Unit 8.ppt

45
Preparation of Project Unit 8

description

project report Financial institutions in India classify projects according to their age and their purposeNew projectsExpansion projectsModernisation projectsDiversification projectsAll these projects are generally profit oriented

Transcript of Unit 8.ppt

  • 5/22/2018 Unit 8.ppt

    1/45

    Preparation of Project

    Unit 8

  • 5/22/2018 Unit 8.ppt

    2/45

    Meaning of project

    Project is an approval for a capital investment to

    develop facilities to provide goods and services.

    (The World Bank) Project may be defined as a scientifically evolved

    work plan devised to achieve a specific objective

    with a specified period of time.

    A project is a productive activity which can be

    analysed, appraised and monitored independently.

  • 5/22/2018 Unit 8.ppt

    3/45

    Characteristics of Project

    1. Investment pattern

    2. Benefits or gains

    3. Time limit

    4. Location

  • 5/22/2018 Unit 8.ppt

    4/45

    Project classification - 1

    Financial institutions in India classifyprojects according to their age and their

    purpose1. New projects

    2. Expansion projects

    3. Modernisation projects4. Diversification projects

    All these projects are generally profit oriented

  • 5/22/2018 Unit 8.ppt

    5/45

    Project classification - 2

    The services oriented projects can be

    classified as

    1. Welfare projects

    2. Service projects

    3. Research and development projects

    4. Educational projects

  • 5/22/2018 Unit 8.ppt

    6/45

    Project life cycle

    Consists of 3 main stages

    1. Pre investment phase

    2. The construction phase

    3. The normalisation phase

  • 5/22/2018 Unit 8.ppt

    7/45

    Project management

    A systematic approach to planning

    and execution of the project

  • 5/22/2018 Unit 8.ppt

    8/45

    Phases of project management

    1. Identification

    2. Formulation

    3. Appraisal

    4. Selection

    5. Implementation6. Management

  • 5/22/2018 Unit 8.ppt

    9/45

    Project Identification

    Selection of a project after a careful

    scanning of the environment ofinvestment opportunity and its likely

    return

  • 5/22/2018 Unit 8.ppt

    10/45

    Project Formulation

    Translation of the idea into a concrete

    project with its importantpreliminary aspects.

    Preparation of feasibility reports

  • 5/22/2018 Unit 8.ppt

    11/45

    Project Appraisal

    Searching, scrutiny, analysis and

    evaluation of market, technical andeconomic variables. Assessing the

    profitability, ROI points

  • 5/22/2018 Unit 8.ppt

    12/45

    Project Selection

    Rational choice of a project in the

    light of objectives and inherentconstraints

  • 5/22/2018 Unit 8.ppt

    13/45

    Project Implementation

    Expeditious completion of the project

    within the allocated resources

  • 5/22/2018 Unit 8.ppt

    14/45

    Project Management

    Judicious operation of a project with

    objectives like maximisation of netpresent value, maximisation of return

    etc

  • 5/22/2018 Unit 8.ppt

    15/45

    1. Project Identification

    Is concerned with collection, compilation

    and analysis of economic data for the

    purpose of finding suitable opportunities forinvestment. (PESTLE)

    Sources of project ideas include friends,

    families, trade and professional journals,customers, intermediaries, research

    institutes, competitors

  • 5/22/2018 Unit 8.ppt

    16/45

    Criteria for selecting a particular

    project Investment size

    Location

    Technology

    Nature of industry

    Demand

  • 5/22/2018 Unit 8.ppt

    17/45

    Importance of project

    identification Projects are catalyst for economic

    development

    Income generation and employmentpotential

    Accelerate the process of social and cultural

    development Spur development of infrastructure andenvironment

  • 5/22/2018 Unit 8.ppt

    18/45

    2. Project Formulation

    Is the process by which an entrepreneur

    makes an objective and independent

    assessment of the various aspects of aninvestment proposition of a project idea for

    determining its total impact and also its

    liability. An important stage of the pre investment

    phase.

  • 5/22/2018 Unit 8.ppt

    19/45

    Objectives of the project

    This can be precisely defined at the start

    of the formulation stage.

    1. General objectivestates in broad termsthe achievements expected

    2. Operational objectivesstates specific

    results expected from the implementationof the project.

  • 5/22/2018 Unit 8.ppt

    20/45

    Stages of Project Formulation

    1. Feasibility analysis

    2. Techno-economic analysis

    3. Project design and Network analysis

    4. Input analysis

    5. Financial analysis

    6. Social costBenefit analysis

    7. Pre investment analysis

  • 5/22/2018 Unit 8.ppt

    21/45

    Planning commissions Guidelines

    for

    project formulation/feasibility reportsfor Industrial projects

  • 5/22/2018 Unit 8.ppt

    22/45

    1. General informationIndustry analysis

    and company details

    2. Preliminary analysis of Alternatives

    demand and supply gap,

    existing companies and their capacities,

    proposed projects,

    information on various options

    considered, their locations, the

    profitability, ROI,

  • 5/22/2018 Unit 8.ppt

    23/45

    3. Project descriptionthetechnology/process chosen for the project,

    the project location, details of plant andmachinery, operational requirements, theutility requirements, organisationalstructure, detailed activity wise

    construction and implementation, riskfactors

    4. Marketing plandemand and supply datafor market to be served, estimates ofprices, price sensitivity, past trend ofprices

    5. Capital requirements and their costs

    funds required

  • 5/22/2018 Unit 8.ppt

    24/45

    6. Operating requirements and their costs

    materials required after the

    commencement of commercial production7. Financial analysisthe financial viability

    of the project, includes pro forma financial

    statements of Balance sheet, profit andloss, cash flow and fund flow for the

    project period.

    8. Economic analysissocial benefitanalysis, benefit to the community, the

    impact on human resources in terms of

    skills up gradation or skill obsolesence

  • 5/22/2018 Unit 8.ppt

    25/45

    Project Design

    It defines the individual activities which are part

    of the project and their inter-relationship with each

    other. It enables to identify the flow of event which must

    take place for the successful implementation of the

    project.

    Network techniques help the management in

    performing these functions efficiently and

    effectively.

  • 5/22/2018 Unit 8.ppt

    26/45

    Network analysis

    Introduction

    Network analysis is the general name given to certain

    specific techniques which can be used for the planning,management and control of projects.

    One definition of a project:

    A project is a temporary endeavour undertaken to

    create a "unique" product or service

  • 5/22/2018 Unit 8.ppt

    27/45

    Network Techniques

    CPM

    PERT

  • 5/22/2018 Unit 8.ppt

    28/45

    CPM / PERT

    Project management techniques developed to meet

    a need to plan, schedule and control complexdevelopment projects

    Forms of network analysis in which the durationof processes required to complete a complex task

    or project is used to aid informed decisions on thescheduling of these processes

    Network analysis developed along two parallelpaths during the late 1950s

    One Industrial (Critical Path Method)

    One Military (Program Evaluation Review Technique)

    The techniques, although not synonymous, areknown by any variation on the names: PERT,

    CPM, or PERT/CPM

  • 5/22/2018 Unit 8.ppt

    29/45

    History - CPM

    CPM was developed by Du Pont and the emphasiswas on the trade-off between the cost of the project

    and its overall completion time (e.g. for certain

    activities it may be possible to decrease their

    completion times by spending more money - howdoes this affect the overall completion time of the

    project?)

  • 5/22/2018 Unit 8.ppt

    30/45

    History - PERT

    PERT was developed by the US Navy for the

    planning and control of the Polaris missile

    program and the emphasis was on completing theprogram in the shortest possible time. In addition

    PERT had the ability to cope with uncertain

    activity completion times (e.g. for a particular

    activity the most likely completion time is 4weeks but it could be anywhere between 3 weeks

    and 8 weeks).

  • 5/22/2018 Unit 8.ppt

    31/45

    CPM - Critical Path Method

    Definition: In CPMactivities are shown as anetwork of precedence relationships usingactivity-on-node network construction

    Single estimate of activity timeDeterministic activity times

    USED IN : Project Management - for the jobs ofrepetitive in nature where the activity time

    estimates can be predicted with considerablecertainty due to the existence of past experience.

  • 5/22/2018 Unit 8.ppt

    32/45

    Critical Path Method (CPM)

    The first recognized formal use of a networkschedule methodology

    CPM provides methodology for determining thecritical path of a network

    Critical Path is the set of activities which determinesthe overall project duration

    Analyzes the network time duration via activityduration

    Utilizes the Forward and Backward pass method CPM can be applied for either ADM or PDM

    Deterministic Method that used a fixed timeestimate (Most Likely) for each activity

  • 5/22/2018 Unit 8.ppt

    33/45

    Critical Path Method (CPM)

    Advantage

    Easy to use and understand

    Enables detailed planning and control by management Used for identifying critical activities

    Disadvantage

    Does not consider the time variations that can have

    impact on completion of complex projects

    Is not suitable for dynamic situations

  • 5/22/2018 Unit 8.ppt

    34/45

    PERT -

    Project Evaluation & Review Techniques

    Definition: In PERTactivities are shown as a network ofprecedence relationships using activity-on-arrow networkconstruction

    Multiple time estimates Probabilistic activity times

    USED IN : Project management- for non-repetitivejobs (research and development work), where the timeand cost estimates tend to be quite uncertain. Thistechnique uses probabilistic time estimates.

  • 5/22/2018 Unit 8.ppt

    35/45

    Program Evaluation and Review

    Technique (PERT)

    PERT is a statistical technique applied to anetwork schedule, which allows for therandomness in task completion times

    Calculates the range of possible completion times and

    probability of meeting deadlines Three time estimates are applied for each activity

    Optimistic: Assumes tasks will go according to plan with fewproblems. Generally the shortest time in which a task can becompleted. Typically 3 standard deviations from the mean

    1% chance of occurrence Most Likely: Based on experience of performing activity in

    past. Completion time having the highest probability

    Pessimistic: The longest time that a task might require.Assumes tasks will NOT go according to plan and requirerecovery actions. Typically 3 standard deviations from the

    mean 1% chance of occurrence

  • 5/22/2018 Unit 8.ppt

    36/45

    PERT (continued)

    Advantages:

    Has potential to reduce both the time an cost

    required for a project

    Provides Expected project completion time

    Provides Probability of completion before a

    specified date

    Determines Critical Path

  • 5/22/2018 Unit 8.ppt

    37/45

    PERT

    Disadvantages

    Time estimates are subjective

    Estimates may be biased

    Tasks never performed before are best guesses

    Not simple for typical users to understand

    Assumes a beta distribution for tome estimates

    Actual distribution may be different

    Assumes probability distribution of the projectcompletion time is the same as that of the critical path.

    Results in under estimation of the project completion time dueto other paths becoming critical during life of project.

    Monte Carlo simulations can be used to reduce this bias

  • 5/22/2018 Unit 8.ppt

    38/45

    Project Report

    Is a document incorporating relevant data inrespect of a project

    Serves as a guide to management Gives details of the inputs and outputs of a

    project

    Records the merits and demerits inallocating resources to production ofspecific goods or services

  • 5/22/2018 Unit 8.ppt

    39/45

    Need and significance of Project

    Report Financial institutions and commercial

    bankers need a project report to

    appraise/evaluate the possibility of a loan. Does not contribute substantially to future

    operations

  • 5/22/2018 Unit 8.ppt

    40/45

    Scope of project report

    1. Economic aspects

    2. Technical aspects

    3. Financial aspects

    4. Production aspects

    5. Managerial aspects

    Contents of Project Report

  • 5/22/2018 Unit 8.ppt

    41/45

    Contents of Project Report

    1. Objective and scope of the report

    2. Product characteristics3. Market situation and trends

    4. Raw materials

    5. Manufacturing details6. Plant and machineries

    7. Land and building

    8. Financial implications9. Marketing channels

    10. Personnel/Organisational details

  • 5/22/2018 Unit 8.ppt

    42/45

    Project Appraisal

    Is an exercise undertaken by a financialinstitution

    To make an independent and objectiveassessment of various aspects of aninvestment proposition

    To arrive at the financing decision

    To assess the viability of the project ondifferent aspects

    Scope of Project Appraisal

  • 5/22/2018 Unit 8.ppt

    43/45

    Scope of Project Appraisal

    Choice of technology/production process

    Size and scale of operations Locational aspects including availability of

    infrastructure and resources

    Plant and machinery selection includingsuppliers capabilities

    Buildings and Plant layout

    Project design and network analysis Effluent and by products

    Project cost estimates, profitability

    Sensitivity analysis

  • 5/22/2018 Unit 8.ppt

    44/45

    Steps in Project Appraisal

    Appraisal is a systematic process

  • 5/22/2018 Unit 8.ppt

    45/45

    Step 1 Economic` Indicates priority use

    Step 2 Technical Involves scale of the project

    and the process adopted

    Step 3 Organisational Suitability is examined

    Step 4 Managerial Adequacy and competenceare critically scrutinised

    Step 5 Operational Capability of the project

    Step 6 Financial Determines the financial

    viability for sound

    implementation and efficient