statement of qualifications
1515 Poydras St. Suite 1875 New Orleans, LA 70112 PH: 504-799-3653 FX: 504-799-3654
TCONSULTANTSFC
T H R E E F O L D
-
7/30/2019 Three Fold Engineering in 2008
2/20
table of contents
company
overview
3
page
At Three Fold, weoffer a level of client
c o m m i t m e n tunparalleled to inthe rest of the
engineering market.
profess
ional
services
5
page
W e p r o v i d e
p r o f e s s i o n a l
engineering services
f o r t h e c i v i l ,
e l e c t r i c a l ,
environmental, and
m e c h a n i c a l
industries.
Copyright 2002. Three Fold Consultants, LLC. All Rights Reserved.
-
7/30/2019 Three Fold Engineering in 2008
3/20
table of contents
our
team
13
page
Our founders are
t e c h n o l o g i c a l l y
proficient and displayexcel lent project
experience.project
experience
9
page
T h r e e F o l dConsultants offers
more than 50 yearso f p r o f e s s i o n a le n g i n e e r i n g
experience. Weserve a wide array ofcustomers in every
industry.
-
7/30/2019 Three Fold Engineering in 2008
4/20
3
New Orleans, LA
company overview
h e c o n s u l t i n g
e n g i n e e r i n gTindustry is about toc h a n g e f o r e v e r .
Introducing Three Fold
Consultants, LLC. Three
Fold Consultants, LLC,
exemplifies the future in
consulting engineering
firms. As a diverse group of
C i v i l , E l e c t r i c a l ,
E n v i r o n m e n t a l , a n d
Mechanical Engineers,Three Fold is not your
typical Engineering Firm.
At Three Fold, we offer a
level of client commitment
unparalleled by the rest of
the engineering market.
We are the quintessential
engineering company thatcan provide turnkey
professional engineering
services to our clients. Our
firm can offer exceptional
service without extensive
Company Overview
overhead. The philosophy
that drives the partnersat Three Fold is the
understanding that the
client should buy only
what he or she need. We
offer our clients in-house,
hands-on expe r t i se
without the cost of hiring
both a lead and a subconsultant hired to
perform the same task
twice. Some clients hire
us for our expertise in a
particular area, but more
often we are hired for our
ability to provide a packaget h a t e n c o m p a s s e s
everything from design to
construction management.
Our ability to design initial
plans for construction,
a l o n g w i t h o u r
commitment to long-term
main tenance o f ourp ro jec t s , saves our
customers money and
keeps them loyal to Three
Fold Consultants, LLC.
New Orleans, Louisiana
-
7/30/2019 Three Fold Engineering in 2008
5/20
company overviewcontinued
Mission
hree Fold Consultants,
LLC is the new millennium
Tconsulting engineering
firm that has established a
reputation as a complete service
engineering firm. Commercial,
Industrial, and Governmental
clients have found our services
capable of accommodating their
diverse engineering needs. We
achieve these requirementsthrough excellent technical
management practices. Three
Fo ld i s compr ised o f a
consortium of engineering
professionals with over 50 years
of combined experience devoted
to the clients' goals.
Objectives
4
To provide high-qual ityc o n s u l t i n g , d e s i g n ,
construction, and operational
services
To set the standard within our
industry for cost-effective and
responsive client service
To provide excellence that
keeps clients coming back
Honesty and integrity towards
our clients, employees, and the
public
Commitment to budgets and
schedules
Objectives
Though one may be overpowered byanother, two can withstand him, and a
threefold cord is not quickly broken.~ Ecclesiastes 4:12
Full service engineering, resulting in reduced
client cost with the highest quality.
-
7/30/2019 Three Fold Engineering in 2008
6/20
-
7/30/2019 Three Fold Engineering in 2008
7/20
professional servicescontinued
6
Three Fold Consultants, LLC, offerssubstantial staff resources in
electrical engineering with extensiveexperience in repair and constructionof facility electrical systems. We havea thorough knowledge andunderstanding of the NationalElectrical Code and its application tofacilities. This experience, along withour extensive database of qualifiedelectrical subcontractors, allowsThree Fold Consultants, LLC, to
design, renovate, or build electricalsystems in any facility. In addition,we are able to perform electricalsystems construction managementand oversight.
EngineeringElectrical
capabilities:
Substation DesignEmergency and Back-up Power Systems
Uninterrupted Power Systems
Short Circuit Analysis
Power Distribution Design & Analysis
Load Calculationss
N E C Compliance
Lightning Protection
Power Systems, PLC and DCS design and
selection
-
7/30/2019 Three Fold Engineering in 2008
8/20
professional servicescontinued
7
Phase I and II environmental siteassessments
Risk assessments
Pollution prevention, minimization, and
reuse
Regulatory compliance
Permitting
Remedial design and construction
Groundwater assessment, monitoring,and treatment
Engineering and design of turnkey plantsto treat hazardous and NOW wastes
capabilities:
p e r m i t t i n g a n d m o d e l i n g
capabilities and has performed
projects for clients nationwide.
EngineeringEnvironmental
Three Fold Consultants, LLC, has
e x t e n s i v e e x p e r i e n c e i n
environmental engineering forindustrial, federal, and municipal
clients. Such projects include
permitting for the Love Canal in
Niagara Falls, NY, oily waste
recycling facilities in the US and
abroad, as well as carbon
regene ra t i on de s i gn and
permitting. Risk assessmentshave been performed under the
requirements of several state
agencies and the Risk Assessment
Guidance for Superfund (RAGS).
Three Fold has extensive air
-
7/30/2019 Three Fold Engineering in 2008
9/20
professional servicescontinued
8
EngineeringMechanical
Pump Design and SelectionPiping Design
Motor Sizing and Selection
Heat Exchangers
Burners Sizing and ReactorsDesign
Filtering Equipment Designand Selection
HVAC Design & Upgrade
Three Fold Consultants, LLC,
has extensive expertise in
designing turnkey mechanical
processes that offer optimal
solutions to clients. Such
processes range from optimal
HVAC designs to thermal
reactor upgrades that treats
solids and liquids.
capabilities:
-
7/30/2019 Three Fold Engineering in 2008
10/20
project experience
Avondale, Louisiana
Environmental Site Assessments, Risk
Analysis, Lit igation Preparation and
Remediation
$1 M
location:
services:
budget:
TFC has provided geotechnical and environmentalengineering to Avondale shipyards. The projectrequired the development of a sampling and analysisplan, geotechnical design for the US Army Corps ofEngineers, and LDEQ Permitting. Due to theproject's close proximity to the Mississippi RiverLevee, a supplemental geotechnical design andevaluation was required. The geotechnical
evaluation was reviewed and approved by the USArmy Corp of Engineers and the West Jefferson LeveeDistrict.
In addition, the project required review and approvalby the landowner and various local agencies. ThreeFold Consultants is performing additional siteevaluation and in the process of securing theadditional approvals from the regulatory agencies.
TFC has also been retained to perform a siteinvest igat ion to de l ineate hydrocarboncontamination and prepare submittals for theLouisiana Department of Environmental Quality.Tasks include drilling, sampling, reporting and riskevaluation.
Northrop Grumman Ship Systems
description:
9
-
7/30/2019 Three Fold Engineering in 2008
11/20
project experiencecontinued
Carrizozo, New Mexico
Permit, design and build 18-million pound/year;
activated carbon regeneration facility.
$2.5 Million
Three Fold Consultants, LLC, was retained as theengineer for the development of a regional carbonregeneration facility. The project required thedesign and construction of surface water controlstructures, geotechnical and structural design forthe facilitys infrastructure and support features. Inaddition, significant agency approvals and publicacceptance were required.
Three Fold Consultants performed geotechnical and
structural designs for various foundations, utilitysupports and buildings. TFC also performed airmodeling, risk evaluations and permitting. TFCcompleted the system design and secured thenecessary approvals from the regulatory agency.
Alesca Company: location
: services
: budget
: description
10
-
7/30/2019 Three Fold Engineering in 2008
12/20
project experiencecontinued
New Orleans, Louisiana
Program Managemet of the design an
construction phases of the Bond Funded Capit
Street Improvements Program.
$250 Million
location:
services:
budget:
Three Fold Consultants, LLC (TFC) has been retainedas a Subconsultant by Earth Tech E&I at the requestof the Owner (City of New Orleans) to serve as teammember of the Program Management Consultants.TFCs role in the Bond Fund Capital StreetImprovements Program is to assist the PrimeConsultants with the complete management andimplementation of the Citys Bond Fund Street
Improvements Program. The project requires thereview of the design and construction phases ofstreet reconstruction projects. In addition,significant interaction and coordination must beorchestrated between outside agencies and thedepartment of public works. TFC also conducts bi-weekly progress meetings with the ProjectManagers for the DPW, as well as assists with allcontract negotiations for contract supplements,claims, change orders, etc.
Three Fold Consultants has been instrumental insetting up various policy and procedures that arecurrently being utilized by the department of publicworks (i.e. Project Close-Out Forms, Project ActionForms, etc.). Three Fold Consultants was also part ofthe team that founded the Department of PublicWorks Coordinating Council (DPWCC) that wasestablished in August 2000.
City
Department
of New Orleans
of Public Works
description:
11
-
7/30/2019 Three Fold Engineering in 2008
13/20
project experiencecontinued
New Orleans, Louisiana
Odor study for the Sewerage and Water Board's
New Orleans West Bank Sewerage Treatment
Facility
$2.0 Million
Three Fold Consultants, LLC is performing an odorstudy for the Sewerage and Water Boards NewOrleans West Bank Sewerage Treatment Facility.The project includes review of the calculation ofsystem flows and retention; calculating theconcentration of potentially odor causingconstituents; and designing an economicallyfeasible electrical power source amicable to the
mechanical mechanisms to be installed for odorcontrol. Additional tasks include analyzing anddeveloping solutions that can economically controlthe release of odor causing agents.
New Orleans Sewerage & Water Board: location
: services
: budget
: description
12
-
7/30/2019 Three Fold Engineering in 2008
14/20
our team
Rodney Williamspresident
MSDOT
LADOT
FHWA/NHI:
TechnicianCertification
Certifications
(Concrete,
Asphalt &
Subsoils)
Certificate of
Training In
Urban Drainage
Design
Education
A.S.,
Engineering
Technology
A.A., Drafing& Design
Technology
Grossmount
Community
College, 1987
Copiah Lincoln
Community
College, 1986
Certifications
President, Three Fold, LLC.
Mr. Williams serves as the President of Three Fold Consultants, LLC. His
responsibilities include performance and oversight of civil engineering projects,
financial management, coordination of corporate resources, business development,
and client liaison activities. His experience includes the design, permitting,
construction management of state and local municipal roadway projects; private
subdivision development projects; storm water and wastewater system design;
potable water system design; and conceptual planning.
Project Coordinator for Transportation and Total Water Management
Projects,
Project Manager,
Squad Leader,
Earth Tech, New Orleans, LA
Krebs, LaSalle, LeMieux Consultants, Inc.
MSDOTD
Mr. Williams was responsible for the Coordination of the overall project scheduling,
invoicing, client liaison, setting up task for subconsultants, attending meetings, fee
negotiations, etc. While at Earth Tech he was part of the management team for the
City of New Orleans Department of Public Works Capital Street Improvement
Program. Mr. Williams served as a member of the Department of Public Works
Coordinating Council that was recommended by Mr. Williams, then later instituted by
the Mayor of the City of New Orleans in an effort to expedite the Street Improvement
Program. Mr. Williams was instrumental in setting up policy and procedures that are
currently in place at the DPW that have allowed the Department to operate at a more
efficient level.
Mr. Williams' responsibilities included the design and supervision of municipal,
private, and state projects in roadway design; oversight of clerical and technical staff
involved with projects under his supervision; preparing monthly invoices for
accounting purposes; assisting in contract negotiations; and participating in training
entry level engineering staff.
Mr. Williams responsibilities included oversight of technical staff, attending project
meetings with section leader and Director, preparing construction cost estimates,
preparing bid documents, and evaluating staff.
Memberships
Louisiana Chapter of A.C.I., A.G.C.
Committee for revising City of New Orleans General Specifications for Street Projects.
Member of Local Chapter of ASCE
Work History
13
-
7/30/2019 Three Fold Engineering in 2008
15/20
our teamcontinued
Work HistoryEducation
Registration
M.S., Civil /
Environment
Engineering,
B.S., Civil
Engineering,
University of
California at
Berkeley, 1987
88
Louisiana Stat
University,
1982-1985
Tarek Elnaggar, MS, PEexecutive vice-president
Executive Vice-President, Three Fold, LLC.
Mr. Elnaggar serves as the Executive Vice President of Three Fold Consultants,
LLC. His responsibilities include performance and oversight of civil and
environmental engineering projects, financial management, coordination of
corporate resources, and client liaison activities. His experience includes civil
engineering and infrastructure design; process design, permitting, construction
oversight, and operation of RCRA incinerators and waste minimization systems;
wastewater treatment and remediation design; environmental site
investigations; air emission calculations and permitting; and regulatory
compliance. Mr. Elnaggar served as the project manager for a $2.5 Million project
for the design and construction of activated carbon.
Environmental Manager,
Manager,
Earth Tech
GDC Enviro-Solutions Inc.
Mr. Elnaggar supervised a group of professionals performing groundwater
monitoring; hydro geological investigations; air permitting and monitoring
services; hazardous waste permitting and compliance; environmental site
assessment activities; risk analysis; and construction oversight.
Mr. Elnaggars responsibilities included oversight of technical and remediation
staff; financial oversight; contract negotiations; hiring and firing staff; and
billing and collection. He negotiated unique regulatory approval for an oily
hazardous waste minimization and recycling facility for a major gulf coast
refinery, which was the first facility of its type approved in the U.S. Mr. Elnaggar
performed air and RCRA permitting, engineering, construction, startup, and
operation of the company's stationary and transportable waste minimization
systems and incinerators under stringent regulatory requirements, which
required extensive negotiations with federal and state regulatory agencies as
well as private and government customers. Under his leadership, the company's
capabilities and permits were expanded to include processing of radioactive and
mixed wastes.
Civil Enginee
P.E.
Environment
Engineer, P.E
Louisiana
Mississippi
New York
Texas
New Mexico
Louisiana
14
PresentationsTreating the Mixture of NORM Contaminated and RCRA Listed Refinery Waste
Streams.Elnaggar, Tarek, Goodson, Fred, and Simms, Christopher. National
Petroleum Refiners Association, San Francisco, California, October 1995.
Elnaggar, Tarek, and Mayes Ph.D., Jim, The On-Site Incineration of Over
50,000 Tons of Liquid and Solid Aniline and Nitrobenzene Waste Streams,1994 Incineration Conference, Houston, Texas, May 1994.
-
7/30/2019 Three Fold Engineering in 2008
16/20
our team
M.S.
Engineering
Science
B.S. ElectricalEngineering
University of
New Orleans,
1990.
Louisiana State
University, 1987
Education
Bassam A. Mekari, MSEEexecutive vice-president
Executive Vice-President, Three Fold, LLC.
Mr. Mekari currently serves as Executive Vice President of Three Fold Consultants,
LLC. His responsibilities include performance and oversight of electrical and
mechanical engineering projects, financial management, coordination of
corporate resources, and client liaison activities. He has over 14 years of design
and construction management experience in the electrical, mechanical, and
industrial processing engineering fields.
Department Head,
International Environmental Manager/Project Manager,
Chief Operating Officer,
Project Manager /Environmental Engineer,
Ghaith Environmental Works
OSCA, Inc.
International Product Recovery, Ltd.
Mr. Mekaris responsibilities included the coordination of corporate resources for
the cleanup and remediation of oil refineries in the United Arab Emirates (UAE).
Mr. Mekari managed and trained office/field engineers and process operators to
perform all levels of Phase I & Phase II assessment, project management, MSDS
handling, and Waste Transportation Manifest. He managed small to medium size
projects (up to $20 million). Over the past 10 years he has gained experience in
Petrochemical & EPA issues; managed $30 million in government bids and
proposals.
Mr. Mekari served as COO for IPR during his tenure. He was in charge of
international projects where he conducted research testing for TEXACO in order to
safely process their high BTU soil from their ponds in Ecuador. A complete technical
and financial feasibility study was detailed in the final report with a
recommendation for the optimal treatment methodology.
Mr. Mekari represented GDC with the EPA and local agencies. He possesses
expertise in managing plant mobilization, construction, debottlenecking, andturnaround scheduling. He set up preventive maintenance, process modifications
and revamping, and critical path schedules in addition to implementing project
estimation, work scope development, and detailed budget development.
GDC Enviro-Solutions
Work History
15
continued
PublicationsRotary Kiln Incinerator design modifications to quadruple its throughput
Environmental Compliance Magazine, 1997
Innovative Methods of Thermally Destroying Hazardous WasteInternational Conference on Thermal Treatment Technologies, 1997. Oakland, CA
-
7/30/2019 Three Fold Engineering in 2008
17/20
-
7/30/2019 Three Fold Engineering in 2008
18/20
Contact Information
contact us
visit us online:
http://www.ThreeFoldLLC.com
17
TCONSULTANTSFC
T H R E E F O L D
-
7/30/2019 Three Fold Engineering in 2008
19/20
contact us
Contact Information
Postal Mail Website:
E-mail:
Phone:
Fax:
http://www.ThreeFoldLLC.com
1515 Poydras St. Suite 1875
New Orleans, LA 70112
(504) 799 - 3653
(504) 799 - 3654
Copyright 2002. Three Fold Consultants, LLC. All Rights Reserved.Booklet designed in Corel Draw by Midnight Technologies
18
-
7/30/2019 Three Fold Engineering in 2008
20/20