DBCOMM 12 Page 1 of 4 www.ehansch.com 13 Design & build of a three storey office and professional centre, including civil and site service to a 40 acre property in Headingley MB. Master planning for the 40 acre property allowed the civil and site services to be installed to fully service all future development on the 40 acre property. CLIENT: SWAN LAKE FIRST NATION DESCRIPTION: DESIGN & BUILD 3 STOREY OFFICE AND PROFESSIONAL CENTRE CIVIL WORKS AND SITE SERVICES TO THE 40 ACRE PROPERTY SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL CENTRE 4820 PORTAGE AVENUE, HEADINGLEY MB

Transcript of SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL … · swan lake first nation swan lake first...

Page 1: SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL … · swan lake first nation swan lake first nation 3 storey office & professional centre 4820 portage avenue, headingley mb

DBCOMM 12

Page 1 of 4

www.ehansch.com

13

Design & build of a three storey office and professional centre, including civil and

site service to a 40 acre property in Headingley MB. Master planning for the 40

acre property allowed the civil and site services to be installed to fully service all

future development on the 40 acre property.

CLIENT:

SWAN LAKE

FIRST NATION

DESCRIPTION:

DESIGN & BUILD

3 STOREY OFFICE AND

PROFESSIONAL CENTRE

CIVIL WORKS AND

SITE SERVICES TO THE

40 ACRE PROPERTY

SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL CENTRE4820 PORTAGE AVENUE, HEADINGLEY MB

Page 2: SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL … · swan lake first nation swan lake first nation 3 storey office & professional centre 4820 portage avenue, headingley mb

The green field site in Headingley had new water main and RM of Headingley water

main metering chamber installed to the property. A low pressure sewer system

and below ground septic tank to service the office building. The land drainage

system and retention pond was design with flow restriction to an existing creek to

meet Manitoba Water Stewardship and Department of Fisheries and Oceans strict

requirements. The land drainage system provides drainage capacity for the 40

acre property’s future developments. New utilities have been installed into the

development, including a new MTS fibre optic hub, Manitoba Hydro gas and electrical

transformer and CSTE for the future development. The parking lot is illuminated with

a combination of pole mounted LED lighting, high level & low level LED light fixtures

and accommodates 215

spaces of light duty asphalt

parking with heavy duty

asphalt fire truck access

and egress to the building

front entrance to meet

RM of Headingley by-law

requirements.

DBCOMM 13

Page 2 of 4

www.ehansch.com

14

CLIENT:

SWAN LAKE

FIRST NATION

SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL CENTRE4820 PORTAGE AVENUE, HEADINGLEY MB

DESCRIPTION:

DESIGN & BUILD

3 STOREY OFFICE AND

PROFESSIONAL CENTRE

CIVIL WORKS AND

SITE SERVICES TO THE

40 ACRE PROPERTY

Page 3: SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL … · swan lake first nation swan lake first nation 3 storey office & professional centre 4820 portage avenue, headingley mb

The three storey office and professional centre is 53,899 square feet of non-

combustible building. Precast concrete piled foundation, cast in place grade beams

and pile caps provide the support for the structural slab and structural steel

framing. Upper floors are metal deck and reinforced concrete slabs, with a R40

modified bitumen roofing system with full latch line life safety system for building

maintenance. Exterior walls provide an R34 wall system, utilizing insulated structural

gauge steel studs with exterior finishing system of acrylic stucco, the windows are

large aluminum framed storefront windows and aluminum main entry doors. The

building heating and ventilation system is provided by 29 roof top units and 1 large

heat recovery ventilation unit providing a very efficient mechanical system, which

is fully monitored with a computerized building management system. The building

is fully sprinklered with each floor its own specific zone. A public central core

incorporating 2500lb hydraulic elevator, high end finishes with ceramic floor tiles,

drywall bulkheads, LED light fixtures, custom millwork and automatic plumbing

fixtures to the public washrooms and universal toilet room, to meet full accessibility

code requirements.

DBCOMM 14

Page 3 of 4

www.ehansch.com

15

CLIENT:

SWAN LAKE

FIRST NATION

SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL CENTRE4820 PORTAGE AVENUE, HEADINGLEY MB

DESCRIPTION:

DESIGN & BUILD

3 STOREY OFFICE AND

PROFESSIONAL CENTRE

CIVIL WORKS AND

SITE SERVICES TO THE

40 ACRE PROPERTY

Page 4: SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL … · swan lake first nation swan lake first nation 3 storey office & professional centre 4820 portage avenue, headingley mb

An integrated design process was utilized through-out the project and proved to be

essential during the tenant improvements phase of the design facilitating smooth and

seamless coordination between the 23 tenants, our client Swan Lake First Nation

and the Ernst Hansch Construction Ltd design team over the 3 phases of the tenant

improvements to meet the client’s allowance and tenant’s requirements. Specialist

tenant requirements incorporated into the design included a 2nd floor data centre which

required a 40KW 72 hour running standby generator complete with transfer switch

and pre-action dry sprinkler system and fire alarm monitoring. The tenant improvements

consisted of large boardroom, large class rooms, computer labs, cafeterias, kitchens,

coffee stations, large reception areas,

printing, storage and data rooms, both

open plan and enclosed office spaces.

The building is fully monitored with

internal & external CCTV security

cameras, card access systems and

automated system to lock and unlock

the building entry doors for business

hours.

CLIENT:

SWAN LAKE

FIRST NATION

SWAN LAKE FIRST NATION 3 STOREY OFFICE & PROFESSIONAL CENTRE4820 PORTAGE AVENUE, HEADINGLEY MB

DBCOMM 15

Page 4 of 4

www.ehansch.com

16

DESCRIPTION:

DESIGN & BUILD

3 STOREY OFFICE AND

PROFESSIONAL CENTRE

CIVIL WORKS AND

SITE SERVICES TO THE

40 ACRE PROPERTY