The Effect of Energy Efficiency and Distributed Generation ... · Investment in Energy Efficiency...
Transcript of The Effect of Energy Efficiency and Distributed Generation ... · Investment in Energy Efficiency...
1
The Effect of Energy Efficiency and Distributed Generation on T&D Planning
USAEE National Capital Area Chapter Lunch Series
Michael Goldman
2
Northeast Utilities’ Massachusetts Operating Companies
NSTAR Gas & Electric Western Massachusetts Electric Company
Massachusetts Energy Efficiency Rankings
3
#1 2011 ACEEE State Energy Efficiency Scorecard - Massachusetts #1 2012 ACEEE State Energy Efficiency Scorecard - Massachusetts #1 2013 ACEEE State Energy Efficiency Scorecard – Massachusetts #1 2013 ACEEE City Energy Efficiency Scorecard – Boston
NSTAR Electric, 2.49% WMECo, 2.48%
What Effects are Increased EE and DG Having on the T&D System?
� What are the effects and associated benefits/challenges of increased energy efficiency (EE) efforts and distributed generation (DG) installations on the transmission and distribution system?
� Potential implications can be massive
– updated transmission & distribution planning can lead to the deferment of projects resulting in cost savings of hundreds of millions of dollars or more
– Possibly negate the need for new generation sources
Why is this such an area of interest now? 4
Stakeholders are interested in understanding what additional benefits energy efficiency is providing
Investment in Energy Efficiency Has Been Rapidly Increasing
$-
$1.0
$2.0
$3.0
$4.0
$5.0
$6.0
$7.0
$8.0
EE P
rogr
am S
pend
ing
or B
udge
ts ($
Bill
ions
)
Gas Electricity 5
Annual Electric and Natural Gas Energy Efficiency Spending or Budgets
2013 ACEEE State Scorecard
Increased Pace of Oil/Coal Power Plant Retirements
6
Age of Coal/Oil Generators in ISO New England
4,044
1,336 604
1,906
382
- 500
1,000 1,500 2,000 2,500 3,000 3,500 4,000 4,500
40-49 yrs 50-59 yrs 60+ yrs
Cap
acity
(MW
)
CoalOil
Approximately 8,300 MW of coal and oil capacity in New England is over 40 years old
Recent Retirements / Announcements • Brayton Point – 1,535 MW • Norwalk Harbor – 342 MW • Vermont Yankee – 604 MW • Salem Harbor – 749 Almost 3,300 MW will be gone in next 5 years
ISO New England 2014 Regional Electricity Outlook
Load Forecasting Ties EE to the T&D Planning Process
7
Internal Process of Incorporating EE into Planning
Energy Efficiency
Load Forecasting
T&D Planning
Energy Efficiency
ISO Planning
Bottoms up forecast of measures to be installed and corresponding level of expected savings
Reduces anticipated system load by expected EE savings
Forecast of required infrastructure to meet load uses load forecast adjusted for EE
ISO develops its long term forecast
EE Dept ensures numbers are in accordance with submitted M&V plan
External Process of Incorporating EE into Planning
Load forecasting is the first place where EE and DG can have an effect on T&D planning
More Precisely Incorporating EE into Load Forecasts Has A Large Impact – ISO-NE
8
ISO-NE forecast methodology is a good example of how altering EE assumptions can have a large impact on anticipated system wide load
Forecasting equations used for Yrs 4-10 (post-FCM) MWh = [ (1-BU) * Budget $ ] / [ $/MWh * PCINCR ] MW = MWh*PER
Where: BU = Budget uncertainty Budget $ = Estimated EE budget dollars $/MWh = Production cost PCINCR = Production cost increases PER = Peak to energy ratio
Final 2014 Energy-Efficiency Forecast 2018-2023, Energy Efficiency Working Group, 5/1/2014
Effects of EE and Other Demand Side Resources Show Up in ISO Forecasts
9
ISO-NE 10 Yr Summer Peak (90/10) Forecast with EE
Approximately 3000 MW difference due to including EE in long term forecast
Business as usual With FCM With EE Forecast
Final 2013 Energy-Efficiency Forecast 2016-2022, Energy Efficiency Working Group, 2/22/2013
Forecast is used for long-term transmission planning studies, economic planning studies, CELT report and Regional System Plan
Difference due to known EE in FCM
Difference due to long term EE forecast
10
Midwest ISO’s long term EE forecast reveals the sensitivity of peak demand savings to EE acquisition rates
Scenario Description Peak Demand Savings by 2030
GEP Scenario Declining avg EE savings from 1% in 2015, 0.9% in 2020, 0.3% in 2025, 0.1% in 2030
11,233 MW
Modified GEP Scenario 1% EE savings throughout forecast period 19,373 MW
Synapse State’s Avg Avg EE savings increases from 1% through 2015 to 1.4% from 2015-2030
23,392 MW
Synapse Best Practices Avg EE savings jumps to 2% from 2020-2030 29,618 MW
More Precisely Incorporating EE into Load Forecasts Has A Large Impact – MISO
Global Energy Partners. (Draft). 2010 Assessment of Demand Response and Energy Efficiency Potential for Midwest ISO, Report No. 1314 Peterson, Paul., Sabodash, Vladlena., Takahashi, Kenji. 2010. Demand Side Resource Potential A Review of Global Energy Partners’ Report for Midwest ISO
Altering a few EE assumptions resulted in a difference of over 18,000 MW in peak demand savings over the forecast period.
Hypothetical Example of Effect of Including Long Term EE Forecasts on PJM Loads
11
Impact of EE Forecast on 2014 PJM Non-Coincident Peak Load Forecast
8,900 MW Difference due to including long term EE in forecast
Jeff Schlegel, Doug Hurley, and Ellen Zuckerman, “Accounting for Big Energy Efficiency on RTO Plans and Forecasts: Keeping the Lights on While Avoiding Major Supply Investments”. 2014 ACEEE Summer Study
Hypothetical Example of how Transmission Year of Need Shifts with Inclusion of EE in Forecast
12 Jeff Schlegel, Doug Hurley, and Ellen Zuckerman, “Accounting for Big Energy Efficiency on RTO Plans and Forecasts: Keeping the Lights on While Avoiding Major Supply Investments”. 2014 ACEEE Summer Study
Demonstration of Deferral of Transmission Project Year of Need in PJM
Transmission Projects are Being Delayed/Deferred Due to Lower Load Growth
Construction / Equipment
Related, 4%
Deferral Based on
Reassessment of Load
Growth, 44%
Other, 28%
Permitting / Siting or
Environmental Litigation / Opposition,
21%
Budget / Cost Issues, 3% 100-120kV
28%
121-150 kV 7%
151-199 kV 7% 200-299 kV
34%
300-399 kV 15%
400-599 kV 9%
Current Transmission Project Delays and Deferrals
Reasons for Transmission Project Delays and Deferrals
NERC 2012 Long-Term Reliability Assessment
Over 5,000 circuit miles of transmission projects were considered delayed or deferred in 2013 with the majority due to reassessment of load growth
Quantified Benefits of EE and DG
� Deferred projects – ISO-NE identified 10 projects in Vermont and New Hampshire that
could be deferred • Avoided/deferred line upgrades and capacitor additions resulted in cost
savings of $260 million • Deferred need for new 345 kV line resulted in $157 million savings
• Total ISO-NE savings of ~ $420 million
– Con Ed substation project serving Brooklyn and Queens • Total cost would be $1.1 billion to get it online by 2019
• If project can be deferred to 2024, savings of $400-$500 million
– Tiverton substation upgrade • Deferring construction of 3rd feeder at this substation through DR would result
in savings of $653,273
14
Quantified Benefits
Less Congestion And Outages Could Result in Lower LMPs
15
Real time LMPs from Midwest ISO, 2/17/2014 Real time LMPs from Midwest ISO, 2/18/2014
Increased DG, co-location of generation and demand, or more transmission infrastructure could help reduce congestion and line losses, smoothing prices across a region
Midwest ISO (MISO) Contour Map and Table, accessed 2/17/2014 and 2/18/2014
Effects of Transmission Constraints – ERCOT 2012
16
2012 CREZ Infrastructure
• 577 instances of negative wholesale prices
• Average negative price was -$2.74
17
2013 CREZ Infrastructure
• 144 instances of negative wholesale prices
• Average negative price was -$2.20
Effects of Transmission Constraints – ERCOT 2013
18
2014 CREZ Infrastructure
• 21 instances of negative wholesale prices
• Average negative price was -$0.70
Effects of Transmission Constraints – ERCOT 2014
19
Effects of Transmission Constraints – ERCOT
EE Effect on Energy vs. Demand
20
ISO- NE Energy Efficiency Forecast through 2023 reveals the different effects that EE has on energy growth and demand growth
Demand Energy
Final 2014 Energy-Efficiency Forecast 2018-2023, Energy Efficiency Working Group, 5/1/2014
Energy forecast is flat while demand forecast is still increasing – suggests system is becoming “peakier”.
Growth in System Demand is Declining
21
The NERC-wide 10-year compound annual growth rate (CAGR) for on-peak summer demand is expected to fall for the 11th consecutive year
Peak demand is still increasing – but at a decreasing rate. This national trend is in line with the trends seen in the New England area.
NERC 2013 Long-Term Reliability Assessment
EE and DG May Be Able to Offset the Need for Some Transmission But Not All
Renewable Integration, 18%
Reliability, 59%
Economic or Congestion
Related, 11%
Other, 12%
22
Primary Drivers for New Transmission Projects
2013 NERC Long-Term Reliability Assessment
It is important to understand where EE and DG may be able to offset new transmission projects and where it cannot
Yes No Maybe
• Economic / Congested Related
• Renewable Integration
• Other • Reliability
Where Can EE/DG Make a Difference?
Reliability is key driver – is it due to load growth or contingencies?
� Transmission build out and capital spend is often driven by concerns other than load in short term:
– Reliability
– Compliance (satisfy N-1-1 conditions)
– Hardening the infrastructure against weather events
– Compensate for generation retirements
Energy Efficiency is unlikely to have an effect on transmission planning or capital expenditures in the short term
As load grows on Cape Cod, existing distribution infrastructure needs to be supplemented with transmission to ensure reliability
Drivers of T&D Construction Pose Challenges for EE and T&D
Demand Side Resources May Not Be Able to Meet Contingency Requirements for Planning Purposes
24
Sub-area Sub-area Load* (in MW)
Required MRA MW Reduction
Percentage of Reduction
Manchester/Barbour Hill
527 82 16%
Middletown 600 345 58%
Greater Hartford 1,283 614 48%
Northwestern Connecticut
484 310 64%
Total 2,894 1,350 47% *Sub-area Load= Remaining load after forecasted Energy Efficiency and cleared Demand Response reductions from FCA #1 – FCA #6 have been accounted for
Market Resources Alternative Analysis – Demand-side Results, Greater Hartford and Central Connecticut Area, ISO New England Demand Resource Working Group, January 30, 2013
ISO-NE Market Resource Alternative Analysis shows how large a load reduction would be necessary to meet contingencies
Load would have to be reduced by nearly 50% in the greater Hartford area to resolve all N-1 and N-1-1 issues
Greater Hartford Market Resource Alternative (MRA) Analysis
DG Interconnection Timing in Massachusetts
128
229
357
677
0
100
200
300
400
500
600
700
800
All Applications Requires SystemModification
Projects Above 2MW
Largest Project7.5 MW
Aver
age
Day
s to
Pro
cess
Distributed Generation Interconnection Application Time*
25
The time necessary to process interconnection has implications for customers finances and system planning assumptions
53% of MW
47% of MW
MA DOER website – Distributed Generation and Interconnection in Massachusetts
* Will not total to 100% as projects can fall into multiple categories
Radial vs. Network Systems
26
Network systems are normally utilized in densely populated urban areas, meaning that T&D will still be needed to get DG to major load centers
System engineers usually do not allow large DG systems on networked systems due to concerns over power backflow
Location Pop. Massachusetts 6,692,824
Boston 645,966
Bedford 95,078
Cambridge 107,289
Brockton 94,089
Fitchburg 40,383
Lynn 91,589
Pittsfield 44,057
Springfield 153,703
W. Springfield 28,684
Worcester 182,544
Total 22%
Network Distribution Systems in Massachusetts
DG vs. Transmission Comparison
27
Technology Size (kW) $/MW Units to Displace 765 kV line
765 kV Line 2,770,000 $1,083,032 n/a
Microturbine 65 $3,100,000 42,615
Microturbine 185 $3,000,000 14,973
Fuel Cell 300 $5,600,000 9,233
Fuel Cell 1,200 $4,820,000 2,308
Gas Turbine 3,000 $2,450,000 923
Gas Turbine 10,000 $1,520,000 277
Reciprocating Engines 100 $2,750,000 27,700
Reciprocating Engines 3,000 $1,450,000 923
Residential Solar PV 5 $4,965,000 554,000
Commercial Solar PV 35 $4,475,000 79,143
Residential Small Wind 3 $6,983,000 923,333
Commercial Small Wind 35 $4,717,000 79,143
Large kV transmission lines are able to transport quantities of electricity equal to hundreds, thousands, and in some cases hundreds of thousands of DG units
• This is a simplified example but illustrates cost and scale
• In some instances, hundreds of thousands of DG units would need to be installed at 6-7x times the cost of comparable transmission
U.S. Energy Information Administration, (2013). Updated Capital Cost Estimates for Utility Scale Electricity Generating Plants ICF International on behalf of the California Energy Commission, (2012). Combined Heat and Power: Policy Analysis and 2011-2030 Market Assessment PJM Media Website, (2006). AEP Interstate Project: Why 765KV AC?
Closer Integration and Collaboration with System Planning
28
2014 Substation Loading Capacity 2016 Substation Loading Capacity
Does Not Exceed Firm Capacity
75% Firm Capacity
At Firm Capacity
Substation Loading Key • Bi-annual update from system planning of
substation loading limits • Focus EE and DG efforts in constrained
areas • Issues still remain with timing and step
loads
Illustrative example of how closer collaboration between system planning and energy efficiency could help promote geo-targeting
Rhode Island Demand Response Pilot
29
Year 2014 2015 2016 2017 2018
Load Reduction Needed (kW)
150 390 630 860 1000
Year Unique Accounts
Central AC thermostats installed
Window AC plug load devices installed
% of 2014 savings goal achieved
% of total savings goal achieved
2012 158 35 0 31% 5%
2013 437 132 145 201% 30%
Total 595 167 145 233% 35%
National Grid is running a pilot in Rhode Island to determine if substation upgrades can be avoid using energy efficiency and demand response
kW Reduction Necessary to Defer Substation Upgrade
Abigail Anthony, and Lindsay Foley, “Energy Efficiency in Rhode Island’s System Reliability Planning”. 2014 ACEEE Summer Study
Progress to Date
How Can We Continue to Better Integrate EE into T&D Planning?
30
Designing CHP incentives in a way that could increase reliability might lead to smaller planned loads
Technology Group Size Availability (%) Avg Mean Down Times (hrs)
Reciprocating Engines <100 kW 97.33 13.71
Reciprocating Engines 100-800 kW 95.99 50.66
Reciprocating Engines 800 kW – 3 MW 98.22 27.06
Gas Turbines 500 kW – 3 MW 97.13 65.38
Gas Turbines 3 -20 MW 94.97 68.63
Gas Turbines 20 -100 MW 93.53 75.3
Energy and Environmental Analysis, Inc. 2004. Distributed Generation Operational Reliability and Availability Database Oak Ridge, Tenn: Oak Ridge National Laboratory
Installing multiple, smaller units instead of one large unit, decreases the chances of a whole facility going offline and requiring full support from the grid
Final Thoughts
� Is EE and DG making a difference?
– Yes
� How big is the effect?
– Difficult to quantify
– It’s the result of a compounded effect, not discrete events
– No readily available counterfactual
31