Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus...

34
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Fault Ride Through Study Work Antony Johnson National Grid – TNS Technical Policy

Transcript of Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus...

Page 1: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Place your chosenimage here. The fourcorners must justcover the arrow tips.For covers, the threepictures should be thesame size and in astraight line.

Fault Ride ThroughStudy Work

Antony JohnsonNational Grid – TNS Technical Policy

Page 2: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Overview

High Level Fault Ride Through Requirements

ENTSO-E Requirements and Implementation

High Level determination of Voltage Against TimeCurves

Study Cases

Summary

Discussion

Page 3: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

3

High Level Fault Ride Through Requirements

Required to:-

Ensure Generation remains connected and stable during mainprotection operating times for Transmission System faults.

Prevent voltage collapse during Transmission System Faults

Ensure appropriate recovery of active power following faultclearance to prevent frequency collapse

Ensure sufficient generation robustness and network resilienceto transmission faults cleared in backup protection operatingtimes.

Ensure requirements are consistent with the credible operatingand design criteria covered in the SQSS

Be achievable by manufacturers and Generators

Page 4: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

4

ENTSO-E RfG - Fault Ride ThroughRequirements – Voltage Against TimeProfile – Figure 3

0 tclear trec1 trec2 trec3

Urec1

Uclear

Uret

1.0

Urec2

t/sec

U/p.u.

Page 5: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

5

ENTSO-E RfG - Voltage Against TimeParameters – Table 7.1 – Type DSynchronous Power Generating Modules

Voltage parameters [pu] Time parameters [seconds]

Uret: 0 tclear: 0.14 – 0.25

Uclear: 0.25 trec1: tclear – 0.45

Urec1: 0.5 – 0.7 trec2: trec1 – 0.7

Urec2: 0.85 – 0.9 trec3: trec2 – 1.5

Table 7.1 – Fault Ride Through Capability of Synchronous Power Generating Modules

Page 6: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

6

ENTSO-E RfG - Voltage DurationProfile – Range compared with GBRequirement

0 0.25 0.45 0.7 1.50.14

0.25

0.5

0.85

0.9

0.15

1.20

1.0

Voltage (p.u)

Time (s)

NOT TO SCALE

RFG Min

RFG Max

GB Requirement

0.8

Page 7: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

7

Implementation

For the purposes of this section of work – consider therequirements only in respect of Large directly connectionSynchronous Plant

Determine Voltage against curve within range permitted byENTSO-E Drafting – study work dependant

Active Power Recovery as per current GB requirements Thereshould be no reason to change this unless there is good reason notto do so.

Asymmetrical faults – as per current GB requirement – applicableonly for faults cleared in main protection operating times?

Pre and post fault conditions – specified in the Bilateral Agreement

Reactive Power injection for Synchronous Generators not specifiedin the ENTSO-E Requirements for Generators and would remain atNational level.

Page 8: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

8

ENTSO-E RfG - Voltage DurationProfile – Range compared with GBRequirement

0 0.25 0.45 0.7 1.50.14

0.25

0.5

0.85

0.9

0.15

1.20

1.0

Voltage (p.u)

Time (s)

NOT TO SCALE

RFG Min

RFG Max

GB Requirement

0.8

Area of Complexity

Page 9: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

9

Determination of Voltageagainst time curve and other characteristics

For Directly Connected Synchronous Generation the area of complexity isin the zone shown in slide 8.

System studies required to determine voltage against time curve.

As a minimum the voltage against time curve should cater for the list ofevents defined in the SQSS plus overall industry resilience

No reason to change other factors such as active power recovery andreactive current injection.

There are still some potential issues over the length of the voltagedepression for longer duration faults eg 85% volts for 1.5 seconds whereas GB is 85% for 3 minutes

Need to understand the impact on station auxiliaries .

Page 10: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

10

Determination of Voltage against timecurve

Achievable requirements

Robust to range of System Conditions – Generation toremain connected remote from fault cleared in back upoperating times

Requirements to be consistent with ENTSO-E RfG andnot more onerous than current GB Specification

Page 11: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

11

Study Cases

Full GB Network under 2013 minimum demand conditions ~ 18GW

Range of scenarios investigated

Low non-synchronous generation

Medium non-synchronous generation

High non-synchronous generation

Range of faults applied to strategic parts of the network, including

Seabank

Drax / Eggborough

Standard fault clearance times applied plus longer duration faults to caterfor issues such as backup protection

Analysis of high impedance faults

Effect on voltage profile observed.

Studies run in Digsilent Power Factor Factory

Page 12: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

12

Fault Ride Through

Example

A

B

X X

X X

Fault Appliedadjacent to

Substation A

CXX

SynchronousGenerator

DXX

XX

Synchronous Generator under FRTsimulation

X

X

EXX

XX

Operating conditions of generator specified pre fault eg Pmax, Qmax (imp / exp)

Pre fault system strength defined atconnection point

Range of high / low imepdanceFaults applied

Page 13: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

13

Fault Ride Through

Example

A

B

X X

X X

Fault Appliedadjacent to

Substation A

CXX

SynchronousGenerator

DXX

XX

Synchronous Generator

X

X

EXX

XX

Fault cleared

Post fault system strength defined atconnection point

Post fault voltage and active power recovery observed

Adjacent circuit breakers openedin typically 100ms

Remote circuit breakers openedin typically 140ms

Note extreme cases where a faultis cleared in backup operating times – typically

500ms

Page 14: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

14

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 140ms Fault

Page 15: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 140ms fault(Z=0)Transmission Voltage

Page 16: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 140ms fault(Z=0)Generator Terminal Voltage

Page 17: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 140ms fault(Z=0)Rotor Angle

Page 18: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

18

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=0)

Stuck breaker – bar cleared 500ms later

Z = 50%

Page 19: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

19

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=0)

Page 20: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

20

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=0)Transmission Voltage

Page 21: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

21

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=0)Generator Terminal Voltage

Page 22: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

22

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=0)Rotor Angle

Page 23: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

23

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=50%)

Stuck breaker – bar cleared 500ms later

Z = 50%

Page 24: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

24

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=50%)Transmission Voltage

Page 25: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

25

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=50%)Generator Terminal Voltage

Page 26: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

26

Seabank – Whitson – Clfynydd,Melksham - Imperial Park DC – 500ms fault (Z=50%)Rotor Angle

Page 27: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

27

Drax – Eggborough Double Circuit(Studies / scenarios as per Seabank – Plots not illustrated)

Stuck breaker – bar cleared 500ms later

Z = Variable

Page 28: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Eggborough 400kV Substation

Stuck breaker – bar cleared 500ms later

Page 29: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

ENTSO-E RfG - Voltage DurationProfile – Study Results

0 0.45 1.28250.14

0.5

0

1.0

Voltage (p.u)

Time (s)

NOT TO SCALE

0.33

Option 1

Option 2 as per option 1with dashed line

0.85

0

0.7

Page 30: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

Study Case – eg 0.5 p.u for 70ms

0 0.14

0.5

0

1.0

Voltage (p.u)

Time (s)

NOT TO SCALE

0

0.7

x(0,5 p.u, 700ms)

700ms

140ms

Page 31: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

ENTSO-E RfG - Voltage DurationProfile – Study Results

0 0.45 1.28250.14

0.5

0

1.0

Voltage (p.u)

Time (s)

NOT TO SCALE

0.33

Option 1

Option 2 as per option 1with dashed line

0.85

0

0.7

x

xx

x

x

X – Study Test Cases

(0 p.u, 140ms)

(0.39 p.u, 250ms)

(0,5 p.u, 700ms)

(0.68 p.u, 1000 ms)

(0.85 p.u, 10 s)

Page 32: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

32

Voltage Duration Profile – Optionscompared with GB and ENTSO – ERequirement

0 0.25 0.45 0.7 1.50.14

0.25

0.5

0.85

0.9

0.15

1.20

1.0

Voltage (p.u)

Time (s)

NOT TO SCALE

RFG Min

RFG Max

GB Requirement

0.8

Option 1

Option 2 as per Option 1with dashed line

0.33

1.2825

Page 33: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

33

Summary

Two initial options proposed for voltage against time curve

Suggested curves believed to provide a blend of the ENTSO-ERequirements and existing GB requirements. The proposals are fullyconsistent with the ENTSO-E requirements

In the scenario’s run, an event such as a stuck breaker has a significantimpact on System Voltage recovery (ie voltage remains low)

Adjacent Generators run at full load and full import of reactive Power (leaststable)

Additional study work required in respect of:-

Wider sensitivities

Other scenarios

Effect on Power Station Auxiliaries

System Frequency impacts

AVR Voltage – High post fault voltage observed

Page 34: Fault Ride Through Study Work - 080514 v2 · 2017. 7. 8. · events defined in the SQSS plus overall industry resilience No reason to change other factors such as active power recovery

34

Discussion