THE TWENTIETH ANNUAL INTERNATIONAL MARITIME LAW ...€¦ · Maritime and Port Authority Of...
Transcript of THE TWENTIETH ANNUAL INTERNATIONAL MARITIME LAW ...€¦ · Maritime and Port Authority Of...
THE TWENTIETH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT
Memorandum for Claimant
On Behalf of:
Panther Shipping, Inc.
80 Broad Street, Monrovia, Liberia
(CLAIMANT)
Against:
Omega Chartering Limited
P.O. Box 911, Vaduz, Liechtenstein
(RESPONDENT)
RIZKY BAYUPUTRA – RAFI YUSZAR – ANGGARDHA ANINDITO
TEAM NO. 12
Team 12 Claimant’s Memorandum
ii
MEMORANDUM FOR CLAIMANT
TEAM NO. 12
Team 12 Claimant’s Memorandum
iii
TABLE OF CONTENTS
LIST OF AUTHORITIES ....................................................................................................................................... v
LIST OF ABBREVIATIONS ................................................................................................................................... x
SUMMARY OF FACTS ......................................................................................................................................... 1
ARGUMENTS FOR CLAIMANT ............................................................................................................................ 2
SUBMISSIONS ON CLAIMS .................................................................................................................................. 2
ARGUMENTS ON THE MERITS OF THE CLAIM .................................................................................................. 2
I. RESPONDENT IS LIABLE FOR ALL LOSSES ARISING FROM MISSING THE NEXT
FIXTURE.......................................................................................................................................................... 2
A. Charter period of ‘about 50-55 days without guarantee’ was not an honest estimate ................. 3
B. Respondent had assumed responsibility for the Loss of Next Fixture ......................................... 4
(i) Respondent had knowledge to contemplate the extent of the loss ............................................ 4
(ii) Respondent understood that late redelivery would place Claimant into poor market
conditions .................................................................................................................................................. 5
C. Claimant’s actions of concluding the Next Fixture during quarantine was reasonable ............. 6
D. There was a substantial chance for Champion to extend the duration of the Charterparty ..... 7
II. RESPONDENT IS LIABLE FOR ALL COSTS IN CONNECTION WITH HCO .......................... 9
A. Respondent’s obligations for HCO had arisen pursuant to Clause 83 of the Rider Clauses ..... 9
B. Claimant had legitimate interest to continue the Charterparty and perform HCO at South
Island ........................................................................................................................................................... 11
(i) Accepting the redelivery and claiming damages would not be an adequate remedy ............ 11
(ii) Claimant’s intentions were not perverse ................................................................................... 12
C. Respondent cannot rely on lump sum offers to indemnify them from HCO Costs .................. 13
(i) Clause 83(d) of the Rider Clauses was amended ...................................................................... 13
(ii) Alternatively, Clause 83(d) of the Rider Clauses’ lump sum provision is too uncertain to be
enforced ................................................................................................................................................... 14
III. RESPONDENT IS LIABLE FOR COMPOUND INTEREST ....................................................... 14
SUBMISSIONS ON COUNTERCLAIMS ................................................................................................................ 15
ARGUMENTS ON THE ADMISSIBILITY OF THE COUNTERCLAIM .................................................................... 15
IV. RESPONDENT’S COUNTERCLAIM IS TIME-BARRED .......................................................... 15
A. Respondent’s notifications did not fulfil the requirement for claims’ notification under
Clause 6 of the ICA .................................................................................................................................... 15
B. Respondent’s notification did not fulfil its commercial purpose ................................................ 16
ARGUMENTS ON THE MERITS OF THE COUNTERCLAIM ................................................................................ 17
V. CLAIMANT IS NOT LIABLE FOR CARGO DAMAGE ................................................................ 17
A. Cargo damage falls outside of the scope of Clause 8(a) of the ICA ............................................ 18
B. Ballasting operations do not fall within Clause 8(b) of the ICA ................................................. 19
Team 12 Claimant’s Memorandum
iv
C. Respondent’s actions had caused the Cargo damage per Clause 8(d) of the ICA .................... 20
VI. THE VESSEL SHALL REMAIN ON HIRE THROUGHOUT THE DETENTION .................. 20
A. The delay for 51 days does not amount to an off-hire event pursuant to Clause 17 of NYPE15
21
(i) The Vessel was not prevented from full working ..................................................................... 21
(ii) Even if the Vessel was prevented from full working, the cause preventing the full working
does not fall under Clause 17 of NYPE15 ............................................................................................ 22
B. In any event, Respondent had assented to the risk of the Vessel being detained ...................... 24
PRAYERS FOR RELIEF ............................................................................................................................. 25
Team 12 Claimant’s Memorandum
v
LIST OF AUTHORITIES
A. Articles and Books
Jie Liu "Chartering policies in the dry bulk market" (2001). World Maritime University Dissertations. 202.
Rathore KS, Keshari R, Rathore A, Chauhan D. A Review on Ebola Virus Disease. PharmaTutor. 2014;
2(10): 17–22.
Rothstein, Mark A. At Law: Ebola, Quarantine, and the Law. The Hastings Center Report 45, No. 1 (2015):
5-6.
B. Cases
Actis Co. Ltd. v The Sanko Steamship Co. Ltd. (“The Aquacharm”) [1982] 1 Lloyd’s Rep 7.
Albion Water Ltd v Dwr Cymru Cyfyngedid [2013] 3 WLUK 785.
Allied Maples Group Ltd v Simmons & Simmons [1996] C.L.C. 153.
Anderson v Anderson [1895] 1 QB 749.
Andre & Cie S.A. v Orient Shipping (Rotterdam) B.V. (“The Laconian Confidence”) [1997] 1 Lloyd’s Rep
139.
Associated British Ports v Tata Steel UK Limited [2017] EWHC 694 (Ch).
Attica Sea Carriers Corporation v Ferrostaal Poseidon Bulk Reederei G.m.b.H. (“The Puerto Buitrago”)
(C.A.) [1976] 1 Lloyd's Rep. 250.
Baird v Hastings [2015] 5 WLUK 107.
Belcore Maritime Corporation v F.Lli. Moretti Cereali S.P.A. (“The Mastro Giorgis”) [1983] 2 Lloyd’s
Rep 66.
Blue Sky One Ltd v Mahan Air [2009] EWHC 3314 (Comm).
Bremer Handelsgessellschaft mbH v Continental Grain [1983] 1 Lloyd’s Rep 269.
Bright v Barnsley District General Hospital NHS Trust [2004] 11 WLUK 781.
British Movietonenews Ltd v London and District Cinemas [1952] AC 166.
Bulfracht (Cyprus) Ltd v Boneset Shipping Co. Ltd (“The Pamphilos”) [2002] 2 Lloyd’s Rep 681.
Bulfracht (Cyprus) Ltd. v Boneset Shipping Co. Ltd. (“The Pamphilos”) [2002] 2 Lloyd's Rep. 681.
C. Czarnikow, Ltd. v Koufos (“The Heron II”) [1967] 2 Lloyd's Rep. 457.
Team 12 Claimant’s Memorandum
vi
C.A. Venezolana De Navegacion v Bank Line “(The Roachbank)” 2 Lloyd’s Rep 498.
Cable & Wireless plc v IBM United Kingdom Ltd [2002] 1 All E.R. (Comm) 1041.
Ceylon v Chandris [1965] 2 Lloyd's Rep. 204.
Chandris v Isbrandtsen-Moller Co Inc [1949/50] 83 Lloyd’s Rep 385.
Clea Shipping Corporation vBulk Oil International Ltd. (“The Alaskan Trader”) (No. 2) [1983] 2
Cobelfret Bulk Carriers NV v Swissmarine Services SA [2010] 1 Lloyd's Rep. 317.
Compagnie Noga D’importation Et D’exportation SA v Abacha & Ors [2003] EWCA Civ 1100.
Continental Pacific Shipping Ltd. v Deemand Shipping Co. Ltd. (“The Lendoudis Evangelos II”) [1997] 1
Lloyd’s Rep 404.
Davies v Taylor [1974] AC 207.
Electrical Wholesalers Ltd v Alcatel Submarine Networks Ltd [1999] 2 Lloyd’s Rep 423.
Emirates Trading Agency v Prime Mineral Exports Private Ltd [2014] 2 Lloyd’s Law Reports 457.
Exportadora Valle de Colina SA v AP Moller-Maersk A/S [2010] EWHC 3224 (Comm).
Five Oceans Salvage Consultants Ltd v Perla Navigation Ltd [2013] EWHC 4055 (Comm).
Forrest v Glasser [2006] 2 Lloyd’s Law Rep 392.
Gator Shipping Corporation v Trans-Asiatic Oil Ltd. S.A. And Occidental Shipping Establishment (“The
Odenfeld)” [1978] 2 Lloyd's Rep. 357
Gosse Millerd, Ltd., And Another vCanadian Government Merchant Marine, Ltd. (“The Canadian
Highlander”) [1927] 28 Ll. L Rep 88.
Hadley v Baxendale (1854) EWHC J 70.
Hall v Wright [1859] 11 WLUK 133.
Hans Peter Moller and Others v Jecks [1865] 144 E.R. 815.
Hayden v Maidstone and Turnbridge Wells NHS Trust [2016] EWHC 3276.
Hayes v South East Coast Ambulance Service [2015] EWHC 18.
Hyundai Merchant Marine Co Ltd v Furness Withy (Australia) Pty (The Doric Pride) [2005] EWHC 945
(Comm).
Imperator I Maritime Co v Bunge SA (The Coral Seas) [2016] EWHC 1506.
Team 12 Claimant’s Memorandum
vii
ING Bank NV v Ros Roca SA [2011] EWCA Civ 353.
Intense Investments Ltd v Development Ventures Ltd [2006] EWHC 1586 (TCC).
IPSOS S.A. v Dentsu Aegis Network Limited (formerly Aegis Group plc) [2015] EWHC 1171 (Comm).
Isabella Shipowner Sa v Shagang Shipping Co Ltd “(The Aquafaith)” [2012] 2 Lloyd’s Rep 61.
Japy Freres and Co. v Sutherland & Co. (C.A.) [1921] 6 Lloyd's Rep. 381.
Kuwait Oil Tanker Co SAK & Anor. v Qabazard [2002] EWCA Civ 34.
Laminates Acquisitions v BTR Australia Limited [2004] 1 All ER (Comm) 737.
Losinjska Plovidba Brodarstovo Dd v Valfracht Maritime Co. Ltd. And Another (“The Lipa”) [2009] 2
Lloyd's Rep 17.
Lyle Shipping Co. v Cardiff Corporation [1899] 5 Com. Cas. 87.
Man Nutzfahrzeuge AG v Freightliner Ltd [2007] EWCA Civ 910.
Mareva Navigation Co. Ltd. v Canaria Armadora S.A. (“The Mareva A.S.”) [1977] 1 Lloyd's Rep. 368.
Marsden v Barclays Bank plc [2016] 2 Lloyd’s Rep 420.
McDonald v Dennys Lascelles Ltd [1933] 48 CLR 457; Johnson v Agnew [1980] AC 367.
Metal Market OOO v Vitorio Shipping Co Ltd [2013] 2 Lloyd’s Rep 541.
Minerva Navigation Inc v Oceana Shipping Ag (“The Athena”) [2013] 2 Lloyd’s Rep 673.
MSC Mediterranean Shipping Co SA v Cottonex Anstalt [2016] 2 Lloyd’s Rep 494.
Nippon Yusen Kaisha Ltd. v Scindia Steam Navigation Co. Ltd. (“The Jalagouri”) [2000] 1 Lloyd's Rep.
515.
Ocean Marine Navigation Limited v Koch Carbon Inc. (“The Dynamic”) [2003] 2 Lloyd’s Rep 693.
Papera Traders Co. Ltd. And Others v Hyundai Merchant Marine Co. Ltd. And Another (Eurasian Dream)
(No. 2) [2002] 1 Lloyd's Rep. 719.
Patience (George) v Mackenzie, [1912] S.C. (J.) 7.
Petroleum Oil and Gas Corporation Of South Africa (Pty) Ltd v Fr8 Singapore Pte Ltd, The [2008] EWHC
2480 (Comm).
Rijn, The [1981] 2 Lloyd’s Rep 267 (Q.B.).
Robin Hood Flour Mills, Ltd. v N. M. Paterson & Sons, Ltd. (The Farrandoc) [1967] 1 Lloyd's Rep. 232.
Team 12 Claimant’s Memorandum
viii
Rock Advertising Limited v MWB Business Exchange Centres Limited [2018] UKSC 24.
ROK Plc (in administration) v S Harrison Group Ltd [2011] EWHC (Comm).
Royal Greek Government v Minister of Transport (“The Illissos”) [1949] 1 KB 7 (Court of Appeal).
Royal Greek Government v Minister of Transport (The Ann Stathatos) [1949] 83 Ll L Rep 228.
Scott v United States [2018] EWHC 2021 (Admin).
Sempra Metals Ltd (formerly Metallgesellschaft Ltd) v Inland Revenue Commissioners and another [2008]
Bus. L.R. 49.
Sempra Metals Ltd v Inland Revenue [2007] UKHL 4.
Sidermar S.p.A. vApollo Corporation (“The Apollo”) [1978] 1 Lloyd’s Rep 200.
Slack v Cumbria CC [2009] EWCA Civ 293.
Spiro v Lintern [1973] 1 WLR 1002.
Summit Navigation Ltd v Generali Romania Asiguarare Reasiguarare SA [2014] EWHC 398 (Comm).
Supershield Ltd v Siemens Building Technologies FE Ltd [2010] 1 Lloyd’s Rep 349.
Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd (“The Sylvia”) 2 Lloyd’s Rep 81.
TCB Ltd v Gray [1986] Ch 621.
Transfield Shipping Inc v Mercator Shipping Inc (“The Achilleas”) [2008] 2 Lloyd’s Rep 275.
Transgrain Shipping (Singapore) Pte Ltd v Yangtze Navigation (Hong Kong) Co Ltd (“Mv Yangtze Xing
Hua”) 1 Lloyd's Rep. 330.
Transpetrol Maritime Services Ltd v SJB (Marine Energy) BV [2012] 1 Lloyd's Rep 564.
Triad Shipping Co. v Stellar Chartering & Brokerage Inc. (“The Island Archon”) [1994] 2 Lloyd's Rep.
227.
Victoria Laundry v Newman Industries, Ltd. [1949] 2 K.B. 528.
Washington, The [1976] 2 Lloyd's Rep 453.
Whistler International Ltd. v Kawasaki Kisen Kaisha Ltd. (“The Hill Harmony”) [2001] 1 Lloyd's Rep.
147.
C. Statutes and Regulations
Arbitration Act 1996 (United Kingdom).
Team 12 Claimant’s Memorandum
ix
IMO Resolution A.1052(27) on Procedures for Port State Control, 2011.
Maritime and Port Authority Of Singapore – Port Marine Circular No. 11 of 2014.
Panama Canal Advisory to Shipping No. A-22-2014 dated September 23, 2014 regarding Measures for the
Prevention and Protection against Ebola Virus Disease (EVD).
United States Coast Guard Sector New Orleans – Marine Safety Information Bulletin No. 1317 ‘Vessel
Reporting Requirements from Countries Posing a Serious Ebola Threat’ dated 10 October 2014.
Prevention and Control of Disease Regulation Cap. 599, section 7, L.N. 203 of 2008 (Hong Kong).
D. Other
New York Produce Exchange 2015 Time Charterparty Form.
Inter-Club New York Produce Exchange Agreement/Inter-Club Agreement per September 2011.
Re: South American P&I Club Circular 01/14 – Ebola – South American Countries.
Team 12 Claimant’s Memorandum
x
LIST OF ABBREVIATIONS
Abbreviation Term
A.C. Law Reports Appeal Cases
Admin Administrative Court
All E.R. All England Law Reports
C.A. English Court of Appeals
Cargo 8,600mt of loose-leaf English tea carried by the
Vessel
Charterparty The time charterparty between Claimant and
Respondent
Claimant Panther Shipping Inc., Panther Shipping, Inc., 80
Broad Street, Monrovia, Liberia
Comm Commercial Court
EWCA England and Wales Court of Appeals
EWHC England and Wales High Court
Fixture Recap End of negotiations between Claimant and
Respondent which signifies the conclusion of the
Charterparty
HCO Hull cleaning operations
ICA Inter-Club Agreement as amended September 2011
IMO International Maritime Organisation
KB King’s Bench
Ll. L. Rep. Lloyd’s Law Report
Lloyd’s Rep Lloyd’s Law Report
Master Captain Rogers, Master of the M/V Thanos Quest
Moot Problem International Maritime Law Arbitration Moot 2019
Moot Scenario (V3) Released 25 March 2019
NYPE15 New York Produce Exchange 2015 Time
Charterparty Form
Preliminary Report Report by Mekon Surveyors published on 7 July
2016
Team 12 Claimant’s Memorandum
xi
QB Queen’s Bench Division
Receivers Hawkeye Import & Export Pty, Wahanda, Bao
Kingdom
Respondent Omega Chartering Limited, P.O. Box 911, Vaduz,
Liechtenstein
Rider Clauses Omega Rider Clauses as negotiated between
Claimant and Respondent in the Fixture Recap
S.C. Scottish Council
UKHL United Kingdom House of Lords
UKSC United Kingdom Supreme Court
Vessel M/V Thanos Quest
W.L.R. Western Law Reports
WPS Wahanda Port Services
Team 12 Claimant’s Memorandum
1
SUMMARY OF FACTS
1. On 18 March 2016, Panther Shipping, Inc. (“Claimant”), owners of the M/V THANOS QUEST
(“Vessel”) entered into a time charterparty with Omega Chartering Ltd. (“Respondent”)
(collectively, the “Parties”) for the delivery of 8,600mt of tea (“Cargo”) from West Coast,
Challaland (“West Coast”) to Wahanda, Bao Kingdom (“Wahanda”) for a period of ‘about 50-
55 days without guarantee’ on an amended NYPE15 Form with Rider Clauses (“Charterparty”).
The Vessel was delivered on 29 March 2016 at West Coast.
2. On 18 April 2016, 100 cases of Ebola virus disease (“Ebola”) were discovered in West Coast.
Nevertheless, Respondent persisted on continuing the shipment of the Cargo and the Vessel
departed on 20 April 2016. The Vessel arrived at Wahanda on 7 May 2016 where she was detained
by Wahanda Port Services (“WPS”) for fear of Ebola. During the detention, the Vessel’s hull
began to foul with marine growth. When the Vessel’s hull is fouled, Respondent is obliged to
perform hull cleaning operations (“HCO”).
3. On 15 June 2016, Claimant entered into a time charter with Champion Chartering Corp.
(“Champion”) for a period of two years plus a further two years on Champion’s option with a
delivery window of 22-28 June 2016 (“Next Fixture”). The Next Fixture is a medium-term
charter, something Claimant have been insistently looking for.
4. The Vessel was released from detention on 26 June 2016, where she proceeded to unload the
Cargo. On 27 June 2016 it was revealed that after Respondent ordered ballasting, Cargo Hold No.
2 was flooded, causing damage to the Cargo. As the Vessel was still performing discharge
operations up to 30 June 2016, Respondent did not redeliver the Vessel to Claimant. This caused
Claimant to miss the Next Fixture.
5. Respondent redelivered the Vessel on 30 June 2016 with the hull severely fouled. Claimant opted
to clean the hull at South Island at a price of USD96,567.42, however, Respondent refused to pay.
On 4 July 2016, Claimant entered into another charter with Fairwind International BVI
Team 12 Claimant’s Memorandum
2
(“Fairwind”) with a delivery window of 4-6 July 2016 for a period of ‘about 50-55 days’
(“Replacement Fixture”).
6. Respondent’s actions, which have led to the loss of Next Fixture and the unpaid costs in relation
to HCO, has led Claimant to initiate arbitration proceedings on 16 October 2018.
ARGUMENTS FOR CLAIMANT
SUBMISSIONS ON CLAIMS
ARGUMENTS ON THE MERITS OF THE CLAIM
I. RESPONDENT IS LIABLE FOR ALL LOSSES ARISING FROM MISSING THE NEXT
FIXTURE
7. Claimant had entered into a single-trip time charterparty with a period of ‘50-55 days without
guarantee’ with Respondent for the shipment of Cargo1 from West Coast to Wahanda on 18 March
2016.2 The Vessel was delivered on 28 March 2016 at West Coast.3 In the course of the
Charterparty, on 15 June 2019, Claimant entered into the Next Fixture,4 which had a delivery
window of 22-28 June 2016.5 However, Respondent failed to redeliver the Vessel during the
delivery window. As a result, Champion cancelled the Next Fixture.6
8. In their Defence Submissions, Respondent admitted that they had breached obligations of late
redelivery though are not liable for the losses arising out of it.7 However, Claimant asserts that
Respondent shall remain fully liable for the entire loss of the Next Fixture, as (A) Charter period
of ‘about 50-55 days without guarantee’ was not an honest estimate, (B) Respondent had assumed
responsibility for the loss of the Next Fixture, (C) Claimant’s actions of concluding the Next
1 Moot Problem, pp. 46-47. 2 Moot Problem, pp. 2-5. 3 Ibid. 4 Moot Problem, pp. 30-33. 5 Moot Problem, pp. 30-33. 6 Moot Problem, p. 40. 7 Moot Problem, p. 72.
Team 12 Claimant’s Memorandum
3
Fixture during quarantine was reasonable, and (D) There was a substantial chance for Champion
to extend the duration of the Charterparty.
A. Charter period of ‘about 50-55 days without guarantee’ was not an honest estimate
9. Respondent may argue that the charter period of ‘50-55 days without guarantee’ exempts
Respondent from liability for the late redelivery of the Vessel. In Lendoudis Evangelos II,8 even
if the charter period was followed by ‘without guarantee,’ charterers are still obliged to provide
an honest estimate at the time of conclusion.9 However, if an event inhibits the performance of an
obligation and the parties did not terminate the contract, the said obligations will be adjusted as to
give the contract commercial sense.10
10. In the present dispute, Respondent’s decision to continue the voyage after the Ebola outbreak had
made the previous estimate of ‘about 50-55 days without guarantee’ commercially insensible and
thus obliges Respondent to provide a new charter period in light of the circumstances surrounding
the Charterparty.11 Respondent as a commercial man12 must have known that sailing from an
Ebola-affected port would prolong the Charterparty significantly as the Vessel would be detained
by port authorities.13 Claimant, as shipowners, will rely on Respondent’s original estimate to plan
future fixtures. Consequently, as Respondent did not provide a charter period in light of the new
circumstances of the Charterparty, the ‘about 50-55 days without guarantee’ charter period was
not an honest estimate and therefore Respondent should be liable for any losses arising out of late
redelivery.
8 The Lendoudis Evangelos II [1997] 1 Lloyd’s Rep. 404. 9 Japy Freres and Co. v Sutherland & Co. (C.A.) [1921] 6 Lloyd's Rep. 381; The Lendoudis Evangelos II [1997] 1 Lloyd’s
Rep 404; The Lipa [2001] 2 Lloyd's Rep 17; Transpetrol Maritime Services Ltd v SJB (Marine Energy) BV [2012] 1
Lloyd's Rep 564. 10 Hall v Wright [1859] 11 WLUK 133; British Movietonenews Ltd v London and District Cinemas [1952] AC 166; Bremer
Handelsgessellschaft mbH v Continental Grain [1983] 1 Lloyd’s Rep 269. 11 The Lendoudis Evangelos II [1997] 1 Lloyd’s Rep. 404. 12 The Achilleas [2008] 2 Lloyd's Rep 275; Sylvia Shipping Co Ltd v Progress. Bulk Carriers Ltd (The Sylvia) [2010] 2
Lloyds Rep 81; Supershield Ltd v Siemens Building Technologies FE Ltd [2010] 1 Lloyd’s Rep 349. 13 Singapore: 60 days (Maritime And Port Authority Of Singapore – Port Marine Circular No. 11 of 2014); Argentina: 30
days, Brazil: 21 days, Uruguay: 21 days (Re: South American P&I Club Circular 01/14 – Ebola - South American
Countries).
Team 12 Claimant’s Memorandum
4
B. Respondent had assumed responsibility for the Loss of Next Fixture
11. A charterer cannot be liable for losses that are too remote unless they had assumed responsibility
of it.14 For a charterer to assume responsibility of a missed fixture after late redelivery, they must
have, at the conclusion of the contract, enough knowledge to contemplate the extent of the loss or
the understanding that redelivering late would put the vessel into poor market conditions.15
12. In the present dispute, Respondent had assumed responsibility for the entire price of the Next
Fixture as (i) Respondent had knowledge to contemplate the extent of the loss of missing the Next
Fixture and (ii) Respondent understood that late redelivery would cause extraordinary loss for
Claimant given the poor market conditions.
(i) Respondent had knowledge to contemplate the extent of the loss
13. Claimant submits that there is sufficient information for Respondent to know the extent of the loss
arising out of missing the Next Fixture. On 1 March 2018, Claimant’s Chatter post stated that
Claimant is ‘looking to fix for 3-5 years’,16 that being a medium-term charter.17
14. In The Achilleas,18 the assessment of whether a charterer is liable for a missed fixture is determined
based on the knowledge of the charterer at the time of conclusion so long as the charterer could
contemplate the extent of the loss.19 As long as the charterer could predict the extent of the loss at
the time of the conclusion of the Charterparty, the Charterer is deemed to have assumed
responsibility. As such, the knowledge of the charterer would lead to the charterer knowing that
there is a possibility of a subsequent fixture and the extent of the loss of missing the subsequent
fixture.20
14 Hadley v Baxendale (1854) EWHC J 70; Victoria Laundry v Newman Industries, Ltd. [1949] 2 K.B. 528; The Heron II
[1967] 2 Lloyd’s Rep 555; The Achilleas [2008] 2 Lloyd’s Rep 275; The Sylvia [2010] 2 Lloyds. Rep 81; Supershield Ltd
v Siemens Building Technologies FE Ltd [2010] 1 Lloyd’s Rep 349. 15 The Achilleas [2008] 2 Lloyd's Rep 275; The Sylvia [2010] 2 Lloyds Rep 81; Supershield Ltd v Siemens Building
Technologies FE Ltd [2010] 1 Lloyd’s Rep 349. 16 Moot Problem, p. 1. 17 Jie Liu (2001) Chartering policies in the dry bulk market, World Maritime University, pp. 33-35. 18 The Achilleas [2008] 2 Lloyd’s Rep 275. 19 Victoria Laundry v Newman Industries, Ltd. [1949] 2 K.B. 528; Heron II [1967] 2 Lloyd’s Rep 555; The Achilleas
[2008] 2 Lloyd’s Rep 275. 20 Ibid.
Team 12 Claimant’s Memorandum
5
15. In the present dispute, there are three reasons why Respondent’s knowledge was sufficient to know
the extent of the loss of missing the Next Fixture and therefore knew the possibility of the Next
Fixture. Firstly, Respondent, as a charterer, knew the market rate of hire.21 Thus, Respondent could
contemplate the extent of loss of missing a medium-term charter. Secondly, time charters are of
standard form terms, which means that the terms of one charterparty to another would not differ
drastically, especially with the popular usage of the NYPE form.22 Thirdly, Respondent
understood, through Chatter, that Claimant was looking for a medium-term charter since 1 March
2016,23 and therefore knew that Claimant would conclude a medium-term charter had there been
an opportunity to do so.
16. Under the three reasons above, Respondent had sufficient information to know the possibility of
a subsequent fixture and therefore knew the extent of loss of missing the Next Fixture.
Conclusively, Respondent had assumed responsibility for missing the Next Fixture and
accordingly Respondent shall be held liable for the loss arising out of missing the Next Fixture.
(ii) Respondent understood that late redelivery would place Claimant into poor market
conditions
17. Respondent may argue that as a result of their late redelivery, Respondent would only be liable for
the difference between the rate of hire of the current charter and the market rate of hire.24 However,
in The Achilleas,25 it was held that if charterers knew, at the time of conclusion, that late redelivery
would put shipowners into a poor market position, then charterers are liable for the entire contract
price of any fixture missed due to the late redelivery.26
21 The Achilleas [2008] 2 Lloyd's Rep 275; The Sylvia [2010] 2 Lloyds Rep 81. 22 Soyer, B. and Tettenborn, A. (2017). Charterparties: Law, Practice and Emerging Legal Issues. 1st ed. London: Informa
Law from Routledge, p. 67. 23 Moot Problem, p. 1. 24 The Achilleas [2008] 2 Lloyd’s Rep 275. 25 Ibid. 26 Ibid.
Team 12 Claimant’s Memorandum
6
18. In the present dispute, an Ebola outbreak occurred in West Coast on 18 April 2016.27 Nevertheless,
on 20 April 2016, Respondent persisted on sailing to Wahanda,28 causing the Charterparty to be
varied by operation of law29 and therefore considered as a newly-concluded Charterparty.30
Consequently, there is a risk of detention of the Vessel, leading to the late redelivery of the
Vessel.31 As such, Respondent must have understood that late redelivery would lead Claimant to
miss an extraordinary opportunity as any employment would be difficult to find for Claimant.
19. Charterers are less inclined to charter vessels who have gone to Ebola-affected ports as major
world ports, such as Panama Canal32 and New Orleans, 33 both being major world trading hubs,
would detain vessels even if the vessels had already obtained clearance from other ports. Having
unhindered access to major world ports are essential to time charters as it is required for any time
charter to be performed with utmost despatch. As the Vessel lacks unhindered access to major
world ports, potential charterers are less inclined to charter the Vessel. Therefore, Respondent’s
late redelivery rendered the market for the Vessel’s services poor.
20. In conclusion, Respondent’s late redelivery led Claimant to miss the Next Fixture and therefore
exposed Claimant to poor market conditions. Accordingly, Respondent shall be held liable for the
entire contract price of the Next Fixture.
C. Claimant’s actions of concluding the Next Fixture during quarantine was reasonable
21. Respondent may argue that they are not liable for the losses arising out of missing the Next Fixture
as Claimant caused the loss by concluding the Next Fixture under detention. However, Claimant
27 Moot Problem, p. 22. 28 Moot Problem, p. 81. 29 See, supra, ¶9-10. 30 McDonald v Dennys Lascelles Ltd [1933] 48 CLR 457; Johnson v Agnew [1980] AC 367; Compagnie Noga
D’importation Et D’exportation SA v Abacha & Ors [2003] EWCA Civ 1100; Slack v Cumbria CC.
[2009] EWCA Civ 293; See, supra, ¶8-9. 31 Maritime and Port Authority of Singapore – Port Marine Circular No. 11 of 2014: Vessels having called at Ebola ports
in last 60 days will be detained; South American P&I Club Circular 01/14: Argentina, Brazil, Uruguay will detain ships
coming from Ebola ports; Panama Canal Advisory to Shipping No. A-22-2014: Vessels who had called at Ebola ports in
last 10 ports of call shall be detained. 32 Panama Canal: Advisory to Shipping No. A-22-2014 dated September 23, 2014 regarding Measures for the Prevention
and Protection against Ebola Virus Disease (EVD). 33 United States Coast Guard Sector New Orleans – Marine Safety Information Bulletin No. 1317 ‘Vessel Reporting
Requirements from Countries Posing a Serious Ebola Threat’ dated 10 October 2014.
Team 12 Claimant’s Memorandum
7
may still recover losses as the conduct of concluding the next fixture was reasonable.34 Deciding
whether a conduct is reasonable depends on each specific circumstance taking into account the
profitability of the shipowner.35
22. Taking into account the circumstances of the present dispute, it can be concluded that Claimant’s
actions in concluding the Next Fixture is reasonable. Firstly, Claimant has been looking for a
charter lasting 3-5 years for months.36 At the time, the Next Fixture was the only opportunity to
secure long-term employment, instead of going on consecutive spot-market charters.37 Secondly,
when concluding the Next Fixture, Claimant had already taken into account that the detention
would end soon. Claimant, as a reasonable businessman in the maritime industry, understood that
Ebola quarantines generally do not exceed 21-30 days,38 especially since the present quarantine
was merely based on a suspicion against two crew members with a common fever and not the
whole crew.39 Thirdly, had they not concluded the Next Fixture, it would be difficult to secure
another medium-term charter as the occurrence of Ebola affected the Vessel’s marketability.40
23. Conclusively, Claimant’s conclusion of the Next Fixture was done reasonably regardless of the
conclusion being done during the Vessel’s detention.
D. There was a substantial chance for Champion to extend the duration of the Charterparty
24. The duration of the Next Fixture is two years extendable for another two years based on a further
negotiation between Champion and Claimant.41 If a third party’s action denied someone the
opportunity to negotiate, that person may claim for the whole profits lost if they could prove that
there was a substantial chance for the negotiation to succeed.42 A substantial chance exists if the
34 Hans Peter Moller and Others v Jecks [1865] 144 E.R. 815; Lyle Shipping Co. v Cardiff Corporation [1899] 5 Com.
Cas. 87; MSC Mediterranean Shipping Co SA v Cottonex Anstalt [2016] 2 Lloyd’s Rep 494. 35 Lyle Shipping Co. v Cardiff Corporation [1900] 5 Com. Cas 87; Metal Market OOO v Vitorio Shipping Co Ltd [2013]
2 Lloyd’s Rep 541. 36 Moot Problem, p. 1. 37 Moot Problem, p. 1, 30. 38 Rathore KS, Keshari R, Rathore A, Chauhan D. A Review on Ebola Virus Disease. PharmaTutor. 2014;2(10):17–22;
Rothstein, Mark A. At Law: Ebola, Quarantine, and the Law. The Hastings Center Report 45, no. 1 (2015): 5-6. 39 Moot problem, p. 24. 40 See, supra, ¶13-16. 41 Moot Problem, p. 32. 42 Allied Maples Group Ltd v Simmons & Simmons [1996] C.L.C. 153; Albion Water Ltd v Dwr Cymru Cyfyngedid [2013]
3 WLUK 785; Baird v Hastings [2015] 5 WLUK 107.
Team 12 Claimant’s Memorandum
8
circumstances of the negotiation and the attitude of the opposing party were favourable to that
person.43
25. In the present dispute, a substantial chance existed for Champion to extend for another two years.
Firstly, it would have been advantageous for Champion to extend the Next Fixture because a
medium-term charter’s purpose is to escape market volatility and to gain as much profit as
possible.44 Champion had the opportunity to enjoy a fixed rate of USD10,500 per day45 without
being subject to market volatility.46 Further, Champion could enjoy the use of a new Ice-class IA
vessel, which means that it would be less likely for her to have faulty equipment.47 Secondly, the
attitude of Champion was favourable to Claimant, showing that there was a substantial chance of
them extending the Next Fixture. This is evident from Champion willing to conclude the Next
Fixture while the Vessel was still in quarantine and having called recently at an Ebola-affected
port.48
26. Since the Next Fixture was highly-profitable for Champion and Champion’s attitude was
favourable, there exists a substantial chance for the Next Fixture to be extended to four years.
Accordingly, Respondent is liable for the full potential four years of the Next Fixture.49
27. In conclusion, Respondent is liable for the whole loss of the Next Fixture. Respondent had failed
to give an honest estimate of the charter period of ‘about 50-55 days without guarantee’ provided
in the Fixture recap, and therefore Respondent is liable for the losses incurred of missing the Next
Fixture.50 Respondent is also liable for general business profits as they could have reasonably
contemplated the Vessel’s marketability after sailing from Ebola-affected Wahanda51 or at least
43 Davies v Taylor [1974] AC 207; Bright v Barnsley District General Hospital NHS Trust [2004] 11 WLUK 781; Hayes
v South East Coast Ambulance Service [2015] EWHC 18 (QB); Hayden v Maidstone and Turnbridge Wells NHS Trust
[2016] EWHC 3276 (QB). 44 Jie Liu (2001) Chartering policies in the dry bulk market, World Maritime University, pp. 33-35. 45 Moot Problem, p. 32. 46 See fn. 40. 47 Moot Problem, p. 1. 48 Moot Problem, p. 30. 49 Davies v Taylor [1974] AC 207. 50 See supra, ¶8-11. 51 See supra, ¶14-19.
Team 12 Claimant’s Memorandum
9
would have known a medium-term fixture would take place pursuant to the Chatter account.52
Claimant’s conclusion of the Next Fixture even during quarantine does not render the losses
unrecoverable, as it was made within good reason.53 In addition, Respondent is liable for the full
loss of four years’ worth of profit with the extension of the Next Fixture having a substantial
chance.54 Under these reasons, Respondent is liable through and through for the loss of general
business profits incurred as a result of late redelivery causing Claimant to miss the Next Fixture.
II. RESPONDENT IS LIABLE FOR ALL COSTS IN CONNECTION WITH HCO
28. On 30 June 2016, Respondent redelivered the Vessel to Claimant with her hull severely fouled,55
as evidenced by pictures provided by the Master.56 Pursuant to Clause 83 of the Rider Clauses,
after the Vessel stayed idly in port for over 30 days in non-tropical waters, the Parties shall arrange
a survey to check whether the hull had been fouled. If the hull is proven to be fouled, then
Respondent is obliged to perform HCO.57 If the hull was fouled and Respondent is prevented to
clean the hull, the Parties are to agree on a lump sum amount pursuant to the needs of HCO.58
29. Claimant submits that Respondent had breached their obligations of HCO and is liable for all costs
in relation to HCO because (A) Respondent’s obligations for HCO had arisen pursuant to Clause
83 of the Rider Clauses, (B) Claimant had legitimate interest to continue the Charterparty and
perform HCO at South Island, and (C) in any event, Respondent’s lump sum offers do not rescind
their obligations for HCO.
A. Respondent’s obligations for HCO had arisen pursuant to Clause 83 of the Rider Clauses
30. Clause 83(a) to (c) of the Rider Clauses stipulates that if, under Respondent’s orders, the Vessel
stays idle in port for over 30 days, then Respondent is obliged to perform HCO.59 Respondent may
52 See supra, ¶20-24. 53 See supra, ¶25-27. 54 See supra, ¶28-31. 55 Moot Problem, p. 42. 56 Moot Problem, p. 29. 57 Clause 83 of the Rider Clauses. 58 Clause 83 of the Rider Clauses. 59 Clause 83 of the Rider Clauses.
Team 12 Claimant’s Memorandum
10
argue that they did not order the prolonged stay.60 Although the long stay that led to fouling61 was
caused by detention and not express orders to stay for purposes of trading, Respondent remains
obliged to clean. This is because Respondent had accepted the risk of detention and quarantine as
result of them coming from Ebola-affected West Coast.62
31. Charterers are to bear the risk resulting from their orders.63 In the present dispute, Respondent,
upon ordering the Vessel to sail to Wahanda,64 understood that they would eventually end up in
detention. Multitudes of P&I clubs and governments had given notices and circulars since the 2014
Ebola Crisis that vessels previously calling Ebola-affected ports will be detained and
quarantined.65 Respondent must have known this and therefore had accepted the risk of being
detained and anything in result of it. Since Respondent’s orders had resulted in hull fouling,
Respondent’s obligations for HCO had arisen.
32. Respondent may argue that since the Charterparty is a single-trip time charter, Claimant had
accepted the risk of being detained as shipowners are to have assented to the risk of any ports
specified in the Charterparty.66 In the present dispute, although the Charterparty is a single-trip
time charter,67 Claimant had not accepted the risk of detention at the time of the conclusion of this
Charterparty on 18 March 2016 because the Ebola outbreak had not taken place in West Coast and
thus Respondent may not deny that HCO obligations had arisen.
33. Conclusively, as Respondent decided to keep sailing from West Coast after an Ebola outbreak,
Respondent had accepted risk of being detained which would lead to hull fouling. Consequently,
60 The Pamphilos [2002] 2 Lloyd's Rep. 681; See also Royal Greek Government v Minister of Transport (The Ann
Stathatos) [1949] 83 Ll L Rep 228; The Rijn [1981] 2 Lloyd’s Rep 267 (Q.B.); The Island Archon [1994] 2 Lloyd’s Rep
227. 61 Moot Problem, p. 34. 62 Hyundai Merchant Marine Co Ltd v Furness Withy (Australia) Pty (The Doric Pride) [2005] EWHC 945 (Comm). 63 The Island Archon [1994] 2 Lloyd’s Rep 227; The Pamphilos [2002] 2 Lloyd's Rep. 681; Transgrain Shipping
(Singapore) Pte Ltd v Yangtze Navigation (Hong Kong) Ltd [2017] EWCA Civ 2107. 64 Moot Problem, p. 81. 65 Maritime And Port Authority Of Singapore – Port Marine Circular No. 11 of 2014: Vessels having called at Ebola ports
in last 60 days will be detained; South American P&I Club Circular 01/14: Argentina, Brazil, Uruguay will detain ships
coming from Ebola ports; Panama Canal Advisory to Shipping No. A-22-2014: Vessels who had called at Ebola ports in
last 10 ports of call shall be detained. 66 Hyundai Merchant Marine Co Ltd v Furness Withy (Australia) Pty (The Doric Pride) [2005] EWHC 945 (Comm). 67 Moot Problem, pp. 2-4.
Team 12 Claimant’s Memorandum
11
Respondent’s orders to sail to Wahanda under Ebola conditions fulfils ‘charterers’ orders’ under
Clause 83(a).68 This, and over 30 days’ idle stay in berth,69 leads to the conclusion that Respondent
is in fact obliged to perform HCO.
B. Claimant had legitimate interest to continue the Charterparty and perform HCO at
South Island
34. If a vessel is prematurely redelivered by a charterer before all obligations had been exercised, a
shipowner may refuse the redelivery and keep the charter alive until all or those obligations are
exercised.70 In other words, a shipowner may refuse a premature redelivery if they had legitimate
interest to continue the contract.71
35. In the present dispute, when the Vessel was redelivered on 30 June 2016, Claimant opted to
continue the Charterparty pursuant to the immediate needs of HCO, an obligation Respondent
failed to perform as they redelivered the Vessel without any consideration of the hull being
fouled.72 Accordingly, Claimant is entitled for all costs in relation to HCO as Claimant had
legitimate interest to refuse redelivery and keeping the Charterparty alive as (i) accepting the
redelivery and claiming damages would not be an adequate remedy and (ii) Claimant’s intentions
were not perverse.73
(i) Accepting the redelivery and claiming damages would not be an adequate remedy
36. In cases of premature redelivery, accepting the redelivery and claiming damages would not be an
adequate remedy if the redelivering party had terminated obligations that must be exercised
immediately or otherwise cause injury to the other party.74 In the Aquafaith,75 damages were not
an adequate remedy when a charterer redelivered a vessel prematurely and the court held that
68 Clause 83 of the Rider Clauses. 69 In fact, over 51 days from 7 May to 26 June 2016. 70 The Puerto Buitrago [1976] 1 Lloyd’s Rep 250; The Odenfeld [1978] 2 Lloyd’s Rep 357; The Alaskan Trader (No 2)
[1983] 2 Lloyd’s Rep 645; The Dynamic [2003] 2 Lloyd’s Rep 693; The Aquafaith [2012] 2 Lloyd’s Rep 61. 71 Ibid. 72 Moot Problem, pp. 43-45. 73 The Puerto Buitrago [1976] 1 Lloyd’s Rep 250; The Odenfeld [1978] 2 Lloyd’s Rep 357; The Alaskan Trader (No 2)
[1983] 2 Lloyd’s Rep 645; The Dynamic [2003] 2 Lloyd’s Rep 693; The Aquafaith [2012] 2 Lloyd’s Rep 61. 74 White & Carter v McGregor [1962] A.C. 413; Reichman v Beveridge [2006] EWCA Civ 1659; The Aquafaith [2012] 2
Lloyd’s Rep 61. 75 The Aquafaith [2012] 2 Lloyd’s Rep 61.
Team 12 Claimant’s Memorandum
12
shipowners were entitled to all hire unpaid as shipowners were redelivered into a difficult market
and could not find a substitute fixture.
37. In the present dispute, HCO needed to be exercised immediately in cooperation with Respondent.76
If HCO was not done immediately, Claimant would fail to meet speed and consumption warranties
for future charterers or even cause the hull to be permanently fouled. 77 If speed and consumption
warranties were not met, the Vessel could be declared off-hire in the course of future
charterparties.78
(ii) Claimant’s intentions were not perverse
38. In the Aquafaith,79 a shipowner holding charterers to the contract for not paying the remaining 91
days of hire was not decided as ‘perverse’, because hire is an express and central obligation for
charterers in time charters.80 In the present dispute, the Parties, evidenced by their incorporation
of Clause 83 of the Rider Clauses within the Charterparty, also saw hull fouling as an inherent
threat to ordinary trading, and therefore a central obligation.81 Marine hull fouling is known to
cause vessels to consume much more fuel in order to reach speeds required in a time charter.82 If
such speed and consumption warranties were not fulfilled, shipowners would be held liable and
the vessel declared off-hire.83 Accordingly, Claimant’s intentions were merely to provide a
seaworthy vessel in service for subsequent shipping operations present in the Replacement
Fixture.84
39. Under the standards provided in (i) and (ii), Claimant had legitimate interest to keep the
Charterparty alive and is entitled to all costs in relation to HCO at South Island pursuant to
Claimant’s Final Hire Statement.85
76 Clause 83 of the Rider Clauses. 77 Moot Problem, p. 44 78 The Pamphilos [2002] 2 Lloyd’s Rep 681; Imperator I Maritime Co v Bunge SA (The Coral Seas) [2016] EWHC 1506. 79 The Aquafaith [2012] 2 Lloyd’s Rep 61. 80 Tankexpress v Compagnie Financière Belge des Pétroles (1948) 82 Lloyd’s Rep. 43. 81 Clause 83 of the Rider Clauses. 82 The Pamphilos [2002] 2 Lloyd’s Rep 681; Imperator I Maritime Co v Bunge SA (The Coral Seas) [2016] EWHC
1506. 83 The Pamphilos [2002] 2 Lloyd’s Rep 681. 84 Moot Problem, pp. 30-31. 85 Moot Problem, p. 53.
Team 12 Claimant’s Memorandum
13
C. Respondent cannot rely on lump sum offers to indemnify them from HCO Costs
40. Clause 83(d) of the Rider Clauses stipulates that if Respondent was prevented to clean, then the
Parties are to agree on a lump sum. Respondent stated that their lump sum offers were justified
and therefore they were no longer liable for HCO cost. However, Respondent cannot assert that
their lump sum offers were sufficient as to rescind their obligations of HCO, as (i) Respondent
was not prevented from performing HCO and (ii) alternatively, Clause 83(d) of the Rider Clauses’
lump sum provision is too uncertain to be enforced.
(i) Clause 83(d) of the Rider Clauses was amended
41. On 9 June 2016, both Parties had agreed to vary Clause 83(d) of the Rider Clauses as it was
impossible to perform HCO in Wahanda.86 If there was no specific mechanism to vary a contract,
then it may be varied through any means of acceptance.87 In the present dispute, such conditions
had been met by the Parties through e-mail correspondence.88 Claimant offered to clean at the next
convenient port and Respondent agreed so, stating that they would pay against the original
invoice.89 As a result, the amended terms gave an effect that Claimant would be the party arranging
HCO at the next convenient port and Respondent was the party to pay against any expenses as a
result of it.90
42. Additionally, Respondent is barred from saying otherwise. If a party had agreed to relinquish a
right under a contract, they are barred from demanding that same right in the future.91 Since
Respondent had agreed for all HCO arrangements to be done by Claimant and pay pursuant to
those arrangements, Respondent cannot assert that Claimant’s actions were non-contractual. Aside
from that, Respondent’s lump sums should be well disregarded due to them no longer having the
right to offer them.
86 Moot Problem, pp. 30-31. 87 Rock Advertising Limited v MWB Business Exchange Centres Limited [2018] UKSC 24; Scott v United States [2018]
EWHC 2021 (Admin). 88 Moot Problem, pp. 34-35. 89 Moot Problem, pp. 30-31. 90 Moot Problem, pp. 30-31. 91TCB Ltd v Gray [1986] Ch 621; Spiro v Lintern [1973] 1 WLR 1002; Intense Investments Ltd v Development Ventures
Ltd [2006] EWHC 1586 (TCC); ING Bank NV v Ros Roca SA [2011] EWCA Civ 353.
Team 12 Claimant’s Memorandum
14
43. To conclude, the Parties’ negotiations have come into the effect that the terms of Clause 83(d) had
been amended so that Claimant shall arrange all HCO actions and Respondent to pay any costs
incurred. Consequently, Respondent shall be liable for the entire costs of and in connection with
HCO in South Island.
(ii) Alternatively, Clause 83(d) of the Rider Clauses’ lump sum provision is too uncertain to be
enforced
44. Clause 83(d) of the Rider Clauses has a purpose to settle disagreements for HCO.92 In Associated
British Ports v Tata Steel UK Limited,93 it was established that settlement agreements may only
be enforceable if there was a clear mechanism on how disagreements would be settled. Without a
clear mechanism, neither party could enforce the clause and render the clause or sub-clause void.94
45. In the present dispute, Clause 83(d) of the Rider Clauses merely regulates the obligation of the
Parties to agree on a lump sum if Respondent was prevented to clean.95 It does not regulate how
lump sums are to be offered, on what basis, and what should happen if the Parties cannot come to
agreement. This shows the insufficiency of the mechanism if the Parties had come to disagreement,
as was evidenced by both Parties unable to come to agreement on the lump sum.96
46. Consequently, as Clause 83(d) of the Rider Clauses is unenforceable, Respondent is liable for all
costs in connection with HCO pursuant to Claimant's final hire statements after the Vessel had
been cleaned at South Island.
III. RESPONDENT IS LIABLE FOR COMPOUND INTEREST
47. Pursuant to Section 49(2) of the Arbitration Act 1996, the Tribunal has the authority to award
simple or compound interest in the absence of an agreement. With the non-existence of such
agreement, Respondent requests this Tribunal to readily grant compound interest on the whole part
92 Clause 83 of the Rider Clauses. 93 Associated British Ports v Tata Steel UK Limited [2017] 2 Lloyd's Rep. 11. 94 Cable & Wireless plc v IBM United Kingdom Ltd [2002] 1 All E.R. (Comm) 1041; Emirates Trading Agency v Prime
Mineral Exports Private Ltd [2014] 2 Lloyd’s Law Reports 457; Associated British Ports v Tata Steel UK Limited [2017]
EWHC 694 (Ch). 95 Clause 83 of the Rider Clauses. 96 Moot Problem, p. 42.
Team 12 Claimant’s Memorandum
15
of damages claimed above. In Man Nutzfahrzeuge AG v Freightliner Ltd,97 it is common for
arbitrators to award compound interest in the exercise of their powers under Section 49(3) of the
Arbitration Act 1996, as simple interest does not fully compensate the injured party for the loss it
suffered. It is also noted that compound interest is not restricted to non-payment of a debt, but also
may be granted upon losses caused by late payment of debt.98 For the reasons mentioned above,
pursuant to Section 49(3) of the Arbitration Act 1996, Respondent shall bear compound interest
to be paid in respect to the whole part of the claimed damages.
SUBMISSIONS ON COUNTERCLAIMS
ARGUMENTS ON THE ADMISSIBILITY OF THE COUNTERCLAIM
IV. RESPONDENT’S COUNTERCLAIM IS TIME-BARRED
48. The Charterparty incorporates the Inter-Club Agreement (“ICA”) by virtue of Clause 53 of the
Rider Clauses and Clause 27 of the NYPE15 Form. Clause 6 of the ICA provides that cargo claims
cannot be brought 24 months after the date of the delivery unless a proper notification had been
sent.99 Although Respondent attempted to give a notification on 27 June and 7 July 2016, Claimant
submits that Respondent is still time-barred as (A) Respondent did not fulfil the requirement under
Clause 6 of the ICA and (B) The notification did not fulfil its commercial purpose.
A. Respondent’s notifications did not fulfil the requirement for claims’ notification under
Clause 6 of the ICA
49. For a notification to be considered proper, they must comply with the requirements laid out in the
relevant claims’ notification clause.100 Clause 6 of the ICA,101 which governs time-bars, stipulates
97 Man Nutzfahrzeuge AG v Freightliner Ltd [2007] EWCA Civ 910; Sempra Metals Ltd v Inland Revenue [2007] UKHL
4; Marsden v Barclays Bank plc [2016] 2 Lloyd’s Rep 420. 98 Sempra Metals Ltd (formerly Metallgesellschaft Ltd) v Inland Revenue Commissioners and another [2008] Bus. L.R.
49. 99 Clause 6 of the ICA provides, “Recovery under this Agreement by an Owner or Charterer shall be deemed to be waived
and absolutely barred unless written notification of the Cargo Claim has been given to the other party to the charterparty
within 24 months of the date of delivery of the cargo or the date the cargo should have been delivered, […] Such
notification shall if possible include details of the contract of carriage, the nature of the claim and the amount claimed.” 100 Forrest v Glasser [2006] 2 Lloyd’s Law Rep 392. 101 Clause 6 of the ICA.
Team 12 Claimant’s Memorandum
16
that “[…] such notification shall if possible include details of the contract of carriage, the nature
of the claim and the amount claimed.” The word “shall if possible” in the clause entails that
Respondent is to provide all information available to them.102
50. In the present dispute, Respondent only provided the cause of the damage to Cargo and the total
amount of Cargo on board,103 therefore Respondent failed to provide the elements required within
Clause 6 of the ICA.104 Firstly, as the holder of bill of lading, that being the contract of carriage,
Respondent did not provide the details of the bill of lading.105 Secondly, Respondent failed to
provide an estimation of the amount claimed, despite having the knowledge of the possible
amount, during the discussions with the Receivers.106Thirdly, Respondent did not specify the
nature of the claim, which is the basis of the claim pursuant to the Charterparty.107 Conclusively,
Respondent’s notification is improper and therefore Respondent is barred from submitting any
Cargo claim.
B. Respondent’s notification did not fulfil its commercial purpose
51. Respondent may argue that the notification given on 27 June and 7 July 2016 had fulfilled the
commercial purpose.108 However, Respondent’s notification was not sufficient to fulfil the
commercial purpose of a claims’ notification pursuant to the claims’ notification clause that
requires the notification to specify certain matters. Such claims’ notification must both be
sufficiently informative and sufficiently certain that a claim has been made and not a possibility
of a claim may arise, so that the receiver of that notification could to take necessary action to
respond to the claim. 109
102 ROK Plc (in administration) v S Harrison Group Ltd [2011] EWHC (Comm). 103 Moot Problem, p. 46. 104 Clause 6 of the ICA. 105 Moot Problem, p. 49. 106 Moot Problem, p. 57. 107 Laminates Acquisitions v BTR Australia Limited [2004] 1 All ER (Comm) 737 108 Moot Problem, p. 47. 109 Electrical Wholesalers Ltd v Alcatel Submarine Networks Ltd [1999] 2 Lloyd’s Rep 423; IPSOS S.A. v Dentsu Aegis
Network Limited (formerly Aegis Group plc) [2015] EWHC 1171 (Comm); Laminates Acquisitions v BTR Australia
Limited [2004] 1 All ER (Comm) 737; Forrest v Glasser [2006] EWCA Civ 1086.
Team 12 Claimant’s Memorandum
17
52. In the present dispute, Respondent notification was neither sufficiently informative nor certain for
two reasons. Firstly, the preliminary report attached on the notification dated 7 July 2016 is not
sufficiently informative as it did not contain the amount of the Cargo claim.110 As a result,
Claimant could not take the necessary actions in response to the claim. These necessary actions
include preparing a settlement for Respondent, which would require the exact amount of the Cargo
claim. Secondly, the cargo claim is not certain as it informed that Receiver had not yet made a
claim. 111 Further, there is a substantial possibility of reconditioning the Cargo or selling it in a
damaged condition, 112 as the price of tea in Bao Kingdom was on the rise.113 It would not be wise
for Claimant commercial activity to try and prepare for a claim that might not arise.114
53. Conclusively, under these two reasons, the notification Respondent provided was neither
informative enough as it did not contain the amount claimed nor certain enough that a claim has
been made as the chance to recondition the Cargo or reselling them in a damaged condition exist.
Therefore, Respondent had not made a proper claim’s notification as the notification di not enable
Claimant to take necessary action to respond to the claim and thus Respondent is barred from
claiming Cargo damage.
ARGUMENTS ON THE MERITS OF THE COUNTERCLAIM
V. CLAIMANT IS NOT LIABLE FOR CARGO DAMAGE
54. Respondent’s e-mail on 27 June115 and 7 July 2016116 provided that the Cargo was damaged
because the Vessel’s crew had mistakenly pumped seawater into Cargo Hold No. 2 during
ballasting. Respondent may argue that Claimant should be fully liable or alternatively should be
liable for half of the Cargo damage under the ICA.117 However, Claimant is not liable for the
Cargo damage since (A) Cargo damage falls outside of the scope of Clause 8(a) of the ICA (B)
110 Moot Problem, p. 48. 111 Moot Problem, p. 45. 112 Moot Problem, p. 48. 113 Moot Problem, p. 23. 114 Electrical Wholesalers Ltd v Alcatel Submarine Networks Ltd [1999] 2 Lloyd’s Rep 423. 115 Moot Problem, p. 38. 116 Moot Problem, p. 46. 117 Moot Problem, p. 74.
Team 12 Claimant’s Memorandum
18
the ballasting operation does not fall within the scope of Clause8(b) of the ICA, and (C)
Respondent’s actions had caused the loss per Clause 8(d) of the ICA.
A. Cargo damage falls outside of the scope of Clause 8(a) of the ICA
55. Under Clause 8(a) of the ICA,118 Claimant would be fully liable for cargo damage if the damage
was caused by error in the management of the vessel. However, in the present dispute the damage
was not caused by errors in management of the vessel, but due to the crew’s mishandling of the
ballasting system, which does not constitute error in management of the vessel.
56. There are two types of management aboard a vessel.119 First is the management of cargo, which
encompasses any equipment in relation to the care of cargo. Second is management of the vessel,
which encompasses any equipment in relation to general vessel operations.120 In The Eternity,121
it was held that to determine whether a piece of equipment that could serve dual functions of both
management of cargo and management of vessel, it must be assessed by the primary function of
such equipment.
57. In the present dispute, the ballasting operation which led to Cargo damage falls outside errors in
management of the Vessel pursuant to Clause 8(a) of the ICA since the cause of Cargo damage
was an error in the operation of the Vessel’s valve system, which in turn had caused ballast water
to flood Cargo Hold No. 2.122 Although the primary purpose of ballasting is to stabilise the Vessel
on voyages, the Vessel’s interconnected internal valves allows floodable holds for ballasting
purpose which could be used to prevent cargo damage.123 When performing ballasting operations,
the valves are also used to protect the Cargo by channelling away the seawater from loaded Cargo
118 Clause 8 of the ICA. 119 The Canadian Highlander [1927] 28 Ll. L Rep 88; Ceylon v Chandris [1965] 2 Lloyd's Rep. 204; The Washington
[1976] 2 Lloyd's Rep; Exportadora Valle de Colina SA v AP Moller-Maersk A/S [2010] EWHC 3224 (Comm). 120 Ibid. 121 The Petroleum Oil and Gas Corporation Of South Africa (Pty) Ltd v Fr8 Singapore Pte Ltd (The "Eternity") [2008]
EWHC 2480 (Comm); applied in Cobelfret Bulk Carriers NV v Swissmarine Services SA (The Lowlands Orchid) [2010]
1 Lloyd's Rep. 317. 122 Moot Problem, p. 46. 123 See Clause 64 of the Rider Clauses.
Team 12 Claimant’s Memorandum
19
holds.124 Since ballasting was done when the Cargo had yet been discharged, then the primary use
of the valves was to prevent seawater from entering Cargo Hold No. 2 and thus protecting the
cargo from any direct damage. Therefore, errors in ballasting is considered as an error in
management of the cargo and not the vessel.
58. Conclusively, the cause of the damaged Cargo is not an error in management of the Vessel.
Therefore, the cause falls outside.
B. Ballasting operations do not fall within Clause 8(b) of the ICA
59. Clause 8(b) of the ICA regulates damages arising out the handling of cargo.125 Although the action
of ballasting is not mentioned in Clause 8(b) of the ICA, Respondent may argue that it falls under
‘other handling of cargo’ as the ballasting system was integrated with the cargo holds and
accordingly should be considered as part of ‘other handling of cargo.’126 Where a clause lists
specific terms and then refers to them in general, the general statement only applies certain terms
within the context of the preceding terms (ejusdem generis).127
60. The preceding terms within Clause 8(b) of the ICA are ‘loading, stowage, lashing, discharge,
storage’ of which all these are aspects of cargo handling strictly for Respondent to perform.128
Accordingly, with the existence of the phrase ‘other handling of cargo,’ Clause 8(b) of the ICA
refers only under handling of cargo that are under charterers’ responsibility. As such, this clause
does not encompass ballasting, as ballasting is Claimant’s responsibility to perform pursuant to
Clause 64 of the Rider Clauses.129 Conclusively, as Cargo damage was caused by ballasting related
124 Robin Hood Flour Mills, Ltd. v N. M. Paterson & Sons, Ltd. (The Farrandoc) [1967] 1 Lloyd's Rep. 232; Papera
Traders Co. Ltd. And Others v Hyundai Merchant Marine Co. Ltd. And Another (Eurasian Dream) (No. 2) [2002] 1
Lloyd's Rep. 719. 125 Clause 8(b) of the ICA stipulates that “Claims in fact arising out of the loading, stowage, lashing, discharge, storage
or other handling of cargo: 100% Charterers unless the words "and responsibility" are added in clause 8 or there is a
similar amendment making the Master responsible for cargo handling in which case: 50% Charterers 50% Owners”. 126 Clause 8 of the ICA. 127 Anderson v Anderson [1895] 1 QB 749; Patience (George) v Mackenzie, [1912] S.C. (J.) 7; Chandris v Isbrandtsen-
Moller Co Inc [1949/50] 83 Lloyd’s Rep 385. 128 Clause 8(a) of NYPE15: “Charterers shall perform all cargo handling, including but not limited to loading, stowing,
trimming, lashing, securing, dunnaging, unlashing, discharging, and tallying,”. 129 Clause 64 of the Rider Clauses.
Team 12 Claimant’s Memorandum
20
operations and not under any cause mentioned in Clause 8(b) of the ICA, Respondent cannot claim
under Clause 8(b) of the ICA.
C. Respondent’s actions had caused the Cargo damage per Clause 8(d) of the ICA
61. Clause 8(d) of the ICA stipulates that a party shall be fully liable for any cargo damages as a result
of that party’s ‘act or neglect.’130 Respondent may argue that the crew’s action of opening the
wrong valve had caused the loss and Claimant should be held liable as the crew was acting on
behalf of Claimant. However, in Transgrain Shipping v Yangtze Navigation,131 it was held that
charterers’ orders are considered an ‘act’ under Clause 8(d) of the ICA and the charterer is
considered to have accepted the risks in result of their orders.
62. In the present dispute, the ballasting ordered by Respondent, which led to Cargo damage, was
done in preparation of the Vessel’s departure to berth.132 Pursuant Clause 8(a) of NYPE15, the
Master is at all times to follow Respondent’s orders, including orders on when to ballast.133 As
Respondent ordered the ballasting operation before the Cargo had been discharged, Respondent
understood that there is a risk of flooding the Cargo. Accordingly, Respondent had accepted the
risk of any mistake during ballasting.
63. Conclusively, Respondent’s actions had caused Cargo damage and as a result, Respondent is fully
liable for all losses incurred pursuant to Clause 8(d) of the ICA.
VI. THE VESSEL SHALL REMAIN ON HIRE THROUGHOUT THE DETENTION
64. Upon the arrival of the Vessel at Wahanda, she was held at anchorage due to WPS’ suspicion that
the crew may be carrying Ebola.134 As a result, the Vessel was detained for 51 days as WPS found
that a number of crew members had fever.135 Despite the occurrence of a detention, the Vessel
shall remain on hire as (A) the delay for 51 days does not amount to an off-hire event pursuant to
130 Clause 8 of the ICA. 131 The Yangtze Xing Hua [2018] 1 Lloyd's Rep. 330. 132 Moot Problem, p. 46. 133 The Hill Harmony [2001] 1 Lloyd's Rep. 147. 134 Moot Problem, p. 25. 135 Moot Problem, p. 24.
Team 12 Claimant’s Memorandum
21
Clause 17 of NYPE15 and (B) In any event, Respondent had assented to the risk of the Vessel
being detained.
A. The delay for 51 days does not amount to an off-hire event pursuant to Clause 17 of NYPE15
65. Upon the arrival of the Vessel in Wahanda, she was detained for 51 days by WPS due to suspicion
that the Vessel was carrying Ebola.136 Clause 17 of NYPE15 stipulates that in order to deduce the
Vessel off-hire, the Vessel must be prevented from full working and the cause falls under Clause
17 of NYPE15.137 Respondent may argue that the Vessel is off-hire pursuant Clause 17 of
NYPE15.138 However, Claimant submits otherwise as (i) the Vessel was not prevented from full
working and (ii) even if the Vessel was prevented from full working, the cause preventing the full
working does not fall under Clause 17 of NYPE15.
(i) The Vessel was not prevented from full working
66. In order to deduce a vessel as off-hire, she must be prevented from full working.139 ‘Prevented
from full working’ means the inability to perform the service required from the Vessel.140 In The
Aquacharm,141 it was held that if a detained vessel was still able to perform what was required of
her under the charterparty then she is not prevented from full working.
67. In the present dispute, even though the Vessel was detained the Vessel was not prevented from
full working. What was required by Respondent was to discharge the Cargo at Wahanda.142 During
the detention, Respondent could have ordered a transhipment in order to discharge the Cargo at
Wahanda. Firstly, the Vessel was equipped with two cranes which would enable transhipment.143
136 Moot Problem, pp. 24-25. 137 Clause 17 of NYPE15. 138 The Mareva AS [1977] 1 Lloyd’s Rep 368; The Apollo [1978] 1 Lloyd’s Rep 200; The Aquacharm [1982] 1 Lloyd’s
Rep 7; The Mastro Giorgis [1983] 2 Lloyd’s Rep 66; The Roachbank [1987] 2 Lloyd’s Rep 498; The Laconian Confidence
[1997] 1 Lloyd’s Rep 139; The Athena [2013] 2 Lloyd’s Rep 673. 139 Royal Greek Government v Minister of Transport (The Illissos) [1949] 1 KB 7 (Court of Appeal); The Apollo [1978] 1
Lloyd’s Rep 200; The Aquacharm [1982] 1 Lloyd’s Rep 7; The Mastro Giorgis [1983] 2 Lloyd’s Rep 66; The Roachbank
[1987] 2 Lloyd’s Rep 498; The Laconian Confidence [1997] 1 Lloyd’s Rep 139; The Athena [2013] 2 Lloyd’s Rep 673. 140 The Aquacharm [1982] 1 Lloyd’s Rep 7. 141 Ibid. 142 Moot Problem, pp. 2-4. 143 Moot Problem, p. 3.
Team 12 Claimant’s Memorandum
22
Secondly, WPS did not restrict the performance of transhipment.144 Conclusively, the Vessel was
not prevented from full working and accordingly the Vessel shall be on hire throughout the
detention period.
(ii) Even if the Vessel was prevented from full working, the cause preventing the full working
does not fall under Clause 17 of NYPE15
68. Assuming but not conceding that the Vessel was prevented from full working, the foregoing cause
does not fall under Clause 17 of NYPE15 as (a) the detention does not fall under ‘detention by
Port State control for Vessel deficiencies’ and (b) alternatively, the detention by WPS does not
fall under ‘any other similar cause preventing the full working of the Vessel.’
(a) The detention does not fall under ‘detention by Port State control for Vessel deficiencies’
69. ‘Detention by Port State control for Vessel deficiencies,’ is a cause of off-hire in Clause 17 of
NYPE15. Since Wahanda applies Hong Kong law,145 Respondent may argue that the Hong Kong
Regulations146 would impose detentions to vessels lacking free pratique. However, Claimant
submits that Section 3.1 of IMO Resolution A.1052(27) (“IMO Resolution”), in force by Hong
Kong’s IMO membership,147 provides the guidelines applicable in Wahanda for identifying a
deficient vessel.148 The causes in Section 3.1 of IMO Resolution, inter alia, include insufficiency
of operational proficiency, or unfamiliarity of essential operational procedures by the crew; and
insufficiency of manning or certification of seafarers. Neither of these include the absence of free
pratique as a deficiency.
70. In the present dispute, although the Vessel did not have free pratique upon the arrival in Wahanda,
the absence of free pratique is not considered a deficiency.149 Additionally, the detention was not
initially caused by the absence of free pratique, but a suspicion of Ebola, which is not included in
144 Section 52 of Prevention and Control of Disease Regulation Cap. 599, section 7, L.N. 203 of 2008; Wahanda applies
Hong Kong laws, see Moot Problem, p. 81. 145 Moot Problem, p. 81. 146 Section 51 of Prevention and Control of Disease Regulation Cap. 599, section 7, L.N. 203 of 2008. 147 List of Member States and Associate Members of IMO
<http://www.imo.org/en/About/Membership/Pages/MemberStates.aspx> accessed on 27 April 2019 148 Moot Problem, p. 81. 149 Section 3.1 of IMO Resolution A.1052(27).
Team 12 Claimant’s Memorandum
23
IMO Resolution A.1052(27). Conclusively, with the detention not a result of Vessel deficiencies,
the Vessel shall be on hire throughout.
(b) Alternatively, the detention by WPS does not fall under ‘any other similar cause preventing
the full working of the Vessel’
71. If the phrase ‘by any other similar cause’ is present, then the ejusdem generis150 rule applies in
accordance with mentioned causes in Clause 17 of NYPE15.151 Accordingly, a Vessel cannot be
held off-hire if the cause of off-hire was an extraneous cause, unless the Parties specifically agreed
to include extraneous causes as a cause of off-hire.152 An extraneous cause is any cause preventing
the vessel from full working that does not originate from the inner-workings of the vessel itself.153
72. In The Laconian Confidence,154 detention by port authorities was held as an extraneous cause.
Even though The Laconian Confidence was prevented from full working, she was on hire as the
detention by port authorities was not ‘of the same kind’ with the named causes. As such, a cause
not mentioned in Clause 17 of NYPE15 can lead to an off-hire event if the foregoing cause is ‘of
the same kind’ with the mentioned causes.
73. In the present dispute, Respondent may argue that Clause 17 of NYPE15 shall include extraneous
causes by seeing the phrase ‘detention by Port State control […] for Vessel deficiencies.’ However,
vessel deficiencies only encompass the deficiencies of inner-workings of the Vessel such as a
defect hull, machinery, and seafarer competency certification.155 The cause preventing the full
working of the Vessel is a suspected Ebola infection among the crew which is an extraneous cause
that is not related to the inner-workings of the Vessel.156 Accordingly, as the events do not fall
150 See supra, ¶59. 151 The Roachbank [1987] 2 Lloyd’s Rep 498; Terence Coghlin, et. al., Time Charters 7th edition (2014), page 450 ¶25.37. 152 The Apollo [1978] 1 Lloyd’s Rep 200; The Aquacharm [1982] 1 Lloyd’s Rep 7; The Mastro Giorgis [1983] 2 Lloyd’s
Rep 66; The Roachbank [1987] 2 Lloyd’s Rep 498; The Laconian Confidence [1997] 1 Lloyd’s Rep 139; The Jalagouri
[2003] 1 Lloyd’s Rep 515; The Athena [2013] 2 Lloyd’s Rep 673. 153 Ibid. 154 The Laconian Confidence [1997] 1 Lloyd’s Rep 139. 155 Section 3.1 of IMO Resolution A.1052(27); Additionally, see supra, ¶80. 156 The Apollo [1978] 1 Lloyd’s Rep 200; The Laconian Confidence [1997] 1 Lloyd’s Rep 139.
Team 12 Claimant’s Memorandum
24
under ‘any other similar cause preventing the Vessel from full working,’ the Vessel shall be on-
hire throughout.
B. In any event, Respondent had assented to the risk of the Vessel being detained
74. Respondent may argue that Claimant had assented to the risk of detention in Wahanda as the
Charterparty is a single-trip time charter. 157 However, a party cannot be held liable for risks they
had not assented to.158 In this regard, Claimant submits that Claimant could only assent to risks
that were known to them at the time of conclusion.159
75. In the present dispute, the risk of detentions as a result of Ebola had only taken place after the
initial Charterparty was concluded. 160 As such, Claimant could not have assented to the risk of
detentions for Ebola. Even though there is an Ebola outbreak in West Coast, Respondent persisted
in sailing from West Coast to Wahanda161, which leads to the Vessel being detained in
Wahanda.162 Respondent, as a commercial man, understood that sailing from an Ebola-affected
port, would expose the risk of Vessel being detained.163 Accordingly, Respondent had assented to
the risks of the Vessel being detained.
76. Additionally, Respondent may argue that the Vessel shall be off-hire as Claimant could have
refused the voyage from West Coast to Wahanda to avoid state sanctions,164 pursuant to Clause
46 of NYPE15.165 However, Claimant submits that the Vessel shall remain on hire. Claimant did
not refuse the voyage from West Coast to Wahanda as Respondent has assented to the risks of the
Vessel being detained.
157 Hyundai Merchant Marine Co Ltd v Furness Withy (Australia) Pty (The Doric Pride) [2005] EWHC 945 (Comm). 158 The Island Archon [1994] 2 Lloyd’s Rep 227; The Pamphilos [2002] 2 Lloyd's Rep. 681; Hyundai Merchant Marine
Co Ltd v Furness Withy (Australia) Pty (The Doric Pride) [2005] EWHC 945 (Comm); Transgrain Shipping (Singapore)
Pte Ltd v Yangtze Navigation (Hong Kong) Ltd [2017] EWCA Civ 2107. 159 The Island Archon [1994] 2 Lloyd’s Rep 227; The Pamphilos [2002] 2 Lloyd's Rep. 681; Transgrain Shipping
(Singapore) Pte Ltd v Yangtze Navigation (Hong Kong) Ltd [2017] EWCA Civ 2107. 160 Moot Problem, p. 2, 22. 161 Moot Problem, p. 81. 162 Moot Problem, pp. 24-25. 163 These ports will detain vessels who have called ports in these countries in the last number of days: Singapore: 60 days
(Maritime And Port Authority Of Singapore – Port Marine Circular No. 11 of 2014); Argentina: 30 days, Brazil: 21 days,
Uruguay: 21 days (Re: South American P&I Club Circular 01/14 – Ebola - South American Countries). 164 Kuwait Oil Tanker Co SAK & Anor. v Qabazard [2002] EWCA Civ 34; Blue Sky One Ltd v Mahan Air [2009] EWHC
3314 (Comm); Five Oceans Salvage Consultants Ltd v Perla Navigation Ltd [2013] EWHC 4055 (Comm); Summit
Navigation Ltd v Generali Romania Asiguarare Reasiguarare SA [2014] EWHC 398 (Comm). 165 Clause 46 of NYPE15.
Team 12 Claimant’s Memorandum
25
77. Conclusively, as Claimant had not assented to the risk of being detained as a result of a suspected
Ebola infection, the Vessel shall not be deduced as off-hire.
PRAYERS FOR RELIEF
For reasons submitted above, Claimant respectfully requests this Tribunal to:
ADJUDGE that Respondent is liable to Claimant for:
(1) All costs in connection with HCO at USD96,567.42 or alternatively, limited to USD33,000;
(2) Damages for late re-delivery and missing the Next Fixture at USD15,330,000.00 (loss of hire
under the Next Fixture, calculated as 4 years at USD10,500 per day).
Further
DECLARE that Respondent’s cause of action for cargo claims are extinguished by time-bar;
Further
ADJUDGE that Claimant is not liable to the Respondent for:
(1) Funds that were paid in hire during time in detention between 7 May 2016 and 26 May 2016 at
USD350,000; and
(2) All Cargo lost as a result of the flooding of Cargo Hold No. 2 as awarded in a further award in
damages.