Over ground stone mine
1. General description
The mine is situated in the proximity of Ploiesti city, on the way of the new(under construction) high way Bucuresti Brasov Arad.
Easy access is ensured by the national road DN1 which connects the city of
Ploiesti with Sinaia and Brasov.
The mine is developed over a hill with altitude of 70 m, the total surface of thehill is 100 ha.
The mine benefits of specific tools, machinery and site organization in value of
1 mil Euro and also exploitation and excavation license for 100 ha.
6/30/2010 Stone mine 1
-
8/9/2019 Stone Mine Cocorastii
2/8
Over ground stone mine
2. Juridical Situation
a. Real estate
The mine developer owning a total surface of 40 hectares from the hill.
b. Permits
Exploitation permit from the National Agency for Mineral Resources is issued for 100ha
The exploitation shall be done in two or three phases, the first phase being fullyapproved. The first phase is developed over 7ha, for the rest of the exploitation until 100ha there shall be fulfilled part of approvals documents
Permit from the Water Management authority for the construction of a station
for sorting and washing the mineral aggregates, road alleys and utilities.
Environmental approval
Construction approval
6/30/2010 Stone mine 2
-
8/9/2019 Stone Mine Cocorastii
3/8
6/30/2010 Stone mine 3
Quantity Unit Unit price Total Euro
Phase 1Production income (sand, stone and mixtures extraction) 22,133,300
Phase 1 Extracted material (
excavating 7 ha ) 4,900,000 m3 4.52 22,133,300
Production Costs 5,880,000
Cost of extraction, equipment
amortization, etc.. 4,900,000 m3 1.2 5,880,000
Phase one profit before taxation 16,253,300
Investments (for phase 2) 3,600,000
Land 60ha 10,000 600,000
Permits 500,000Equipments 2,500,000
Phase 2 Production income 120,152,200
Phase 2 Extracted material (excavating 10 ha ) 26,600,000m3 4.52 120,152,200
Production Costs ( for phase 2) 31,920,000
Cost of extraction, equipmentamortization, etc.. 26,600,000 m3 1.2 31,920,000
Phase tow profit before taxation 84,632,200
Total business income 100,885,500
Business acquisition price 9,000,000
Over ground stone mine
Feasibility
-
8/9/2019 Stone Mine Cocorastii
4/8
Over ground stone mine
Technical data
Accordingly with topographical and geotechnical measurements the exploitation has a
height of 70 m over ground and underground is going until 100m
Longitudinal profile Latitudinal profile
6/30/2010 Stone mine 4
-
8/9/2019 Stone Mine Cocorastii
5/8
Over ground stone mine
Exploitation material quality data
The exploitation materials have been certified (stone for high wayconstruction, for train line construction, mixtures for concrete factory, send ...)
Exploitation material quantities by type: 0-4mm 38% 4-8mm 12.3%
8-16mm 15%
16-31% mm 19%
31,5 mm 14%
6/30/2010 Stone mine 5
-
8/9/2019 Stone Mine Cocorastii
6/8
Over ground stone mine
6/30/2010 Stone mine 6
-
8/9/2019 Stone Mine Cocorastii
7/8
Over ground stone mine
6/30/2010 Stone mine 7
-
8/9/2019 Stone Mine Cocorastii
8/8
6/30/2010 Stone mine 8
Over ground stone mine