The Romanian Wind Energy Market EMERGING vs CHALLANGING ROMANIAN WIND ENERGY ASSOCIATION
-
Upload
pascale-joseph -
Category
Documents
-
view
36 -
download
1
description
Transcript of The Romanian Wind Energy Market EMERGING vs CHALLANGING ROMANIAN WIND ENERGY ASSOCIATION
The Romanian Wind Energy MarketEMERGING vs CHALLANGING
ROMANIAN WIND ENERGY ASSOCIATIONEuropean Wind Energy Association Conference 2012,
Emerging Markets Session, April 19, 2012
2
CONTENT:
1. Current status of wind energy production
2. Estimations on installed wind power by 2020
3. Challenges
4. Perspectives
CURRENT STATUS
3
There were 982 MW installed at the end of 2011, out of which 520 MW were installed during 2011, most of the capacities in the South-Eastern part of the country (Dobrogea area)
COUNTRY/YEAR 2009 2010 2011
TURKEY 801 1329 1799
POLAND 724 1180 1616
ROMANIA 14 462 982
CURRENT STATUS VS ESTIMATIONS
4
TARGETS
5
YEAR Law 220/2008 (%)
Law 220 Amended (%)
Achieved
2010 8.30 8.30 1,6%
2011 8.30 10 3,5%
2012 8.30 12
2013 9.00 14
2014 10.00 15
2015 10.80 16
2016 12 17
2017 13.20 18
2018 14.40 19
2019 15.60 19.5
2020 16.80 20
CURRENT STATUS
GE 34%
Vestas 31,5%
Gamesa17,9%
Nordex 2%
Fuhrlander 0,9%
Suzlon 0,8 %
AREAS
2011- 97% of the installed capacity was in Dobrogea area
2012- a shifting towards NE is noticed
6
Green-operationalBlue-Connection ContractRed-Connection Permit
RWEA ESTIMATIONS
RWEA has a more ambitious forecast based on the plans of the investments but the forecast needs to be correlated with a
healthy grid improvement plan
clear plan for decommissioning old inefficient coal power plants plan
stable legal framework
8
1850
2450
1975
2800-3000
2012 2013
ANRE
RWEA
MW to be installed in wind
9
CHALLENGE NO 1: GRID CONNECTIONCHALLENGE NO 1: GRID CONNECTION
Status of wind projects TOTAL MW
With grid connection permit 10 378
With grid connection contract 10 216
Wind farms in operation 1140
The large number of contracts and permits raises concern, as Transelectrica declared only approx. 4000 MW could be integrated
CHALLENGE NO 2: LEGAL FRAMEWORK STABILITY
Law 220 promoting renewables was published in 2008 and applied in November 2011 due to :
lack of secondary legislation long process of notifying the European
Commission-DG Energy on state aid matters long national procedures before enforcing the
law
New provisions Individual notification to the European
Commission of the projects with installed capacity over 125 MW
Priority access is redefined Monitoring mechanism introduced in order to
avoid overcompensation
10
CHALLENGE NO 3: LEGAL FRAMEWORK PREDICTABILITY
Monitoring mechanism -imposed by the decision of the EC-DG Competition and
enforced by the regulator
-introduces the possibility for the support mechanism to be changed yearly
-analyses the specific investment cost and adjusts the support in case this cost decreases
-the number of green certificates for each technology can change but the IRR accepted should remain constant (10.9% for wind energy)
-the new number of green certificates resulted from the analysis of year n is announced in n+1 and applied in n+2
11
PERSPECTIVES
Currently the Parliament debates an Emergency Ordinance containing the new provisions.
Clarification is expected regarding the predictability of the support scheme.
Investors and financing institutions plead for stability. Some investment decisions are standing by for a clear picture of the future related to the support scheme.
12
13
14
Thank you for your attention!Thank you for your attention!
ROMANIAN WIND ENERGY ASSOCIATION
Dana Duica
Executive Director