Sole Agent

26

description

Sole Agent. Informatics Pulse. Ibrahim A. ALHawawi (CEO). Tele: (+966505470505) – (+966553595000). - PowerPoint PPT Presentation

Transcript of Sole Agent

Page 1: Sole Agent
Page 2: Sole Agent

Sole Agent

Informatics Pulse has the right of the sole agent in Saudi Arabia and neighboring Middle East contries regarding Kyce's construction technologies.If you have any questions about Kyce's construction technologies, please contact Informatics Pulse and inquire about them.

Informatics PulseTele: (+966505470505) –

(+966553595000)

Ibrahim A. ALHawawi (CEO)

Page 3: Sole Agent

Sole Agent Certificate

Sole Agent CertificateSole Agent CertificateWe certify that

Informatics Pulse P.O. BOX 7226Riyadh, 11462, Kingdom of Saudi Arabia

is an authorized exclusive agent for the following territories;…………………Saudi Arabia & Middle east countries………………………..

This certificate is valid for a period of 3 years.

Date : 1st of November of 2008

--------------------------Han, Min-ho - CEO & PresidentKun Yang Construction & Engineering Company, Limited

Kun Yang C&E Co., LTD : Room No. 308, Gold Tower, 386, Mannyeon-dong, Seo-gu, Daejeon, Korea

Page 4: Sole Agent

Obtained Inno-Biz Certification

Designated as a Venture Business

Authorized as a Research Institute

Obtained ISO9001 / ISO14001 Certification

Obtained Certificate Quality Innovation Excellent Company

Obtained A Certificate of Business Transparency

Awarded in 2002/2003 Korea Patented Technology Contest

Selected as Good Technology of Small and Medium Enterprise

Innovation Contest

Tel: +82-42-472-0546

Fax: +82-42-472-0549

http:///www.kyce.co.kr

Email: [email protected]

Page 5: Sole Agent

CONTENTS

1. Outline of Semi-shield method & Micro-shield / Micro-tunnelling

2. Characteristics of Semi-shield method & Micro-shield / Micro-tunnelling3. Types of Semi-shield method & Micro-shield / Micro-tunnelling

3-1. Mud-injection earth pressure balance type

3-2. Water-injection earth pressure balance type

4. Construction Work Procedure of Semi-shield method & Micro-shield / Micro-tunnelling

5. Outline of HDD method

6. Characteristics of HDD method

7. Construction Work Procedure of HDD method

8. Construction Case (Micro-shield / Micro-tunnelling)

Page 6: Sole Agent

조 직 도

Semi-shield method is to minimize noise, dust, the ground subsidence, traffic difficulties and others caused by the existing open-excavation method for making sure of safety of civil infrastructure and support facilities such as upper sewerage, electricity, communication, gas pipe, airport, train and so on.

Early in development, open-shield manpower excavation method had been used but, to apply for the soft ground and an increase of sill’s construction and to cope with difficult construction work, mechanical excavation method has been developed and improved so that the semi-shield method of a Mud-injection earth pressure balance type has been widely supplied.

The semi-shield method of a Water-injection earth pressure balance type also has recently been used because of demerits of Mud-injection earth pressure balance type which were expensive costs of PLANT facility and work space for separating injected mud-water and soil.

1. Outline of Semi-shield & Micro-shield/Micro-tunnelling

(Micro-shield/Micro-tunnelling are also the same methods as that of Semi-shield.)

Page 7: Sole Agent

2. Characteristics of Semi-shield method & Micro-shield/Micro-tunnelling

Long distance propulsion can be applied without equipments of middle bases. Problems with the press of a propulsion pipe created in composite soil can be solved by automatic injection equipment of lublicator for soil. Construction work of long distance and tunnel curve can be precisely carried out with automatic measurement equipment. Minimize the ground displacement Minimize traffic difficulties and environmental damage Applicable to various kinds of soil Construction period can be shortened with high propulsion speed. Relatively small sizes of starting work shaft and arrival work shaft

(Micro-shield/Micro-tunnelling are also the same methods as that of Semi-shield.)

Page 8: Sole Agent

조 직 도3. Types of Semi-shield method & Micro-shield/Micro-tunnelling

Reinforcement support wall is constructed in front of shield machine and then by injecting Mud-water into the blind end sealed up and pressing it, it can be rapidly moved to soil discharge device with seeking safety of the blind end, moved out to the ground through a pipe together with the soil excavated by a rotating cutter. PLANT on the ground separates injected mud-water from the soil, and separated mud-water is reused for construction work while the soil is discharged.

3-1. Mud-injection earth pressure balance type3-1. Mud-injection earth pressure balance type

(Micro-shield/Micro-tunnelling are also the same methods as that of Semi-shield.)

Page 9: Sole Agent

조 직 도Types of Semi-shield method & Micro-shield/Micro-tunnelling

This method is to propel shield with keeping a safety blind end by using the soil which was cut with a rotating cutter device depending on propulsion of shield and moved into cutter chamber. Only a moderate quantity of soil is discharged continually both through the machinery for soil discharge of screw type installed in cutting chamber and through machinery for soil discharge, such as slide gate or rotary feeder and others installed in shaft of just that machinery.

3-2. Water-injection earth pressure balance type3-2. Water-injection earth pressure balance type

(Micro-shield/Micro-tunnelling are also the same methods as that of Semi-shield.)

Page 10: Sole Agent

조 직 도4. Construction Work Procedure of Semi-shield method

& Micro-shield / Micro-tunnelling

Installation of starting work shaft

Construction of reinforcement support wall

Installation of a guide rail for propulsion

Setting the propulsion work shaft

Setting equipment and installation of a propulsion pipe

Taking out equipment

Linking propulsion pipe

Propulsion and Excavated soil discharge

Installation of arrival work shaft

Repeat

(Micro-shield/Micro-tunnelling are also the same methods as that of Semi-shield.)

Page 11: Sole Agent

조 직 도5. Outline of HDD method

As a kind of horizontal propulsion methods, this is the method of tunnelling through the ground surface-to-ground surface without vertical work shaft.

After fixing Bit on the end of pipe, the ground is punched and at this time, high pressure water is sprayed into the pipe. The service water used at this moment is to compound materials of bentonite or gel component.

Page 12: Sole Agent

조 직 도6. Characteristics of HDD method

Mainly used for establishing communication cable, electric power line

Short damage to the ground surface

Few civil petitions like traffic difficulties

Shortening construction period and being economical

Page 13: Sole Agent

조 직 도7. Construction Work Procedure of HDD method

Checking out buried underground materials in punching section

Preparing for equipment and construction materials

ShootingInput drill head-> Control jetting pressure-> Checking out

head position with deep locator-> Arrive at drill head target pit

Arrangement of construction site and withdrawal

ReamingRemove drill head-> Attach reamer

-> Fix Swivel pipe/cable with grip-> Control jetting pressure

CompletionStop Jetting-> Remove swivel and grip from Pipe-> Seal up the shift of pipe/cable with end cap

Page 14: Sole Agent

8. Construction Case (Micro-shield / Micro-tunnelling)

Installation of a guide rail for propulsion

Project D300. General soil L=50.0M

Installation of laser measurement machine for direction adjustment

Page 15: Sole Agent

Construction Case (Micro-shield / Micro-tunnelling)

Initial work of a propulsion leading machine

Project D300. General soil L=50.0M

Page 16: Sole Agent

Work of initial propulsion

Project D300. General soil L=50.0M

Join a propulsion leading pipe to a pipe

Construction Case (Micro-shield / Micro-tunnelling)

Page 17: Sole Agent

Propulsion after joining a propulsion leading pipe to a pipe

Project D300. General soil L=50.0M

Propulsion of a propulsion pipe

Construction Case (Micro-shield / Micro-tunnelling)

Page 18: Sole Agent

Propulsion of a propulsion pipe

Project D800. Soil contained gravel L=116.0M

Construction Case (Micro-shield / Micro-tunnelling)

Page 19: Sole Agent

Display propulsion conditions on monitor

Project D800. Soil contained gravel L=116.0M

Inject lublicator for soil

Construction Case (Micro-shield / Micro-tunnelling)

Page 20: Sole Agent

Arrival of a propulsion leading machine at the final base

Project D800. Soil contained gravel L=116.0M

Pull up a propulsion leading machine after separating from a propulsion pipe

Construction Case (Micro-shield / Micro-tunnelling)

Page 21: Sole Agent

Separate Auger in casing & take it out after finishing propulsion

Project D800. Soil contained gravel L=116.0M

Construction Case (Micro-shield / Micro-tunnelling)

Page 22: Sole Agent

Project D500. General soil L=60.0M

Propulsion of a propulsion pipe

Construction Case (Micro-shield / Micro-tunnelling)

Page 23: Sole Agent

Join a propulsion pipe

Project D500. General soil L=60.0M

Propulsion of a propulsion pipe

Construction Case (Micro-shield / Micro-tunnelling)

Page 24: Sole Agent

Arrival of a propulsion leading machine at the final base

Project D500. General soil L=60.0M

Pull up a propulsion leading machine after separating from a propulsion pipe

Construction Case (Micro-shield / Micro-tunnelling)

Page 25: Sole Agent

Project D500. General soil L=60.0M

Separate Auger in casing & take it out after finishing propulsion

Construction Case (Micro-shield / Micro-tunnelling)

Page 26: Sole Agent