Getting Ready for El Nino Wednesday, February 8, 2016 TAC Campus Tech Meeting

Transcript of TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community...

Page 1: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

Getting Ready for El Nino

Wednesday, February 8, 2016

TAC Campus Tech Meeting

Page 2: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

EL NIÑO FEMA Fullerton Flood Zone

• Text goes here.

Page 3: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

IT El Niño Preparation Updates

• Move IT equipment off of the floor– Basement/First Floor sweep - Completed

• POD is delivered and placed on the platform• Temporary Data Centers

– CP -250 • Electrical/Cooling work in progress• Ready to move equipment this week

– Irvine Data Center –• Equipment Move Completed

• Contingency plan for remaining Data Center Equipment– Move IT equipment from the basement to higher floors

Page 4: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

Move This Weekend• Complex Move• Requires a lot of collaboration• Coordinated shutdown and restart

procedures• IT Resources are available during the

entire move period• Details to follow

Page 5: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

Secondary Data Center Location

Page 6: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

POD On Site

Page 7: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

POD On Site

Page 8: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

Secondary DC Tentative Timeline• February

– 1st week : POD Configuration/Fiber Termination– 2nd week : POD Commissioning– 12th : Move redundant network equipment– 13th 2pm – 14th 6am: Move servers and storage

(Group 1) – Moodle will be down during the move.– 14th 2pm – 15th 6am: Move servers and storage (Group

2) – Titan Card will be down during the move.– 15th POD is operational with backup generator– 20th POD gets utility power and fully operational

Page 9: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

POD Move ScheduleFor TAC Only. Do not distribute outside of TAC/IT

Estimated Move Window

Saturday Sunday

Before 2PM Administrators shut down services completely. (Any VM’s not shut down by 2PM will be shut down by IT Server team.)

2PM-6PM NetApp, Moodle, ½ VCL, ½ email, ½ Prod Vmhosts

Compellent, ½ ERP, Equalogic, ½ Email. Web applications/DBs

7PM-11PM ½ VCL, Ironport, Telesoft, and ½ ERP

½ Prod Vmhosts, Colo Vmhosts, Wireless/Wireless housing, Csgold, Authentication services

11PM-Complete

Racking of Servers. Restoration of services. Validation and Testing.

*Titanium (down Sat 2PM-Sun 6am), Adobe Connect and VCL will be completely offline

*Titan Card, Departmental services in our VM /Colo Vmware will be down

**Communication to campus community is degradation of service Fri-Mon 2/12-2/15.

Page 10: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

Move Logistics• Command Center (PLS-299)

– Hours of operations (2pm – 11pm) Sat/Sun– Contact numbers

• Skype for Business (657-278-5962) PIN# 779027

• IT PMs at the Command Center, POD and Data Center

• IT Help Desk will be minimally staffed for general campus community calls

• Timely shutdown and restart

Page 11: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

What is Expected of Me?• Ensure you are on DL-Campus-Techs• Send cell phone number to [email protected]• Check e-mail continuously for updates during the move on Saturday

and Sunday• By Wednesday 2/10, ensure that your server patches are updated to

prevent delays during actual shutdown time.• Perform a test shut down early this week, if possible. • Pre-shutdown Applications/OS verification• Ensure that your servers are completely shut down by 2PM of the

designated day. • Validate applications hosted on VM’s as they are back online• Call in to Skype Command Center line for questions and updates• Communicating to your respective users of impact and providing

necessary updates.

Page 12: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

• April 12, 2016• Theme: Information Security• Amir will be the keynote speaker• Breakout Sessions• Vendors

Tech Day – Save the Date!

Page 13: TAC Campus Tech Meeting - fullerton.edu · Vmware will be down **Communication to campus community is degradation of service Fri-Mon 2/12-2/15. ... Tech Day –Save the Date! QUESTIONS.

QUESTIONS