TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion...

26
1 TransCanada’s Napanee Generating Station (NGS) Presentation to the Community Liaison Committee Wednesday, September 17, 2015

Transcript of TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion...

Page 1: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

1

TransCanada’s Napanee Generating Station (NGS)

Presentation to the Community Liaison Committee Wednesday, September 17, 2015

Page 2: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

2

1. Project Updates

1. E.S. Fox

2. Matrix NAC

2. Transfer of Combustion Turbine Generator parts from Pickering to Taylor

Kidd Warehouse

3. Delivery of Duct Work from Cambridge

4. Piping Shipments from Toronto

5. Heat Recovery Steam Generator (HRSG) Component Delivery - Overseas

6. Condenser Delivery from US

7. Combustion Turbine Generator (CTG) Foundation Concrete Pours

8. Combustion Turbine Delivery Japan and Savannah, Georgia

Introductions & Agenda

Page 3: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

3

OBL – Project Status/Activities/Look Ahead

E.S. Fox Ltd.

Page 4: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

4

E.S. Fox – Project Status/Activities/Look Ahead

Page 5: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

E.S. Fox – Project Status/Activities/Look Ahead

5

Q3 Activities

• Complete civil earth works by the end of September

• Completed installation of the duct bank and raw water service pipe into the Lennox GS pumphouse

• Installed and backfilled sanitary sewer line

• Cooling water discharge

pipe installed to Lennox GS discharge channel

(complete by Sept.30)

Page 6: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

E.S. Fox – Project Status/Activities/Look Ahead

6

Q3 Activities

• Station to station grounding is nearing completion

• Final pavement and curb replacement will be completed in October

• Installed and backfilled sanitary sewer line

• Cooling water discharge

pipe into Lennox GS channel

(complete by Sept.30)

Page 7: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

E.S. Fox – Project Status/Activities/Look Ahead

7

Q4 Look Ahead

• Current staffing approximately 15

• Plan to demobilize in mid-November

• Return in spring 2016 to install pumping equipment

Page 8: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

8

Project Status/Activities/Look Ahead

Matrix NAC

Page 9: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

Matrix – Project Status/Activities/Look Ahead

Q3 Activities

• Installed temporary construction and permanent site entrances including traffic lights at temporary entrance

9

Page 10: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

Matrix – Project Status/Activities/Look Ahead

Q3 Activities

• Focus has been and remains the installation of buried services, equipment and building foundations (E.g. HRSG pours)

• Completion of Storm Water Management System

10

Page 11: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

Matrix – Project Status/Activities/Look Ahead

Q4 Look Ahead

• Major equipment deliveries – details to follow

• Focus will continue on civil work including additional large

concrete pours for:

• Combustion Turbine Generator foundation & pedestal

• Steam Turbine Generator foundations

(pours of approximately less than 1,000 cu metres)

• Completion of landscaping berms

• planting will take place as early as possible in 2016

11

Page 12: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

Matrix – Project Status/Activities/Look Ahead

Q4 Look Ahead

• Recently introduced a second shift

• Current manpower is approximately 300

• Anticipated manpower during Q4 – approximately 450

12

Page 13: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

13

TransCanada’s Napanee Generating Station (NGS)

Heavy Haul Activities

Page 14: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

14

• This activity involves approximately 250-300 truck loads of

material to be moved from a warehouse in Pickering, Ontario

to Matrix’s rental warehouse space on Taylor Kidd Road

(Bombardier).

• Includes 12 oversized or permitted loads.

• Shipping route should include Highway 401, County Road 4

and Taylor Kidd Road. (confirm)

• These shipments have started and will continue at a rate of

approximately 2 trucks per day.

• Shipments complete by October 31.

Transfer of CTG Parts from Pickering

Page 15: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

15

• This activity involves a total of 48 shipments from

Cambridge, Ontario including 36 oversized or permitted

loads.

• At present 1 permitted truck per day but could go to as many

as 3 trucks/day.

• Shipping route will include Highway 401 to County Road 4 to

Highway 33 to the NGS site

• Scheduled to be complete by mid-September

Delivery of Duct Work from Cambridge

Page 16: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

16

• Initially 6 trucks/week at Taylor Kidd warehouse and 10

trucks/week at site

• 31 trucks scheduled over the next two weeks

• Shipping route will include Highway 401 to County Road 4 to

Highway 33 to the NGS site.

• Currently being affected by a strike

Delivery of Piping from Toronto

Page 17: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

17

• 2 large concrete pours (approximately 1,000 sq.

metres/pour) to form the foundations for the Heat Recovery

Steam Generators.

• Completed on September 8 and 14

Heat Recovery Steam Generator Foundation Pours

Page 18: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

18

• Delivery of 24 large HRSG components and 6 steam drums

will be via ship to Lafarge (heaviest module 232,036 kg)

• Component will be carried to site on 18-axle trailers

(goldhofer)

• Trip from Lafarge to site is expected to take 15 minutes

• 2 shipments per day between 7:00 a.m. and 7:30 p.m.

• Commitment to avoid school busing times 8-8:30 a.m. and 3:30-4:00 p.m.

• OPP escort required in front and behind each shipment- can

order convoy to stop to reduce traffic congestion

• Schedule – ship currently expected to arrive September 27

or 28

• 8 days of deliveries

Heat Recovery Steam Generator (HRSG) Component Delivery

Page 19: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

19

• Delivery will stand down any time Lafarge need their dock

• Other Requirements:

• Approximately 8 residential electrical services will have to

be raised prior to the first delivery

• Goldhofer stored on NGS site at night

• Message signs to be installed prior to shipments

Heat Recovery Steam Generator Component Delivery

Page 20: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

20

• Delivery of condenser from supplier in US will be by barge to

Lafarge

• One 12-line hydraulic platform trailer making two deliveries

per day over two days between Lafarge and site

• Size requires either full road closure or escort (TBD)

• Schedule : Barge scheduled to arrive October 13

Condenser Delivery

Page 21: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

21

• Large concrete pours (approximately 800 to 1,000 cu

metres/pour) to form the foundations and pedestals for the

Combustion Turbine Generators. And the Steam Turbine

Generator

• Similar to HRSG pours - will involve one concrete truck

arriving and leaving the site every 5 minutes beginning at

7:00 a.m. for 8-10 hours.

• Main batch plant will be the CBM plant set up at the

Cruickshank Quarry location on Taylor Kidd Road.

• Backup will come from CBM Kingston and then Belleville

batch plant.

• Currently determining schedule for these pours.

Combustion Turbine & Steam Turbine Foundation Concrete Pours

Page 22: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

22

• Delivery will be via ship from Japan and Savannah, Georgia

to Lafarge

• 4 shipments to NGS site expected to take approximately 15

minutes

• Road closure and/or OPP escort required

• Target delivery date is early November

Combustion Turbine Generator Delivery

Page 23: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

23

Newspaper Ad and Direct Mail Flyer

Page 24: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

24

NGS Calendar - September

Monday Tuesday Wednesday Thursday Friday Saturday Sunday

31 August 1 September 2 3 4 5 6

Pickering Warehouse

Duct Work Deliveries

HRSG Foundation

Transfer

36 permitted loads

Piping Container

Bell Fiber

(250-300 loads)

Shipments

Cabinet Installation

7 8 9 10 11 12 13

Start of School

Duct Work

Bell Fiber

Pickering Warehouse

Deliveries

Piping Container

HRSG Foundation

Transfer

Shipments (40 loads)

Bike Tour (30-40

riders)

14 15 16 17 18 19 20

Piping Container

Lafarge

Shipments

Algoma Delivery

Pickering Warehouse

Transfer

21 22 23 24 25 26 27

Pickering Warehouse

Transfer

Amherst Island

Ship Arrives at Lafarge

HRSG Component

Dry Stone Wall

Deliveries

Festival

28 29 30

Pickering Warehouse

Transfer (on-going)

HRSG Component

Deliveries

24 modules, 6 steam

drums & associated

equipment

Page 25: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

25

NGS Calendar - October

Monday Tuesday Wednesday Thursday Friday Saturday Sunday

1 2 3 4

Pickering Warehouse Transfer

HRSG Component

Deliveries

5 6 7 8 9 10 11

Pickering

HRSG Component

Warehouse Transfer

Deliveries

(Starting at noon)

MTO-Permitted Load

Restrictions

12 13 14 15 16 17 18

MTO Permitted Load

Restrictions

Pickering

Lafarge Petcoke

Condenser Delivery

Warehouse Transfer

Unloading

19 20 21 22 23 24 25

Pickering

Warehouse Transfer

26 27 28 29 30 31

Pickering

Warehouse Transfer

Page 26: TransCanada’s Napanee Generating Station (NGS)€™s Napanee Generating Station ... Combustion Turbine & Steam Turbine Foundation Concrete Pours . 22 •Delivery will be via ship

26

NGS Calendar - November

Monday Tuesday Wednesday Thursday Friday Saturday Sunday

1

2 3 4 5 6 7 8

Combustion

Turbine Delivery

9 10 11 12 13 14 15

16 17 18 19 20 21 22

23 24 25 26 27 28 29