STANDARD COSTING By SUPRIYA SEHGAL 1

description

Standard Costing

Transcript of Standard Costing Ppt

Page 1: Standard Costing Ppt

STANDARD COSTING

By SUPRIYA SEHGAL

1

Page 2: Standard Costing Ppt

STANDARD COSTING SYSTEM The management evaluates the performance of a company by comparing it with some predetermined measures

Therefore, it can be used as a process of measuring and correcting actual performance to ensure that the plans are properly set and implemented

2

Page 3: Standard Costing Ppt

PROCEDURES OF STANDARD COSTING SYSTEM Set the predetermined standards for sales margin and production costs

Collect the information about the actual performance

Compare the actual performance with the standards to arrive at the variance

Analyze the variances and ascertaining the causes of variance

Take corrective action to avoid adverse variance

Adjust the budget in order to make the standards more realistic

3

Page 4: Standard Costing Ppt

FUNCTIONS OF STANDARD COSTING SYSTEM Valuation Assigning the standard cost to the actual output

Planning Use the current standards to estimate future sales volume and

future costs

Controlling Evaluating performance by determining how efficiently the current

operations are being carried out

4

Page 5: Standard Costing Ppt

Motivation Notify the staff of the management’s expectations

Setting of selling price

5

Page 6: Standard Costing Ppt

VARIANCE6

Page 7: Standard Costing Ppt

VARIANCE ANALYSIS

A variance is the difference between the standards and the actual performance

When the actual results are better than the expected results, there will be a favourable variance (F)

If the actual results are worse than the expected results, there will be an adverse variance (A)

7

Page 8: Standard Costing Ppt

8

Profit variance

Selling and administrativeCost variance

Total production Cost variance

Total sales margin variance

Sales marginPrice variance

Sales margin volume variance

Materials costvariance

Labour Cost variance

Variable Overhead variance

Fixed Overhead variance

Page 9: Standard Costing Ppt

9

Materials cost variance

Material Price variance Material Usage variance

Labour cost variance

Labour rate variance

Labour Efficiency variance

Page 10: Standard Costing Ppt

10

Variable Overhead variance

VO Expenditure variance VO Efficiency variance

Fixed Overhead variance

Fixed Expenditure variance Fixed Volume variance

Page 11: Standard Costing Ppt

COST VARIANCE11

Page 12: Standard Costing Ppt

COST VARIANCE

12

•Cost variance = Price variance + Quantity varianceCost variance is the difference between the standard cost and the Actual cost

•Price variance = (standard price – actual price)*Actual quantity A price variance reflects the extent of the profit change resulting from the change in activity level

•Quantity variance = (standard quantity – actual quantity)* standard cost

A quantity variance reflects the extent of the profit change resulting from the change in activity level

Page 13: Standard Costing Ppt

THREE TYPES OF COST VARIANCE Material cost variance

Labour cost variance

Variable overheads variance

13

Page 14: Standard Costing Ppt

MATERIAL AND LABOUR VARIANCE

14

Page 15: Standard Costing Ppt

MATERIAL COST VARIANCE Material price variance

= (standard price – actual price)*actual quantity

Material usage variance

= (Standard quantity – actual quantity)* standard price

= (Standard quantity for actual production – actual quantity production) * standard price

15

Page 16: Standard Costing Ppt

LABOUR COST VARIANCE

Labour rate variance

= (standard price – actual price)*actual quantity

Labour efficiency variance= (standard quantity – actual quantity)*standard price= Standard quantity for actual production – actual quantity used) *

standard price

16

Page 17: Standard Costing Ppt

EXAMPLE17

Page 18: Standard Costing Ppt

18

ABC Ltd. makes and sells a single product. The company uses a Standard marginal costing system. It plans to produce and sell 1000 units in May 2005. A budget statement is produced as follow:

Budgeted income statement for the month ended 31 May 2005$ $

Sales ($50*1000) 50000Less: Variable cost of goods sold

Direct materials ($3*4000) 12000Direct labour ($5*3000) 15000Variable overheads ($2*3000) 6000 33000

Budget contribution 17000Fixed overhead 3000Budget profit 14000

Page 19: Standard Costing Ppt

19

The actual sales and production is 800 units. The actual income statement is shown as follows:

Income statement for the month ended 31 May 2005$ $

Sales ($60*800) 48000Less: Variable cost of goods sold

Direct materials ($3.2*2400) 12000Direct labour ($6*3200) 15000Actual Variable overheads 5500 32380

Contribution 15620Fixed overhead 2600Net profit 13020

Page 20: Standard Costing Ppt

20

Material cost variance

Material price variance

= (standard price – actual price)*actual quantity

= ($3 - $3.2)*2400

= $480 (A) Material usage variance

= (Standard quantity – actual quantity)* standard price

= (Standard quantity for actual production – actual quantity production) * standard price

= (4*800 – 2400)*$3

= $2400 (F)

4000 units1000 units

Page 21: Standard Costing Ppt

MATERIAL COST VARIANCE Material price variance $480 (A)

Material usage variance $2400 (F)

Total Material cost variance $1920 (F)

21

Page 22: Standard Costing Ppt

22

Labour cost variance

Labour rate variance

= (standard price – actual price)*actual quantity

= ($5 - $6)*3200

= $3200 (A)

Labour efficiency variance= (standard quantity – actual quantity)*standard price

= Standard quantity for actual production – actual quantity used) * standard price

= (3* 800 – 3200)*$5

= $4000 (A)

3000 units1000 units

Page 23: Standard Costing Ppt

LABOUR COST VARIANCE

Labour rate variance $3200 (A)

Labour efficiency variance $4000 (A)

Total labour cost variance $7200 (A)

23

Page 24: Standard Costing Ppt

OVERHEADS VARIANCE

24

Page 25: Standard Costing Ppt

OVERHEADS VARIANCE

Variable overheads variance

Fixed overheads variance

25

Page 26: Standard Costing Ppt

VARIABLE OVERHEADS VARIANCE Variable overheads variance is the difference between the standard variable overheads absorbed into the actual output and the actual overheads incurred

26

Page 27: Standard Costing Ppt

27

Actual VOBudgeted VO(SP * Actual hours worked

Absorbed VO(SP* standardhours for actualoutput

VO expenditure variance/VO spending variance

VO efficiency variance

Total VO variance(under-/over- absorbed)

Page 28: Standard Costing Ppt

CALCULATION ON OVERHEAD ABSORBED Step 1

Step 2

28

POAR = Budgeted overheads

Budgeted activity level in standard hours

Overhead absorbed = POAR * Standard hours for actual number of units produced

Page 29: Standard Costing Ppt

VARIABLE OVERHEADS VARIANCE

Variable overheads variance

= variable overheads absorbed – actual variable overheads incurred

Variable overheads expenditure variance

= standard variable overheads for actual hours worked – Actual variable overheads incurred

Variable overheads efficiency variance

= Standard variable overheads for standard hours of output – Actual variable overhead absorbed

= (standard hours for actual output – Actual hours worked)* standard price 29

Page 30: Standard Costing Ppt

EXAMPLE30

Page 31: Standard Costing Ppt

31

ABC Ltd. makes and sells a single product. The company uses a Standard marginal costing system. It plans to produce and sell 1000 units in May 2005. A budget statement is produced as follow:

Budgeted income statement for the month ended 31 May 2005$ $

Sales ($50*1000) 50000Less: Variable cost of goods sold

Direct materials ($3*4000) 12000Direct labour ($5*3000) 15000Variable overheads ($2*3000) 6000 33000

Budget contribution 17000Fixed overhead 3000Budget profit 14000

Page 32: Standard Costing Ppt

32

The actual sales and production is 800 units. The actual income statement is shown as follows:

Income statement for the month ended 31 May 2005$ $

Sales ($60*800) 48000Less: Variable cost of goods sold

Direct materials ($3.2*2400) 12000Direct labour ($6*3200) 15000Actual Variable overheads 5500 32380

Contribution 15620Fixed overhead 2600Net profit 13020

Page 33: Standard Costing Ppt

33

POAR = Budgeted overheads

Budgeted activity level in standard hours

Overhead absorbed = POAR * Standard hours for actual number of units produced

= $2 *3 hr per unit * 800 units

= $6000 3000

= $2

Standard hr per unit = 3000 hr /1000 units

Page 34: Standard Costing Ppt

VARIABLE OVERHEADS VARIANCE

Variable overheads variance

= variable overheads absorbed – actual variable overheads incurred

= $4800 - $5500

= $700 (A)

Variable overheads expenditure variance

= standard variable overheads for actual hours worked – Actual variable overheads incurred

= ($2* 3200 hr) - $5500

= $900 (F)34

Page 35: Standard Costing Ppt

Variable overheads efficiency variance

= Standard variable overheads for standard hours of output – Actual variable overhead absorbed

= (standard hours for actual output – Actual hours worked)* standard price

= (3 hr *800 units – 4 hr *800 units)*$2

= $1600 (A)

35

Actual hour per unit = $3200 hr/800 units

Page 36: Standard Costing Ppt

VARIABLE OVERHEADS VARIANCE

Variable overheads expenditure variance $900 F

Variable overheads efficiency variance$1600 A

Total Variable overhead variance$400 A

36

Page 37: Standard Costing Ppt

SALES VARIANCE37

Page 38: Standard Costing Ppt

38

Actual contribution

Budgeted contribution(Standard margin * Actual Volume)

Budgeted contribution(Standard margin* Standard volume)

Sales margin price variance Sales margin volume variance

Total sales margin variance

Page 39: Standard Costing Ppt

SALES VARIANCE (MARGINAL COSTING)

Total sales margin variance= actual contribution – budgeted contribution= [(Actual selling price – Standard cost of sales )*Actual sales volume] – Budgeted contribution

Sales margin price variance

= (Actual contribution per unit – Standard contribution per unit) * Actual sales volume

Sales margin volume variance= (Actual volume – Budget volume)* Standard contribution per unit

39

Page 40: Standard Costing Ppt

SALES VARIANCE (ABSORPTION COSTING)

Sales margin price variance

= (Actual profit margin per unit – Standard profit margin per unit) * Actual sales volume

Sales margin volume variance= (Actual volume – Budget volume)* Standard profit margin per unit

40

Page 41: Standard Costing Ppt

EXAMPLE41

Page 42: Standard Costing Ppt

42

ABC Ltd. makes and sells a single product. The company uses a Standard marginal costing system. It plans to produce and sell 1000 units in May 2005. A budget statement is produced as follow:

Budgeted income statement for the month ended 31 May 2005$ $

Sales ($50*1000) 50000Less: Variable cost of goods sold

Direct materials ($3*4000) 12000Direct labour ($5*3000) 15000Variable overheads ($2*3000) 6000 33000

Budget contribution 17000Fixed overhead 3000Budget profit 14000

Page 43: Standard Costing Ppt

43

The actual sales and production is 800 units. The actual income statement is shown as follows:

Income statement for the month ended 31 May 2005$ $

Sales ($60*800) 48000Less: Variable cost of goods sold

Direct materials ($3.2*2400) 12000Direct labour ($6*3200) 15000Actual Variable overheads 5500 32380

Contribution 15620Fixed overhead 2600Net profit 13020

Page 44: Standard Costing Ppt

SALES VARIANCE (MARGINAL COSTING) Total sales margin variance= actual contribution – budgeted contribution= [(Actual selling price – Standard cost of sales )*Actual sales

volume] – Budgeted contribution= [($60 - $33)*800] - $17000= $21600 - $17000= $4600 (F)

44

$33000/1000 units

Page 45: Standard Costing Ppt

SALES VARIANCE

Sales margin price variance

= (Actual contribution per unit – Standard contribution per unit) * Actual sales volume

= [($60 - $33) – ($50 - $33)]*800

= $8000 F

Sales margin volume variance= (Actual volume – Budget volume)* Standard contribution per unit= (800 -1000)*$17= $2800 (A)

45

$33000/1000 units

$17000/1000 units

Page 46: Standard Costing Ppt

SALES VARIANCE (MARGINAL COSTING) Sales margin price variance $8000 F

Sales margin volume variance $3400 A

Total sales variance $4600 F

46

Page 47: Standard Costing Ppt

SALES VARIANCE (ABSORPTION COSTING)

Sales margin price variance

= (Actual profit margin per unit – Standard profit margin per unit) * Actual sales volume

= [($60-$36) – ($50-$36)]*800

= $8000 F

Sales margin volume variance= (Actual volume – Budget volume)* Standard profit margin per unit

= (800-1000)*$14= $3400 A

47

(33000+3000)/1000 units

$14000/1000 units

Page 48: Standard Costing Ppt

SALES VARIANCE (ABSORPTION COSTING) Sales margin price variance $8000 F

Sales margin volume variance $2800 A

Total sales variance $5200 F

48

Page 49: Standard Costing Ppt

FIXED OVERHEAD VARIANCE

49

Page 50: Standard Costing Ppt

50

Actual FO Budgeted FO

Absorbed VO(SP* standardhours for actualoutput

FO expenditure variance/FO spending variance

FO volume variance

Total FO variance(under-/over- absorbed)

Page 51: Standard Costing Ppt

FIXED OVERHEAD VARIANCE

Fixed overheads variance

= Fixed overheads absorbed – Actual fixed overheads incurred

Fixed overheads expenditure variance

Budgeted fixed overheads – Budgeted overheads absorbed

Fixed overheads volume variance

= Absorbed fixed overheads – Budgeted overheads absorbed

51

Page 52: Standard Costing Ppt

EXAMPLE52

Page 53: Standard Costing Ppt

53

ABC Ltd. makes and sells a single product. The company uses a Standard marginal costing system. It plans to produce and sell 1000 units in May 2005. A budget statement is produced as follow:

Budgeted income statement for the month ended 31 May 2005$ $

Sales ($50*1000) 50000Less: Variable cost of goods sold

Direct materials ($3*4000) 12000Direct labour ($5*3000) 15000Variable overheads ($2*3000) 6000 33000

Budget contribution 17000Fixed overhead 3000Budget profit 14000

Page 54: Standard Costing Ppt

54

The actual sales and production is 800 units. The actual income statement is shown as follows:

Income statement for the month ended 31 May 2005$ $

Sales ($60*800) 48000Less: Variable cost of goods sold

Direct materials ($3.2*2400) 12000Direct labour ($6*3200) 15000Actual Variable overheads 5500 32380

Contribution 15620Fixed overhead 2600Net profit 13020

Page 55: Standard Costing Ppt

FIXED OVERHEAD VARIANCE

Fixed overheads variance

= Fixed overheads absorbed – Actual fixed overheads incurred

= ($1*3*800) - $2600

= $200 A

Fixed overheads expenditure variance

= Budgeted fixed overheads – Budgeted overheads absorbed

= $3000 - $2600

= $400 F

Fixed overheads volume variance

= Absorbed fixed overheads – Budgeted overheads absorbed

= ($1*3*800) - $3000

= $600 A55

Page 56: Standard Costing Ppt

FO VARIANCE IN MARGINAL AND ABSORPTION COSTING In marginal costing: Fixed overheads are charged as period costs instead of charging to

product in marginal costing. It is assumed that the fixed overheads remain unchanged with the

change in the level of activity. Single fixed overhead expenditure variance will be used

56

Page 57: Standard Costing Ppt

In absorption costing Fixed overheads are charged to the products and included in the

valuation of closing stock. Total fixed overheads variance is divided into fixed overheads price

variance and fixed overheads volume variance

57

Page 58: Standard Costing Ppt

PROFIT RECONCILIATION

STATEMENT58

Page 59: Standard Costing Ppt

PROFIT RECONCILIATION STATEMENT Profit reconciliation statement is used to sum up all variances

It can help the top management to explain the major reasons for the difference between budgeted and actual profits

The sales margin variance and fixed overheads variance are different between absorption and marginal costing system

59

Page 60: Standard Costing Ppt

REASONS FOR VARIANCES Material price variance Price changes in market conditions Change in the efficiency of purchasing dept. to obtain good terms

from suppliers Purchase of different grades or wrong types of materials

60

Page 61: Standard Costing Ppt

REASONS FOR VARIANCES Materials usage variance More effective use of materials/ wastage arising from the efficient

production process Purchase of different grade or wrong types of materials Wastage by the staff Change in production methods

61

Page 62: Standard Costing Ppt

REASONS FOR VARIANCES Labour rate variance Non-controllable market changes in the basic wage rate Use of higher/lower grade of workers Unexpected overtime allowance paid

62

Page 63: Standard Costing Ppt

Labour efficiency variance Purchase of different grade or wrong types of materials Breakdown of machinery High/low labour turnover Changes in production method Introduction of new machinery Assignment wrong type of worker to work Adequacy of supervision Changes in working condition Change in motivation methods

63

Reasons for variances

Page 64: Standard Costing Ppt

Variable overheads expenditure variance It may be caused by the non-controllable change in the price level of indirect wages or utility rates since the predetermined rate is set

It is meaningless to interpret this kind of variance on its own. One should look various components of the fixed overheads

64

Reasons for variances

Page 65: Standard Costing Ppt

Variable overheads efficiency variance Both the variable overheads and direct labour cost vary with the

direct labour hours worked

65

Reasons for variances

Page 66: Standard Costing Ppt

Fixed overheads expenditure It is meaningless to interpret this kind of variance on its own. It may be caused by the change in the price levels of rent, rates

and other fixed expenses

66

Reasons for variances

Page 67: Standard Costing Ppt

Fixed overhead volume variance When the level of activity is higher than the budgeted level, there is

a favourable variance

67

Reasons for variances

Page 68: Standard Costing Ppt

Sales margin price variance Change in the pricing strategies of the company Response to the change of pricing policies of its competitors Higher profit margin with growing demand for the product Lower profit margin for simulating sales

68

Reasons for variances

Page 69: Standard Costing Ppt

Sales margin volume variance Change in prices and demand Change in the market share of its competitiors

69

Reasons for variances