The Outlook on Potential Uranium ISL Mining at Nyota ... · June 2014 А. Boytsov, S. Stander, V....
Transcript of The Outlook on Potential Uranium ISL Mining at Nyota ... · June 2014 А. Boytsov, S. Stander, V....
June 2014
А. Boytsov, S. Stander, V. Martynenko
URAM 2014, IAEA, Vienna, Austria
The Outlook on Potential Uranium ISL Mining at Nyota Deposit (Tanzania)
| 2 | WWW.URANIUM1.COM
1. Uranium One – Introduction & Operational Overview
2. The Mkuju River Project - History & Status
3. Geology and Mineral Resources of the Nyota Deposit
4. The Key Motivation for Investigating ISL
5. Work Completed and Results to Date
6. Future Test Work Planned
7. Key Challenges: Commercial, Technical & SHEQ
8. Conclusion
Outline of Presentation
| 3 | WWW.URANIUM1.COM
• Uranium One Inc. is a Canadian-based company and a wholly owned subsidiary of Rosatom.
• It has a globally diverse portfolio of assets located in Kazakhstan, USA, Australia and Tanzania.
• Uranium attributable production growth of 3,8 times within 5 years. • 2013 attributable production 5,140 tons U – a top five U producer. • All U is produced via ISL method.• 2013 average production cost was $42/kgU
Uranium One – Introduction & Operational OverviewGlobal Footprint
1 3692 857
4 098 4 711 5 140
0
1 000
2 000
3 000
4 000
5 000
6 000
2009 2010 2011 2012 2013
Tonn
es U
Uranium One Historical Uranium production
2013 analytics production cost estimations (USD/kgU)
| 4 | WWW.URANIUM1.COM
Mkuju River is a uranium development project located in southern Tanzania, ~ 470 km southwest of Dar es Salaam. It is owned by Mantra Tanzania Ltd.
Uranium One is the operator of the Mkuju River Project
Mantra portfolio consists of 103 tenements. Mkuju River is the core project containing the large Nyota deposit
A definitive feasibility study is being prepared and current activity is focused on licensing and permitting, with a Special Mining License having been secured.
The UNESCO World Heritage Committee approved an application by the Tanzanian Government for a minor adjustment to the boundary in order to exclude the project from the Selous Game Reserve.
The Mkuju River Project - History & Status
WWW.URANIUM1.COM555
Geology and Mineral Resources of the Nyota Deposit
Regional Terrain
WWW.URANIUM1.COM666
Geology and Mineral Resources of the Nyota Deposit
The Mkuju River project is located within the Selous Sedimentary Basin, part of the greater Karoo Basin.
The Nyota deposit, which is the key asset, occurs in the Triassic Mkuju Series
Major lithologies: feldspathic sandstones, arkose sands and gritstone
It is located to the NW of a major NE-SW trending fault, and is subject to a Special Mining License.
Nyota DepositSML
Geological Setting
WWW.URANIUM1.COM777
The Nyota deposit is a near surface deposit, located via the large surface radiometric anomaly. The Mkuju River project holds a number of lesser, but equally prospective satellite anomalies Typical Nyota section demonstrates shallow depth of mineralization and lateral continuity of horizons Note inter-bedded shale and mudstone horizons
Geology and Mineral Resources of the Nyota DepositGamma Survey Map and Cross Section View
WWW.URANIUM1.COM888
• The host rocks are braided fluviatile sediments consisting of grits, sandstones and siltstones.• The sediments are soft, barely consolidated and sub- horizontal.
Geology and Mineral Resources of the Nyota Deposit
• Only Secondary U minerals are recognised to date, ppredominantly uranyl phosphates - phosphuranylite and meta – autinite, occurring interstitial to sediments grains.
Rock types and Mineralization
| 9 | WWW.URANIUM1.COM
17.1
28.5
65.572.7
93.399.3
113.5
124.6
35.927.5
55.8
35.9
19.326.1
16.523.6
27.5
0
20
40
60
80
100
120
140
2009/01 2009/12 2010/1 2010/11 2011/09 2011/09 2012/07 2012/11 2013/03
Con
tain
ed M
lbU
3O8
Measured & Indicated Inferred 100 ppm Cut-off
Geology and Mineral Resources of the Nyota Deposit
CIM compliant Mineral Resources
• Current resources 152.1 Mlbs U3O8 (58.5tU), including 124.6Mlbs (48tU) of Measured and Indicated resources
• Since 2009• 4.2x increase in total and
7.3x increase in the M+I• Since September 2011
• 28% growth in total resource
• 33% growth in M+I resources
• Significant exploration potential
| 10 | WWW.URANIUM1.COM
DFS - Multiple open pits 30% of resources out of designed pit shells 3D groundwater surface model developed One third of resources occur below the water table, 40%
of of which are out of designed pit ISL advantages versus conventional mining: Lower CAPEX and OPEX Lower surface environmental impact
The Key Motivation for Investigating ISL
above water below water total
outside pit 24.1 21.0 45.1
inside pit 76.5 30.5 107.0
0.0
20.0
40.0
60.0
80.0
100.0
120.0
Mlb
s U
3O8
| 11 | WWW.URANIUM1.COM
Work Completed and Results to Date
Factors affecting ISL process Favorable parameters* Obtained parameters Factor
Hydraulic conductivity (permeability factor) 1-5 m/day. 1.8 - 5.1 m/day. +
Transmissivity of ore horizon 10-100 m2/day 18.7-34.3 m2/day +
Depth of mineralization <200 26 - 56 m ++
Carbonate content (СО2) 1-2 % 0.7 % ++
Mineral composition of ore Disseminated uranium oxides
Secondary uranium mineralization +
Ore productivity 1-5 kg/m2 1.2 – 18 kg/m2 +
Water confining beds in the aquifer top, bottom Stable water confining beds
Local clay beds 0.4m to 3.5m thick + -
Depth of underground water 10-100m 21.8 -24m +
Ground waters mineralization TDS <1 g/dm3 <1.0 g/dm3 ++
Water abundance (specific yield) 0.1-0.5 l/sec 0,1 l/sec + -
Thickness of productive aquifer 10-30 Over 30m, local to 1.5m thick confining beds - +
Mineralization location in aquifer In the middle and bottom parts
In the upper and middle part + -
Temperature of ground waters 10-30о 26о +
A selected mineralised area, below the water table, outside the pit designs was tested.
Preliminary Hydro-geological Investigation
| 12 | WWW.URANIUM1.COM
Work Completed and Results to Date
The success and positive indicators achieved with the preliminary hydrological test, led to the approval of the next testing program, which was a Push-Pull test.
The main objective of this test was to evaluate the principal amenability of the mineralization to ISL operations, with a specific focus on: Effectiveness of various leaching solutions Hydraulic conductivity, transmissivity and specific
yield of the aquifer Ore productivity of the well field
The main reagents were: Alkaline - bicarbonate, (with and without Н2О2) Sulphuric Acid
Push Pull Test - Objectives
| 13 | WWW.URANIUM1.COM
Work Completed and Results to Date
The test was conducted in 2013 at the site of the preliminary hydrological investigation Two recovery wells, five monitoring wells and one disposal well were completed Necessary governmental approvals were obtained. The depth of mineralisation was only ~26m, the thickness ~8m, and the grade ~1000ppm U3O8 The test was conducted by Rusburmash, with support from Mantra staff
Push Pull Test – Plan View and Geological Section
H2SO
4H
2SO4
NH
4HC
O3
NH
4HC
O3
| 14 | WWW.URANIUM1.COM
Work Completed and Results to DatePush Pull Test – Site Photo’s
An on-site laboratory was erected and equipped
Push-pull test site Push-pull site – wells location
Pregnant solutions pumping 150mkr/hour – radioactive background
| 15 | WWW.URANIUM1.COM
Work Completed and Results to Date
The NH4HCO3 concentration varied between1, 5 and 10 g/l Bicarbonate reagent yielded disappointing results (below 4,5mg/l U) This was expected, as metallurgical test-work during the DFS indicated this.
0.50.5
1.5 1.51.75
2.5
1.5
1.0
0.75
0.5
1.0
1.8
2.5
3.1
2.5
1.8
1.5
1.0
0.5 0.5
0
1.5
3.5
2.5
4.5
3.5 3.5
2.5 2.5
1.51.5
0
3.5 3.5 3.5 3.5 3.5 3.5
2.5 2.5 2.5
1.5
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
0 1 2 3 4 5 6
Cu,
mg/
l
V, m3
NH4HCO3-5 g/l-17 h
NH4HCO3-5 g/l-41 h
NH4HCO3-5 g/l-65 h
NH4HCO3 -10 g/l+Н2О2 - 2g/l -91 h
Push Pull Test – Alkaline leaching results
| 16 | WWW.URANIUM1.COM
Work Completed and Results to Date
0
6.5
17.5
19.5
16.512.0
4.5
1.5 1.5 0.5 0.5
19.5
42.541.5
29.5
21.5
10.5
2.5 2.5 2.01.5
44.5
54.5
39.5
28.5
20.5
9.52.5
1.5 0.5 0.50
10
20
30
40
50
60
0 1 2 3 4 5 6
Cu,
mg/
l
V, m3
18 h
42 h
67 h
17.5
58.5
75.575.5
69.5
37.5
10.54.5
1.5 1.00
54.5
119.5 118.5
82.5
60.5
22.5
6.63.5 1.5 1.50
48.0
105.0 105.0
81.0
60
30.0
156
3 3
0
20
40
60
80
100
120
0 1 2 3 4 5 6
Cu,
mg/
l
V, m3
18 h
38 h
69 h
10 Mg/l H2SO4
46.6
94.5 98.589.5
79.0
56.6
32.5
22.520.5
9.515.5
72.5
105.5
116.5
124.5
112.5
65.5
31.0
16.58.5
0
20
40
60
80
100
120
140
0 1 2 3 4 5 6
Cu,
mg/
l
V, m3
67 h19 h
20 Mg/l H2SO4 Acidic leaching solutions 5, 10 and 20 mg/l Leaching time 18 to 69 hours All the solutions managed to recover
uranium into solutions in short timeframes Uranium concentration reached 125mg/l The 10mg/l solution proved to be the
optimal economic reagent The acidic test results were very successful
5 Mg/l H2SO4
Push Pull Test – Sulphuric Acid Results
| 17 | WWW.URANIUM1.COM
Five Spot Test must demonstrate the economic viability of the ISL mining
Future Test Work Planned
• To determine the direction and speed of groundwater flow;• The hydraulic connection between the ore bearing aquifers and the
surface streams; • How solutions will spread through the strata, • The size of the groundwater depression cone• The probable impact on the surface stream flows.
Hydrological Studies
• To determine main mineralization and ISL process parameters and to model ISL process dynamics.
• The test duration is one year. Five Spot Field Test
• To determine how the aquifer can be restored after ISL completion. • The set of works will enable to estimate data for the EIADemineralization Test
• Geological model update and resources re-estimation based on ISL criteria (productivity, permeability, ground water level, etc.)
Geological model and resources update for ISL
| 18 | WWW.URANIUM1.COM
Commercial Open Pit vs. ISL mining Lower grade ore available outside pits
Technical R&D phase Water confinement (aquacludes) Water yield How to marry ISR with Open Pit mine Topography
SHEQ ISL never been used in Africa Water quality & use – pristine, animals Selous Game Reserve Environmental management
Key Challenges: Commercial, Technical & SHEQ
| 19 | WWW.URANIUM1.COM
The model of Aquifer Natural Attenuation after five spot ISL test
Basic environmental requirements:• Keeping balance
between injection and recovery volumes
• Using monitor wells
• Aquifer restoration through:• Natural attenuation • Forced
demineralisation • Residual solution in
situ neutralisation
WWW.URANIUM1.COM202020
С (SO4) =7,45 g/l
С (SO4) = 0,91 g/l
С (SO4 )=0,63 g/lС SO4 =0,6 g/l
Five-Spottest
| 21 | WWW.URANIUM1.COM
Conclusion
The Nyota deposit is a world class deposit, which holds over 50Mlb which is potentially amenable to ISR.
Significant resources upside potential.
Initial ISL testing has yielded encouraging results, which should be followed up.
The ISR project is currently at the R&D stage, and the next steps have been identified and planned.
Technical, commercial and SHEQ challenges remains that must be overcome.
Uranium One will continue to investigate the ISR potential via a responsible, toll gated approach.
Successful testing could unlock a new ISL production region.
| 22 | WWW.URANIUM1.COM
We like ISL