Supplier Quality Manual - Valcor Engineering Corporation€¦ · SUPPLIER QUALITY MANUAL SQM-001...
Transcript of Supplier Quality Manual - Valcor Engineering Corporation€¦ · SUPPLIER QUALITY MANUAL SQM-001...
Uncontrolled when printed. Verify document revision online at www.Valcor.com
Valcor Engineering Corporation
SUPPLIER QUALITY MANUAL
SQM-001 August 20, 2014
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 3 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Contents 1.0 Supplier Quality Visual Model ........................................................................................................... 4
2.0 Valcor’s Quality Policy ....................................................................................................................... 5
3.0 Introduction ...................................................................................................................................... 5
3.1 Precedence of documents ............................................................................................................ 5
3.2 Certificate of Conformance and Analysis ...................................................................................... 6
3.3 Record Retention .......................................................................................................................... 6
3.4 Flow-Down to Sub-Tier Suppliers .................................................................................................. 6
3.5 Foreign Object Damage (FOD) Prevention .................................................................................... 6
3.6 Right of Access .............................................................................................................................. 7
3.7 Export Control ............................................................................................................................... 7
4.0 Supplier Approval Process ................................................................................................................ 8
5.0 Supplier Audit Process .................................................................................................................... 10
6.0 Change Request .............................................................................................................................. 12
7.0 Non-Conformances ......................................................................................................................... 13
7.1 Supplier Deviation Flow Chart .................................................................................................... 13
7.2 Supplier Quality Escape Flow Chart ............................................................................................ 15
8.0 Supplier Corrective Action .............................................................................................................. 17
9.0 Delivery Requirements .................................................................................................................... 19
9.1 Packaging .................................................................................................................................... 19
9.2 Foreign Object Damage (FOD) .................................................................................................... 21
9.3 Labeling ....................................................................................................................................... 21
10.0 Supplier Performance ..................................................................................................................... 22
10.1 Overall Performance Rating ........................................................................................................ 24
11.0 Dock-to-Stock Authority.................................................................................................................. 25
12.0 Valcor Owned Property ................................................................................................................... 26
13.0 Appendix A: Valcor Supplier Quality Survey SF1016A .................................................................... 27
14.0 Appendix B: Deviation/Change Request SF1019A .......................................................................... 32
15.0 Appendix C: Material Rejection Report SF-104/R.03/12 ................................................................ 34
16.0 Appendix D: Corrective Action Request/Report SF1018A .............................................................. 36
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 4 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
1.0 Supplier Quality Visual Model
Supplier Managment
Supplier Collaboration
Supplier Information
Certificate Management
Risk Assesmnet
ScoreCard
Reference Documents
Valcor Documents and Specifications
Warranty and Cost Recovery
SCAR
Change Request
Certificate of Analysis/
Conformance
ESTITRACK
Real-time data driven Decisions
Supplier Improvement
Dock-to-Stock
Reduce Risk
Customer Satisfaction
Engineering
Purchasing
Quality Inspection Data
Supplier Related Customer Complaints
Budget Time Cost
Potential Supplier
Performance Audit/ 3rd Party Audit
Deviation Request
Quality AssuranceInformation
Management
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 5 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
2.0 Valcor’s Quality Policy
Achieve total customer satisfaction by continuously improving all work processes to satisfy our internal and external customers
3.0 Introduction Valcor’s mission is to provide innovative, high quality, reliable fluid control components and systems to
customers in response to their specialty requirements. This supplier quality manual is based on
prevention and continuous improvement rather than defect detection. Valcor expects their suppliers to
aspire to zero defects, zero failures, and zero losses.
Valcor encourages all suppliers of components, materials, or services to institute a Quality Management
System that follows: AS9100 Quality Management System Requirements for Aviation, Space & Defense
Organizations and/or ISO 9001:2008 International Industry Quality Standards. The Nuclear division may
impose additional nuclear specific requirements depending on the nature of work. Valcor may choose to
conduct on-site assessment(s) to determine the supplier’s ability to meet Valcor’s requirements.
3.1 Precedence of documents In the case of a conflict and between the requirements, the precedence of documents is as follows;
1. Purchase order
2. Terms and Conditions
3. Part Drawing
4. Supplier Quality Manual
3.2 Applicable Forms The following forms are referenced within this manual and are available from
http://www.valcor.com/customer-product-support/suppliers/
Form Number Form Title
SF1016A Valcor Supplier Quality Survey
SF1019A Deviation/ Change Request
SF1018A Supplier Corrective Action Request
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 6 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
3.3 Certificate of Conformance and Analysis All suppliers shall provide a Certificate of Conformance, Physical or Chemical Analysis, or Calibration,
when applicable. Each shipment must be certified by an authorized representative with their signature,
title, and date. The supplier shall verify and confirm compliance with the drawing, specification, and/or
any special processes as described on the Purchase Order. Without this documentation, Valcor cannot
receive the parts, and both the payment and parts will be placed on hold until resolution in
documentation can be provided.
The following information is required on the Certificate of Conformance at a minimum:
Supplier Name, address and contact information and manufacturer’s name (if different from
Supplier)
Purchase Order Number
Valcor part number, revision, lot, and quantity
Specification Number including revisions and amendments
Additional information may be required for parts returned for rework
Identify when parts have been reworked
Return Purchase Order Number
Non-conformance Deviation Number
3.4 Record Retention Valcor shall identify supplier records requirements on the purchase order, drawing notes, or
procurement specifications. The delivered product’s records shall be maintained for a minimum of
fifteen (15) years at the supplier, unless otherwise specified. Upon request, the supplier shall provide
copies to Valcor.
3.5 Flow-Down to Sub-Tier Suppliers Suppliers shall flow down applicable requirements noted on Valcor’s Purchase Order and Terms and
Conditions to all sub-tier suppliers.
3.6 Foreign Object Damage (FOD) Prevention When applicable, noted on Valcor’s purchase order, the supplier shall establish, document, and maintain
a program to control and prevent FOD during manufacturing, assembly, test, inspection, and any sub-
tier supplier operations. This program can follow NAS412 or be an otherwise approved control by
Valcor. The supplier shall maintain work areas and inspect for foreign objects/materials to reduce the
risk of FOD incidents.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 7 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
3.7 Right of Access Suppliers shall allow Valcor, customers and regulatory agencies reasonable access to the applicable
areas of all facilities involved in fulfilling the purchase order requirements and to all applicable
documentations. Valcor has the right to conduct surveys, audits, inspections, and surveillance of
Supplier’s facilities and sub-tier suppliers with prior coordination to determine capability.
When required, source and/or government inspection will be noted on the purchase order. The supplier
shall ensure the product is not released until source and/or government inspection is completed.
3.8 Export and Import Compliance The products, technical data and services produced and/or provided by Valcor Engineering Corporation
may be subject to the provisions of the Export Administration Act of 1979 (50 USC 2401-2420), the
Export Administration Regulations promulgated there under (15 CFR 730-774), and the International
Traffic in Arms Regulations (22 CFR 120-130). These statutes and regulations impose restrictions on
import, export, re-export and transfer to third countries of certain categories of hardware, data,
technical services and information, and that licenses from the U. S. Department of State and/or the U. S.
Department of Commerce may be required before such hardware, data, technical services and
information can be provided/disclosed hereunder, and that such licenses may impose further
restrictions on use and further disclosure of such data, technical services and information.
Disclosure of data, technical services and information to foreign persons, as defined at ITAR 120.16, and
at EAR 734.2(b), is subject to the above regulations regardless if the export occurs in the U.S. or
abroad. Violation of these export laws are subject to severe criminal penalties.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 8 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
4.0 Supplier Approval Process This process applies to all new potential Valcor suppliers and defines Valcor’s criteria of selection and
assessment.
Flowchart
Send survey to Supplier
Review if Supplier requirements were met per
survey
Supplier Approved?
Determine if an Audit is needed?
Approve Supplier
Potential Supplier?
Perform Audit
Supplier approved per
audit?
Supplier to fill out Survey
Supplier Agrees to an Audit?
YES
Disqualify Supplier
YES
Supplier to return survey and other
required documents
Request for Supplier Corrective Action
Supplier to return corrective Action
Work with Supplier?
NO YESYES
YES NO
NO
NO
Supplier
Purchasing
Quality Assurance
Review Supplier CA
Accept CA?
YES
NO
NO
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 9 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Supplier Approval Process
Responsibility
All potential suppliers are required to fill out a quality survey (SF1016A) to collect general information about the company and its products or services. This form will be used to indicate the standards of a potential supplier and will be performed as a self evaluation survey.
Potential suppliers will be evaluated on their ability to provide a quality product based on the Supplier Quality Survey Form and the Supplier’s quality system certifications.
Valcor recognizes all third –party certifications that are compliant to ISO-9001, AS9100, NADCAP, and/or ISO 17025 accreditations which an onsite audit may be waived. The supplier quality survey form and attached certifications will be assessed by Valcor’s Quality department and will reserve the right to conduct an onsite audit when deemed necessary. Suppliers that meet all requirements will be placed on the Approved Supplier List.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 10 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
5.0 Supplier Audit Process The purpose of this procedure is to establish a process to evaluate the supplier’s quality system, control
of process and product quality, and the maintenance of product compliance.
Audit Flow Chart
NO
Audit is required
Schedule Audit and send the Audit agenda to the
Supplier
Supplier Agrees to an Audit?
YES
Perform Audit
Supplier to Review Audit Report and send a response when applicable
Request for Supplier Corrective
Action
NO
Review Audit Report Response
Accept Supplier Response?
NODisqualify Supplier
NOSend Feedback to
the supplier
Review Supplier CA
Supplier to return corrective Action
Determine if a follow-up audit is
neededNO
YES
Accept CA?
YES
Update Supplier List
YES
YES
Supplier
Quality Assurance
Purchasing
Send Audit Report to Supplier
YES
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 11 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Supplier Audit Process
Procedure
Valcor may conduct an audit at the supplier to make a physical evaluation of the supplier’s quality system. Audits performed at the supplier will be completed by the appointed lead auditor.
Non-conformities observed during Audit
Upon detection of a nonconformance, the auditor’s first concern will be to determine if any work in process is affected and will verbally notify the supplier. The supplier will immediately need to stop work on that item. In all cases of a non-conformance a quality audit report will be sent to the supplier for the purpose of initiating a corrective action plan. The report shall be submitted within a specific time period not exceeding 30 days.
Follow-up audit
A follow up audit at the supplier, when directed by Quality Assurance, will be performed to assure effective action has been taken to correct the significant condition.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 12 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
6.0 Change Request When required, the supplier shall not change the plans, drawings, designs, product definition, processes
or specifications associated with the parts referenced on the Purchase Order. If a change is needed, the
supplier and sub-supplier must receive prior written approval from Valcor.
Configuration Control Flow Chart
Change Request is initiated
Review Change Request
Approve Change Request
YES
Make appropriate changes and update PO
NOUpdate Request
database
Supplier
MRB Review
NO
Repeat Request
YES Purchasing
Communicate Y/N to supplier
Procedure
The supplier submits a Change Request form (SF1019A) and includes a complete description of the
proposed change to Valcor’s Purchasing Department. Based on the change request, it will be evaluated
by engineering, purchasing, and/or quality assurance. Once the Change Request is dispositioned, Valcor
will inform the Supplier.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 13 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
7.0 Non-Conformances A non-conformance exists when a discrepancy is found in packaging, documentation, and/or quality
(defects in form, fit, or function) to the part or P.O. requirements.
Non-conformances will be identified:
At supplier prior to shipping – Supplier Deviation Flow Chart – Section 7.1
At Valcor – Quality Escape Flow Chart – Section 7.2
7.1 Supplier Deviation Flow Chart
Detect a quality deviation
Issue and forward the Deviation
Request to Valcor
Approve deviation request?
Parts need to be replaced
Receive Deviation Form
Supplier
Purchasing
MRB Review
Notify Supplierof rejection
YES
Notify Supplier of approval
Send Rejected Deviation Report to the Supplier
Annotate Deviation # on
CofC
Send parts and a copy of an approved
deviation to Valcor
NO
Receive parts into inspection
Recieving
Corrective Action
Required
Quality Assurance
Send Corrective Action Request
to SupplierFollow section
8.0
YES
NO
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 14 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Non-Conformance: Supplier Deviation
Procedure
The supplier shall initiate and submit a formal Deviation/Change Request (SF1019A) to Valcor for
disposition (approval or rejection) of the non-conforming parts or process. The deviation form shall be
completed per the following:
Supplier and Part Information
Current Requirement: Fully describe the current part or process requirements and
specifications.
Request for Deviation: Fully describe the requested deviation from the current part or process
requirements and specification
Reason for Request: Describe the reason for the deviation.
And forwarded to Valcor’s Purchasing Department (use email unless not available, otherwise send as
facsimile). The Supplier shall provide any test and inspection data to support their request for approval
of the deviation. Purchasing will coordinate the disposition within Valcor and return a response to the
supplier within 72 hours.
Deviation Approval
If the deviation request is approved, Purchasing will inform the supplier of the disposition. The Supplier
is required to indicate the approved deviation number on their Certificate of Compliance/Conformance
and include an approved copy of the deviation with the parts. When all paperwork has been completed
and approved, the product may then be shipped. The parts or materials shipped under an approved
deviation request shall be tagged with the deviation number.
Deviation Rejection
In the case that the deviation request is rejected, Purchasing will notify the supplier and return the
rejected deviation form. The discrepant material and/or parts may not be shipped to Valcor. The
supplier will then need to replace the parts to fully meet the Purchase Order specifications.
Corrective Action
Valcor may issue a Supplier Corrective Action based on deviation request. Suppliers must follow
Corrective Action steps as identified in Section 8.0.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 15 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
7.2 Supplier Quality Escape Flow Chart
Material Rejection Report (MRR) initiated and
reviewed
Quality Assurance
Use as is
Return compliant parts to Valcor
Supplier
Rework in house
MRB Review
Non-conformance detected
Scrap, Rework, or Replace
Containment of affected items
Communicate and send reports to
Supplier
Is a Corrective Action Required
NO
YES
Send Corrective Action Request to
SupplierFollow Section 8.0
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 16 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Non-Conformance: Supplier Quality Escape
Procedure
The discrepancies will be documented on a Material Rejection Report (MRR). The MRR will be evaluated
by Valcor’s Material Review Board (MRB) personnel who will determine the disposition of the discrepant
parts and a copy will be sent to the Supplier. The supplier may contest the quality escape with objective
evidence.
Valcor will disposition the supplier’s parts per the following:
Return to Supplier
Use as is
Rework in house
When returned, the supplier must have a method to distinguish on paper and clearly identify if each
shipped part has been:
reworked
replaced
left unchanged
If requested on the PO or drawing, the Supplier shall make Valcor aware of any processes that are outside of the regular production procedures or controlled work conditions in critical processes (forging, casting heat-treating, welding, stamping, and any other special processes). Corrective Action
Valcor may issue a Supplier Corrective Action based on a quality escape. Suppliers must follow
Corrective Action steps as identified in Section 8.0.
Charges to Supplier
Valcor, at their discretion, may choose to rework or sort any non-conforming parts to prevent
interruption of the production line. Valcor reserves the right to charge the supplier for all costs
associated with the quality escape.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 17 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
8.0 Supplier Corrective Action This process is to outline the Supplier’s submission of a Corrective Action report.
Corrective Action Flow Chart
Develop a Corrective Action Plan
Send Corrective Action to Valcor
Identify Corrective Action is needed
Send Correction Action Request to
the Supplier
Contain defective hardware
Review CA Plans
Determine Root Cause
Approve CA?
Audit Required?
YESComplete Audit at
Supplier
NO
CAR effectiveness review
Close Corrective Action
Quality Assurance
Supplier
MRB Review
Communicate with Supplier
NO
Effective? NOYESCloseout CAR
Verify findings on CA have been
adressedYES
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 18 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Supplier Corrective Action
Procedure
A Supplier Corrective Action Request/Report (SF1018A) may be required when a nonconformance is
identified. Containment must be completed within 72 hours and the corrective action plan must be
submitted within 30 calendar days of the initial request.
Upon Supplier notification that a Corrective Action Request plan is approved, the supplier is expected to
complete all planned actions within 60 calendar days unless otherwise agreed to by Valcor. Valcor and
the supplier will verify and ensure that all findings on the Corrective Action have been addressed;
however they do not need to be closed at the same time. The effectiveness review due date will be
determined as appropriate and will conclude if the achieved results were met. A supplier corrective
action request form will stay open until the verification and effectiveness review have been validated by
Valcor.
An extension may be granted, only if the supplier made an initiative and periodic updates were provided
to Valcor. When there is no communication made between the supplier and Valcor, the request will be
denied and the supplier’s scorecard will be affected.
A repeated nonconformance is an indication of poor root cause analysis and/or corrective action. If such
a case arises, Valcor will pose rigid containment requirements based of the severity of the
nonconformance and re-assign a second corrective action request. Due to the risk it may present to
Valcor or its customers, an onsite supplier audit may be required.
If the Supplier does not know how to complete the corrective action request, it is the responsibility of
the Supplier to contact Valcor’s Supplier Quality Department for assistance.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 19 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
9.0 Delivery Requirements The Supplier will inform Valcor of any delay in delivering the product and provide a new date. If the
Supplier ships non-conforming (quality escape) parts and materials to Valcor, the Supplier will be
responsible for the return expenses.
9.1 Packaging Suppliers are responsible to ensure that parts meet same quality conditions as they were manufactured.
All supplier packaged shipments shall follow good commercial practice, unless otherwise stated on the
purchase order and/or drawings.
Piece part Cell Packaging Acceptable Bulk Packaging
- Sub- assemblies - Critical parts* - Tubes (non-raw material) - Seats - Seal discs - Machined threaded parts - Bodies - Filters - Other parts will be noted on PO
- Washers - Nuts - Screws - Springs and Helicoils - O’Rings
*All items that have a 16 Ra surface finish or lower (defined on the drawing) are considered as “critical
parts”.
The shipping container and parts requirements are, but not limited to:
package each item separately to ensure adequate protection from physical contact with
other parts
packaging must be strong enough for the weight of the part for it to remain intact
parts are cushioned against impact from each other
parts are secured to prevent movement during shipment
package to provide enough clearance from the item and the external packaging
o To prevent product damage against shock and vibration there should be
cushioning placed away from the walls of the box.
Machined castings, forging parts, and other parts subject to corrosion shall be packaged with anti-corrosive packaging such as capping, VCI anti-rust wrapping/bagging, plugging, covering, or any other suitable methods to prevent against cosmetic and functional damage of the part.
Additional special packaging requirements will be identified on the Purchase Order or drawing.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 20 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Packaging Requirements Examples
Acceptable Packaging Suggestions
Unacceptable Packaging- will be written up on a non-conformance
-Parts packaged in single tubes to protect ends (size can vary). -Cushioned from each other to prevent shock, vibration, and damage
-Parts are able to move freely -Not protected from each other -Not enough clearance from external packaging
-Sub-assembly/valves protected and adequately cushioned from the external walls -Inlet/outlet ports capped and plugged
-Sub-assembly/ valves not protected from each other. -Threaded inlet/outlet ports not protected
-Parts wrapped in anti-corrosive bags
Rust
-Parts not wrapped and subject to corrosion
Further examples go to www.Valcor.com and click the “Supplier” link.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 21 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
9.2 Foreign Object Damage (FOD) As defined on the purchase order, all parts with openings, internal and external threads shall be
protected from foreign object damage. Packaging materials that generate particles, fibers, or other
debris are not acceptable.
Any form of “free flow or loose fill” material (such as peanuts, popcorn, or similar) regardless of material
type is not acceptable as this will create a FOD hazard.
Example of Packaging a FOD prone item:
Packaging Requirements
9.3 Labeling Parts and material must be identified by the supplier with an identification label on each box, crate, or
container shipped to Valcor. When shipping a product, the Purchase order number must be referenced
on the UPS, FedEx, or other carrier shipping label.
An identification label at minimum should have the following information:
Purchase Order
Supplier name
Box X of Y (example “Box 2 of 3” if it is the second box of a total of 3).
Example: Threaded part with caps and plastic bag
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 22 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
10.0 Supplier Performance Supplier performance will be monitored on a monthly basis through the purchasing and quality
departments and will be available quarterly to the supplier. The data will show comparative results and
will provide the strengths and weaknesses amongst individual suppliers.
The measurement for supplier performance will be evaluated on the following criteria; quality and
delivery.
Main Categories
Category Total Points Sub-category Weight
Quality 100
# Quality Escapes 60%
# Deviations 20%
Past due Corrective Actions 10%
Accuracy of Paperwork/Documentation 10%
Delivery 100 % On time Delivery 100%
Sub-Categories
Main Category : Quality Total Weight : 100%
Sub-category Weight Points Evaluation Basis
# Quality Escapes 60%
100 0 quality escapes
0-99
Measures a supplier's quality impact at Valcor to meet agreed specifications .6 x (total lots -# quality escapes/ total lots ))x 100
# Deviations 20%
100 0 deviations
0-99
Measures a supplier's quality impact prior shipping to Valcor to meet agreed specifications. .2 x (total lots - # deviations/ total lots ))x 100
On time Corrective Actions 10%
100 0 late Corrective Actions
0-99
Measure the responsiveness of a corrective action .1 x (On time Corrective Actions/ Total Corrective Actions) x 100
Accuracy of Paperwork/Documentation
10% 0-100
Measures errors that appear on the C of C (qty received PO #, part number, revision, and/or missing special processes) .1 x (# accurate documents/ total lots received) x 100
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 23 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
Main Category : Delivery Total Weight : 100%
Sub-category Weight Points Evaluation Basis
% On time Delivery 100% 0-100 Measures the agreed delivery date on the PO (on-time shipments/ total shipments received) x 100
Separate consideration will be given for low volume suppliers. Adjustments will be made as applicable to
the performance categories and their weights to reflect the different purchase order requirements.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 24 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
10.1 Overall Performance Rating Valcor’s supplier rating system measures the performance of current suppliers and rates them based on
a supplier scale.
Performance Rating
Supplier Classification Description
95 - 100% Preferred Meets all Valcor requirements in quality, cost, and delivery.
85 - 94% Acceptable Meets minimum Valcor requirements.
75 - 84% Restricted Does not meet Valcor minimum requirements.
Required written corrective action.
Management approval to bid new work
0 - 74% Unacceptable
On Probation unless documented evaluation justifies continued use.
No new business and the existing business will be phased out.
Corrective Action Plan needs to be implemented and “Acceptable” status within 60 days.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 25 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
11.0 Dock-to-Stock (DTS) The DTS program exempts a supplier’s parts from routine incoming inspection at Valcor. Suppliers that
produce high quality parts and have an effective quality system can be considered a candidate for the
Dock-to-Stock program.
To become a DTS candidate, the supplier must achieve:
A performance level of 100% lot acceptance based on the most recent 12 months or 10 most
recent lots
98% or better piece count acceptance
An approved on-site surveillance (if appropriate) to assure that product quality will be
maintained
No open or late corrective actions for the part number (or family of parts)
Demonstrate certification and/or compliance to AS9100, ISO9000, or equivalent
The supplier’s part will continue to be put through a random inspection frequency determined by
Valcor.
Note: This program does NOT apply to Valcor Nuclear products.
Advantage of DTS:
Certified “Dock-to-Stock” suppliers will be considered ahead of non-DTS for additional business
Non-compliant part
If a deviation to the blueprint is found at the supplier’s facility follow Section 7.1 (Supplier Deviation).
However, when a nonconformance is identified at Valcor, the supplier’s part may be removed from
Dock-to-Stock authority, and will follow Section 7.2 (Supplier Quality Escape). In addition, suppliers
failing to maintain an overall score of 95% rating two consecutive quarters may be put on probation. A
supplier on probation may only be returned to the Dock-to-stock program when 10 consecutive lots
have been accepted without rejection or when the quarterly performance rating meets the 98%
requirement in two consecutive quarters.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 26 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
12.0 Valcor Owned Property The supplier, at their facilities, is responsible for the maintenance and protection of Valcor owned
property. The supplier is required to establish control methods that will help prevent property loss,
damage, or mishandling.
Valcor owned products can consist of the following but not limited to:
Re-usable packaging containers
Tooling
Gages
Inspection gages damaged or not sent to Valcor with the product will be considered as late, and result in
an on time delivery score reduction.
To protect Valcor’s investment, the supplier is responsible for the following furnished items:
Raw material
Partially process components
Sub-assemblies
The supplier needs to notify Valcor immediately of a nonconformance, and if needed, a corrective action
will be requested. Liability for the occurrence, per case, shall be determined and discussed with the
supplier.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 27 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
13.0 Appendix A: Valcor Supplier Quality Survey SF1016A
VALCOR SUPPLIER QUALITY SURVEY FORM
2 LAWRENCE ROAD ▪ SPRINGFIELD, NJ 07081 TELEPHONE: 973-467-8400 ▪ FAX: 973-467-9391 Page 1 of 4
Valcor Supplier Quality Survey Form Revision Date: 21 November 2013
Form # SF1016A
GENERAL INFORMATION Supplier’s Name
Street Address
City
State Zip Phone Fax Website
Major Product/Process
CHECK APPLICABLE BOXES For VALCOR use Only
Approved Disapproved Conditional
Approved By:__________________Date_________
SURVEY TYPE: Self Evaluation On-Site Evaluation 3rd Party
SURVEY CLASSIFICATION: Distributer Processor Manufacturer Other _________________________
KEY SUPPLIER MANAGEMENT PERSONNEL # OF EMPLOYEES President/ Owner
Quality Mgr. Name Total Personnel
Manufacturing Engineering
Sales/Service
Production Quality Assurance Quality Control Inspection
Engineering
Other BUILDING/FACILITIES Type: Corporation Partnership Individual
Square Footage
To whom does the Quality Organization report to?
Established since
Is a current organization chart available?
YES NO
% of Manufacturing Capacity Utilized
Is security clearance required? YES NO
NAME OF MAJOR CUSTOMERS: THREE (3) MINIMUM CUSTOMER NAME APPROVAL DATE CUSTOMER NAME APPROVAL DATE
QUALITY PROGRAM Do you have a written quality manual?
YES NO
If yes, Title of Q.A. Manual_____________________________ Rev____________ Date _________________
Does your quality program meet the following (check all those applicable) For suppliers ISO-9001, AS9100, NADCAP, and/or 17025 accredited: complete the above section only, and sign the last page. Include a copy of your certificates and your Quality Assurance Manual.
MIL-Q-9858A MIL-I-45208A MIL-STD-45662
AS9001 ISO-9001 NQA-1
10CFR50, Appendix B ANSI N45.2 ISO 17025
NADCAP A2LA
If none of the above are applicable, describe the Quality Management System:
VALCOR SUPPLIER QUALITY SURVEY FORM
2 LAWRENCE ROAD ▪ SPRINGFIELD, NJ 07081 TELEPHONE: 973-467-8400 ▪ FAX: 973-467-9391 Page 2 of 4
Valcor Supplier Quality Survey Form Revision Date: 21 November 2013
Form # SF1016A
SPECIAL PROCESS For each special process performed in-house and at sub-tier suppliers, list the processes and governing specifications and standards (AWS D17.1, J-STD-001, AMS2700, etc.). Attach supporting evidence that substantiates process approval.
Process Specification(s) Standard(s) Expiration Date Welding
Soldering
Plating
Painting
Surface
Finishing
Other
SUPPLIER SELF EVALUATION QUESTIONNAIRE 1.0 MANUFACTURING CONTROL & INSPECTION YES NO N/A
A. Is there a definite training program for inspectors & other personnel whose job function affects product quality?
On job training, Classroom
B. Are inspections documented and do records provide evidence of the following: Lot quantity, Level of inspection, result of inspection
C. Are incoming parts/material inspected to verify compliance to PO requirements?
D. Are end products inspected/tested before delivery to customer?
E. Does the program provide provision of material traceability where applicable?
F. Do you use Statistical Process Control (SPC) to control major processes?
G. Is sampling inspection utilized? Based on what plan? _________________________________________________________
H. Does the program address retention time of inspection records? __________months/years.
I. Is software, when used in the manufacture and inspection of product, controlled?
2.0 CALIBRATION CONTROL YES NO N/A
A. Is there a gauge calibration system?
B. Do you allow the use of personal gauges?
C. Are procedures in effect which describe the method and frequency of calibration?
D. Is measuring and test equipment marked to indicate calibration status and when next calibration is due?
E. Is adequate measuring equipment available to inspection for verifying conformance of supplies/materials?
VALCOR SUPPLIER QUALITY SURVEY FORM
2 LAWRENCE ROAD ▪ SPRINGFIELD, NJ 07081 TELEPHONE: 973-467-8400 ▪ FAX: 973-467-9391 Page 3 of 4
Valcor Supplier Quality Survey Form Revision Date: 21 November 2013
Form # SF1016A
F. Is there an evaluation recall and notification procedure of hardware inspected by a gauge later found to be out of tolerance?
3.0 PROCUREMENT/ MATERIAL CONTROL YES NO N/A
A. Are procurement sources controlled to assure that all procured material meets all imposed requirements?
B. Is a list of approved sources maintained and periodically reviewed for status?
C. Are certifications/test reports of purchased material required?
4.0 EVALUATION OF SUBCONTRACTORS YES NO N/A
A. Are the records of acceptable subcontractors such as an “Approved Supplier List” or other such document?
B. Is there confirmation that the quality system controls are effective at the subcontractors?
5.0 DOCUMENT CONTROL POLICY YES NO N/A
A. Has a process been established to control all documents, data, and engineering drawing that relate to the purchase order, including to the extent applicable, external standards, and customer drawings?
B. Is there a system for identification/ retrieval/ removal of obsolete documents from all points of issue or use?
C. Are all inspection records being kept and maintained?
6.0 NON-CONFOROMANCE AND CORRECTIVE ACTION YES NO N/A
A. Is control established to prevent nonconforming material from inadvertent use?
B. Does the Material Review Board consist of both Engineering and Quality Personnel?
C. Is corrective action obtained on significant or repetitive non-conformance?
D. Is customer authorization obtained before delivering items that deviate from contractual requirements?
E. Do you perform Internal Audits?
7.0 PACKAGING/SHIPPING/STORAGE YES NO N/A
A. Are procedures written controlling the preservation, packaging, and shipping processes?
B. Do you maintain in-house or subcontracted packaging facility to meet special customer requirements?
C. Is material with life, age or other limitations controlled and identifiable to the limitation and remaining usefulness?
8.0 HOUSEKEEPING/SAFTEY YES NO N/A
A. Do you enforce 6S?
B. Are facilities equipped with automatic sprinkler system?
C. Does facility have well marked and well located fire protection equipment?
VALCOR SUPPLIER QUALITY SURVEY FORM
2 LAWRENCE ROAD ▪ SPRINGFIELD, NJ 07081 TELEPHONE: 973-467-8400 ▪ FAX: 973-467-9391 Page 4 of 4
Valcor Supplier Quality Survey Form Revision Date: 21 November 2013
Form # SF1016A
9.0 DO YOU HAVE A GOVERNMENT INSEPCTOR? YES NO N/A
Resident
Itinerant: Agency Name _________________
SELF-EVALUATION SURVEY PARTICIPANTS
I certify the above Self-Evaluation Survey has been completed in accordance with our Quality Assurance procedures and is accurate and correct.
Surveys without a supplier signature will not be accepted.
Filled Out By: ____________________________________ Date: ___________________ (Print Name) Signature: ____________________________________
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 32 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
14.0 Appendix B: Deviation/Change Request SF1019A
DEVIATION/CHANGE REQUEST FORM
Form # SF1019 Rev. A
DCR #
SUPPLIER INFORMATION PART INFORMATION
Date: Part Number:
Supplier Name: Part Description:
Supplier Code: Revision Level: Quantity:
Contact: Phone #: PO Number:
DESCRIPTION
1st
Time
Repeat, DCR#______________
Product Related
Process Related
Current Requirement:
DEVIATION REQUEST
Request for Deviation:
Reason for Request:
CHANGE REQUEST
Request for Change:
Reason for Request:
Acknowledgment (Departments to sign when needed) Date Approve/Disapprove Comments
Purchasing: YES NO
Engineering: YES NO
Manufacturing: YES NO
Quality Assurance: YES NO
VALCOR DISPOSITION
Drawing/Spec Change Required? YES NO If Yes, ECO# __________________
Corrective Action Required? YES NO If Yes, CAR# __________________
Final Disposition and Comments:
Supplier Note: If deviation is approved, a copy of this form shall be included inside the shipping container with each affected
shipment.
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 34 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
15.0 Appendix C: Material Rejection Report SF-104/R.03/12
Valcor Engineering Corporation®
2 Lawrence Road, Springfield, NJ 07081 CAGE Code 96487
Supplier Quality Manual
Unauthorized use, manufacture or reproduction in whole or in part is prohibited. Drawing, design and other disclosures are property of Valcor Engineering Corporation®.
SQM-001 Revision -
Copyright © 2014, Valcor Engineering Corporation®. Sheet 36 of 39 Uncontrolled when printed. Verify document revision online at www.Valcor.com
16.0 Appendix D: Corrective Action Request/Report SF1018A
CAR Number 4
Supplier Corrective Action Request
Date Defined / /
Status Open
Part NumberInventory Number
Defined by 1111 TEST USER CustomerSupplier
P.O NoNonconformance
Serial No
Operation No 0
WorkcenterDepartmentStandard
1. Problem Description
Date Completed: / / Status:Responsible:
What, Where, and When? Include evidence observed.
2. Team MembersEstablish a team of people with product/process knowledge.
Date Completed: / / Status:Responsible:
Define and execute actions to isolate discrepant and/or potentially discrepant materials/parts until corrections have been implemented and verified. Define the action(s) taken to eliminate the existing situation at each manufacturing phase (ex. Shipped, Raw Material, Finished Goods, WIP, etc.).
3. Containment Actions / Reinspection Findings
08/11/2014 08:40:30 AM Page 1Valcor Engineering Corporation
CAR Number 4
Supplier Corrective Action Request
Date Defined / /
Status Open
Part NumberInventory Number
Defined by 1111 TEST USER CustomerSupplier
P.O NoNonconformance
Serial No
Operation No 0
WorkcenterDepartmentStandard
Date Completed: / / Status:Responsible:
Determine and verify what caused the defect to be produced. Support with evidence by using root cause analysis (Recommended Tools: 8D, 5 Whys, Fishbone, Flowchart, etc.)
4. Root Cause(s)
5. Select / Verify Corrective Actions
Date Completed: / / Status:Responsible:
Describe all planned and completed actions which address the root cause and prevent recurrence of the non-conformance.
08/11/2014 08:40:30 AM Page 2Valcor Engineering Corporation
CAR Number 4
Supplier Corrective Action Request
Date Defined / /
Status Open
Part NumberInventory Number
Defined by 1111 TEST USER CustomerSupplier
P.O NoNonconformance
Serial No
Operation No 0
WorkcenterDepartmentStandard
6. Implement Corrective Actions
Date Completed: / / Status:Responsible:
Provide objective evidence (photos, training records, work instructions, ECOs, and etc.) to verify that all findings have been addressed.
7. Verification
8. Congratulate Team
Date Completed: / / Status:Responsible:
Determine and provide objective evidence that a change has occurred and that the product and process achieved desired results.
Date Completed: / / Status:Responsible:
Preventative Actions: Determine and implement actions to prevent the recurrence of this root cause and all similar problems.
08/11/2014 08:40:30 AM Page 3Valcor Engineering Corporation