TaylorCivil 411 2014
Transcript of TaylorCivil 411 2014
-
7/25/2019 TaylorCivil 411 2014
1/21
10/01/20
Instrumentation of the TEO
(Tunel Emisor Oriente)
East Sewer Main Tunnel
Mexico City
Rob Taylor, B.ASc. P.Eng.
President, RST Instruments
Georox 74
RST Instruments Ltd.
Head Office: Maple Ridge, British Columbia, Canada
Mexico City/Distrito Federal
3rdlargest urban center in the world
8.8e6 / 21e6 population city/metro
1500 km2/ 7800 km2area city/metro
4e6 cars
Sewer peak flow 315 m3/s (sanitary + storm)
-
7/25/2019 TaylorCivil 411 2014
2/21
10/01/20
Geologic Setting
Once, Mexico City was a island in a large lake
The lake was >100 km long in a 2200 m
plateau surrounded by 5000 m volcanic peaks
The lake is gone, groundwater extraction has
caused massive (9m) settlement in the soft
clays to 40 m
http://localhost/var/www/apps/conversion/tmp/scratch_7//upload.wikimedia.org/wikipedia/commons/b/b3/AerialViewMexicoCity.jpg -
7/25/2019 TaylorCivil 411 2014
3/21
10/01/20
-
7/25/2019 TaylorCivil 411 2014
4/21
10/01/20
TEO Project
7 m ID / 8 m bored tunnel
62 km long
150 m3/s capacity
Depths 15-140 m (gradient/basement)
24 shafts, 6 TBMs, 6 contractors
230e9 pesos -> $18e9
-
7/25/2019 TaylorCivil 411 2014
5/21
10/01/20
Shaft Construction
24 shafts
Typically 12 m ID, 16 m ID for TBM launch
Made by slurry wall, steel ring beams
-
7/25/2019 TaylorCivil 411 2014
6/21
10/01/20
-
7/25/2019 TaylorCivil 411 2014
7/21
10/01/20
Shaft Instruments
Inclinometers
Strain Gauges
Vibrating Wire
Embedment Gauge
Vibrating Wire
Push-in Piezometer
Vibrating Wire Sensors
Common in geotechnical applications
Response is as frequency change, not voltageor resistance
Excellent immunity from wet cable conditions
-
7/25/2019 TaylorCivil 411 2014
8/21
10/01/20
R
F
v
L
F
sin2FFR
R
L
2sin
R
LFF w
R
R
Lvm
R
LFF wwR
2
m
Fv ww
w
ww
w
ww
wwww
E
Lf
A
AEfL
2
1
2
)( 22
0 ffCFs
Vibrating Wire
Physics
+VE
FACE
A1. POSITIVE DEVIATION VALUE I I I
UPPER
WHEEL
Inclinometer
-
7/25/2019 TaylorCivil 411 2014
9/21
10/01/20
Actually the Mexican approach is very
good:
Tough
Dry Accessible
TBM Tunnels
All drives are EPB TBMs
Ground support is by precast concrete lining
Lining is machine placed in the shield directly
behind the cutterhead and grouted
Secondary CIP lining slipcast to protect precast
mechanicals
-
7/25/2019 TaylorCivil 411 2014
10/21
10/01/20
Tunnel Lining Instrumentation
External Loading
Internal Response
Global Response
Vibrating Wire
Tunnel Lining
Total Stress Gauge
-
7/25/2019 TaylorCivil 411 2014
11/21
10/01/20
-
7/25/2019 TaylorCivil 411 2014
12/21
10/01/20
-
7/25/2019 TaylorCivil 411 2014
13/21
10/01/20
-
7/25/2019 TaylorCivil 411 2014
14/21
10/01/20
Rigid Body Lining Response
The rebar and concrete strain gauges measure
response within the lining sections.
What about the relative movement at the
joints?
The response takes place soon after
placement, but access near cutter is tough
-
7/25/2019 TaylorCivil 411 2014
15/21
10/01/20
Space is Tight
TBM mechanicals 95 m long, absolutely packed
Any diametral instrument (tape extensometer
etc) will never fit
We came up with a lining response system
based on sensing the tilt on each segment
Devices are bus-based, so connections are
daisy-chained, 4 pin connectors, goes in very
quickly, up and running in
-
7/25/2019 TaylorCivil 411 2014
16/21
10/01/20
What is MEMS?
Micro Electro-Mechanical System
Sensor and electronics are made in one
piece using microelectronic fabrication
techniques
For now, tiltmeters
MEMS Tiltmeters
Really a DC accelerometer: a = g sine (a)
Sensitive Axis ~ horizontal, asmall
Consists of:
Suspended mass
Spring suspension
Capacitive position sensor
Oscillator
Demodulator Amplifier (with calibration DAC etc.)
All on a single small block of silicon
M
MEMS Up Close
-
7/25/2019 TaylorCivil 411 2014
17/21
10/01/20
Instrument Summary
Instrumentation of the shafts and primary
lining segments has gone very well Long-term monitoring is challenging, as
distances, pressures, maintenance will be very
adverse
-
7/25/2019 TaylorCivil 411 2014
18/21
10/01/20
REVESTIMIENTOSECUNDARIODEFINITIVO
INYECCIN DECONTACTODOVELA-SUELO
EJE HASTIAL DEL
TNEL AINSTRUMENTAR
RASANTE DEL TNELA INSTRUMENTAR
DE EXCAVACIN
REVESTIMIENTOPRIMARIO
EJE HASTIAL DEL
TNEL AINSTRUMENTAR
CLAVE DEL TNEL AINSTRUMENTAR
RADIO
Progress Report
Theyve had a rough time of it!
3 years behind One shaft was flooded by overflow of adjacent
canal, yes, that is sewage!
All that sediment, water requires EPB TBM
But theyve hit a lot of rock, heavy going
Basalts and tuffs, need more powerful
machines $$$, time, politics
-
7/25/2019 TaylorCivil 411 2014
19/21
10/01/20
In the News
The Good News
Best news is: so far rock is not associated with
major water problems
Over 60% of tunneling done, secondary lining
going in
First drive is completed, in service
-
7/25/2019 TaylorCivil 411 2014
20/21
10/01/20
Whats Next
They have been recycling machines from
completed sections to speed up
New tunnel completion date is 2015, sewer
commissioned 2016
Next up: Tunel Poniente
Conclusions
Instruments provided valuable data on external
conditions, structure FS and response Because of the automated/prefab nature of
construction, observational method is risk
management for design
Integrating instruments into construction
systems reduced associated delay, improved
capture of early response
-
7/25/2019 TaylorCivil 411 2014
21/21
10/01/20
Questions?