Distributed Generation – Customer Experience Workshop UK Power Networks – 3 October 2013

Transcript of UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013...

Page 1: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Distributed Generation – Customer Experience WorkshopUK Power Networks – 3 October 2013

Page 2: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Welcome and introductionsSteve Halsey Distributed Generation Development Manager

Page 3: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Safety and Housekeeping

• No planned fire alarms

• Toilets

• Mobile phones

• Emergency exits

• Fire assembly point

3

Page 4: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Emergency exitsSmile 3 & 4, Ground Floor, Prospero House

There are no planned fire drills today. If the fire alarm is heard please leave the building using the nearest fire exit. Once outside turn left onto Avon Place and assemble on Swan Street.

4

Page 5: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Agenda10:00 Welcome, Introductions & feedback SH10:10 Google maps asset data visualisation CP10:40 Setting the scene SB10:45 A) Enquiry and application Connections

B) Design and assessment Asset Management C) Programme delivery Capital Programme

(11:30 Tea and coffee All)

13:15 Lunch All

14:00 D) Strength in numbersE) Interactivity All DirectoratesF) Standards

15:15 Formal close MA15:30 Opportunity for 121 discussions All

5

Page 6: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Introductions/who’s here today?Connections

Mark Adolphus Director of ConnectionsSteve Bradley Head of Major ConnectionsSteve Halsey DG Development ManagerSteve Carlow Major Connections Manager SESteve Foster Major Connections Manager LondonJim Vasey Major Connections Manager EastSteve Rogers CiC ManagerWill Bowen Risk and Compliance ManagerKellie Payne DG Business AnalystRichard Austen Project Manager East

6

Asset Management

Robert Kemp Head of Network Strategy & PerformanceNuno da Fonseca Infrastructure Planning Manager East Kevin Burt Substation Standards Manager

Capital Programme

Ian Cameron Senior Project Manager East

Strategy & Regulation

Sotiris Georgiopoulos FPP Project Director

Information Systems

Chris Potter Real Time Systems Engineer

Customer Services

Nazrin Mehdiyeva Head of Stakeholder Engagement

Page 7: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Issues/questions from last workshopIssue Update

Publish applications anonymously via LTDS We have taken this into account for possible inclusion in future updates to the mapping tool

Consistency of people approving designs. Publication of design standards and dedicated design assurance team implemented 

Acknowledgement of application would be nice From 1st October an acknowledgement email will be sent from our new gateway email address

On‐going visibility/engagement Our DG surgeries have proven very popular and allow you to meet and discuss your project with our teams.

Staged payments We have introduced staged payments for schemes with a value less than £250K

If you ask for a 10 MVa connection and only 8 MVa is available you should be able to change your request accordingly and keep you place in the queue

Our interactivity framework does not permit this currently but we are considering the introduction of a feasibility study type approach that may allow this to happen 

Connections for dummies booklet Significant improvements made to website and DG Q&A mailbox introduced to assist new applicants

Internet – portal service that tracks where application is by distribution line

This will be delivered as part of our Business Transformation Process during 2014

2 – stage application: Key is really to improve the relationship so efforts are efficiently managed

See above

7

Page 8: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Feedback from 2013

“the service your department is “the service your department is providing is excellent and totally 

refreshing. You and your colleagues have taken the initiative to engage with 

generation developers and this approach has de‐mystified grid availability and undoubtedly made the process more clear, 

efficient and cost effective.  Well done.” 

Why is it so hard to get UKPN to agree to a meeting?

Actions from meetings often unaddressed typically because this is another part of UKPN

I would like to say having dealt with other DNOs it really is a breath of fresh air to speak to a DNO who (on the most part) is very willing to communicate with their customers; this week we had a very interesting and useful meeting

Wow Wow ‐ for me this was the best use of 90 minutes this year! Your guys did a fantastic job in reviewing sites with me, their assistance, knowledge and customer friendly approach is much appreciated

What would be really useful would be to know where we are in the "interactive" process i.e. what position we are and when the other applicants' 30 days expire.

Commitment to agreed timescale, how is it shared with UKPN, does anyone actually care about the date we want to connect ?

Very beneficial, Very beneficial, would be keen to come again

Workshops are an excellent innovation

8

Page 9: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Growth in Distributed Generation enquiries continues

9*Excludes G83 stage 1 enquiries

UK Power Networks Distributed Generation Enquiries*

Volumes

Page 10: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Our East of England and South East networks• The total accepted PV generation

YTD is 123 schemes totalling 1,031,273kW. (approx.1000MVA)

• Accounts for £37m of £170m Capital income

• Some areas “at capacity”

10

Page 11: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Google Maps Asset Data VisualisationChris Potter

Page 12: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Previous Meeting

• Presented a Google Earth representation of 11kV point to point routes

• Positioned substations• Due to licensing issues only produced map of Ipswich

12

Page 13: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Previous Results – EPN Primary/Grid Sites

13

Page 14: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Previous Results – Ipswich Overview

14

Page 15: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Feedback from previous session

• Most DG connections were not at 11kV• DG community interested at viewing 33kV and 132kV• Some concerns over fuzzing of cable routes• Desire for the dataset to be online and regularly updated

15

Page 16: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

What we did next

• Formed a rapid project team from our Information Systems, Asset Management and Connections directorates

• Explored current and alternative dataset options• Obtained a Google Maps for Business API license• Worked with our Enterprise Content Management team

on producing a website with authentication to host the new solution

16

Page 17: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Issues During Analysis Phase

• Found that the point to point data for the 33kV and 132kV routes fuzzed the actual route

• Needed to switch data source from our Control System (PowerOn) to our Asset Management system (Ellipse)

• No underground cable data from new data source

17

Page 18: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Development of Tool

• Redeveloped tool to use the JavaScript API (Advanced Programming Interface) from Google to use the internet as the presentation layer

• Worked with Asset Management to extract pole and tower data from our asset management database (Ellipse)

• Processed Ellipse data and integrated output into the final design

18

Page 19: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Live Presentation of New Tool

• Presentation of new web based mapping tool which, after user registration, is available soon (end Oct) from the UK Power Networks website.

• UK Power networks will email when fully operational

19

Page 20: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Future Enhancements

• Displaying circuit load information and additional capacity

• Display basic positions of pending approved connections• Further develop the tool to add in user tools making

applications easier• Work with vectorised data once it becomes available

20

Page 21: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Questions & Answers

• Any questions, feedback or suggestions for future enhancements?

21

Page 22: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Setting the SceneSteve Bradley Head of Major Connections

Page 23: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Setting the Scene - Our objectives for today

23

• To share with you progress on our Service Improvement Plan

• To gain feedback on what we’ve achieved

• To gather your views for our 2014 Plan• What should we start doing/do more of?• What should we do stop doing/do less of?

Page 24: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Feedback sessions

Page 25: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Start doing/More of

Stop doing/Less of

Your Feedback

25

Page 26: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

A) Enquiry and application

Page 27: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Highlights/good newsEarly engagement/surgeries – 15 held to date, 400+ schemes discussed

Recruitment – additional vacancies in Projects Gateway and Connections team

Staged payments – for projects valued at less than £250K

Website content – significant improvement  Link to LTDS Heat mapsDG Q&A mailbox 

Standardised witness testing charges – for East of England, London and South East

Simplifying offer documentation – breakdown of charges added

Convertible quotes pilot continues – roll out for DG customer mid 2014

DUoS charges – early notification for EHV projects from 1 August 2013

Gateway automatic acknowledgement email from 1 October 2013

Distribution list to replace newsletter – timely updates to distribution group

Segmentation strategy – projects below 1MVA now handled by HV/LV Projects Teams27

Page 28: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Enquiry Process

Offer

To make application  you:

Complete ENA application and send with two maps to:

Post:Projects Gateway, UK Power Networks, Metropolitan House, Darkes Lane, Potters Bar, Hertfordshire. EN6 1AG

Email:[email protected]

Assess point of connection considering impact on plant rating, voltage & fault level

Confirm level of interaction

Produce costing

Produce offer documentation POC drawing & offer letter

Undertake technical & financial reviews

Provision offer letter issued with POC drawing by email or post.

Offer valid for 90 days unless interactive then 30 days (if more than 30 days remain)

Application acknowledgement 

letter issued

<1MVA Budget Est 10 Working Days>1MVA Budget Est 20 working Days  LV Generation 45 Working Days 

HV/EHV Generation 65working Days

28

We will publish an ENA form with the minimum information requirements highlighted

Considering use of Letters of Authority

Page 29: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Looking ahead to 2014

What should we start doing/do more of?What should we stop doing/do less of?

29

Page 30: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Tea and Coffee break

30

Page 31: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

B) Design and assessment

Page 32: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Highlights/good newsStreamlined the internal approval process  

Dedicated staff to generation referrals (patches for Tactical Planners to manage interactivity for an area)

Provide upfront budget estimates where there are known to be significant network constraints

Early engagement – heads‐up regarding project viability

Bi‐monthly DG workshop

An allocated resource to Digsilent generation model

Heat/capacity maps

Public access to network diagrams ‐ DG mapping tool

Trialling radio communication technologies to replace pilot cable for certain inter‐tripping functionality

Flexible Plug & Play 

Page 33: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Looking ahead to 2014

What should we start doing/do more of?What should we stop doing/do less of?

33

Page 34: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

C) Programme Delivery

Page 35: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Highlights/good newsRecruitment – Dedicated Connection focussed Delivery Team

Weekly conference calls with Connections/Asset Management

Primavera project planning/ Outage Management meetings

Dedicated Generation Design Team

Kit approach to most Point of Connection solutions

Protection Settings solution

Innovation‐ Intertripping / 33kV Tower connections

35

Page 36: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Design Assurance Process

36

assurance

10d

Design Package is sent into 

Design assurance Mailbox and 

copied into Connections PM to 

monitor

A Scheme file is created and a 

CommentsSheet is 

compiled

Civil Engineer 

extracts Civil 

Drawingsand 

reviews submission, 

detailing comments Comments sheet is issued to Customer 

and Connections 

PM, 

Approved/Awaiting 

clarification

Review 

and 

Approval 

UKPN

Designers  

rectify  

Comments Electrical Engineer 

extracts Electrical

Drawings and reviews 

submission, detailing 

comments

1 3

9

9

5? 9

Page 37: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Looking ahead to 2014

What should we start doing/do more of?What should we stop doing/do less of?

37

Page 38: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Lunch and networking

Page 39: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

D) Strength in numbers – forming a consortiumE) InteractivityF) Generation Standards

Page 40: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

D) Strength in numbers –forming a consortium

Page 41: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Generation Landscape in EPN

• Approximately 2.3GW of contracted export in EPN withgas and wind generation representing 77% of the totalportfolio in EPN.

Source LTDS (May 2013)

GasOff Shore WindLandfill GasOn Shore WindCHPOther

41

Page 42: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Application for connection in EPN

• Even with a low acceptance rate, there is over 1700MWof generation to be connected to the EPN distributionnetwork in particular:

• Bramford: 461MW

• Walpole: 280MW

• Norwich Main: 174MW

• Eaton Socon: 136MW

• Burwell: 134MW

WalpoleNorwich Main

Bramford

Wymondley

Burwell

Eaton Socon

Pelham

Rayleigh

>200MW

100-200MW

50-100MW

<50MW

42

Page 43: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Distribution network constraints

• Further generation connection to the EPN electricity distribution network is restricted:• Thermal Constraints • Fault level Increase

– Synchronous generators contribution of 6 to 7x rated output– Inverter connected generators contribution of 1.2 to 2.6 x rated output

• Operation of Protective Devices– Directional overcurrent limitation on transformers (typical 50%)

• Load Masking• Islanded Networks• Voltage and frequency control Issues • System Automation Issues• Generation Intertripping/Turn Down Schemes

43

Page 44: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

• Network constraintsare reflected in thegeneration capacitymap;

• Multiple and complexlevels of interactivitybetween generationapplications.

August 2013 EPN Generation Capacity Map

Distribution network constraints

44

Page 45: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Overcoming the challenge

• Provision of firm connections to the 11kV or 33kVnetwork in the amber and red areas is limited;

• Most generation applications are being offered 33kVconnection via new 132/33kV Grid substations. Thesecan be costly and time-consuming, therefore lessappealing to smaller generators;

• In the short to medium term such solutions would enablemultiple generators to connect to the network, openingthe possibility for consortium type applications;

45

Page 46: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Overcoming the challenge

• UK Power Networks are working in conjunction withNational Grid to understand the impact of acceptedgeneration on the transmission network;

• UK Power Networks are also working with developerslooking for alternative solutions such as:

• Increase efficiency of existing network assets such as overhead lines;• Commercial alternatives such as provision of non-firm connections;• Implementation of new control and network monitoring technologies;• New Telecommunications platform to pave the way for regional active

network managment;

46

Page 47: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Overcoming the challenge

• Discuss potential for developers to form a consortium• Feasibility study funding• UKPN need time to identify and obtain resources to carry

out feasibility studies• Could release up to 100MW capacity in selected areas• Likely to be a 132kV multi-million pound solution to

reinforce the existing network• Additional cost for network extension as required• Possible 3-5 year time frame depending on

solution/scale

47

Page 48: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

E) Interactivity

Page 49: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Interactivity

Interactivity occurs where UK Power Networks receives two or moreapplications for connection, which could make use of the same part of thedistribution system but where there is insufficient spare capacity or othernetwork constraints on the distribution system that will prevent allapplications being connected.

Interaction can be caused by restrictions at a different level in thedistribution system to the proposed point of connection i.e. a connection at11kV can be interactivity due to an issue at 33kV or even 132kV level.

Position in an interactive queue is determined by the date of the application(subject to the receipt of full and final information).

49

Page 50: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Application received

UKPN determine interaction and the order

First applicant offer sent ?

Send Interactive Notice (Revision of Offer) to first applicant to inform them that their offer is now Interactive and unconditional, and to confirm the Quote Valid Date if this is changed (UKPN will reduce the quote validity to 30 days if more than 30 days remain)

Send Interactive Notices to all other applicants to inform them that their offer is now Interactive.

Second and subsequent applicant offers sent as conditional 30 day interactive offers.

Send Interactive Notices to all applicants to inform them that their offer is now Interactive.

First applicant offer sent as unconditional 30 day interactive offer.

Second and subsequent applicant offers sent as conditional 30 day interactive offers.

Yes No

Applicants accept offer by signing and returning Acceptance form and making payment within the validity period detailed in the offer

(or as revised)

First applicant accepts offer?

Yes NoFirst applicant proceeds to delivery. Subsequent applicants have payment repaid in full

Second applicant proceeds to delivery, if accepted. Subsequent applicants have payment repaid in full. And so on if Second applicant has not accepted

High Level Interactive Process

50

Page 51: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

• What do you think of the interactive process?

• What are the issues you have with the process?

• How do you think we could improve this process?

Interactive Discussion

51

Page 52: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

F) Generation Standards

Page 53: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Generation Standards

Progress to date, specifically for generation connections:• EDS 08‐0051 ‐ Guidance on 6.6kV‐ 33kV new demand and 

generation connections, plus associated block diagrams. • EDS 07‐0020 – Civil requirements for HV supply and generator 

connections, plus associated drawings. Additional standards under development:• Further diagrams to support 33kV standards (distance 

protection on looped circuits)• 132kV standards for generation connections

53

Page 54: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Generation Standards

Issues we are investigating and seeking to resolve:• Network capacity – what are the limiting factors on maximum 

export level (circuit/transformer capacity, protection settings)? How should these be dealt with?

• Alternatives to pilot wire intertripping for islanding and thermal overloads.  

As new issues arise we will deal with them as quickly as practicable and where appropriate produce/modify standards to suit. 

At the one to one discussions there is the opportunity for you to put your ideas forward. 

54

Page 55: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

Mark AdolphusDirector of Connections

Page 56: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group

2011. UK Power Networks. All rights reserved

Page 57: UK Power Networks – 3 October 2013 · Gateway automatic acknowledgement email from 1 October 2013 Distribution list to replace newsletter –timely updates to distribution group