380KV Contingency Scan

download 380KV Contingency Scan

of 12

Transcript of 380KV Contingency Scan

  • 8/17/2019 380KV Contingency Scan

    1/12

     The Turkish Grid have many transmission lines with 380 KV voltage level. The totalnumber of 380 KV transmission lines is 161 line. set of !ontingen!ies related tothese lines was built" this set of !ontingen!ies have 30# !ontingen!ies. fter runningthis !ontingen!y set on the Turkish $ower %ystem" the following !ontingen!ies wereinse!ure&

      6' ().8*+ *,.)6 -nse!ure )/T/% 380. #3#610 #31110  68 (,.,8+ *'.3' -nse!ure )%2 380. #31110 #3#610  133 (81.0#+ #*.86 -nse!ure )K245K$- 380. )#0*11 )##010  161 (''.,)+ *,.,8 -nse!ure )%/4-%/7- 380. *10010 *10#10  16# (''.,)+ *,.,, -nse!ure )4$-2 380. *10#10 *10010  163 (''.,)+ *,.,8 -nse!ure )%/4-%/7- 380. *10010 *10110  16) (''.,)+ *,.,8 -nse!ure )V%K 380. *10110 *10010  16* (''.,)+ *,.,, -nse!ure )4$-2 380. *10#10 *10110  166 (''.,)+ *,.,8 -nse!ure )V%K 380. *10110 *10#10  16' (''.1,+ *,.,' -nse!ure )K%380 380. *1)310 *10110  168 (''.,)+ *,.,8 -nse!ure )V%K 380. *10110 *1)310  1'0 ('1.#*+ *#.'# -nse!ure )/25945/ 380. *#0111 *#0010

      1'1 (',.01+ *3.'3 -nse!ure )/2-:- 380. *#0110 *#0111  1'# ('1.#)+ *#.*3 -nse!ure )/25945/ 380. *#0111 *#0110  1'3 (''.1,+ *,.,' -nse!ure )K%380 380. *1)310 *#0110  1') ('8.6*+ *1.,3 -nse!ure )/2-:- 380. *#0110 *1)310  1'* (''.,)+ *,.,8 -nse!ure )%/4-%/7- 380. *10010 )#0,10  1'' (''.,)+ *,.,8 -nse!ure )%/4-%/7- 380. *10010 )#0*10  1', (''.,)+ *,.,8 -nse!ure )%/4-%/7- 380. *10010 *#0010  18* ('8.'1+ *#.8' -nse!ure )/2-:- 380. *#0110 330310  18' ('8.03+ *,.8# -nse!ure )K4;%- 380. 61#'10 610)10  188 (',.'1+ *,.8) -nse!ure ):T-2K4 380. 610)10 61#'10  18, ('8.03+ *,.8# -nse!ure )K4;%- 380. 61#'10 61#310  1,1 (',.),+ *,.83 -nse!ure )%; 380. 6#0610 6#0#10

      1,3 (',.*1+ *,.8) -nse!ure )7

  • 8/17/2019 380KV Contingency Scan

    2/12

    tri??ing the line they will be isolated from the network" !ausing the instability. Thesetwo generators are the se!ond biggest generators in the Turkish Grid.

    Generator angle (degrees)

    Time (sec)

    0.000 0.166 0.332 0.497 0.663 0.829 -30

     144

     318

     492

     666

     840

    Generator angle (degrees)

    Time (sec)

    0.000 0.166 0.332 0.497 0.663 0.829 -20

     150

     320

     490

     660

     830

    Figure 1: System Response for Contingencies 67, and 68

    Contingencies 133, and 292:

     This !ontingen!y is !ausing a tri??ing of a main transmission line with a series!a?a!itor in it" the system res?onse was terminated early as shown in 9igure #" leftside. To solve this ?roblem then the a@ Generator %?eed eviation setting in T%Tis in!reased to 1 ?.u instead of 0.1 ?.u. The result system res?onse is shown in9igure #" right side. The system behavior after the fault shows an interestingse?aration between the generators" the generators !an be divided into 3 maingrou?s =or 6 grou?s>. s a result" this !ontingen!y !an be !onsidered as aninteresting !ontingen!y for more investigation.

    Generator angle (degrees)

    Time (sec)

    0.00 0.02 0.04 0.06 0.08 0.10 -13

     -0

     13

     25

     38

     51

    Generator angle (degrees)

    Time (sec)

    0.000 0.528 1.057 1.585 2.113 2.642 -1000

     5600

     12200

     18800

     25400

     32000

    Figure 2: System Response for Contingencies 133, and 292 for dierent S! setting

    Contingencies 161, 162, 163, 16", 16# and 166:

     The simulation was terminated at early stage dire!tly after the fault was a??lied" asshown in 9igure 3" left side. 9or solving that as mentioned before the a@ Generator%?eed deviation was in!reased to 1 ?.u instead of 0.1 ?.u. The simulation result is

  • 8/17/2019 380KV Contingency Scan

    3/12

    shown in 9igure 3" right side. 9rom 9igure 3" it !an be seen that this fault is !ausingthe three generators !onne!ted to bus =*10#10 )4$-2 380> to run out ofsyn!hronism" these generators are&*1068G/25)4$-2*106,G/25)4$-2*10'0G/25)4$-2

    Generator angle (degrees)

    Time (sec)

    0.000 0.021 0.042 0.064 0.085 0.106 -13

     -0

     13

     25

     38

     51

    Generator angle (degrees)

    Time (sec)

    0.000 0.087 0.173 0.260 0.347 0.433 -100

     700

     1500

     2300

     3100

     3900

    Figure 3: System Response for Contingencies 161, 162, 163, 16", 16#, and 166

    Contingencies 167, and 168:

     The simulation was terminated at early stage dire!tly after the fault was a??lied" asshown in 9igure )" and 9igure * left side. 9or solving that as mentioned before thea@ Generator %?eed deviation was in!reased to 1 ?.u instead of 0.1 ?.u. Thesystem res?onded in a diAerent way for both !ontingen!ies" although both!ontingen!ies are related to the same transmission line.9or !ontingen!y 16'" the system res?onse was stable as shown in 9igure )" rightside. n the other hand" the system res?onse was unstable for !ontingen!y 168" asshown in 9igure *" right side. The generators !aused instability for !ontingen!y 168were as follows&*1068G/25)4$-2*106,G/25)4$-2*10'0G/25)4$-2*1101G/25K/2-5/2B*110#G/25K/2-5/2B*1103G/25K/2-5/2B*110)G/25K/2-5/2B*110*G/25K/2-5/2B*1106G/25K/2-5/2B

     The !ontingen!y 168 !an be !onsidered as interesting in some way for our resear!h.

  • 8/17/2019 380KV Contingency Scan

    4/12

    Generator angle (degrees)

    Time (sec)

    0.00 0.02 0.04 0.06 0.08 0.10 -13

     -0

     13

     25

     38

     51

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -40

     -16

     8

     32

     56

     80

    Figure ": System Response for Contingencies 167 for dierent S! setting

    Generator angle (degrees)

    Time (sec)

    0.00 0.02 0.04 0.06 0.08 0.10 -13

     -0

     13

     25

     38

     51

    Generator angle (degrees)

    Time (sec)

    0.000 0.207 0.415 0.622 0.830 1.037 -1000

     1600

     4200

     6800

     9400

     12000

    Figure #: System Response for Contingencies 168 for dierent S! setting

    Contingencies 17$, 171, and 172:

     This fault is !ausing a tri??ing of transmission line with a shunt indu!tan!e=#03.'Vr>. The simulation was terminated at an early stage as shown in 9igure 6"left side. 9rom 9igure 6" left side" we !an say that the system is inse!ure be!ause of1 generator running away from syn!hronism" that generator is =*#1)61 G(/2-:6.30>. n the other hand if we tried to for!e T%T to advan!e the simulation afterthat to !he!k the system res?onse at later stages by in!reasing the a@ Generator%?eed deviation to 1 ?.u instead of 0.1 ?.u." the system was se!ure as shown in9igure 6" right side.9rom the ?revious result" it !an be seen that if the simulation terminated at earlystages dire!tly after the fault" then more investigation is needed to make sure thatthe !ontingen!y under study is indeed inse!ure.

  • 8/17/2019 380KV Contingency Scan

    5/12

    Generator angle (degrees)

    Time (sec)

    0.000 0.037 0.073 0.110 0.147 0.183 -14

     3

     21

     38

     56

     73

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -30

     -8

     14

     36

     58

     80

    Figure 6: System Response for Contingencies 17$, 171, and 172 for dierent S! setting,%eft insecure, rig&t secure

    Contingencies 173, and 17":

     This fault is ha??ening in a tie line !onne!ting rea *1 and rea *#. 9or the normalsettings of T%T related to a@ Generator %?eed eviation settings as 0.1 ?.u" thesystem res?onse was inse!ure" and terminated at early stage for both !ontingen!iesas shown in 9igure '. ;ut if this setting was in!reased to 1 ?.u" then the systemres?onse was se!ure" as shown in 9igure 8C

    Generator angle (degrees)

    Time (sec)

    0.00 0.02 0.04 0.06 0.08 0.10 -13

     -0

     13

     25

     38

     51

    Generator angle (degrees)

    Time (sec)

    0.000 0.041 0.082 0.122 0.163 0.204 -20

     6

     32

     58

     84

     110

    Figure 7: System Response for Contingencies 173, and 17" for S! 'a( )enerator Speed*e+iation as $1 pu

  • 8/17/2019 380KV Contingency Scan

    6/12

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -80

     -48

     -16

     16

     48

     80

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -60

     -26

     8

     42

     76

     110

    Figure 8: System Response for Contingencies 173, and 17" for S! 'a( )enerator Speed*e+iation as 1 pu

    Contingencies 17#, 177, and 179:

     These !ontingen!ies is related to tie lines !onne!ting bus =*10010 )%/4-%/7-380> in rea *1" to diAerent areas" rea )#" rea )#" and rea *# res?e!tively. Thesame s!enario is re?eating here" the system res?onse is terminated at early stage"and for that the a@ Generator %?eed eviation was in!reased to 1 ?.u. The systemres?onse for these !ontingen!ies shows that the inse!urity is !aused by threegenerators" as shown in 9igures ," 10" and 11 res?e!tively. These generators are&*1068G/25)4$-2*106,G/25)4$-2*10'0G/25)4$-2

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -1000

     11800

     24600

     37400

     50200

     63000

    Figure 9: System Response for Contingencies 17# for S! 'a( )enerator Speed *e+iationas 1 pu

  • 8/17/2019 380KV Contingency Scan

    7/12

    Generator angle (degrees)

    Time (sec)

    0.000 0.099 0.198 0.297 0.397 0.496 -100

     840

     1780

     2720

     3660

     4600

    Figure 1$: System Response for Contingencies 177 for S! 'a( )enerator Speed *e+iationas 1 pu

    Generator angle (degrees)

    Time (sec)

    0.000 0.099 0.198 0.297 0.397 0.496 -100

     840

     1780

     2720

     3660

     4600

    Figure 11: System Response for Contingencies 179 for S! 'a( )enerator Speed *e+iationas 1 pu

    Contingency 18#:

     This fault is ha??ening in a tie line !onne!ting rea *# and rea 33. 9or the normalsettings of T%T related to a@ Generator %?eed eviation settings as 0.1 ?.u" thesystem res?onse was inse!ure" and terminated at early stage for both !ontingen!iesas shown in 9igure 1#" left side. ;ut if this setting was in!reased to 1 ?.u" then thesystem res?onse was se!ure" as shown in 9igure 1#" right sideC

  • 8/17/2019 380KV Contingency Scan

    8/12

    Generator angle (degrees)

    Time (sec)

    0.000 0.041 0.082 0.122 0.163 0.204 -20

     6

     32

     58

     84

     110

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -60

     -26

     8

     42

     76

     110

    Figure 12: System Response for Contingencies 18# for dierent S! 'a( )enerator Speed*e+iation setting

    Contingencies 187, 188, 189, 191, 193, 19", 19#, 196, 197, 198, 213,

    and 273:

    9or all these !ontingen!ies the simulation terminated dire!tly at the time when thefault a??lied to the system" and T%T indi!ated all these !ontingen!ies as inse!ure.9or investigating the system res?onse after the fault a??lied" the simulation isfor!ed to be advan!ed by in!reasing the a@ Generator %?eed eviation u? to 1 ?.uinstead of 0.1 ?.u" the results are shown in 9igures 13" 1)" 1*" 16" 1'" and 18"res?e!tively. 9or all the mentioned !ontingen!ies" ) generators were !ausing theinstability" these generators are&6#031G/25)7

  • 8/17/2019 380KV Contingency Scan

    9/12

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -20

     86

     192

     298

     404

     510

    Generator angle (degrees)

    Time (sec)

    0.000 0.037 0.073 0.110 0.147 0.183 -20

     168

     356

     544

     732

     920

    Figure 1": System Response for Contingencies 189, and 191 for S! 'a( )enerator Speed*e+iation as 1 pu

    Generator angle (degrees)

    Time (sec)

    0.000 0.037 0.073 0.110 0.147 0.183 -20

     168

     356

     544

     732

     920

    Generator angle (degrees)

    Time (sec)

    0.000 0.037 0.073 0.110 0.147 0.183 -20

     168

     356

     544

     732

     920

    Figure 1#: System Response for Contingencies 193, and 19" for S! 'a( )enerator Speed*e+iation as 1 pu

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -20

     88

     196

     304

     412

     520

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -1000

     14000

     29000

     44000

     59000

     74000

    Figure 16: System Response for Contingencies 19#, and 196 for S! 'a( )enerator Speed*e+iation as 1 pu

  • 8/17/2019 380KV Contingency Scan

    10/12

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -1000

     13600

     28200

     42800

     57400

     72000

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -1000

     13800

     28600

     43400

     58200

     73000

    Figure 17: System Response for Contingencies 197, and 198 for S! 'a( )enerator Speed*e+iation as 1 pu

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -20

     86

     192

     298

     404

     510

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -20

     86

     192

     298

     404

     510

    Figure 18: System Response for Contingencies 213, and 273 for S! 'a( )enerator Speed*e+iation as 1 pu

    Contingencies 286, 288, 291, and 3$1:

    9or all these !ontingen!ies the simulation terminated dire!tly at the time when thefault a??lied to the system" and T%T indi!ated all these !ontingen!ies as inse!ure.9or investigating the system res?onse after the fault a??lied" the simulation isfor!ed to be advan!ed by in!reasing the a@ Generator %?eed eviation u? to 1 ?.uinstead of 0.1 ?.u" the results are shown in 9igures 1," and #0" res?e!tively. Thesystem res?onse was se!ure for all the !ontingen!ies.

  • 8/17/2019 380KV Contingency Scan

    11/12

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -90

     -54

     -18

     18

     54

     90

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -90

     -54

     -18

     18

     54

     90

    Figure 19: System Response for Contingencies 286, and 288 for S! 'a( )enerator Speed*e+iation as 1 pu

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -30

     -6

     18

     42

     66

     90

    Generator angle (degrees)

    Time (sec)

    0.00 1.00 2.00 3.00 4.00 5.00 -90

     -54

     -18

     18

     54

     90

    Figure 2$: System Response for Contingencies 291, and 3$1 for S! 'a( )enerator Speed*e+iation as 1 pu

    Conc%usion

    9rom the ?revious results" it !an be said that for all the 380 KV transmission lines"only three !ontingen!ies !an be !onsidered as !riti!al" and it needs moreinvestigations and studies on them. These !ontingen!ies are as follows&133 (81.0#+ #*.86 -nse!ure )K245K$- 380. )#0*11 )##010168 (''.,)+ *,.,8 -nse!ure )V%K 380. *10110 *1)310#,# (81.0#+ #*.86 -nse!ure )K245K$- 380. )#0*11 )#0*10

    nother thing to be noti!ed is that for any !ontingen!y that is terminated at earlystage from its simulation" it needs more investigations on it. 9or T%T simulation?rogram" the a@ Generator %?eed eviation setting should be in!reased beyond itsdefault value of 0.1 ?.u to !he!k the se!urity of ea!h of these !ontingen!ies that areterminating in early stage of the simulation.

  • 8/17/2019 380KV Contingency Scan

    12/12