Transitional PSD Applicability Scenarios

18
Transitional PSD Applicability Scenarios July 20, 2010 Jay Hofmann President trinityconsultants.com Troutman Sanders/Trinity Consultants PSD and Title V Tailoring Rule Seminar

description

Transitional PSD Applicability Scenarios. July 20, 2010 Jay Hofmann President. Troutman Sanders/Trinity Consultants PSD and Title V Tailoring Rule Seminar. trinityconsultants.com. Overview. Six PSD Applicability Transition Scenarios - PowerPoint PPT Presentation

Transcript of Transitional PSD Applicability Scenarios

Page 1: Transitional PSD Applicability Scenarios

Transitional PSD Applicability Scenarios

July 20, 2010Jay Hofmann

President

trinityconsultants.com

Troutman Sanders/Trinity Consultants

PSD and Title V Tailoring Rule Seminar

Page 2: Transitional PSD Applicability Scenarios

Overview Six PSD Applicability Transition Scenarios

Scenario A – Existing Minor Source (will become major due to a plant expansion project sometime in the future)

Scenario B – Existing Minor Source (will become major on July 1, 2011 due to GHG emissions and the Tailoring Rule) – Minor modification permit applications pending

Scenario C – Existing Major Source – Pending PSD application

Scenario D – Existing Major Source – Minor modification permit issued and actual construction will begin prior to January 2, 2011

Scenario E – Existing Major Source – PSD permit issued just prior to January 2, 2011 – Actual Construction will not begin until March, 1, 2012

Scenario F – Existing Minor Source (will become major on July 1, 2011 due to GHG emissions) – Pending project to be issued authorization to construct prior to July 1, 2011

Page 3: Transitional PSD Applicability Scenarios

Scenario A Site is an existing minor source for PSD Owners currently planning a project that

is minor and no permit limits at the source will be changed

After the project, site will be a major source

Will the Tailoring Rule directly impact the planned project for PSD purposes?

Page 4: Transitional PSD Applicability Scenarios

Scenario A (Cont.) Minor sources can not trigger PSD

unless the project results in the relaxation of an existing synthetic minor limit (a PSD “(r)(4)” limit) or the project is major “in and of” itself

Tailoring rule transition will not impact this project.

After the project, site will be major and future modifications maybe impacted by PSD

Page 5: Transitional PSD Applicability Scenarios

Scenario B Site an existing minor source for PSD. Site will become major due to Tailoring

Rule (GHG emissions above thresholds on a mass and GWP basis) as of July 1, 2011.

Any permit applications pending as of July 1, 2011 for plant modifications, will need to be evaluated for PSD applicability

A similar situation is addressed in Scenario F

Page 6: Transitional PSD Applicability Scenarios

Scenario C Site is an existing major source for PSD A PSD application has been submitted and

construction authorization/permit modification is pending

Permit application did not address GHG Permit must be finalized and issued prior

to January 2, 2011, else owner must address PSD GHG applicability

What if actual construction has not begun prior to January 2, 2011? Scenario E

Page 7: Transitional PSD Applicability Scenarios

Scenario D Site is an existing major source for PSD Minor modification permit application

submitted and the construction authorization is pending – Authorization will be finalized and permit issued prior to January 2, 2011. GHG not addressed in application

Site expects tobegin actual constructionprior to January 2, 2011

Issues?

Page 8: Transitional PSD Applicability Scenarios

Scenario E

Site is an existing major source for PSD PSD applicable project construction

authorization (without consideration of GHG) issued on December 28, 2010

Project’s net emissions increase of GHG is more than 75,000 tpy (GWP basis) and more than 0 tpy (mass basis)

Actual construction not expected to begin until March 1, 2012

Page 9: Transitional PSD Applicability Scenarios

Scenario E (cont.)

Construction authorization contains the following language:“Approval of construction shallbecome invalid if construction is notcommenced within 18 months afterreceipt of such approval, if construction is discontinued for a period of 18 months or more, or if construction is not completed within a reasonable time.”

Page 10: Transitional PSD Applicability Scenarios

Tailoring Rule Preamble – Step 1 EPA’s Step 1 Transitional Guidance – No

“Grandfathering” “We are not promulgating an exemption for PSD permit

applications that are pending when Step 1 of the permitting phase-in begins for those sources that would otherwise need to obtain a PSD permit based on emissions of pollutants other than GHGs. Any PSD permits issued to such Step 1 sources on or after January 2, 2011 will need to address GHGs.”

“Final PSD permits issued before January 2, 2011 need not be reopened or amended to incorporate requirements for GHGs that take effect after the permit is issued.”

“A source that is authorized to construct under a PSD permit but has not yet begun actual construction on January 2, 2011 may begin actual construction after that date without having to amend the previously-issued PSD permit to incorporate GHG requirements, provided the permit has not expired.”

Page 11: Transitional PSD Applicability Scenarios

Scenario E

Probably “OK” with respect to GHG

Page 12: Transitional PSD Applicability Scenarios

Scenario F Site is an existing minor source for PSD Site will become a major source for PSD

after July 1, 2011, due to existing GHG emissions and the Tailoring Rule (Step 2)

Pending project expects construction authorization to be issued prior to July 1, 2011

Issues?

Page 13: Transitional PSD Applicability Scenarios

Tailoring Rule Preamble – Step 2

EPA’s Step 2 Transitional Guidance – No “Mercy” “Sources that are not subject to PSD permitting

requirements until Step 2 need not obtain a PSD permit addressing GHGs in order to continue any actual construction that begins before July 1, 2011, when such a source was not a major stationary source required to obtain a PSD permit.”

“However, Step 2 sources that begin actual construction in Step 2 may do so only after obtaining a PSD permit.”

Page 14: Transitional PSD Applicability Scenarios

Tailoring Rule Preamble – Step 2 (cont)

A picture is sometimes worth a thousand words…….

Page 15: Transitional PSD Applicability Scenarios
Page 16: Transitional PSD Applicability Scenarios

“Begin Actual Construction”

Begin actual construction - means, in general, initiation of physical on-site construction activities on an emissions unit which are of a permanent nature. Such activities include, but are not limited to, installation of building supports and foundations, laying underground pipework and construction of permanent storage structures. With respect to a change in method of operations, this term refers to those on-site activities other than preparatory activities which mark the initiation of the change.

Page 17: Transitional PSD Applicability Scenarios

Scenario F

Site will need to begin actual construction prior to July 1 to be certain to avoid GHG requirements

Page 18: Transitional PSD Applicability Scenarios

Questions?

Jay Hofmannjhofmann@trinityconsultants.

com