    INDUSTRIAL TRAININGUP NIRMAN NIGAM LTD. UNIT-19

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    2/23

    PAGE 1

    CONTENTS

    ACKNOWLEDGEMENT ........................................................................................................................ 2

    INTRODUCTION ................................................................................................................................... 3

    PROJECT SNAPSHOT ........................................................................................................................... 3

    EQUIPMENTS USED ............................................................................................................................. 5

    Transit mixer ....................................................................................................................................... 5

    Back hoe .............................................................................................................................................. 6

    Concrete Pump: .................................................................................................................................. 7

    BATCHING PLANT ............................................................................................................................ 8

    FLY ASH .............................................................................................................................................. 8

    FLY ASH BRICK .................................................................................................................................. 9

    BRICK WORK ..................................................................................................................................... 9

    PROCEDURE ........................................................................................................................................ 10

    Excavation: ......................................................................................................................................... 11

    PCC ..................................................................................................................................................... 11

    LAYING OF FOUNDATION ............................................................................................................ 11

    Raft foundations ................................................................................................................................ 12

    FORM WORK .................................................................................................................................... 13

    SCAFFOLDING/PROPS USED .........................................................................................................14DESIGN DETAILS ................................................................................................................................. 15

    CONCRETING ................................................................................................................................... 15

    REINFORCEMENT ........................................................................................................................... 16

    COLUMN ........................................................................................................................................... 17

    RING TIES AND BARS ..................................................................................................................... 18

    Spacing between the rings: ............................................................................................................18

    Beams: ................................................................................................................................................ 19

    Shear Reinforcement: .................................................................................................................... 19

    COVER BLOCKS ............................................................................................................................... 20

    SAFETY NETS ........................................................................................................................................ 21

    CONCLUSION ...................................................................................................................................... 22

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    3/23

    PAGE 2

    ACKNO WLEDGEMENT

    I would like to thank Mr. Atul Singh, under his guidance this traininghas proven such a success.

    I would also like to thank my college ,faculty members and friends fortheir support and enthusiasm

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    4/23

    PAGE 3

    INTRODUCTION

    Construction of extension of Allahabad high courts lucknow bench began in 2012

    The estimated cost of construction is 697 lakhs

    UP NIRMAN NIGAM LTD. Is the builder which has been awarded the contract The high court is spread in an area of 40 acres

    PROJECT SNAPSHOT

    The project is located near polytechnic crossing and is 25 kilometers (km) away fromAmausi Airport and 11 km from Hazratganj. The project has good road connectivity.

    The project will provide ample parking space.

    The project is an extension to the Allahabad high courts lucknow bench

    The bench consists three highly qualified ex-officio jurists, the administrative capital ofthe state.

    Completion date :2014

    RCC framed structure

    Floors:Marble flooring

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    5/23

    PAGE 4

    External doors and windows :window steel frame with wooden shutter doors

    Creation of chambers for judges and chief judges

    Creation of toilets on each floor at crossroads both ladies and gents

    Creation of Z shaped stairs through the stairs and lobbies

    Expansion & contraction joints are provided

    Bitumen Treatment are provided on roof

    Water proofing is done using Penybar (chemical)

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    6/23

    PAGE 5

    EQUIPMENTS USED

    It is device that homogeneously combines cement, aggregate such as sand or gravel,

    and water to form concrete.

    Transit mixer is truck mounted by a revolving drum to mix the components. Forsmaller volume works portable concrete mixers are often used so that the concrete can

    be made at the construction site.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    7/23

    PAGE 6

    A backhoe, is a piece of excavating equipment or digger consisting of a digging bucketon the end of a two-part articulated arm.

    They are typically mounted on the back of a tractor or front loader. The section of thearm closest to the vehicle is known as the boom, and the section which carries the

    bucket is known as the dipper or dipper stick.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    8/23

    PAGE 7

    The main type of concrete pump is either mounted on a truck and known as a truck-mounted concrete pump or placed on a trailer, and it is commonly referred to as a line

    pump or trailer-mounted concrete pump.

    This pump requires steel or rubber concrete placing hoses to be manually attached tothe outlet of the machine.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    9/23

    PAGE 8

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    10/23

    PAGE 9

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    11/23

    PAGE 10

    EXCAVATION

    PCC

    LAYING OFFOUNDATION

    FORM WORK

    SCAFFOLDING

    REINFORCEMENT CONCRETING

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    12/23

    PAGE 11

    Excavation was carried out both manually as well as mechanically. Adequate precautions are taken to see that the excavation operations do

    not affect the adjoining structures.

    After the process of excavation, laying of plain cement concrete that isPCC is done. A layer of 75 mm was made in such a manner that it was

    not mixed with the soil.

    It provides a solid base for the raft foundation and a mix of 1:3:6 that is, 1part of cement to 3 parts of fine aggregates and 6 parts of coarse

    aggregates by volume were used in it.

    At the site, Raft foundations was used to spread the load from astructure over a large area, normally the entire area of the structure.

    Normally raft foundation is used when large load is to be distributed and it is

    not possible to provide individual footings.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    13/23

    PAGE 12

    have the advantage of reducing differential settlements as

    the concrete slab resists differential movements between loading positions.

    They are often needed on soft or loose soils with low bearing capacity. Raft Foundation had a thickness of 750 mm. Bars of 25 mm to 16 mm were used and chairs were used.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    14/23

    PAGE 13

    Forms or moulds or shutters are the receptacles in which concrete isplaced, so that it will have the desired shape or outline when hardened.

    Once the concrete develops adequate strength, the forms are removed.Forms are generally made of the materials like timber, plywood, steel,

    etc.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    15/23

    PAGE 14

    Scaffolding is a temporary structure used to support people and materialin the construction or repair of buildings and other large structures.

    It is usually a modular system of metal pipes or tubes, although it can befrom other materials.

    The key elements of a scaffold are standards, ledgers and transoms.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    16/23

    PAGE 15

    DESIGN DETAILS

    Type of Cement Used :P.P.C (A.C.C) Grade of concrete in slabs and beams :M-20 Grade of concrete in coloumns:M-30 Grade of concrete in P.C.C work:M-10 Grade of concrete in Raft foundation:M-25 Concrete was made at the site only at the batching plant. From there it was carried upto the site with the transit mixer. Capacity of a transit mixer :6m3 Aggregates sizes :20 mm ,10mm Fine aggregate (sand):zone 2

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    17/23

    PAGE 16

    Fe-500 grade of steel was used. High strength deformed bars conforming to IS: 1786 ,grade Fe 500,

    indicate yield stresses 500 N/mm2 are commonly used.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    18/23

    PAGE 17

    Total no. of columns in a floor was 69, in which 64 have dimension750*250 and remaining 5 columns having dimension 600*250.

    There were 10 bars used in the columns in which the corner bars were ofdia. 25 mm, and the remaining were 20 mm dia. till 3 th floor.

    4 th to 7 th floor bars of dia. 20 mm and 16 mm were providedrespectively in the corner and in the middle.

    From 7 th onwards till the end the bars of dia. 16 mm and 12 mm wereprovided.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    19/23

    PAGE 18

    8 mm dia. bars were used as ring. The larger ring was of dimension 650*150 mm which holds the corner

    bars and the smaller ring was of dimension 350*150 which holds the

    inner bars.

    SPACING BETWEEN THE RINGS:

    The spacing between the top and the next ring was 80 mm and also thesame spacing was provided for the bottommost and the ring above it.

    Rest all the spacing between the rings was 120mm.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    20/23

    PAGE 19

    Beams were of sizes 230*400,small beams of size 230*160 was alsoprovided.

    Main Reinforcement: Mostly bars of dia 25,20 and 16 mm were provided.

    SHEAR REINFORCEMENT:

    Stirrup was of dia. 8mm.

    Stirrups were provided for the shear reinforcement ,1 st stirrup is at 40

    mm from face of the supporting member.

    Spacing of the stirrup was upto 2*(dia of the main bar)

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    21/23

    PAGE 20

    Cover blocks are placed to prevent the steel rods from touching theshuttering plates and there by providing a minimum cover and fix the

    reinforcements as per the design drawings.

    Covers should be made of cement sand mortar (1:3). Ideally, covershould have strength similar to the surrounding concrete, with the least

    perimeter so that chances of water to penetrate through periphery will

    be minimized.

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    22/23

    PAGE 21

    SAFETY NETS

  • 8/22/2019 TRAINING REPORT for UP nirman nigam

    23/23

    CONCLUSION

    This training is comprehensive in filling the gap between the theoretical& practical studies

    At the site there was a good management system between the contractor,the consultant, and the client.

    I found that there was good understanding between the supervisor andthe workers, though works are interdependent but there were no

    contradiction between them.