SQSS Industry Workshop 2012.pdf

download SQSS Industry Workshop 2012.pdf

of 76

description

SSQS -

Transcript of SQSS Industry Workshop 2012.pdf

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    1/76

    Place your chosenimage here. The four

    corners must justcover the arrow tips.

    For covers, the threepictures should be thesame size and in a

    straight line.

    SQSS Industry Workshop 21 June 2012

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    2/76

    2

    Welcome

    Health and Safety

    Introductions

    Agenda for rest of the day

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    3/76

    3

    Agenda

    10:10 - 10:20 SQSS governance

    10:20 - 11:15 Recent SQSS developments and

    update on ongoing modifications

    11:15 11:35 ENTSO-E interaction with SQSS

    11:35 12:15 Future SMARTer Transmission

    Networks and Impact on SQSS

    12:15 12:30 Interconnector Workgroup Progress

    12:30 13:00 Industry Input / open discussion

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    4/76

    Place your chosenimage here. The four

    corners must justcover the arrow tips.

    For covers, the threepictures should be thesame size and in a

    straight line.

    SQSS Governance

    Thomas Derry (National Grid)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    5/76

    5

    Presentation outline

    Brief Background

    Current SQSS Review Panel

    Modification Process

    SQSS Website

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    6/76

    6

    Brief Background

    Review Panel developed governance proposals in 2011

    Industry Consultation (15 July 05 September 2011)

    Five supportive responses received

    Refined and developed proposals further based on comments

    Produced final conclusions document (05 March 2012)

    Terminology alignment with industry codes

    New Panel members

    Revised SQSS Objectives with new European Objective

    Clarification of Panel Functions

    New governance arrangements went live 31 March 2012

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    7/76

    7

    Current SQSS Review Panel

    Chair David Wright

    Secretary James Cooper

    Members

    Distribution Alan Creighton

    Generation Simon Lord

    NGET Andrew Hiorns, Xiaoyao Zhou

    OFTOs Sean Kelly, Geoff Singleton

    SHETL Brian Punton, Bless Kuri

    SPT Cornel Brozio, Dave Carson

    Authority Sheona Mackenzie

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    8/76

    8

    Modification Process

    Availableonline in the

    IndustryGovernanceFrameworkdocument

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    9/76

    9

    Modification Process

    Modification Proposal

    SQSS Panel Review

    SQSS Panel determineprogression Workgroup

    Industry Consultation

    Produce and submitModification Report

    Authority review and

    make determination

    ModificationReg

    ister

    Documentation available online

    Proposal

    Agenda, Minutes

    & Papers

    Agenda &

    Minutes

    Consultation &Response

    Proforma

    Report

    Authority

    DecisionModification

    Register

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    10/76

    10

    SQSS Website

    Expect future changes

    What can I find here?

    SQSS

    Review Panel information (contact details, meeting dates)

    Modification Register

    Associated documents

    Address:http://www.nationalgrid.com/uk/Electricity/Codes/gbsqsscode/

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    11/76

    11

    Questions?

    Contact:

    Thomas Derry

    [email protected]

    01926 65 4208

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    12/76

    Place your chosenimage here. The four

    corners must justcover the arrow tips.

    For covers, the threepictures should be thesame size and in a

    straight line.

    Recent SQSS developments: GSR008

    Regional Variations and Wider Issues

    Vandad Hamidi (National Grid)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    13/76

    13

    GSR008 - Regional Variations and

    Wider Issues

    Recommendations:

    The requirement to consider an N-1-1 condition at peak demand in design studies inEngland and Wales should be relaxed

    The use of dynamic ratings in operational timescales should be explicitly referred to

    Flexibility should be allowed in setting the reactive output of generators in backgroundconditions across GB, as is currently permitted in Scotland

    Changes to the degree to which embedded generation is considered when assessing

    demand security should be made to align the NETS SQSS more closely with P2/6 Presentational changes should be made to demand security table to better align with

    P2/6

    Clarifications on the applicability of demand and generation criteria to composite groupsshould be made

    Generation trips should be considered when assessing compliance with the standard

    Flexibility should be introduced into voltage limits to allow more efficient system designand operation where there is no impact on customers

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    14/76

    14

    GSR008 - Regional Variations and

    Wider Issues

    Progress:

    Report submitted to Ofgem Autumn 2011

    Ofgem consultation recently completed

    4 consultation responses currently being considered

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    15/76

    Place your chosenimage here. The four

    corners must justcover the arrow tips.

    For covers, the threepictures should be thesame size and in a

    straight line.

    SQSS Workgroup Updates GSR010

    Generator Connections Workgroup

    Cornel Brozio (SPT)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    16/76

    16

    Generation ConnectionsCustomer Choice

    Problem with current arrangements

    Many smaller connecting customers exercise customer choice to choose a non-SQSS compliant connection.

    lowers their connection charge

    potentially facilitate an earlier connection to the grid

    TO required to design and document a bespoke connection arrangement for eachcustomer

    Complex for the customer to enable them to understand the options available.

    No explicit Cost Benefit Analysis (CBA) justification as to what may be consideredappropriate.

    Proposed solution Reference connection methodologies for 9 classes of generation

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    17/76

    17

    Generation ConnectionsConnection Methodologies

    Connection method 1

    For 0 50 MW generation

    Connection method 4

    For 100 MW 300 MW wind generation

    It is recommended these changes become the 9 standard onshore

    connections for different generation sizes

    CUSC Panel to separately consider any charging changes

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    18/76

    18

    Generation ConnectionsOnshore Required Connection Methodologies

    3599

    1799

    1319

    699

    299

    99

    49

    Max

    3600***

    1800**

    1320*

    700

    300

    100

    50

    0

    Min

    999H

    888G

    777F

    766E

    665D

    554C

    224B

    111A

    >70%

    e.g. CCGT

    40-70%

    e.g. biomass

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    19/76

    19

    Generation ConnectionsConsultation

    Industry Consultation launched 18th June

    Response deadline 17th August

    Consultation documents available on National Grid website:

    http://www.nationalgrid.com/uk/Electricity/Codes/gbsqsscode/Modifications/GSR010/index.htm

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    20/76

    20

    Generation ConnectionsConsultation Questions

    1. Minimum System Connections for Generation Connections do you agree that theproposed modification meets the principles and/or objectives of the SQSS?

    2. Minimum System Connections for Generation Connections do you have any

    comments on possible commercial implications that you would wish the CUSCPanel to take into consideration? Which CUSC option would be preferable - redefinewhen compensation should be paid (but with potentially higher TNUoS) or maintainthe existing arrangements?

    3. System Resilience for generation at single circuit risk do you agree that theproposals are appropriate and satisfy the principles and/or objectives of the SQSS?

    4. Revision of Selected Definitions - do you agree that the proposed modificationprovide clarity and better meets the principles and/or objectives of the SQSS?

    5. Standard Connection Schemes - do you agree that the proposed modificationprovide useful guidance and transparency and satisfy the principles and/orobjectives of the SQSS?

    6. Location of Grid Entry Points are you satisfied that the proposals further theprinciples and/or objectives of the SQSS?

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    21/76

    Place your chosenimage here. The four

    corners must justcover the arrow tips.

    For covers, the threepictures should be thesame size and in a

    straight line.

    SQSS Workgroup Updates GSR011

    Offshore Workgroup

    Vandad Hamidi (National Grid)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    22/76

    22

    GSR011 Offshore workgroupConclusions:

    Economics of Round 3 connections similar to those of Rounds 1 and 2

    No justification to change standard

    Connection capacity of 100% TEC is appropriate

    The recommendations of GSR009 - wind scaled to 70% in infrastructure analysis can beapplied to networks with high volumes of offshore wind generation

    In designing the transmission system the following should be considered as secured events:

    an N-1 outage of an offshore circuit

    an N-1-1 outage involving an offshore circuit on prior outage followed by either anoffshore circuit or an onshore circuit fault outage

    an N-1-1 condition with an onshore circuit containing a cable section on prior outage,followed by an offshore circuit fault outage.

    This is consistent with the GSR008 proposals for considering N-1-1 events in planning.

    Short duration losses of a DC link carrying more than the Infrequent Infeed Loss can betolerated where parallel routes can increase their flows

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    23/76

    23

    GSR011 Offshore working group

    Progress:

    Draft working group report submitted to May 12 Review Panel

    Final report to be submitted to July 12 Review Panel

    Industry consultation August / September

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    24/76

    24

    Infeed losses

    Response held to cover limit freq fall to 0.8Hz for1.8GW generation loss (from 2014)

    For loss above 1.8 GW, can contain fall using sameresponse if restore some generation quickly enough

    Amount of restoration required increases with greatertime delay

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    25/76

    25

    Loss of 2GW for limited time

    Loss of 2 GW wind (27 GW system - high wind FFR)

    0

    0.5

    1

    1.5

    2

    2.5

    3

    3.5

    4

    4.5

    5

    200 300 400 500 600 800 1000 1200 1400 1600 1800 2000

    Wind Reconnected (MW)

    MaximumA

    llowedT

    ime(s)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    26/76

    Place your chosenimage here. The four

    corners must just

    cover the arrow tips.For covers, the threepictures should be thesame size and in a

    straight line.

    SQSS Workgroup Updates - GSR013

    Offshore Infeed Loss Risk

    Xiaoyao Zhou (National Grid)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    27/76

    27

    Offshore infeed loss risk

    Normal and infrequent infeed loss

    HVDC Converter fault HVDC converter failure rate Power infeed loss after HVDC fault Mitigation factor

    offshore cable failure Cable failure rate Multiple cable failure due to anchor draggingMitigation factor

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    28/76

    28

    SQSS infeed loss risk

    limits post 2014

    The Security and Quality of Supply Standard considerstwo infeed loss risk limits

    Normal: 1320 MW, to avoid a deviation of systemfrequency by more than 0.5Hz.

    Infrequent: 1800 MW, to avoid a deviation of systemfrequency outside the range 49.5Hz to 50.5Hz for morethan 60 seconds.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    29/76

    29

    Normal Limit Count of Events

    Electricity Act requires: maintain the frequency within 49.5 to 50.5Hz,save in exceptional circumstances

    CEGB reckoned (legal opinion) that the man in the street would regard upto 2 events pa as exceptional circumstances

    N.Grid in 1994, re-judged that 4 events pa could be exceptional

    circumstances

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    30/76

    30

    Beyond the Infrequent Limit

    For instantaneous losses >1800MW, we have the Defence Measure ofLow Frequency (LF) relays; which shed demand in 5% blocks

    Operated once in anger on 26/May/2008 (restoration ~ 40 minutes)

    What is instantaneous? N.Grid have no formal policy on this: as fast as practicable;

    without incurring costs prior to the first fault Certainly we do not restore Response within 5 minutes of a first1000+MW Loss On average, given Fast Reserve used, we restore Response upto 20

    minutes of a first Loss

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    31/76

    31

    HVDC Forced Outage Rates (FOR)

    Frequency of converter fault

    Typical limit based on CIGRE report = 1.4 per year

    Normal infeed loss risk limit applies

    Frequency of cable faults

    Assume 1 forced outage/10 years

    Infrequent infeed loss risk limit applies

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    32/76

    32

    Symmetrical monopole

    converter outage incurs 100% energy unavailability

    1800MW lose instantaneously; does not meet SQSS

    requirements (Normal infeed loss risk limit applies)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    33/76

    33

    Bipole with neutral return via third

    conductor

    Pole outage incurs 50% energy unavailability

    900MW lose instantaneously, within the normal infeed loss risk

    Third conductor represents significant additional cost to the project

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    34/76

    34

    Bipole with neutral return via sea

    electrodes

    Pole outage incurs 50% energy unavailability

    900MW lose instantaneously, within the normal infeed lose risk

    Short duration ground return current until reconfiguration

    Metallic return transfer breaker (MRTB) commutates current back to cablefollowing reconfiguration

    Environmental issues under investigation, not been used in UK system

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    35/76

    35

    Bipole with no neutral return

    Pole outage incurs 100% energy unavailability until dc side reconfigured

    1800MW lose instantaneously and 900MW recovered followingreconfiguration

    For 1800MW HVDC, if the DC reconfiguration can be done within 1.35ssecond and recover half of the capacity (900MW); the system frequencycan be kept above 49.5HZ; if not can not meet the SQSS requirement

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    36/76

    36

    Bipole with no return with quick

    reconfiguration

    49.40

    49.50

    49.60

    49.70

    49.80

    49.90

    50.00

    1.00 1.99 3.00 4.01 5.02 6.03 7.04 8.05 9.06 10.0711.08 12.08 13.08 14.0815.08

    Time [s]

    Note: Fault is at 1s

    Frequ

    ency[Hz]

    900MW back at 2.35s

    900MW back at 2.4s

    900MW back at 2.45s

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    37/76

    37

    SQSS recommendation for HVDC

    converter fault The Converter fault remains at a frequency which should be covered

    down to the Normal Infeed risk

    Two configurations can meet the SQSS requirements

    No change to current SQSS

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    38/76

    38

    Cable Separation Risk N.Grid prefers that identifiable events do not lose Infeed > 1800MW

    Near-adjacent losses of infeed within 10-15 minutes pose a risk of alow frequency incident

    IF: we want to cover the Ship Dropping Anchor risk (speed 10-20 knots),we have to separate cables by 10-20 knots x 0.17-0.25hr = 3.1 to 9.3 km

    This must be completely impracticable for most large offshore windfarms

    If the risk is only 1 in 100year per cable-route, x 0.35 (probability thatoffshore wind output > 50% of rating) = 1 in 300year, the risk is certainly notworth covering

    IF: we want to cover the Ship Dragging Anchor risk (speed 0.5knots),

    we have to separate cables by 0.5 knots x 0.17-0.25hr = 150-250m This appear a more reasonable proposal If the risk is 1 in 20year per cable-route, 0.35 (probability that offshore windoutput > 50% of rating) = 1 in 60year, this approaches credible

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    39/76

    39

    SQSS review recommendation on

    cable separationPossible proposal to separate the cable by 250m but it is notrecommended by working group for the following reasons:

    There are a number of ~ 1-in-100year onshore Infeed loss risks of2000-5000MW. A few extra offshore risks would not give anoverwhelming case for mitigation. OFTOs are already under incentives to minimise downtimes of valuable

    wind connection assets. It is not clear that an SQSS requirement addsmuch, to what OFTOs will strive towards anyway. Good practice on laying offshore cables already typically leaves aseparation of 100-200m, in order to gain unfettered access to a cable incase of fault. Hence a requirement of 250m separation adds little. Circumstances along individual cable routes will vary. Difficult seabedconditions may naturally drive a section of route towards close cableseparation. A blanket requirement for 250m separation does not respectsuch individual considerations.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    40/76

    Place your chosenimage here. The four

    corners must just

    cover the arrow tips.For covers, the threepictures should be thesame size and in a

    straight line.

    ENTSO-E Network Code Development and SQSS

    Vandad Hamidi

    SMARTer System Performance Manager

    National Grid

    SQSS Public Workshop June 2012

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    41/76

    41

    Grid Code Requirement Variationsbetween different TSOs

    European Network Code

    Development

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    42/76

    42

    European Network Code

    Development

    European Network ofTransmission System Operatorsfor Electricity (ENTSO-E)

    41 TSO Members:

    serving 525 million citizens,

    880 GW generation,

    270,000 km transmission lines,(over 220 kV)

    3,300 TWh/Year Demand,

    400 TWh/ Year Exchange.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    43/76

    43

    European Network Code

    Development

    Main tasks:

    Establishment of network codes

    Ensure coordination of network operation by commonnetwork operation tools

    Develop a ten-year network development plan

    Planning Standard (Project Evaluation Rules)

    Publish annual work programme, annual report andannual summer and winter generation adequacy outlooks

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    44/76

    44

    European Network Code

    Development

    A generic grid code format; the structure, designations,figures, method of specification, definitions and units arefixed and agreed upon.

    Technical requirements which will maximise efficiency for allparties and in particular benefit for:

    Manufacturers, who will be required only to develop commonhardware and software platforms;

    Developers, who will benefit from reduced development costs(connection cost, cost of particular type of turbine, etc.);

    Consumers, who will benefit from lower costs;

    System operators, especially those who have yet to developtheir own grid code requirements for new technologies.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    45/76

    45

    ENTSO-Es Ultimate Goal

    Facilitating Integration of Renewables

    Maintaining Security of Supply Facilitating the Market

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    46/76

    46

    European Network Code

    Development

    Grid Connection Framework Guidelines result

    in the following Network Codes:

    Requirements for Generators (RfG)

    Demand Connection Code (DCC)

    HVDC Connection Code (HCC)

    Connection Procedures Code (CPC)

    Priority (expected at

    the end of 2012)

    To Follow on shortly thereafter

    Starting in 2013

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    47/76

    47

    NC RfG Harmonization Principles

    In addition, Power Generating Modules (PGM) are divided into 4 Typesranging from Type A (down to 0.8 kW) up to Type D with units above 30 MWor connected at or above 110kV.

    Offshore (ACConnection)*Non-synchronousSynchronousApply to all

    Specific RequirementsGeneral Requirements

    Four Categories of NC RfG General and Specific Requirements

    Baltic StatesIrelandGreat BritainNordic StatesContinental Europe

    Five Regional Requirements

    Rather than complete harmonization of all requirements for all generatingunits which is neither pragmatic nor cost effective, the document provides

    a consistent set of requirements for all generation under 4 categoriesand

    allows for regional differences across 5 areas.

    * All offshore DC Connections will be Discussed in HVDC Connection Code

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    48/76

    48

    RfG- Offshore CP

    Interaction with SQSS

    AC Grid

    WTG WTG WTG WTG WTG

    WTGWTGWTGWTGWTG

    Sub-Sea CableOnshore Cable

    Intertidal Cable

    Unity PFNo Change0.95 PF Lead/Lag

    No Change

    RfG Off h CP

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    49/76

    49

    RfG- Offshore CP

    Interaction with SQSS

    WTG WTG WTG WTG WTG

    WTGWTGWTGWTGWTG

    WTG WTG WTG WTG WTG

    WTGWTGWTGWTGWTG

    AC Grid

    0.98 PF Lead/Lag0.95 PF Lead/Lag

    This Arrangement is currently not allowed under the existing Grid Code

    D d C ti C d

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    50/76

    50

    Demand Connection Code

    Interaction with SQSS

    Frequency Response

    Frequency Reserve Reactive Power MVAR exchange between T & D & power factor limits

    Voltage withstand capabilities

    Frequency withstand capabilities

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    51/76

    51

    ENTSO-E Network Codes,

    and SQSSConclusions

    ENTSO-E Network Codes do not have any direct influence on HOWEuropean TSOs design their own Network The impact will be mainly

    through changes on the Grid Connection Codes and may require updatingthe national design standards (i.e. SQSS in GB)

    RfG Code will have very little material impact on SQSS (Chapter 2 Studiesmainly intended for Generation Connection)

    Future Codes:

    DCC Code is still under development (the impact on SQSS is likely tobe on Chapter 3 Studies and how Demand is treated i.e.Distinguishing between Responsive and Non-Responsive, Voltagewithstand Capability etc.) Also the reactive power exchange betweenT&D network may require slight modification of Chapter 4 studyProcedure.

    HVDC Connection Code is yet to be drafted; it is expected that it willmainly cover System Performance issues.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    52/76

    52

    Discussion & Questions?

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    53/76

    Place your chosenimage here. The four

    corners must just

    cover the arrow tips.For covers, the threepictures should be thesame size and in a

    straight line.

    Future SMARTer Transmission Networksand Impact on SQSS

    Vandad HamidiSMARTer System Performance

    National Grid Warwick UK

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    54/76

    54

    Outline

    Challenges for GB Power System

    The issue of Transmission Constraint

    Integrated Offshore Networks

    Western / Eastern HVDC Project

    Series Compensation

    Dynamic Thermal Rating

    Phasor Measurement Unit (PMU)

    Automation of QBs

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    55/76

    55

    Chart example

    So far 19% reduction achieved equivalent ofremoving 22m passenger vehicles from the UK

    What are the targets:

    1990 593 Mt CO22020 438 Mt CO22030 332 Mt CO2

    Offshore wind capacityOffshoreWi df

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    56/76

    56

    To meet 2020targets*

    Alreadycontracted

    16GW 27GW

    Windfarm

    Development* against Gone Green scenario

    NSN

    BritN

    ed

    Nemo

    IFA

    Hornsea

    Norfo

    lk

    Dogger Bank

    Round 1Round 2Round 2+Round 3

    Moyle

    EWIC

    Stepwise evolution to aNORWAY

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    57/76

    57

    European supergrid

    NSN

    BritN

    ed

    Nemo

    IFABELGIUM,

    FRANCE

    THE NETHERLANDS,

    GERMANY

    DENMARK

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    58/76

    58

    Transmission ConstraintHistoric power flows

    generally north southFuture power flows vary in

    time and direction

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    59/76

    Activity 1. Integrated Offshore

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    60/76

    60

    Activity 1. Integrated Offshore

    Networks

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    61/76

    61

    Activity 1. Integrated Offshore Networks

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    62/76

    62

    Activity 1. Integrated Offshore Networks

    Onshore Substation 1

    Onshore Substation 1

    Onshore GridWindfarm

    GG

    Full Reactive Power SupportRegardless of Direction

    of Active Power

    Rapid power reversal possible (simply change thedirection of current) No Filter Switching Time etc.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    63/76

    63

    System Performance

    Activity 1. Integrated Offshore Networks

    1.000.50-0.50-1.00

    1.00

    0.50

    -0.50

    -1.00

    Controllability of mode: -0.283 +0.039*jMagnitude: 0.286 1/s, Angle: 172.240 degPeriod: 162.944 s, Frequency: 0.006 HzDamping: 0.283 1/s, Ratio of Amplitudes: 105904023741220360000.000Min. contribution: 0.100

    Cluster 3:Grid / Non-Frequency response H6; psie: 0.20 / 12.1 deg

    Cluster 4:Grid / SCCL-1; speed: 1.00 / 0.0 deg

    Cluster 1:Grid / Non-Frequency response H4; speed: 0.14 / -167.1 deg

    Cluster 2:Grid / Non-Frequency response H6; speed: 0.53 / -162.2 deg

    DIgSILENT

    0.2381-0.0609-0.3599-0.6589-0.9580-1.2570 Neg. Damping [1/s]

    1.5178

    1.0342

    0.5507

    0.0671

    -0.4165

    -0.9000

    Damped Frequency [Hz]

    Stable Eigenvalues

    Unstable Eigenvalues

    DIgSILENT

    0.2381-0.0609-0.3599-0.6589-0.9580-1.2570 Neg. Damping [1/s]

    1.5178

    1.0342

    0.5507

    0.0671

    -0.4165

    -0.9000

    Damped Frequency[Hz]

    Stable EigenvaluesUnstable Eigenvalues

    DIgSILENT

    1.000.50-0.50-1.00

    1.00

    0.50

    -0.50

    -1.00

    Controllability of mode: -0.112 +0.126*jMagnitude: 0.168 1/s, Angle: 131.611 degPeriod: 49.904 s, Frequency: 0.020 HzDamping: 0.112 1/s, Ratio of Amplitudes: 265.250Min. contribution: 0.100

    Cluster 1:Grid / Induction Machine Load; speed: 0.47 / 0.9 degGrid / Pump storage; speed: 0.46 / 0.8 degGrid / Non-Frequency response H4; speed: 0.34 / 0.1 degGrid / Non-Frequency response H6; speed: 1.00 / 0.0 deg

    DIgSILENT

    Activity 2. Western HVDC Project(E t d 2015/16)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    64/76

    64

    (Expected 2015/16)

    2.2 GW Link Between Hunterston (Scotland) and Connahs

    Quay (North Wales)

    420km - 600 kV Subsea Cable in the Irish Sea (the first of its

    kind in the world at this voltage level)

    Key Characteristics:

    Based on Line Commutated Current (LCC) Technology

    Power Oscillation Damping (POD) Capability

    Challenges

    Requires Minimum Fault Level (Network Strength) to Operate

    No Provision for Power Reversal (LCC Limitation)

    Harmonics and Sub Synchronous Resonance Issues

    Activity 3. Proposed Eastern HVDCP j

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    65/76

    65

    Project(Expected 2018)

    Around 2 GW HVDC

    Subsea link between Peterhead inScotland and Hawthorne Pit in England

    VSC / LCC ?

    Potential for Multi-Terminal VSC-HVDCLinks (we need DC breakers!)

    If VSC:Dynamic Reactive Support to the Grid

    Power Reversal Capability

    No Harmonics / Resonance Issues

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    66/76

    66

    Activity 4. Series Compensation (Expected 2014)

    Increasing the Power Transfer from 3.3GW (Stability Limit) to around 4.3 GW

    (Thermal Limit)

    To be installed at both Eastern andWestern AC Power Corridors)

    Compensation Level around 35%

    Fixed vs TCSC

    Challenges:Sub Synchronous Resonance

    Distance Protection

    Activity 4. Series Compensation

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    67/76

    67

    y p

    (TCSC)

    R

    L

    C

    MOV

    Main Spark Gap

    CB

    Damping circuit

    Auxiliary Spark Gap

    Benefits of Thyristor ControlledSeries Compensation

    Allows Variable Compensation Level(Dynamically)

    Mitigation Measure for SSR

    TCSC at Low Frequencies is

    Inductive Could Reduce the Compensation

    Level in case of Resonance

    Better Power Oscillation Damping (POD)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    68/76

    68

    Activity 5. Dynamic Thermal Rating

    Dynamic & real time ratings couldtemporarily enhance boundary capacity- particularly for intermittent generation

    Tools already employed

    Circuit Thermal Monitor (CTM)

    provides condition based ratings -approx 20 ccts

    Met office rating enhancement(MORE) approx 30 ccts

    Humber Smart Zone:

    Activity 6. Phasor Measurement Unit(PMU) (2012)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    69/76

    69

    (PMU) (2012)

    Synchronized measurements and sampling of voltage and currentwaveforms. Synchronization is achieved using timing signals from the

    GPS. Synchronized phasor measurements elevate the standards of power

    system monitoring, control, and protection to a new level.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    70/76

    70

    Activity 7. Automated QB Tapping Currently QBs are Tapped Individually to mitigate

    Local overloading (N-D condition)

    Optimized Automated Tapping of Multiple QBs to Allowfurther loading an Area

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    71/76

    71

    Activity 7. Automated QB Tapping

    There are 10 QBs with a total of 12630 MVAoperating at levels of 275kV and 400kV on the grid

    for power flow control.

    Each QB is controlled independently in operationsand they play an important role in setting up a

    cardinal point in network operations.

    Current Operational procedure limits 6 times tapchanges of single/pair of QBs for 10 mins overload

    condition and 15 times tap changes of single/pair ofQBs for 20 min overload condition

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    72/76

    72

    Interaction with SQSS SQSS ensures a reliable, and efficient network design procedure.

    New Technologies mainly enhance the capability of the Utilization of

    Existing Assets (i.e. Dynamic Thermal Rating), or Provide moreFlexibility in Design/Operation (i.e. VSC HVDC by Providing DynamicReactive Power Response).

    Therefore, the existing SQSS as it stands today is currently fit for

    purpose. SQSS Working Group is constantly reviewing the SQSS, making

    required modifications (i.e. Working Group on Loss of infeed over1800MW).

    Stakeholders are welcome to request modifications which will beconsidered in the working group.

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    73/76

    73

    Discussion & Questions?

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    74/76

    Place your chosenimage here. The four

    corners must justcover the arrow tips.

    For covers, the threepictures should be thesame size and in a

    straight line.

    Interconnector Workgroup GSR012

    Andy Hiorns (National Grid)

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    75/76

    75

    SQSSR: Interconnector WG (1) Presence, location and size of Interconnectors is out-of-scope

    Europe likes to treat Interconnectors as Transmission

    But GB still treats as Merchant; hence SQSS must take locationand size of Interconnector as a given

    Connection for Interconnectors remains at maximum flow in eitherdirection

    Largest issue wrt planning of Infrastructure for Interconnectors is theexpected direction of flow

    GSR009 Security has set this to zero

    SQSS cannot specify this, for GSR009 Economy

    We will handle this via the Planned Status of each Interconnector

    We now treat all non-Irish Interconnectors as Planned Status= Float

  • 7/14/2019 SQSS Industry Workshop 2012.pdf

    76/76

    76

    SQSSR: Interconnector WG (2) Only remaining issue for Interconnector WG is the weight to be given,

    in Planning studies, to the extremes of all Interconnectors importinginto GB and all Interconnectors exporting from GB

    This needs forecast data of:

    Duration and Distribution of individual interconnector flows

    Correlation of same across multiple interconnectors

    History 2001-2011 is unlikely to be a good indicator of 2015 or2025

    There is no History for new Interconnectors, eg BelgiumNorway

    Europe- wide merit orders have been prepared; but are ofdoubtful quality and are onerous to implement

    Can any in the Industry help us on this?