TENNESSEE J THE MEMPHIS DEPOT
Transcript of TENNESSEE J THE MEMPHIS DEPOT
5 71 0 File: 541.460.000nC.H.
J_ THE MEMPHIS DEPOTTENNESSEE
ADMINISTRATIVE RECORD
COVER SHEET
AR File Number _r] T
C.H.
571 1
BRAC Cleanup Team
Meeting Minutes
September 16, 1999
" 571 2
SEPTEMBER 8CT MEETINGMINUTES
Attendees
Name Organization Phone
Stanley Tyler RAB Member (901) 942-0329
Shawn Phillips Depot (901 ) 544-0611
Jordan English TDEC-DSF (901) 368-7953
Turpm Ballard EPA Region IV (404) 562-8553
Brian Deeken TDEC-DSF (901) 368-7955
JLrn Mornson TDEC-DSF (901) 368-7957
Denise K. Cooper Depot (901 ) 544-0610
Jack Kallal Depot (901) 544-0614
Scott Bradley CEHNC (256) 895-1637
Steve Duma CEHNC (256) 895-1144
Kurt Braun CESAM (334) 690-3415
Neil Anderson CESAM (901 ) 686-6195
Greg Underberg CH2M Hill (423) 483-9032
Terry Flynn Frontline (888) 848-9898
Review of Previous Meeting Minutes
The BCT discussed, approved and signed the August meeting mmutes.
Review of Open Action Items
The BCT and project team reviewed the action item list. Mr. Steve Dunn reported that the Memphis Depot
chemical warfare materiel removal action could not be moved ahead of the Ogden Depot project. Mr
Turpm Ballard responded to the question regarding the need for a feasibihty study for a record of decmton
that consisted of only institutional controls A feasibility study should be developed in order to compare the
costs of institutional controls to the costs of clean-up alternatives that allow unrestricted use. The
feasibility study will provide the public something to review by way of comparison Mr Shawn Phillipsfulfilled the action to provide the Depot Redevelopment Corporation (DRC) with documentation regardmg
sites that require no further action by providing the DRC a copy of the Federal Facilities Agreement. TheBCT changed suspense dates to pending for some project schedule items The attached action item list
provides updates to the August action items and provides action items resulting from the September BCTmeeting
Mr. Stanley Tyler requested clarificationofmformationprovlded m the action item revlew. Specifically,
Mr. Tyler asked what level of contamination would reqmre the government to return to the Memphis
Depot and conduct more cleanup actions. The BCT responded that the government would respond to
anythmg that was identified and detenmne the appropriate course of events Mr. Tyler asked ff there would
571
SEPTEMBERBCT MEETINGMINUTES
3
be some form of community notification if something was identified by a tenant. The BCT responded that
the government would be reqmred to follow the community involvement process identified in the National
Contingency Plan for removal actions, once the contamination was confirmed to be a result of the
government's past use of the facility and not from the tenant If the contamination was caused by the
tenant, then the tenant would be required to follow the same process
Review of Project Status
Offsite Monitoring Wells West of Dunn Field
Mr Kurt Braun reported that the Corps and the contractor, OHM, had negotiated the contract modification
for the installation of four additional offslte recovery wells The modification was at the district office for
s_gnature, but that it may not be signed untd the first part of October due to end of fiscal year workload
The contractor had dmcussed the project with the drilling sub-contractor and they may be able to mobilize
by the end of September based on the completed negotmtxon of the contract mo&ficatlon. Mr Braun willprovide Mr Phillips a schedule as soon as the contractors confirmed the dates
Interim Remedial Action for Groundwater Phase 11,4 - Additional Onslte Recovery Wells
Mr Braun indicated OHM had provided hun with an updated esttmate to install the four ad&tional
recovery wells Mr. Braun anticipated the wells would be installed by October 31, 1999, but wouldprovide Mr Phillips a schedule as soon as OHM confirmed the dates
Mr Philhps requested Mr. Braun and Mr. Dunn coordinate work schedules for the installation of the
&scharge piping system and the chemical warfare materiel removal action. Mr. Ptulhps requested thepiping system be m place and running by May 3, 2000
Operations and Maintenance for Wells
Mr. Braun said the contracting office had issued the request for proposal to Sverdrup Environmental, Inc.
and that they had conducted a site ws_t last week to lock at the groundwater pump and d_scharge system.
OHM and CH2M Hdl are updatmg the Operations and Mamtenance plan to mclude the monitoring
prevxously conducted by the United States Gcologlc Survey (USGS). Mr Braun anticipates recewmg the
updated plan by September 20, 1999, and awarding the contract on October 29, 1999 There will be no
break in O&M services as the current contract expires on November 4, 1999
Mr Philhps told Mr Ballard that the updated O&M plan requires two transducers to be placed m the
fluvml aquifer, one upgra&ent/onsite and one downgradient/offsite from the pumping system, to momtor
how the fluwal aquifer and the pumping system respond to precipitation The transducers monitored by
USGS were in the lower sands aquifer, but Mr. Phillips qnesttooed whether they were needed at all. The
BCT agreed the lower sands transducers were necessary to momtor how the lower sands responded to Allen
Well Field pumping Mr Braun questioned whether five transducers were enough Mr Phdhps instructedMr Braun to purchase six transducers - three for the lower sands wells, two for the fluvial aquifer and one
spare
Mr Ballard questioned if the momtonng wells to be installed west of Dunn Field would monitor the effects
of the four additional recovery wells Mr. Underberg responded affirmatwely that the additional
momtoring wells would be located to provide data on the effects of the additional recovery wells
Mr. Phillips also requested Mr Braun, Mr Underberg and Mr Dunn coordinate work schedules to allow
O&M of the onsite momtormg and recovery wells once the CWM removal action begins. Mr. Dmm
m&cated the contractors usually worked four 10-hour days, so O&M could occur on the days the
contractors were not working.
571 4 ....... ......SEPTEMBER BCT MEETINGMINUTES
Engineering Evaluation�Cost Analysis for the Old Paint Shop and Maintenance Area
Mr Braun received the final design from CH2M Hdl for this removal action Mr Neal Anderson was
reviewing the final demgn The request for proposal was scheduled to be awarded to Sverdrup by the end
of September, and the contract was scheduled to be awarded by the nuddle of November. Sverdrup would
then begm preparing the project safety and health plan and the work plan. Mr Braun anticipated the work
plan would be available for distribution to the BCT by January 15, 1999. Mr Braun will continue to
discuss vath Mr Ptullips how best to distnbut¢ the work plan. Mr Phillips anticipated a 30-day review of
the work plan by the BCT
Dunn Field Chemical Warfare Materiel Removal Action
Mr. Phillips began the chscusmon by aslang about the timeframe for work to begin at the Ogden Depot as
he wanted to discuss a trip to Ogden with the RAB tonight. The Defense Logistics Agency approved Mr.
Phdhps' request to fund the trip for two RAB members, and he wanted to begin the selection process Mr
Duma said the Site Safety Submissmn for Ogden was in the Department of Army review process, but that
he anticipated the contractors would mobilize on the jobsite m November 1999 Mr. Tyler volunteered to
mention the Ogden tnp and the need to choose two members during his BCT meeting remarks at the RAB
meeting.
Mr Dunn reported that annotated responses to comments on the draft Site Safety Submission (SSS) weresubmitted to the Depot, EPA and TDEC via emml on September 15, 1999. He requested that everyone
review their own comments and the annotated responses and contact him with any questions or comments
Mr Dunn reported that an advance copy of the draft final SSS with all appropriate Depot, EPA and TDEC
comments incorporated was scheduled to be subnutted to CEHNC for internal review on September 24,
1999. He anticipated the document would be forwarded to the BCT on October 4, 1999, with detailed
comment responses. The final SSS was scheduled to be distributed to CEHNC and the BCT in November1999. Once CEHNC has reviewed the fmal, it wall be forwarded to the Department of Army and the
Department of Health and Human Services in De_ember 1999.
Mr Ballard asked if evacuation procedures for the community had been incorporated into the Site Safety
Subrmssion as discussed at last month's BCT meeting Mr Phillips indicated he had discussed the matter
with Mr. Dunn and had provaded him with a point of contact and phone number for the Local EmergencyPlanning Committee. Mr. Phillips continued that he wanted to see m the SSS or the Protective Action Plan
(PAP) a summary of LEPC's evacuation procedures, at a mmimum, or LEPC's entire evacuatton
procedures, at a maximum. Mr Dunn &scussed the on-site notification chain and the maximum credible
event The BCT and Mr. Tyler stressed to Mr Dram that the community did not care about on-sitenotification chums or the maximum credable event The community wanted to know how they would be
notified in case of an emergency The BCT stressed to Mr Dunn that he needed to establish with the chainof notfficatlon with the LEPC and mclude this chain and the evacuation procedures in the SSS or PAP.
Mr Plulhps requested language such as, 'Upon any breakthrough of agent at the tent's exterior boundary,
the site safety and health officer will contact the LEPC LEPC will then determine how to proceed.' Mr
Terry Flynn suggested that the contractors conduct a dry run of the notification procedures once mobilized.
Mr. Phillips would provide comments on the action memorandum as soon as possible. Mr. Dunn will
provide the Depot contractor responses to the CWM removal EE/CA public comments on September 28,1999.
Dunn Field Remedial Investigation
Mr Underberg reported that CH2M I-hll processing the Dunn Field Remedml Investigatmn report and it
was on schedule to be distributed to the BCT on October 18, 1999 EPA, TDEC and CH2M l-hll
participated in a conference call on August 30, 1999, to discuss EPA and TDEC comments on the Dunn
Field risk assessment approach technical memorandum Mr. Underberg said the groundwater analytical
results from the well installed on the Belz property was free of volatde organic compounds (VOCs)
' 571 5SEPTEMBER BCT MEETINGMINUTES
Mr Phillips asked if there was a well between Dunn Field and the Allen Well Field, and Mr. Underberg
responded that it was the well installed on the Belz property that was free of VOCs. Mr. Underberg
continued that he had discussed the area's geology and hydrogeology with the University of Memphis
Groundwater Institute The general consensus was that depressed areas m the clay layer are located on
either end of Dunn Field Mr. Underberg mentioned that he needed the latest geophysical logs from USGS,
and Mr Ballard said he would contact USGS about provl&ng CH2M Hill with the information
Mr Underberg reported that he had identified with TDEC and the Depot four locations on the southeast
quadrant of Dunn Field to collect surface and subsurface soil samples One location was m the northem
porhon of the former bauxite pile area. One location was on the eastern edge of the fluorspar pile area
One was in the center ofa fiuorspar pile, and the sod bormg would be drilled through the concrete. One
was to the west of the westernmost pde In all, four soil borings to 30 feet below ground surface will be
drilled and five samples taken from each boring Three surface soil samples will be collected from a bare
spot where the newly planted grass has not grown. Aerial photos from 1964 showed a bare spot m the
same location, and that the spot was visible then. Mr Underberg said the spot could either be a swamp, as
the area holds water after a ram, or a concrete pad that has been covered with dirt since then Mr Tyler
asked what analysis would be run. Mr Underberg responded that the samples would be analyzed for the
full suite of analytes, since we have no information as to what may have been stored or spilled there. Mr.
Underberg wall provide each BCT member a sampling schedule via email
Mr. Ballard asked Mr. Underberg what he was looking at to clear the pistol range backstop Mr
Underberg responded that CH2M Hill had collected soil samples and analyzed them for metals. CH2M
Hill also dug pits into the backstop, looked through the removed dirt and found bullets. He continued that
the analytical results were not indicating risk levels that would require cleanup, but that the site was stillbeing evaluated m the Remedml Investigation Mr Underberg suggested s_eving the soft to remove the
bullets and reduce the cost of disposing of the dirt as a hazardous material, ff analytical results indicated
such. Mr. Anderson interjected that the cost of slewng the material would be manpower heavy and may not
be as cost effective as sunply removing one to two feet of sod and disposing of it
Mr Ballard suggested collecting confirmation samples before replacing any removed soft Mr Ballard also
suggested a way to calculate the risk 1) Weigh the excavated soft 2) Sieve out the bullets and weigh them.
3) Calculate the concentration as ffthe lead were chspersed in the soft, and estunate the risk from thatconcentratxon.
Mr Phillips brought the focus back to the need for a removal action or for the site to proceed through the
record of decision process. He reminded the BCT that since the lead was not migrating from the area and
that the property had not yet been transferred to become a park, the need for a removal acnon versus a
record of decision would be detenmned by the city's need for the area He suggested continuing with the
current process Mr. Braun offered the altematave that if the workload for Sverdrup slowed down, this soil
removal could be fit m. Mr. Ballard mentioned the documentation preparation and review as well as the
public participation required for a non-tune cnncal removal action and the BCT's upcommg review
schedule that may not allow a quick turn-around for a document review and approval. He continued that itcould be accomphshed as an intertm remedial action by pulhng the information from the ongoing Dunn
Field Remedml Investigation report and wrappmg it into a proposed plan. The proposed plan would also
require the BCT and public review and comment requirements, but it required less documentation
preparation than a removal action.
Main Installation Remedial Investigation
Mr. Underberg reported that the draft: final Main Installation Remedml Investigation was on schedule to bedistributed to the BCT on September 24, 1999 Mr Phillips provided Mr. Underberg the cover letter Mr.
Philhps also provided Mr. Underberg the address for Mr. David Ladd of USGS and requested two copies
be sent directly to Mr Ladd as part of the EPA subanttal.
. 571 6SEPTEMBER BCT MEETINGMINUTES
Mr. Underberg &scussed a recommendation to install another monitoring well offthe southwest comer that
resulted from development of the draft Main Installation Feasibility Study Mr Underberg indicated the
well should be installed between Elvls Presley Boulevard and the existing offsite monitoring well located
near the comer of Ball Road and Perry Road. Analytical data from this existing offsite well mdieated the
groundwater m that area was coming onto the Depot and it also indicated levels of PCE htgher than haswas found on the Depot Mr. Underberg said CH2M Hall had not determined if this was from an offsite
source and needed analytical data from the additional well to provide a better picture of what was
happening There are several potential sources, dry cleaners, m the area If the analytical data from the
additional well indicates the source is the Depot, then the data will be used to determine the extent of the
PCE plume.
Mr Philhps requested Mr Underberg to schedule installation of the additional well offthe southwest
comer of the Main Installation and provldmg the information via email directly to the Depot, EPA and
TDEC.
Mr Underberg proposed using a new amino assay field testmg kit to analyze the groundwater from theadditional well to quickly determine lfPCE was present. If this new field kit detected PCE, then Mr
Underberg wanted to close that well and move toward Elvls Presley Boulevard. Mr Plulhps respondedthat DLA would not want to chase the source once CH2M Hill determmed the Depot was not the source
Mr. Ballard interjected that the Department of Defense (DoD) has the authority to require someoneidentified as a source of contamination unpaeting DoD property to comply with the National Contingency
Plan and to clean up.
Mr. English added that the State was already planmng to conduct a prehminary assessment at that area.
He did not see identifying a potential responsible party and reqmring clean up as DoD's responslbfllty. He
said he appreciated DoD looking Into this area of contammation and for providing TDEC with the data.
Mr Underberg mentioned the PCE levels identified in the monitonng well north of Dunn Field on McLean
Street. Mr English indicated the State was also looking at that area for a possible preliminary assessment.
Mr. Ptullips mfonned Mr Underberg that if the first well installed offthe southwest comer of the MainInstallation indicated PCE, then he could install one additional well Mr. Ballard reminded Mr Phdhpsthat even if the source of the PCE contamination at the southwest comer was someone offslte, the
groundwater contanunatlon still affected the Community Environmental Response and Facditation Act(CERFA) environmental condition of category for those parcels. The BCT agreed to table this discussmn
untd they received further information regarding the source of PCE groundwater contaminatmn at thesouthwest comer of the Mare Installation.
BRAC Cleanup Plan
Ms. Cooper discussed the update of the BRAC Cleanup Plan (BCP) Work continued on Chapter 6 of the
BCP, so the Depot proposed distributing the draft BCP by September 30, 1999. The Depot will provade
revision pages that indicate text additmns and deletmns to allow greater ease m determining what was
updated. The Depot wdl request comments and concurrence on only the BCP Abstract and the installationrestoration schedules in order to forward the BCT to DLA on November 1, 1999
Ms. Cooper informed the BCT that Mr Dunn was workmg with the CWM field mvestigation contractorsand Mr Wilson Waiters, a Corps of Engineers CWM specialist, to prepare documentation regarding sites
identified as potentaally containing CWM m the 1997 Enwronmental Baselme Survey that were notincluded in the CWM removal action EE/CA Mr Philhps mdieated he had also discussed with Mr Duma
the issue of erastmg site numbers versus the site identifiers used m the CWM removal EE/CA, and MrDunn assured him the site numbers would be referenced m all future documentation.
571
SEPTEMBER BCT MEETINGMINUTES
7
Strategic Planning Session
Mr Flynn dmtributed a memo coneernlng the October 26 - 27 Memphis Depot Strategic Planning Sessionto be conducted at PickWick State Park that mcluded reformation regarding the accommodations and room
reservanons The BCT agreed to cooduct the Oetober BCT meetlag the afternoon of Monday, October 25,
1999, from 1 00 p.m until 5:00 p m. Mr Flyan will make arrangements for a conference room with the
hotel. The BCT suggested the following as Strategic Planmng Session agenda items' IRP schedule for the
BCP and the BCP Abstract. Mr. Flynn requested the project team provide Ms Alma Moore any other
agenda 1terns by October 15, 1999
Community Focus Group
Mr. Flynn provided the BCT a copy of the Focus Groups and Survey Report He indicated this report
provided the Depot and Fronthne with a real gauge of what affect the commumty relanons program have
had He continued by saying the Depot and Frontline must take this information, contmue to mold the
program based on the report's mformation and recommeodatlons, and continue to monitor future progress
using the same methods
Mr. Flyrm indicated the commumty's biggest issue, according to the focus groups and survey, was grounds
keeping. According to the report, the commumty feels that ffthe Depot cannot keep the grass mowed, thenhow can it do a quahty job of enxqronmental restoratmn, especially CWM removal The report also
mdtcated the community does not see any d_fferenee between the federal government at the Depot and the
city government. Therefore, the Depot Redevelopment Corporatmn's (DRC) actions impact the
commumty's attitude toward and trust in the Memphis Depot Caretaker Division.
Mr Enghsh recommended that the Depot resist that the DRC better involve the commumty or put more
effort into bnnging more reuse information to the commumty table He also recommended that the Depot
send the message to the commumty that public partlclpatmn regarding reuse occurred in the planmng
stages. Mr. Phllhps interjected the Depot cannot address the community's concerns regarding reuse. The
DRC is the appropriate organization to respond to these community concerns The Depot has neither the
knowledge nor the authority to respond to reuse issues involwng the DRC.
Mr Flynn continued that until the public puts pressure on the DRC, the DRC will let the Depot handle the
community's eoneems about reuse. The Depot needs to forward community information/coneerns to the
DRC for a response. The Depot should then respond to the commumty that the issue had been brought to
the DRC's attention If the Depot recewes no response, then the Depot should suggest that the community
contact the DRC or the DRC board of directors.
Mr English suggested reiterating the RAB charter mission statement as well as the missmns of the Depotand the DRC at the beginning of every RAB meeting. Mr. Jim Momson suggested the Depot prepares and
has available at every RAB meetmg a hst of frequently asked questions indicating the point of contact and
orgamzatmn to which the questaon pertains. Ms. Cooper also suggested including a reference to BCT or
RAB mectmg mmutes at which the issue was dmcussed
Mr. Flynn presented Mr. Ptulhps a plaque commemorating the 1999 Award of Excellence for External
Communicatloas Programs presented by the Canadmn Pubhc Relations Society for the commumty
relations program at the Memphis Depot Mr. Flynn also announced that the Memphis Depot's community
relations program had been awarded the International Association of Business Communicators 1999 Silver
Leaf Award for Community Relations
: 8571
SEPTEMBER 8CT MEETINGMINUTES
SI_AWN PHILLIPS
Memphis Depot CaretakerBRAC Environmental Coordinator
TURPIN BALLARD
Environmental Proteehon AgencyFederal Facihties Branch
JOint and Conservation
Division of Superfund
BRAC Cleanup Team member
DATE
_ "_ 571 9
"O_2
o
CD
_Z cn
u=
oo_ o
_D
_ _Oo
_ _ ._'__._.._._
-_ _'_
--_ _'_'12 ,._
._ _o_m om
Co
>
r_
o
o
e_.o
"-6
(.)
I
0o
r_
<
r_o
o
8
0
o
I
i
c_o 6
_ _ 0
_'_ _oo
_ _o
o
_ o ._
•_ -_- ._
o_
o
Ss_s
£
oo
I
_9
0
_ o
" 571 10
I I I ¢_ I I IO_
g >
00
r,.)
0 _
0)_ "7,_ o
o __ r..)
•_ .o o
.N
•r_ _0 _
0 ._
0
_.0
• N .._
o
o
I1)
o_
m_
e_
o
0
2
" _ "" 571 II
0
i _ I i i i i i i
0 0o o
oo _. _ __ _
_ 0 _ _
_ _ o oo _ 0= _ _
.o
"_ o _-_ m= _ o=o _' "m=o oo_ "_ _.
"_.
°o _ _ _"_- o=
• _,. ¢._ -_ _,0
I=
.,<I=
o"cl
"_ = 0
0 '_"0 _.)m _
0
_ _,_
0
_ o .
• -"""' 5?I 2
e_
_J_d
0
_ o_J
_o
_ o ,.__ n_ 0
0
o _ ..o
_ .o
5?I 13
FINAL PAGE
ADMINISTRATIVE RECORD
FINAL PAGE