanned 80 104 256 160 184 64 136 - 112 208 288 120 272 - 376
Real 89 101 146 269 221 35 110 4 92 231 242 390 348 73 407
0
500
1000
1500
2000
2500
3000
Hou
rs
1994 1996 1998 2000 2002 2004 2006 2008 2010
Year
RILIS operation
2756 h – Total 2527 h – On-line
• > 50 % of the Total running time of ISOLDE facility197 (250) shifts in 2011~ 250 (300) planned for 2012
Laser ON timein 2011:
Ion beams of 15 elements were produced
![Page 6: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/6.jpg)
REX Operation
• Delivered shifts for experiments and LOIs in 2011:
– REX – 147 shifts (160 shifts scheduled)
• Similar plans for 2012: ~200 shifts to be scheduled
– Enable 2 ms RF pulse length on all amplifiers for slow extraction tests to be done in 2012– A few “difficult” light beams will require testing and further tuning
![Page 7: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/7.jpg)
New experimental setups using post-accelerated beamsRare decays of 6He
with an optical chamber
TriggerRecording
system
d
a
charge amplification zone GEM foils
e
E
ionizationelectrons
light
HV electrodes
gas at atmospheric pressureincoming
6He ions
gating electrode
CCD PMT
REX
![Page 8: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/8.jpg)
New experimental setups using post-accelerated beams
Scattering chamber for studies of nuclosynthesis
(rapid proton-capture)
Nuclear structure of very light nuclei with an active target
p
ΔE-E
Ec.m.
![Page 9: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/9.jpg)
Source of 44Ti:PSI
Core collapse supernovae
Ejected 44Ti becomes gamma emitter=> Sensitive diagnostic of explosion mechanism
Exotic radionuclides from accelerator waste for science and technology ~1018 atoms available
Offline experiment: Measure 44Ti(a,p) reaction at supernova energy
Extraction and acceleration:Material: Experiment:
![Page 10: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/10.jpg)
Outline• Status and plans for 2012 experiments
• Shifts and schedule• RILIS and REX operation• New experiments for post accelerated beams 2012
• HIE-ISOLDE status and plans• Reports and recommendations from the IAP• Cavity design and tests• Civil engineering and installation work LS1
• Foreseen activities for LS1• Target area activities• Modifications in the experimental hall• Other plans
![Page 11: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/11.jpg)
Highlights from the IAP report:Cryomodule Design
• The top loading design is a good choice with examples in ISAC-II, LNL, MSU and ANL.
• For the cryogenic safety the IAP has the impression that the numbers presented for the burst disk size to mitigate overpressure in the case of a venting accident are over conservative
• Concerns about the use of MLI => consider nickel plating of thermal shield and electro-polishing large surfaces (mirror-like) helium reservoir
• The cryomodule assembly sequence should be optimized to give adequate access to the cavities in case they have to be rinsed in the future
• The capability to helium condition the cavities by adding a leak system to the cryomodule should be analyzed at the cavity testing stage
• A 1400 W cryogenic plant should have sufficient margin.
![Page 12: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/12.jpg)
Highlights from the IAP reportRF Cavities
• Work on the cavity has made good progress and is on the right path although many cold tests are still necessary to get things settled
• It is almost certain that the very stringent specification on the inner conductor beam port is too tight by probably a factor of ten at least. It is suggested that cavity development should proceed with this as a fact while beam simulations are done in parallel to confirm.
• It is noted that one of the RF performance curves reaches the high field value 6 MV/m and has a very low Q-slope for a sputtered cavity but a Qo which is a factor of ten from the goal.
– evaluate influence of tuner plate
![Page 13: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/13.jpg)
Highlights from the IAP report:General
• Possible concerns are related to realities of funding which may cause complicated procurement strategies
• Synergies between ESS and HIE-ISOLDE should be explored with regard to the training of people
• The goal of having the 5.5 MeV/u linac commissioned in 2014 is tight but still possible => risk analysis by Sep. 2012
• Diagnostics look well thought out and conceptually well advanced for this stage of the project.
• Compare safety protocols with other operating facilities
• A finalization of the experimental layout is required
• The IAP suggests that attention must be given on the production of x-rays
• The IAP strongly support the addition of the storage ring to the ISOLDE infrastructure
![Page 14: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/14.jpg)
![Page 15: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/15.jpg)
RF Measurements @ 4.5K (2011)
0 1 2 3 4 5 6 71E+06
1E+07
1E+08
1E+09Q1 Mag Dec 2010-1st (150ºC) Q1 Mag Feb 2011-2nd (150ºC) Q1 Diode Jul 2011 (150ºC)
Q2 Mag Sept 2011 (150ºC) Q1 Mag Nov 2011 (370 ºC) Q2 Diode Dec 2011 ( 470ºC)
HIE-ISOLDE specification
Eacc(MV/m)
Qua
lity
Fact
or
![Page 16: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/16.jpg)
RF Measurements (2012)
0 1 2 3 4 5 6 7 81E+07
1E+08
1E+09
Q2_6 January 2012Q1_9 cal1Q1_9 cal2
Eacc (MV/m)
Qua
lity
fact
or
~ 70 W @ 6 MV/m
~ 35 W @ 6 MV/m
![Page 17: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/17.jpg)
Outlook for 2012
Completion of Civil Engineering Works by Q3 2012
Installation of Main Services (EL, CV, Transport)
Launch procurement of Cryogenic Plant (FC Mar. 2012)
Launch procurement of first batch of 5 (+5 option) high-beta cavities + ancillaries by Q1 2012.
Review Cryomodule Design (26-27 Apr. 2012) and launch procurement of CM1 by Q2 2012.
Review HEBT Layout (25 Apr. 2012) and launch procurement
Validate LLRF system and tuner plate design
![Page 18: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/18.jpg)
18
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
2011 2012 2013 2014 2015 2016
Civil
Main servicesCryo
CM 1&2 CM 3&45.5MeV/u
10MeV/u
Beam Transfer Lines
CM 5&6
Hie-Isolde Planning
A simplified presentation of the different stages:
-What is the impact on operations?Dec 2012 - Apr 2014
sd sd sdCM1&2
Isolde & REX Ops shutdown
LS1
Cryo Mod 1 & 2 install(Isolde normal operations)(REX perturbations)
Timeline:
sd
VentilationDemi waterElectrical syst.s
![Page 19: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/19.jpg)
Civil EngineeringNew SAS
January 2012
![Page 20: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/20.jpg)
Main ServicesElectrical systems, Cooling & Ventilation
Start installation main services July 2012
![Page 21: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/21.jpg)
Electrical systems
Electrical systems: July 2012 – June 2013
![Page 22: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/22.jpg)
Cooling & Ventilation
Cooling & Ventilation: July 2012 – June 2013
![Page 23: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/23.jpg)
23
Cryogenics
Compressors: July 2013 – December 2013
Cold Box: Jan 2014 – June 2014
![Page 24: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/24.jpg)
Tunnel and Cryo Line
Cutting walls & install tunnel: Sep 2013 LS1 Cryo Cold Line: January 2014 – June 2014
![Page 25: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/25.jpg)
Hie-Isolde SC Linac
First 10MeV/u by March 2016
Hie-Isolde SC Linac:
Bunched beam by 2017 ?
5.5MeV/u by the autumn of 2014
![Page 26: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/26.jpg)
Outline• Status and plans for 2012 experiments
• Shifts and schedule• RILIS and REX operation• New experiments for post accelerated beams 2012
• HIE-ISOLDE status and plans• Reports and recommendations from the IAP• Cavity design and tests• Civil engineering and installation work LS1
• Foreseen activities for LS1• Target area activities• Modifications in the experimental hall• Other plans
![Page 27: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/27.jpg)
LS1 Activities for ISOLDE• Robot replacement
• Hot Cell Installation• Medicis
• Target storage area
• Miniball move• ISOLTRAP platform
• RFQ Cooler alignment• HIE-ISOLDE
• PAD-MAD installation– Building 115 move/installation– Building 507 (light building)
Target Area
Experimental Area
![Page 28: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/28.jpg)
Target Area:Robot replacement
• The current ISOLDE robots:– are coming to the end of their lifetime.
• No compatible spare parts
– Are prone to faults– Have no back-up redundancy– Are limited in flexibility
• No further programming possible
• Part of the long term improvements in operation is to replace the existing robots.
![Page 29: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/29.jpg)
Target Area:Replacement robot
• New robot system based on “known” system.
Installation in target area – Q4 2013
![Page 30: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/30.jpg)
Target Area: ISOLDE Hot Cell• For the dismantling and oxidation of used
ISOLDE targets• Pre-conditioning prior to shipment to PSI for
waste treatment
Location of new Hot Cell
Installation scheduled for long shutdown 2013
Building 179 with target area
![Page 31: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/31.jpg)
Target Area: MedicisMedical Isotopes Collected from ISOLDE
• At present 1.4GeV, 2μA p. May have 2GeV, 4-8μA protons in 2018, of which 90% can be recuperated at the dump position.
• Samples can be transferred to Class A labs via a pneumatic transport system
• "Presentation at ICTR-PHE 2012 conference“ by Thierry STORA
![Page 32: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/32.jpg)
• - Ta(p,X)149Tb is one of the most efficient production method. G. Beyer et al., Radiochim. Acta 90, 247 (2002)
• Can use CERN specific technologies for isotope production (i.e. nano-structured target, patent WO2010/034364, CERN)
• Large variety of isotopes accessible
Target Area: Medicis
![Page 33: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/33.jpg)
• Beam transfer line– 1 straight section with 2 branches– Oct 2013 – Sept 2014
• MINIBALL move– Oct 2013 – April 2014
• Planning to be discussed in upcoming MINIBALL Collaboration meeting in 2 weeks
Miniball
Actar / Helios
Beam diagnostics
Exp.station
Miniball
Exp. Hall: MINIBALL Move
![Page 34: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/34.jpg)
Exp Hall: ISOLTRAP• Mass measurement
experiment situated in the middle of the ISOLDE hall
• Platform made of wood– Inacceptable for a Class C
type laboratory• Plans to re-furbish the
platform– Replace wooden platform
with an aluminium platform
![Page 35: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/35.jpg)
Exp Hall: RFQ Cooler• RFQ Cooler Alignment check• Laser at limit of transmission for optical
cooling experiments• External alignment checks done at the end of
2011– But to no avail
• Internal alignment checks need to be done
![Page 36: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/36.jpg)
PAD & MAD Installation
![Page 37: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/37.jpg)
PAD & MAD Installation
• Integration currently under discussion• Limited space in hall (especially near HRS entrance)• Integration in target area
– Conflict with hot cell operations– Access difficulties for large equipment (eg. FE’s, BTY
magnets)
![Page 38: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/38.jpg)
38
Present situation (ground floor Jura side):
Control room
Buildings 115 & 507
![Page 39: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/39.jpg)
39
Solid State Lab 115
1. Increasing the surface of the Solid State Lab in B.115:
Control room
![Page 40: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/40.jpg)
40
Replace building 507
Control room
2. Replacing the existing building 507 by a new building - Ground floor (only accessible from within the surveyed area):
![Page 41: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/41.jpg)
41
Control room
2. Replacing the existing building 507 by a new building - First floor (accessible from outside the surveyed area):
Replace building 507
![Page 42: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/42.jpg)
Building status• Building 115 (extended solid state laboratory)
– Plans completed– Costs
• 407kCHF (to be secured)
– Make building 275 available for other users– Implies all handling of radioactive sources to within the confines of the ISOLDE
perimeter
• Building 507 (light building)– Under discussion– HIE-ISOLDE data acquisition rooms outside hall– Visitor’s room – access to visitors will be denied in future when the hall will be
defined as a controlled area.– A new version being considered based on partly metallic structure and partly
“portacabin” type modules
![Page 43: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/43.jpg)
2 new Kuka linear RobotsIn Isolde Target Area
(2013)
Target Storage Area
Deliver the new target to the exchange point for the Kuka robots
Remove hot target and place on the shelf (during shut down)
Move the 3 years decayed target from shelf to hot cell
Move waste containers (with “standard” trans-pallet)
Handling with1 remote
controlled vehicle
To PSINew hotCell (2013) New
Target S. Marzari
![Page 44: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/44.jpg)
44
2012 2013 2014
Isolde LS1 Planning
Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Robots
Hot Cell
PAD/MAD?
Medicis
ISOLTRAP
RFQ Cooler
Building 115
Building 507?
Target storage?
Miniball move
Target area
Exp. hall
HIE-ISOLDE installation
ISOLDE operation
![Page 45: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/45.jpg)
Summary• Operations 2012
– A busy year ahead with a little more planned due to the extended operation time.
– The shift backlog clearly indicates the growing demand for physics at ISOLDE
• HIE-ISOLDE– Moving out of the R&D phase and into the procurement phase.– Important milestones to attain in 2012 to maintain the current schedule
• ISOLDE LS1 planning– A few tasks remain to be confirmed– A clear overlap of activities in the target area in Q4 2013– A potential conflict between HIE-ISOLDE installation and ISOLDE
operation in April 2014.
![Page 46: ISOLDE & HIE ISOLDE Status and Plans](https://reader035.fdocuments.net/reader035/viewer/2022062222/56815b13550346895dc8c181/html5/thumbnails/46.jpg)
Thank you for your attention
Acknowledgements • GS/SE : DANIEL PARCHET, ELISEO PEREZ-DUENAS• EN/MEF : STEPHANE MARIDOR• BE/ABP : FREDRIK WENANDER • BE/OP : DIDIER VOULOT, ERWIN SIESLING• PH/SME : MAGDA KOWALSKA, SUZANNE KREIM• EN/HDO : YACINE KADI• BE/RF : MATTEO PASINI, MATTHEW FRASER• EN/CV : PAUL PEPINSTER, BENOIT LACARELLE• EN/EL : RENE NECCA• TE/CRG : NICOLAS DELRUELLE, JOS METSELAAR• EN/STI : THIERRY STORA, ANA-PAULA BERNARDES, VALETINE FEDOSSEEV,
BRUCE MARSH, STEFANO MARZARI• GS/DI : CYRILLE BEDEL• TE/MSC : JEAN-PHILIPE TOCK, YANN LECLERCQ,
LLOYD WILLIAMS, ARNAUD BOUZOUD• EN/HE : BRUNO FERAL, JEAN LOUIS GRENARD, KEITH KERSHAW