The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

8
The SaTH Foundation Trust The SaTH Foundation Trust Programme Programme Deborah Shaw Deborah Shaw March 29th 2007 March 29th 2007

Transcript of The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

Page 1: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

The SaTH Foundation Trust The SaTH Foundation Trust Programme Programme

Deborah ShawDeborah Shaw

March 29th 2007March 29th 2007

Page 2: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

Achieving FT Status for SATH:Achieving FT Status for SATH:

Likely FT Timeline for wave 8Likely FT Timeline for wave 8 Key Milestones and Work streamsKey Milestones and Work streams Next Steps Next Steps

Page 3: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

DH Application Process

There is an opportunity to apply for FT approval every 3 months

Proposed authorisation dates:

•Wave 4 July 2007•Wave 5 October 2007•Wave 6 January 2008•Wave 7 April 2008•Wave 8 July 2008•Wave 9 October 2008•Wave 10 January 2009

Page 4: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

FT Application Process for SATH wave 8

Preparatory work: SHA quarterly review of progress with Trust

Sept 07: SHA submits list of acute trusts

October 07: DH advise which Trusts should go to public consultation

Nov-Jan 08: Trusts carry out public consultation on their applications.

Feb 08: Formal application for Secretary of State support.

March 08: Secretary of State approval decision

April-June 08: Monitor’s assessment process.

July 08: Authorisation given.

Page 5: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

Key MilestonesKey Milestones

Deliver 07/08 financial plan Deliver 07/08 financial plan March 07March 07 Establish all FT work streams Establish all FT work streams March 07March 07 Market assessment completed Market assessment completed June 07June 07 Clinically-led fact based service review Clinically-led fact based service review

Sept 07Sept 07 Draft workforce strategy completed Draft workforce strategy completed Sept 07Sept 07 Draft Integrated Business Plan to SHA Draft Integrated Business Plan to SHA Sept Sept

0707 SHA support for applicationSHA support for application Sept 07 Sept 07

Page 6: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

Key MilestonesKey Milestones

DH support to progress to consultationDH support to progress to consultation Oct Oct 0707

Public consultation Public consultation Nov 07- Jan 08Nov 07- Jan 08 Submission to DHSubmission to DH Feb 08 Feb 08 Due diligence work Due diligence work Feb 08Feb 08 Secretary of State approvalSecretary of State approval March 08 March 08 Monitor assessmentMonitor assessment April – June 08 April – June 08 AuthorisationAuthorisation July 08 July 08

Page 7: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

Key Work streams:Key Work streams:

Service Development Strategy and market assessmentService Development Strategy and market assessment Workforce StrategyWorkforce Strategy Finance and ContractingFinance and Contracting Constitution, Governance and Constitution, Governance and MembershipMembership Stakeholder engagementStakeholder engagement Capacity and capability buildingCapacity and capability building Service Improvement and redesignService Improvement and redesign

Five year Integrated Business Plan

Foundation Trust Programme Board

Page 8: The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.

Next StepsNext Steps

Establish the Programme BoardEstablish the Programme Board Establish Programme Governance Establish Programme Governance

arrangementsarrangements Agree high level project planAgree high level project plan Begin Stakeholder EngagementBegin Stakeholder Engagement Schedule the programme of work for the Schedule the programme of work for the

Service Development Strategy (SDS)Service Development Strategy (SDS) Board Development ProgrammeBoard Development Programme Detailed work plans to May Trust BoardDetailed work plans to May Trust Board Progress reported to each trust BoardProgress reported to each trust Board