The network connection of Niehl 3 CCPP
The first 380kV long-distance cable project in Germany since the Bewag projects in 2000
Fabian Schell, FICHTNER
Co-author:Heinz Uhlenküken, RheinEnergie (RNG)
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Overview
• Project background
• The need
• The concept
• The challenge
• Cable route
• Impressions from site
• Quality control and testing
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Project backgroundIn 2012 RheinEnergie decided to build a new 450 MW block at the existing plant location of the Niehl combined cycle power plant within the Cologne harbor area.
Niehl 2
Source: RheinEnergie, Alstom New 380kV GIS
• Jicable’15, 21 - 25 June 2015 - Versailles - France
The needThe network connection of Niehl 3 (NAN3) comprised three levels :
• 380kV connection to Germany’s transmission network
• 110kV connection to RheinEnergie’s distribution network
• Feeding RheinEnergie’s heat district system.
The particular location of the new plant - however - made a solution for the network connections more challenging , especially that of the 380 kV level.
Commissioning of the new plant will start in autumn 2015. Niehl 3 will finally enter commercial service in 2016.
• Jicable’15, 21 - 25 June 2015 - Versailles - France
The conceptConnecting the plant-side 380kV GIS with the transition point at RheinEnergie’s Merkenich S/S by 380kV underground cable.
From there, a 380kV OHL connection to the German transmission network at Amprion’s Opladen S/S.
Installation of a 380/110kV phase-shifting transformer at plant-side GIS for a 110kV cable connection to RheinEnergie’s Kalk S/S.
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Ranking of large 380kV projects in GermanyWith a system length of almost 9 km , the underground section of the Niehl 3 network connection (NAN3) is Germany’s longest 380kV XLPE cable connection - so far.
Project name Year System Length
No. ofcircuits Conductor
NAN3, Cologne 2015 9.1 km 1 1x1600 Al solid
Bewag I (Berlin Mitte - Friedrichshain) 1998 6.5 km 2 1x1600 Cu segmented
Bewag II (Berlin Friedrichshain - Marzahn) 2000 5.4 km 2 1x1600 Cu segmented
EnLAG project Wesel-Meppen(2 partial undergrounding sections) 2015 ~3 km 2 2x2500 Cu segmented
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Cologne in 1945
• Jicable’15, 21 - 25 June 2015 - Versailles - France
The challengePlanning an almost 9 km long underground cable system inside a complicated environment like the city of Cologne surely is a more complicated than in other environments:
− Still today there are numerous bomb disposals and UXO (unexploded ordnance device) suspects and every year.
− Due to reconstruction over the past decades there are nowadays numerous other utility lines , sewers and galleries in almost every street; unfortunately, not all of them are registered to date.
⇒ Very narrow trench available only !
⇒ Decision for a well-proven space saving ductbank design .
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Cable route9 sections (27 cable lengths) of up to 1210 meters per drum.
8 joint bays of ⇒ 24 joints21 “pulling pits” for use of cable pushers during laying.
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Impressions from site - construction phase
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Impressions from site – cable laying
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Impressions from site – cable laying
Pushing with up to 2x 2.2 to and Braking with up to 2x 2.5 to
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Impressions from site – installation
Joint bay:18m x 3m x 2,5m (LxWxD)
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Transition point at Merkenich S/S
• Jicable’15, 21 - 25 June 2015 - Versailles - France
GIS chamber at Niehl
• Jicable’15, 21 - 25 June 2015 - Versailles - France
Quality control and testingQuality control measures for the NAN3 project comprised: − Quality checks during production
− Routine and sample tests
− Tests for the extension of an existing prequalification (ePQ)
All test requirements were specified in the new German EHV cable standard DIN VDE 0276-2067 (2013-08).
Test requirements for the ePQ are slightly higher than those in IEC 62067, following the experience from the Bewag projects , e.g. test frequency, higher sensitivity and test voltage for PD measurement beyond others.
The ePQ was executed between April and September 2014.
• Jicable’15, 21 - 25 June 2015 - Versailles - France
After installation testsOn-site testing was performed in early April 2015.
The test voltage of 374kV (1h) was produced by a setup comprising four 260kV modules.
PD measurement (UHF method) was performed simultaneously on all 10 accessories per phase. ⇒ No (dangerous) PD detected