TBM Facility Requirements in ITER and Estimated Cost ‘A very preliminary assessment’
description
Transcript of TBM Facility Requirements in ITER and Estimated Cost ‘A very preliminary assessment’
Special assignment, OFES, USA1
ITER, Cadarache, January 26, 2007ITER, Cadarache, January 26, 2007
Clement Wong, General Atomics, USAClement Wong, General Atomics, USAValery Chuyanov, Valery Chuyanov,
Chang Shuk Kim, Chang Shuk Kim, at this time the only TBM engineerat this time the only TBM engineerAlessandro Tesini, Alessandro Tesini, the remote handling managerthe remote handling manager
Markus Iseli, Markus Iseli, Kimihiro Ioki, Kimihiro Ioki, replaced by Michael Pickreplaced by Michael Pick
Manfred Glugla, Jerry Sovka, ITERManfred Glugla, Jerry Sovka, ITEROtto Bede, KFKI-RMKI, Hungary, Otto Bede, KFKI-RMKI, Hungary, generated the AEU drawingsgenerated the AEU drawings
most likely has left Cadarache most likely has left Cadarache
TBM Facility Requirements in ITER
and Estimated Cost‘A very preliminary assessment’
September 07 IO action items background, by C. Wong
footer text, location, date2
Three Interface Areas Three Interface Areas +tritium area a total of 4 areas+tritium area a total of 4 areas
Ancillary Equipment
1. Port Cell Area
2. Hot Cell Area
3. TCWS Area
EU HCPB helium system
TBM Port Plug
Cooling lines
footer text, location, date3
1. Port Cell Area: replacement of TBM1. Port Cell Area: replacement of TBM
TBM Removal:
Step 1: Disconnect port plug and ancillary equipment, move AEU awayStep 2: Bring in transfer cask and extract port plug and move it to hot cellStep 3: Move and insert port plug into the hot cell “red zone”
TBM Return:
Step 4: Test of TBM and ancillary equipment at the hot cell areaStep 5: Disconnect utilities and put port plug on the transfer cask and move it to the port cell Step 6: Insert TBM, take transfer cask away and reconnect TBM with the ancillary equipment
AEU & transport TBM transfer cask
Cutting and re-weldingof PbLi pipes on the AEwill be done in a tent
Hot cell area
Mainly for the purpose of cost estimate, transfer cask to be supplied by IO
footer text, location, date4
2. Hot Cell Area2. Hot Cell Area
Utilities: e.g. AC/DC, water, high pressure helium, diagnostics…etc., for the testing of TBM and ancillary equipment
Needs additional
• Hot cell “red zone” windows and services• RH equipment• Hot cell area for ancillary equipment maintenance• Utilities for TBM and ancillary equipment tests
To be parked and Maintained here
AEU
footer text, location, date5
TBM ExchangeTBM Exchange
• Since then at the TBWG-18 meeting, remote handling area presented the transport cask carrrying the tubes area and AEU
• EU group coordinated presentation with in-situ remote cutting and re-weld of tubes
• US presented a mostly hands-on port plug removal approach
• These are not only approaches and should be analyzed by parties
footer text, location, date6
footer text, location, date7
footer text, location, date8
footer text, location, date9
footer text, location, date10
US suggestion: Moving the bioshield inwardand re-locate the interface 2 to next to the AEU between11 and 9
footer text, location, date11
NextNext
• Action items from CS Kim