STUDENT HOUSING TASK FORCE REPORT
Board of Directors
March 26, 2007
AGENDA
Background
Ramifications, Short Term and Long Term Alternatives
Summary, Final Comments, Q&A
HISTORY
Citizens Facility Advisory Committee Bond Advisory Committee February 6 bond election Resolution #85 2006-07 Student Housing Task Force May 15 bond election
BOND PROJECTS LISTProject Description Year of
Completion
Sparks Stadium: replace turf, track, scoreboard and sound system 2008
Highly Capable Program: upgrade housing 2008
Districtwide Emergency Storage Sheds and Safety Equipment 2008
Sunrise Elementary: replace carpet and roof 2008
Ferrucci Junior High: remodel office, commons, and entry spaces 2008
Junior High Science Classrooms: modernize or build new 2008
Districtwide Classroom Technology Systems and Equipment Phase I 2008-2012
Puyallup High School Phase II: build 200 student classroom addition 2009
Emerald Ridge High School: build 400 student classroom addition 2009
Wildwood Park Elementary: upgrade heating and ventilating system 2009
Hunt Elementary: upgrade fields, painting, and roof 2009
Districtwide Playground Equipment, Reader Boards, or Site Improvements 2009-2011
Districtwide Facility Accessibility (ADA): improvements for wheelchair and other access 2009-2012
Firgrove Elementary School: replace 2010
New Elementary School (Southwest Area): build new school 2010
Rogers Performing Arts Center: upgrade storage and related equipment 2010
Districtwide Life Cycle Projects: including earthquake improvements 2010-2012
Northwood Elementary School: replace 2011
Spinning Elementary School: replace 2012
CHARTER
“This task force was commissioned by the Board of Directors for the purpose of identifying, studying, and reporting on the impacts to the District if voters reject the May 15, 2007 bond measure.”
Members
Casey Cox Gerald Denman Rudy Fyles Celeste Hurst Sandra Jacobson
Guy Kovacs Brian Lowney Dave Maxwell Lynne Rosellini Debra Aungst
APPROACH 5 Major Categories Growth
Instructional Program Support
Technology and Related Professional Development
Facility Improvement
Health, Safety, and Emergency Preparedness
4 SECTIONS IN EACH
Which projects fall into this category?
Ramifications of a May 15, 2007 bond failure and what problems are created?
Alternatives for managing these problems in the short run?
Alternatives for managing these problems in the long run?
OVERARCHING THEMES
1. Growth:Even with new classrooms opening next year, existing enrollments require more classrooms now and the need will continue to grow.
2. Deteriorating Facilities:Past overcrowding, the wear and tear of intensive use of buildings and classrooms and the degraded condition of heavily used equipment require replacement or upgrading of our capital facilities if they are to continue to be useful.
Continued on next page
OVERARCHING THEMES
3. Many capital expenditures are necessary whether or not the bonds are available to pay for them and instructional dollars must be used instead.
4. Failure to deal with capital needs on a timely basis has both immediate and cumulative effects on students, families and teachers.
(continued)
750,000
800,000
850,000
900,000
950,000
1,000,000
1,050,000
1,100,000
1,150,000
1,200,000
97/1998 99/2000 01/2002 03/2004 05/2006 07/2008 09/2010 11/2012 13/2014 15/2016 17/2018 19/2020
School Year
Sq.
Ft.
Existing Total SF 2006 Project SF Need LOS 94.27
Historical 9-12 Years 13 Years Plus5-8 Years0-4 Years
400,000
450,000
500,000
550,000
600,000
650,000
700,000
750,000
800,000
97/1998 98/1999 99/2000 00/2001 01/2002 02/2003 03/2004 04/2005 05/2006 06/2007 07/2008 08/2009 09/2010 10/2011 11/2012 12/2013 13/2014 14/2015 15/2016 16/2017 17/2018 18/2019 19/2020 20/2021
School Year
Sq. F
t.
Existing Total SF 2006 Project SF Need LOS 124.35
12 Years PLus
400,000
450,000
500,000
550,000
600,000
650,000
700,000
750,000
800,000
850,000
School Year
Sq
. Ft.
Existing Total SF 2006 Project SF Need (LOS 145)
0 to 4 Years
5 to 8 Years
9 to 12 Years
Historical
GROWTH: Overview
Growth through at least 2020
Elementary and high school bulges
Junior highs are full
Growth in all areas of the district
GROWTH: 1-3 Years
Portables, if possible; impacts on classrooms, libraries, parking, playgrounds, commons, restrooms
Assign students to other schools
Use stages, hallways, commons, and small spaces—displace other activities
Eliminate/reduce inter- and intra-district transfers
Negative Impact to Students
GROWTH: Beyond 3 Years
Extended day and/or double shift
Year-round school
More students per classroom
Displace pull-out model programs and use for basic education classrooms
Negative Impact to Students
INSTRUCTIONAL PROGRAM SUPPORT: Overview
Secondary science classroom and lab space inadequate and insufficient
Culinary Arts program access is limited
Sparks Stadium turf out of warranty; surface has degraded
INSTRUCTIONAL PROGRAM SUPPORT: 1-3 Years
Science instruction in the regular classroom—compromises ability to conduct lab experiments
Limit the number of students in programs
Program access inequity between schools
Negative Impact to Students
INSTRUCTIONAL PROGRAM SUPPORT: Beyond 3 Years
Modify science curriculum to “fit” the physical plant limitations
Reduce or eliminate culinary arts and other magnet programs
Close Sparks Stadium; rent practice and game space; pay to play to pay for turf replacement
Negative Impact to Students
TECHNOLOGY: Overview
Technology tools help us meet the needs of the 21st century learner, a digital native
Lack of bandwidth causes excessively slow response times and loss of instructional time
Core mission-critical systems are at the end of their life
TECHNOLOGY: 1-3 Years
As technology fails, do not replace; over time student access will become increasingly limited
Reassign computers to teachers and other staff when new teachers and other staff are hired or existing machines fail
Negative Impact to Students
TECHNOLOGY: Beyond 3 Years
Eliminate technology-based instructional programs when they fail
Continue inequitable access to appropriate technology between schools
Redirect money from instructional needs to install systems necessary for payroll and vendor payments
Negative Impact to Students
FACILITIES & SITES:Overview
2.6 million SF; 22,000 students
Maintain investment in existing assets
A stitch in time
Inequity between schools
Equal access is limited
Provide appropriate learning environments for students!
FACILITIES & SITES:1-3 Years
Limit access to District facilities and fields
Ask PTAs to raise money to cover the cost of some items
More duct tape on ripped carpet
Negative Impact to Students
FACILITIES & SITES: Beyond 3 Years
Close classrooms and fields in disrepair
Solicit businesses to pay for Sparks Stadium improvements
Redirect increasing amounts of instructional resources from classrooms to facility/site emergency repairs
Negative Impact to Students
HEALTH, SAFETY & EMERGENCY: Overview
Buildings are not protected without seismic upgrades
Emergency supplies are inadequate stored inside or outside of schools
Buildings are compromised and deterioration accelerated if leaking roofs are not repaired/replaced
HEALTH, SAFETY & EMERGENCY: 1-3 Years
Delay major capital upgrades
Recruit volunteer fundraising for emergency storage & equipment
Build cement barrier in front of Firgrove (reduce risk of vehicles in traffic accidents ending up on school grounds)
Negative Impact to Students
HEALTH, SAFETY & EMERGENCY: Beyond 3 Years
Redirect money used for classroom instruction to pay for facility and site improvements
When hazardous playground equipment is removed, do not replace it
Negative Impact to Students
SUMMARY
Student Growth is Continuing
Costs Continue to Rise
Portables Are Only a Temporary and Undesirable Option
FINAL COMMENTS
Voters will make a choice on May 15, 2007. This report was commissioned by the Board of Directors to identify, study, and report on the impacts and options if this measure is rejected. Unfortunately, the alternatives are not easy. Nearly every short term option is both expensive in its own right and even more costly in the long run.
FINAL COMMENTS
There are financial costs.
More importantly,
there are educational and human costs.
QUESTIONS & ANSWERS