Tp Case Study L

22
Tomas Pivoras - CP assessment "V ernitas" 1 Case Study Textile company Cleaner Production Assessment Tomas Pivoras Kaunas University of Technology Kaunas, Lithuania

description

Fashion, apparel, textile, merchandising, garments

Transcript of Tp Case Study L

  • 1. Case Study T extile company Cleaner Production Assessment Tomas PivorasKaunas University of Technology Kaunas, Lithuania

2. Information about Vernitas

  • Products:
    • Bulk, polyacryl nitrile (PAN) yarns;
  • Production capacity:
    • 6.000 tons of yarn sper year;
  • Market:
    • export to EU approximately 70%.

3. Production processes

  • Yarn Preparation,sub-processes:
    • Stretch-breaking
    • Rebreaking
    • Intersecting
    • Finishing
  • Spinning
  • Twisting
  • Bulking
  • Dyeing

4. Auxiliary processes

  • Ventilation
  • Boiler house heating and steam production
  • Water preparation
  • Compressed air production

5. Methodology

  • A top-down investigation
  • The company was analyzed on three levels:
    • Level 1: Main data for black box - entire company;
    • Level 2: Main process data (building a layer cake);
    • Level 3: Detailed data and measurements for one or two specific processes.
  • In the initial phase focus on level 1 and 2.
  • Later level 3 data were collected/measured for the 2-3 focus areas.

6. Energy balance 7. H eat consumption 8. Energy savings ( electricity savings ) 2.7 98 000 36 600 671,300 Total 2.4 68 000 29 000 551,300 Installation of variable speed drives on fans 3.8 30 000 7 800* 120,000 Optimisation of humidification system years EUR EUR/ year kWh/year Units Pay back Investment Savings Elec. savings Electricity savings 9. Energy savings ( heat recovery) 2.8 70 000 25 000 753,300 Total 1.5 14 500 9 500* 290,000 Recycling of steam condensate in dyeing dept. 2.0 15 000 7 500 303,300 Heat recovery on air compressors 5.2 40 600 7 800* 160,000 Modernisation of heating substation years EUR EUR/ year kWh/year Units Pay back Investment Savings Heat savings Heat recovery 10. Optimisation of the humidification system - replacement of the spraying nozzles

  • Savings by reduction of consumption of both water and compressed air.

11. Installation of variable frequency drives on fans

  • S ignificantlyincreasedenergy efficiency of the fans at part load (50-90%), which was approx. 75% of the operation time.

12. Heat recovery in the compressed air system 13. Recycling of steam condensate in dyeing dept. 14. MainCleaner Productionprojects

  • 1) Treatment of waste water from dyeing department
  • 2) Possibility of recycling the waste water from dyeing department
  • 3) Reduction and substitution of chemicals used in dyeing processes
  • 4) Recycling of cooling water from spinning machines

15. Minimisation/optimisation of chemicals used

  • 1. investigatethe use of the chemicals
  • 2. investigatethe possibilities to omitthe use of the chemicals
  • 3. investigatethe possibilities to reducethe use of chemicals (this step should not be considered if the chemicals are evaluated to be hazardous, unless substitution is not possible)
  • 4. investigatethe possibilities to substitutethe chemicals with alternatives that have less negative impacts on the environment.
  • Vernitas:
  • 160 different chemicals
  • Total quantity of 26,419 kg .

16. Zinc emission to effluent

  • Stoptreating the effluent for removalof zinc (Zn)
  • Findthe source of the zinc (Zn) emission in the effluent.
    • It is much cheaper and more environmental friendly to change the source

17. Dyes containing heavy metals 18. Continual improvements:

  • Elimination/reducing of:
  • dyestuffcontainingheavy metals
  • azo-dyestuff , which splits off carcinogenic amines.
  • toxic chemicals(T or T xmarked according to EU regulations)
  • hazardous surfactant s giving rise to environmental concerns do to their poor biodegradability, their toxicity and potential to act as endocrine disrupters.
  • hazardous complexingagent

19. Wastewater from dyeing department 20. Wastewater treatment plant 21. Membrane filtration

      • Investment:
      • EUR.250 000.
      • Pay back:
      • 17.5 years

22. Reuse of cooling water fromspinning machines

  • Total use of water is about:
    • 24,000 m 3 / year
  • Total installation cost is:
    • 818 EUR.
  • Simple payback period is:
    • 1.67 year.
    • ( not including usage of electricity by water pump and water pumping from well )