Street Conditions
• Part 1 – State of the Streets• Part 2 – Repairs and Maintenance
Costs• Part 3 – Options for Funding
![Page 2: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/2.jpg)
Street ConditionsPart 2 - Repair
and Maintenance Costs
![Page 3: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/3.jpg)
Pothole Repair
• Temporary fix• Clean out loose material• Cold patch asphalt• Larger holes require dig-out
![Page 4: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/4.jpg)
Crack Sealing
• Blow out crack• Apply asphalt sealer• $ 1/linear foot• Not cost effective for streets• Keeps water out of subgrade
![Page 5: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/5.jpg)
Slurry Seals
• Clean pavement• Apply thin asphalt emulsion, sand
slurry• $0.20/ft2
• Service life 3-5 years
![Page 6: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/6.jpg)
Dig-outs
• Dig out hole to base material
• Fill with hot mix• Pavement has
failed structurally• Service life 25
years• $5/ft2
![Page 7: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/7.jpg)
Overlays
• Grind existing gutter edge
• Pave with 1 ½ - 2” hot asphalt
• $1.10/ft2
• Service life 15-20 years
![Page 8: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/8.jpg)
AC – asphalt concrete$1.10 /ft2Willow St.
ARHM – asphalt rubber hot mix
$1.80/ft2S. Montgomery St.
![Page 9: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/9.jpg)
Other: Striping
• Single white line• Yellow and
double-yellow• Crosswalks• Parking spaces• Fog lanes• Bike paths
![Page 10: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/10.jpg)
Pre-2006 Pavement Management
Program• Emergency repairs only• Limited Caltrans maintenance work
on SR 150 and SR33 in city limits• Maintenance staff positions cut• Minimal preventative maintenance
since 2003
![Page 11: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/11.jpg)
Pavement Condition Index (PCI)
• What is it? Computerized quality rating 0-100 0 no structural stability, very deteriorated 100 new street
• How is it calculated? Type and percentage of cracks, thickness of pavement, condition
• City has 147 road segments.• Average PCI Citywide is 48• Other Cities Try to Maintain +/- 65
![Page 12: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/12.jpg)
Current Street Conditions
• 0-20: 21 segments• 21-40: 33 segments• 41-60: 40 segments• 61-80: 39 segments• 81-100: 14 segments
![Page 13: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/13.jpg)
Identifying NeedScheduling Repairs
• Pavement Condition Index (<20)• Traffic Volume (increased volume
= decreased street life)• Truck traffic• 06-07 $400,000 budget (includes
5 years of STP funding)
![Page 14: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/14.jpg)
San Francisco/Bay Area Transportation Commission
![Page 15: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/15.jpg)
Repair Costs
• Estimated repair cost $8 million• Reconstruct or overlay• Assumes PCI=65• Assumes maintenance budget is
provided.
![Page 16: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/16.jpg)
Five-Year Pavement Improvement Plan
• Repair cost $1.6 M annually for five years plus $80K maintenance
• Some emergency repairs will be needed before five years.
• Assumes City = PCI 65
![Page 17: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/17.jpg)
RecommendedAnnual & Preventative Maintenance Program
Striping – ½ city/year $15,000Slurry seal – 5 year intervals $50,000Crack sealing – not recommendedPothole Repair – As needed, requires
reinstatement of maintenance personnel plus materials $15,000
(material only)
![Page 18: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/18.jpg)
Projected Future Costs
(Assumes 5-yr, $8M street repair completed to maintain PCI=65)
Annual Overlay Cost $370,000Annual Maintenance Cost $ 80,000Annual Investment $450,000
![Page 19: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/19.jpg)
Caltrans Maintenance Contract
• $74,000 contract to perform maintenance on SR 150 and SR 33 in the City limits
• Better knowledge of City needs • Fast response time• Limited by reduction of PW
maintenance staff
![Page 20: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/20.jpg)
Proposed 06-07 Street Improvements
• Cuyama (SR33-Church) 54250 ft2
• Cuyama (Church-Del Norte) 41040 ft2
• Palomar (Bristol-Cuyama) 26280 ft2
• El Paseo (Bristol-Cuyama) 6520 ft2
• Canada (SR150-McKee) 102160 ft2
• Vista Hermosa (Foothill-Del Oro)19680 ft2
• Fulton (SR150-Grand) 72720 ft2
![Page 21: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/21.jpg)
Cuyama
![Page 22: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/22.jpg)
Palomar
![Page 23: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/23.jpg)
El Paseo
![Page 24: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/24.jpg)
Canada
![Page 25: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/25.jpg)
Vista Hermosa
![Page 26: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/26.jpg)
Fulton
![Page 27: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/27.jpg)
State Transportation Program
Local Funds
$214,629($43,000/year for 5 years)
![Page 28: Street Conditions Part 1 – State of the Streets Part 2 – Repairs and Maintenance Costs Part 3 – Options for Funding.](https://reader036.fdocuments.net/reader036/viewer/2022062712/56649c925503460f9494d556/html5/thumbnails/28.jpg)
Next meeting: Part 3 – Funding Options