~$the Formwork to the Millau Viaduct

download ~$the Formwork to the Millau Viaduct

of 104

Transcript of ~$the Formwork to the Millau Viaduct

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    1/104

    The Formwork to The Millau Viaduct

    ice Ireland

    Engineers Ireland

    Nov 2007

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    2/104

    Tonights Menu

    Introduction

    Background

    The Deck

    The Pier Bases

    The Piers

    The system used for climbing

    Shape and the challenges in forming it

    The philosophy behind the formwork engineering

    On the Way Up

    The completed Piers

    The Toll Plaza Canopy

    Conclusion

    What did we get for the money

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    3/104

    The Framework of the Presentation

    Background to the bridge

    Why it was built

    Where it is

    Who provided initial design

    How it came to look the way it does

    When it started and was finished

    What it is made of

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    4/104

    Where

    A75 Motorway link from Clermont Ferrand to Berziers

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    5/104

    Satellite Photo of the Trace

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    6/104

    Why

    That stretch is missing link in motorway route from

    Paris to Barcelona

    Before viaduct traffic drove down into the valley andthrough the town of Millau

    August regularly saw delays of 5 hrs+ in Millau, which

    gridlocked an entire town

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    7/104

    Millau

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    8/104

    Background to Design

    Originally designed by Michel Virlogeux whose concept was taken up by

    Sir Norman Fosters practise

    Pont de Normandie

    Wishbone Pylon and Cable Stay

    Briefly the longest cable stay span in the world

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    9/104

    Design

    The slender design of the Virlogeux/Foster Viaduct was chosen but had acontrasting pier design to the Pont De Normandie

    The wide based Wishbone of the Normandie Piers had become a veryslender Y shape for Millau

    High Level Wind Loads in Valley created a weak point in the wishbone

    One of the Millau piers is 4 times higher than the Normandie piers

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    10/104

    The Open Hands Pier Design

    The Single main stem with transition to Open Hands

    deck support gave best accommodation of wind loads

    in the upper levels of the Tarn Valley.

    The Main Stem is hollow with internal cross slabs.

    The point of bifurcation is solid

    The twin piers are hollow

    Designed for 200km/h winds at deck level

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    11/104

    Why was this design chosen

    Slender lines had least impact on environment of the valley

    Visually Stunning

    Had potential to make a striking architectural statement

    Kept traffic right out of Millau In March 2001 Eiffage TP won the contract to construct with a

    75 year concession to operate (which can be removed if provestoo profitable!)

    Deck was curved to a 20km radius to avoid sensation ofdreaming or flying, and to allow sight of all pylons

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    12/104

    Dont trip out at the wheel

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    13/104

    Framework..

    The Deck

    Vital Statistics

    What that means for the piers Why it is curved

    How it was moved

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    14/104

    The Deck

    Is a trapezoidal Box Girder design

    If made from reinforced concrete it would be 7m deep and weigh c.200,000 tonnes

    By making it in steel, the deck can reduce in depth to 4m, and inweight to 36,000 tonnes

    However, the reduction in dead weight on to the pier heads meantthat the deck would need stressing tendons down to thebifurcation point for stability.

    This adds 6,000 tonnes load per pier

    The dead weight of the single pier section is sufficient for stability

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    15/104

    More Vital Statistics

    Carries 10,000 tonnes of tarmac on main carriageways and another

    4,000 tones on hard shoulders

    Each pylon anchoring the cable stays is steel and weighs 700

    tonnes

    Each Main Cable can take tensile load equivalent to 25 Jumbo Jets

    at full thrust

    Steel of the cable stays adds 1500 tonnes to the overall weight

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    16/104

    Deck Movement

    Hydraulic Lift and move Rams - Enerpac

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    17/104

    The Movement of the Deck

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    18/104

    The Enerpac Rams

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    19/104

    Lets now start at the Bottom

    In order to get from abutment to abutment, 14km of

    road were constructed including a temporary bridge

    over the Tarn.

    The Pier Bases

    Concentrate on Pier No.2 (P2) as this is the tallest

    Soil is principally Limestone and riddled with caves and

    fissures containing bacteria used in the making of the

    regions main export..

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    20/104

    Roquefort Cheese

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    21/104

    The Foundations

    Each pier is founded on a plate or base, and four posts

    or piles

    The piles are each 5m diameter and extend down to amax depth of 14m

    On top is the base itself, which for P2 is 6m deep

    The Initial Launch pour for the pier is conventionallyshuttered

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    22/104

    The Base Plate

    As a solid concrete entity, base was too

    big to tie shutters conventionally so each

    base shutter was supported with PERI SB

    Brace Frames anchored into purposely

    laid rc base

    The piers together required 10,000

    tonnes of reinforcement steel

    The bases required 13, 450 tonnes ofrebar

    The piles required 1,200 tonnes of rebar

    The piles alone used 6,000m3 of concrete

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    23/104

    Pouring the Launch Pour

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    24/104

    The Piers

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    25/104

    The Piers

    Slender pier designed as running, tapered octagon

    Seven no. piers in total, similar shape from deck down,

    but differing heights

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    26/104

    Pier Heights

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    27/104

    The Pier Elevations

    Each Pier continually tapers in both planes from base to top

    In general, each pier is identical from the road deck down

    For a distance of 90m from the deck, a twin pier is used

    90m below deck is a transition point where twin pier becomes a single pier

    Pier no.2 is benchmark at 245m high

    All others are cut from below

    MUST FIND A WAY TO CLIMB FORMWORK 90m

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    28/104

    How To Construct the Pier

    It was decided to pour the pier in 4m lifts using a climbing form system

    Ideally it would go something like this

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    29/104

    So how do we climb? - We asked an Expert

    An automatic rail climbing system (ACS)

    Formwork Shutter and Work platforms areintegral

    Hydraulic Rams push shutter and carriage up

    the rail

    Rail runs through shoes fixed to concrete

    Rams lift rail up when carriage is fixed inposition

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    30/104

    Basic System Used Worldwide

    Weichsel Bridge Warsaw

    Petronas TowersAndromeda Tower

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    31/104

    Mega Bridge Bangkok

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    32/104

    Sharq Building Kuwait

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    33/104

    And Many More

    North Danube Bridge, Hungary Turning Torso, Malmo

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    34/104

    And at Millau

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    35/104

    Section Through a Complete External Climbing Unit

    Struts punch against

    wall

    Lattice withsuspended formwork

    elements

    Self climbing systemACS with hydraulic ram

    (caterpillar)

    Rail

    Climbing Shoe

    Pouring Platform

    Finishing Platform

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    36/104

    One Complete Lift of the Shutter and Carriage

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    37/104

    How the Rail is Lifted

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    38/104

    Section Through a Complete External Climbing Unit

    Struts punch against

    wall

    Lattice withsuspended formwork

    elements

    Self climbing systemACS with hydraulic ram

    (caterpillar)

    Rail

    Climbing Shoe

    Pouring Platform

    Finishing Platform

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    39/104

    The Anchors

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    40/104

    Advantages of the ACS System

    Self Climbing Can climb without crane

    Carries the shutters on retracting carriage so all shutter

    work can be done on board

    Carries follow up platform for finishing off tasks

    Can operate in 180km/h winds

    Acts as windshield for rebar fixing and internal work Allows all shutter modifications

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    41/104

    ACS

    ACS is a self contained system that allows pure

    repetition of procedure with each climb, simplifying

    high rise concrete construction, and offering

    tremendous speed of turn round.

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    42/104

    Advantages of 4m lift heights

    Straightforward shutter maintenance on deck

    Easier control of concrete pours

    Highly accurate plumbing of shutters

    Greater adherence to performance tolerances

    Optimum positioning of ties

    One level in pour means less hole plugging

    Allows 3 day pour cycle.

    Allows maximum repetition of procedure actually verylogical

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    43/104

    Strict Formwork tolerances

    All edges are sharp and straight

    No horizontal board lines within the 4m

    pour

    Minimum no. of Ties and regular tiepattern and level

    Regular and unobtrusive anchor pattern

    0.5mm tolerance on vertical panel joints

    Max allowed 5mm deflection over 2m

    length of shutter face plate

    Trapezoidal inverse beading delineates

    pours

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    44/104

    The concrete and the shutter

    60N/mm strength

    Generated face pressure on shutter of 100kN/m2

    Reduce ties by tying over top of pour

    Consequently use steel faced and backed shutter

    Waler for Tie positions

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    45/104

    Pier Profile

    RunningTaper design means pier footprint changes dramatically

    P2 starts at 27m x 18m and tapers to 14.4m x 16.13m in single section

    Twin section tapers from 14.4m x 16.13m to 11m x 15.5m

    Need formwork system that can accommodate that change in layout

    With a pier involving over 60 pours, each one is different!!!!!,

    Each subsequent pour is 4m further off the ground

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    46/104

    The Changing Face of the Formwork

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    47/104

    In Conclusion, the challenge is

    To take a system based on repetition and use it on a

    job with NO REPETITION in the climb whatsoever.

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    48/104

    The Shutter - How do we cope with changing Geometry ?

    Adaptaptability

    Identify areas that remain Constant

    Vi d d Mill

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    49/104

    Viaduc de Millau

    Description of the formwork solution

    External Formwork

    Basic element

    Basic element

    Box out

    Compensationelements

    E t l Sh tt Ad t ti

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    50/104

    External Shutter Adaptation

    Adaptation to the

    geometry

    Telescopic Waler

    Sliding Corner

    T l i W l

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    51/104

    Telescopic Waler

    Telescopic steel waler in

    compensation area

    Rear of Steel Shutter

    Shutter rises and closes (exaggerated)

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    52/104

    Shutter rises and closes (exaggerated)

    Corner Closes (exaggerated)

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    53/104

    Corner Closes (exaggerated)

    Sliding Corner

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    54/104

    Sliding Corner

    The Corner Pieces

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    55/104

    The Corner Pieces

    Articulated corner connection Corner connection incompensation area

    The Platforms need to Adapt Also

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    56/104

    The Platforms need to Adapt Also

    Telescopic area

    Removables

    Internal Platforms

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    57/104

    Internal Platforms

    Telescopic area

    Internal Climbing System

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    58/104

    te a C b g Syste

    Every 8 lifts a concrete cross slab is cast internally

    Prevents continued use of rail climbing system

    Use conventional crane handled jump form system

    PERI SKS

    The Internal Climbing System

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    59/104

    g y

    The issues of adaption remain, but here the crane is used

    to lift units up and occasionally out.

    Major Internal Adaptions

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    60/104

    j p

    Can crane entire units out for modification

    The Twin Pier Section

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    61/104

    Twin Pier Platforms

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    62/104

    Externals

    Twin Pier Sections

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    63/104

    Internal

    Dont Forget Your Packed Lunch !!!

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    64/104

    The Finishes

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    65/104

    The Concrete Finish on the less exposed faces

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    66/104

    What was Used

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    67/104

    3 complete sets of formwork and climbing kit for single pierstructures (External)

    3 sets for above (Internal)

    3 complete sets for twin pier structures (External)

    3 Sets for above (Internal)

    1 complete set for the transition area from single to twin pier(Internal and External)

    Kit moved from pier to pier as programme needed

    6.5km2 of formwork face

    196 ACS Frames

    96 SKS Frames (Internal)

    12 special frames

    Design Demands

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    68/104

    For those of you who like paperwork

    800 Formwork Drawings

    100 Assembly Plans

    200 Method Statements

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    69/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    70/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    71/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    72/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    73/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    74/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    75/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    76/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    77/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    78/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    79/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    80/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    81/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    82/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    83/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    84/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    85/104

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    86/104

    9th December 2003

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    87/104

    The worlds tallest piers are all completed

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    88/104

    Not to be outdone

    PERI l b ti littl d t

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    89/104

    PERIs celebrations were a little more modest

    The Finish on the Exposed Faces

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    90/104

    The Peerless Piers

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    91/104

    Millau My - What a Bridge !.....

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    92/104

    A perspective on the height..

    The Royal Gorge Bridge Colorado

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    93/104

    The Royal Gorge Bridge, Colorado

    The Millau Toll Plaza

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    94/104

    The Segment Factory

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    95/104

    Segments or Elements cast inside factory shutter

    Since segments were to be joined in final construction theneighbouring segment was cast above.

    Used Ceracem instead of Reinforced concrete

    The Queen Bee and her Offspring

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    96/104

    Pre-Cast Elements

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    97/104

    The Finished Article

    A 98m x 28mConcrete Canopy

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    98/104

    Concrete Canopy

    Bolted and tensionedSegments

    Locates on 4 pairs oftrees

    4km from viaduct

    Stunning Gateway toan inspiring structure

    The Millau Viaduct

    2.46km Long on a 20km radius

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    99/104

    2.46km Long on a 20km radius

    The longest multiple cable stay bridge in the world

    The Tallest bridge piers in the world (244.96m)

    One third taller than the previous tallest

    Tip of the Pylon is 343m high

    Timeline

    16th October 2001 C t ti St t

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    100/104

    Construction Starts

    November 2002

    P2 reaches 100m height

    26th February 2003

    Deck launch begins

    28th May 2003

    P2 clears 180m to surpass Kochertal Viaduct and become worlds tallest pier

    November 2003

    Completion of the piers

    26th March 2004

    Southern deck reaches P3

    4th April 2004

    North Deck reaches P2

    28th May

    The Decks meet

    16th December 2004

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    101/104

    Its Open at Night, Too

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    102/104

    So what do you get for your 400m Euros

    700,000 visitors in first 9 months

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    103/104

    In summer now gets up to 50,000 vehicles per day

    Of Course, you could always have .

    A Regional Icon A Global Structure

  • 8/3/2019 ~$the Formwork to the Millau Viaduct

    104/104