THEMIS FRRSC - 1 KSC, Feb 12, 2007 SPACECRAFT OVERVIEW/STATUS Peter R Harvey THEMIS Project Manager.
-
Upload
egbert-evans -
Category
Documents
-
view
221 -
download
2
Transcript of THEMIS FRRSC - 1 KSC, Feb 12, 2007 SPACECRAFT OVERVIEW/STATUS Peter R Harvey THEMIS Project Manager.
THEMIS FRR SC - 2 KSC, Feb 12, 2007
• Mission Overview• Flight Systems Processing• Ground Systems• Reviews• Summary
Agenda
THEMIS FRR SC - 3 KSC, Feb 12, 2007
Probe conjunctions along Sun-Earth line recur once per 4 days over North America.
Ground based observatories completely cover North American sector; can
determine auroral breakup within 1-5s …
… while THEMIS’s space-based probes determine onset of Current Disruption and
Reconnection each within <10s.
: Ground Based Observatory
Mission Science
THEMIS FRR SC - 4 KSC, Feb 12, 2007
LaunchVehicle: Delta II, Eastern RangeApogee: 91845.2 km ± 9567 kmPerigee: 435 km ± 10 km (500 km ± 7 km on or after
3/1/2007)Inclination: 16.0 deg ± 0.5 degDate: February 15, 2007
Space SegmentSpacecraft: 5 Spinning Probes with Fuel for Orbit & Attitude
AdjustInstruments: 3-Axis Electric Field, Magnetic Field
3-D Ion & Electron Particle DetectorsSpin Rate: 20 RPMOrbit Period(s): 1, 2 and 4 daysOrientation: Ecliptic Normal
Ground SegmentObservatories: 20 Northern with All Sky Imagers and
MagnetometersControl Facilities: Mission and Science Operations Centers
OperationsPhases: L&EO, Cruise, Ascent, Campaigns, De-orbitLifetime: 2.3 years
Mission Summary
THEMIS FRR SC - 5 KSC, Feb 12, 2007
Instrument Configuration
IDPU: Instrument Data Processor UnitSPB : Spin Plane Booms (4x)AXB : Axial Booms (2x)SST : Solid State Telescope (2x)ESA : Electrostatic Analyzer FGM : Fluxgate MagnetometerSCM : Search Coil Magnetometer
THEMIS FRR SC - 6 KSC, Feb 12, 2007
Fuel Tank
ESA
EFI SPB
Thruster T1
EFI Axial Booms (2, Stowed)
BatteryBAU
Repress Tank
Miniature Sun Sensor
Transponder
Thruster T2
IDPU
Fuel Tank
Antenna
EFI SPB
EFI SPB
Thruster A1
Thruster A2
AEB
Gyros
Probe Configuration
THEMIS FRR SC - 7 KSC, Feb 12, 2007
Standard Delta 10 ft. Fairing Static Envelope
3712 PAF
Probe Carrier Assembly (PCA = 5 Probes + Probe Carrier) on L/V
Probe Carrier Assembly (PCA = 5 Probes + Probe Carrier) on L/V
THEMIS Launch Configuration
THEMIS Launch Configuration
Probe Carrier Assembly (PCA) on Delta 3rd StageProbe Carrier Assembly (PCA) on Delta 3rd Stage
Launch Configuration
Dedicated launch accommodated within standard Delta 7925-10 vehicle configuration and services
10’ Composite Fairing required to accommodate five Probes on the Probe Carrier in the “Wedding Cake” configuration
PC stays attached to Delta 3rd stage after probe dispense
Each probe dispense from the PCA is coordinated with but independent of the other probes
No single probe anomaly precludes dispense of remaining probes
Star 48 3rd Stage
THEMIS FRR SC - 8 KSC, Feb 12, 2007
Environments
Thermal Vacuum
Acoustics
Spin Balance
EMC
VibrationMagnetic
s
THEMIS FRR SC - 9 KSC, Feb 12, 2007
Probe Processing
Bolt Cutter Installation
Performance Tests
Solar Array Illumination
Delivery to ASO
THEMIS FRR SC - 10 KSC, Feb 12, 2007
Probe Fueling
Vibration
Thermal Vacuum
Acoustics Spin Balance
Storage
Dry Weigh & Pressurize Fueling
THEMIS FRR SC - 11 KSC, Feb 12, 2007
PCA Processing
Vibration
Acoustics Spin Balance
Storage
SSS Installation
Ready for Probes
Final checks
Spin Balance
PCA Integration
Fairing Installation
THEMIS FRR SC - 12 KSC, Feb 12, 2007
Ground System Diagram
Ground System Elements•Ground Stations
•Ground Network
•Space Network
•Mission Operations Center
•Science Operations Center
•Flight Dynamics Center
Including•Mission Design
•Orbit & Attitude Determination
•Maneuver Planning
•Limit Detection and Notification
•Network Security
THEMIS FRR SC - 13 KSC, Feb 12, 2007
Mission Operations Center
BGS Antenna, Equipment Racks and FOT Workstations at the Mission Operations Center
THEMIS FRR SC - 14 KSC, Feb 12, 2007
Ground Stations
Ground StationStation
DesignatorFigure of
MeritLocation Function
Berkeley, CA BGS 11-m 24.0 dB/K37.879° N 122.243° W
Primary TLM/CMD/TRK
Wallops Island, VA WGS 11-m 23.0 dB/K37.925° N75.476° W
Secondary TLM/CMD/TRK
Merritt Island, FL MILA 9-m 1/2 21.6 dB/K28.508° N80.693° W
Secondary TLM/CMD/TRK
Santiago, Chile AGO 9-m 21.6 dB/K33.151° S70.668° W
Secondary TLM/CMD/TRK
Hartebeesthoek, SA HBK 10-m 20.4 dB/K25.883° S27.708° E
Secondary TLM/CMD/TRK
Mission Supported by 5 Ground Stations• Ground Stations: BGS, WGS, MILA, AGO, HBK• GN, SN and FDF Support Documented in PSLA• All Stations Have Successfully Flowed Data with MOC
THEMIS FRR SC - 15 KSC, Feb 12, 2007
LEO Acquistion
LEO AcquisitionMultiple Ground Assets Have Good View Following LaunchProbe Attitude Around 1:30 MET is Poor for Telemetry Probes Contacted at 4Kbps for 5 Minutes each from 1:20 to 1:40
THEMIS FRR SC - 17 KSC, Feb 12, 2007
LEO Early Orbit
Early Orbit Activities• TDRSS Pass to Observe Separation at T+73 min• Round-robin Contacts
– Starting at T+81min, Each Probe Will Be Contacted for 5 Mins– Expected Battery SOC to Remain > 87%
• Initial Orbit and Attitude Determination– Record and Process Two-way Doppler Data– Perform Attitude Determination in Real-time– Both UCB and GSFC FDF Function in Parallel
• Round-Robin Checkout of Key Systems on Each Probe– Reaction Control System Readiness– Attitude Sensors Functionality
• Perform Attitude Maneuver to Ecliptic Normal• Systematic Instrument Power-up and Check-out
– Leads to Decision of Probe Orbit Placement in Appx 26 Days
THEMIS FRR SC - 18 KSC, Feb 12, 2007
Ground Based Observatories Ground Based Observatories
• UCB has Delivered All 20 GBO (GMAG and ASI) units• 19 Have Been Installed, 1 Needs Repair• Automatic Data Collection and Archiving in Progress• Remote Commanding and Diagnostics Working • Expect to be Fully Functional at Winter 2008
Courtesy H.Frey, UCB
GeographicLongitude 324°
Geographic Longitude 195°
GeomagneticNorth Pole
GeographicNorth Pole
THEMIS FRR SC - 19 KSC, Feb 12, 2007
IIRT RFA Status
IIRT Performed 27 Formal Reviews of THEMIS
IIRT Issued 308 Requests for Action
Project Completed all 308
IIRT Concurred on all 308
Final Two Closed since MRR• RCS Proof
• Launch Window Analysis
THEMIS FRR SC - 20 KSC, Feb 12, 2007
Reviews Ahead
Start Event Description Status1/5/2007 MRR Mission Readiness Review at GPMC Complete
1/12/2007 LVRR Launch Vehicle Readiness Review Complete1/19/2007 SMSR Systems and Safety Mission Assurance RComplete1/23/2007 MRB Mission Readiness Review Complete2/1/2007 LSRR Launch Site Readiness Review Complete
2/12/2007 FRR Flight Readiness Review In Progress2/14/2007 LRR Launch Readiness Review
THEMIS FRR SC - 21 KSC, Feb 12, 2007
Summary
Issues Bolt Cutter Taping – Closed P1115 Connector Demated – Closed PCA-3rd Stage CG Offset – Closed
Summary Status Probes and Probe Carrier are Flight Ready Mission Operations is Complete Launch Team and Operations Teams are Ready
Readiness Statement THEMIS is Ready to Continue Processing for Launch