StrategicCapacityMgmt

download StrategicCapacityMgmt

of 22

Transcript of StrategicCapacityMgmt

  • 8/3/2019 StrategicCapacityMgmt

    1/22

    STRATEGIC CAPACITY MANAGEMENT

  • 8/3/2019 StrategicCapacityMgmt

    2/22

    ObjectivesObjectives

    To understand the strategic capacity planning

    To learn some methods that help strategic capacity

    planning To understand capacity expansion strategies

  • 8/3/2019 StrategicCapacityMgmt

    3/22

    Strategic Capacity PlanningStrategic Capacity Planning

    CapacityCapacity is the ability to hold, receive, store, oraccommodate raw materials, finished products,customers, etc.

    Strategic capacity planningStrategic capacity planning is an approach fordetermining the overall capacity level of capital intensive

    resources, including facilities, equipment, and overalllabour force size.

    Capacity usedCapacity used is the rate of output actually achieved.

    The best operating levelbest operating level is nominally the capacity for

    which the process was designed.Capacity Used

    Capacity Utilization RateBest Operating Level

    !

  • 8/3/2019 StrategicCapacityMgmt

    4/22

    Best Operating LevelBest Operating Level

    Example:Example:

    Engineers design engines and assembly lines to operate at anideal or best operating level to maximize output and minimizewear.

    Under-utilization

    Best Operating Level

    Averageunit costof output

    Volume

    Over-utilization

  • 8/3/2019 StrategicCapacityMgmt

    5/22

    Capacity UtilizationCapacity Utilization

    Example:Example:

    During one week of production, a plant produced 83 units of aproduct. Its historic best utilization was 120 units per week. Whatis this plants capacity utilization rate?

    Capacity UsedCapacity Utilization RateBest Operating Level

    !

    83 /

    0.69 69%120 /

    units week

    units week! ! !

  • 8/3/2019 StrategicCapacityMgmt

    6/22

    Economies ofScaleEconomies ofScale

    100-unit

    plant200-unit

    plant 300-unitplant

    400-unitplant

    Volume

    Averageunit costof output

    Economies of scale and operating level curves

    Diseconomies of scale start to take effect

  • 8/3/2019 StrategicCapacityMgmt

    7/22

    Experience (Learning) CurvesExperience (Learning) Curves

    As plants produce more products, they gain experience inthe best production methods and reduce their costs per unit.

    Total accumulated production of units

    Cost/priceper unit

    Yesterday

    Today

    Tomorrow

  • 8/3/2019 StrategicCapacityMgmt

    8/22

    Other Capacity Planning ConceptsOther Capacity Planning Concepts

    The concept of the focused factoryfocused factory (also called capacitycapacityfocusfocus) holds that production facilities work best whenthey focus on a fairly limited set of production objectives.

    The plants within plantsplants within plants (PWP) concept extendscapacity focus ideas to an operational level.

    Capacity flexibilityCapacity flexibility allows rapid increase or decrease ofproduction levels, and can be achieved in three ways:

    Flexible plants

    Flexible processes

    Flexible workers

  • 8/3/2019 StrategicCapacityMgmt

    9/22

    Capacity PlanningCapacity Planning

    Three important considerations in capacity planning: Maintaining system balance

    In the ideal case, the output of one stage is the exact inputrequirements for the next stage.

    Frequency of capacity additions

    There are costs in adding capacity too frequently as well as tooinfrequently.

    External sources of capacity

    It might be cheaper to outsource some production.

    Determining capacity requirements Forecast sales (within each individual product line)

    Calculate equipment and labour requirements to meet forecasts

    Project equipment and labour availability

  • 8/3/2019 StrategicCapacityMgmt

    10/22

    Capacity Requirements ExampleCapacity Requirements Example

    A manufacturer produces mustard in small and family-sized plastic bottles, with the following demand forecasts.

    Three 100,000 units-per-year machines are available for smallbottle production. 2 operators are required per machine.

    Two 120,000 units-per-year machines are available for family-

    sized bottle production. 3 operators are required per machine.

    How much capacity is used and what are the machineand labour requirements?

    Year 1 Year 2 Year 3 Year 4

    Small (000's) 150 170 200 240Family (000's)

    115 140 170 200

  • 8/3/2019 StrategicCapacityMgmt

    11/22

    Capacity Requirements Example (2)Capacity Requirements Example (2)

    Machine capacity: 300 000 small, 240 000 family size

    Labour availability: 6 for small, 6 for family size

    Year 1 Year 2 Year 3 Year 4

    Small (000's) 150 170 200 240

    Family (000's) 115 140 170 200

    Year 1 Year 2 Year 3 Year 4

    Small (000's) 150 170 200 240

    Family (000's) 115 140 170 200Small

    % capacity used 50.00%machines req'd 1.50

    labour req'd 3.00

    Family Size

    % capacity used

    machines req'd

    labour req'd

    150 0000.50

    300 000

    ! !

    150 0001.5

    100 000 per machine! !

    21.5 3.0

    operatorsmachines

    machine! v !

    Year 1 Year 2 Year 3 Year 4

    Small (000's) 150 170 200 240

    Family (000's) 115 140 170 200Small

    % capacity used 50.00%machines req'd 1.50

    labour req'd 3.00

    Family Size

    % capacity used 47.92%machines req'd 0.96

    labour req'd 2.88

    115 0000.4792

    240 000! !

    115 0000.96

    120 000 per machine! !

    30.96 2.88operatorsmachinesmachine

    ! v !

    Year 1 Year 2 Year 3 Year 4

    Small (000's) 150 170 200 240

    Family (000's) 115 140 170 200Small

    % capacity used 50.00% 56.67% 66.67% 80.00%machines req'd 1.50 1.70 2.00 2.40

    labour req'd 3.00 3.40 4.00 4.80

    Family Size

    % capacity used 47.92% 58.33% 70.83% 83.33%machines req'd 0.96 1.17 1.42 4.25

    labour req'd 2.88 3.50 4.25 5.00

  • 8/3/2019 StrategicCapacityMgmt

    12/22

    Decision TreesDecision Trees

    A decision treedecision tree is a schematic model of the steps in thecapacity planning problem.

    Steps:1. Draw the various decisions

    2. Add the possible states of nature, probabilities, and payoffs

    3. Determine the expected value of each decision

    4. Make decision (the one with maximum expected value)

  • 8/3/2019 StrategicCapacityMgmt

    13/22

    Decision Trees ExampleDecision Trees Example

    A glass factory specializing in crystal experiences substantial

    backlog, and management is considering three courses of action:A. Arrange for subcontracting

    B. Construct new facilities

    C. Do nothing (no change)

    The correct choice depends largely upon demand, which may be low,

    medium, or high. By consensus, management estimates therespective demand probabilities as 0.1, 0.5, and 0.4.

    The management also estimates the profits when choosing from thethree alternatives under the differing probable levels of demand.These profits, are as follows:

    Low (p=0.1) Medium (p-0.5) High (p=0.4)

    A 10 000 50 000 90 000

    B -120 000 25 000 200 000

    C 20 000 40 000 60 000

  • 8/3/2019 StrategicCapacityMgmt

    14/22

    Decision Trees Example (2)Decision Trees Example (2)

    Medium demand (0.5) $50k

    Medium demand (0.5) $25k

    Medium demand (0.5) $40k

    AA

    BB

    CC

    Decisions:Decisions: States, probabilities, and payoffs:States, probabilities, and payoffs:

    High demand (0.4) $90k

    Low demand (0.1) $10k

    High demand (0.4) $200k

    Low demand (0.1) -$120k

    High demand (0.4) $60k

    Low demand (0.1) $20k

    StartStart

  • 8/3/2019 StrategicCapacityMgmt

    15/22

    Decision Trees Example (3)Decision Trees Example (3)

    Medium demand (0.5) $50k

    Medium demand (0.5) $25k

    Medium demand (0.5) $40k

    AA

    BB

    CC

    Expected values ofeach decision:Expected values ofeach decision:

    High demand (0.4) $90k

    Low demand (0.1) $10k

    High demand (0.4) $200k

    Low demand (0.1) -$120k

    High demand (0.4) $60k

    Low demand (0.1) $20k

    ! !0.4 90 0.5 50 0.1 10 $62kA

    EV

    , ,A A i A ii

    EV P V

    !

    ! !0.4 200 0.5 25 0.1 120 $80.5kBEV

    ! !0.4 60 0.5 40 0.1 20 $46kC

    EV

    Choose decision B

    (highest expected value)

  • 8/3/2019 StrategicCapacityMgmt

    16/22

    Service Capacity vs. Manufacturing CapacityService Capacity vs. Manufacturing Capacity

    Capacity planning in services is different than inmanufacturing in three key ways:

    Time

    Goods can not be stored for later use

    Capacity must be available to provide a service when it is needed

    Location

    Service goods must be at the customer demand point

    Capacity must be located near the customer

    Volatility of demand

    Much greater in services than in manufacturing

  • 8/3/2019 StrategicCapacityMgmt

    17/22

    Service Growth MatrixService Growth Matrix

    Chain restaurants

    Hotels

    Car and truck rentalsAirlines

    Specialty stores

    Department storesBanks

    Dry cleanersRestaurants

    Mom and pop stores

    HospitalsResorts

    Universities

    Multisite

    Single-site

    Single-service Multi-service

  • 8/3/2019 StrategicCapacityMgmt

    18/22

    CapacityExpansion Strategies:CapacityExpansion Strategies:

    EntrepreneurialStageEntrepreneurialStage

    Shift resources to different tasks as needed

    Customer co production

  • 8/3/2019 StrategicCapacityMgmt

    19/22

    CapacityExpansion Strategies:CapacityExpansion Strategies:

    Multisite Rationalization StageMultisite Rationalization Stage

    Add services to existing site

    Duplicate existing services at additional sites

    Do both

  • 8/3/2019 StrategicCapacityMgmt

    20/22

    CapacityExpansion Strategies:CapacityExpansion Strategies:

    Growth StageGrowth Stage

    Bermuda Triangle of operational complexity Management difficulty exceeds management ability

    New capacity management challenges Need for fresh ideas

    Need to upgrade older facilities

  • 8/3/2019 StrategicCapacityMgmt

    21/22

    CapacityExpansion Strategies:CapacityExpansion Strategies:

    MaturityStageMaturityStage

    Focus on operational efficiencies

    Remodeling and replacement

    Service modification

    Duplication across entire service system

  • 8/3/2019 StrategicCapacityMgmt

    22/22

    SummarySummary

    Capacity decisions should be made carefully, as they

    can commit significant resources to assets that

    cannot be changed easily or economically.

    Capacity is affected by management decisions

    regarding the number ofhours worked, product mix,

    staffing levels, machine capabilities, level ofquality,and product yield.

    Watch out for the Bermuda Triangle ofoperational

    complexity, where management difficulty exceeds

    management ability (management bottleneck!).