Solar Pre-commissioning Check List Site Contact
Transcript of Solar Pre-commissioning Check List Site Contact
Hoval Limited Northgate - Newark - Nottinghamshire NG24 1JN - UK Tel: (01636) 672711 - Fax: (01636) 673532 (International: +44 1636 673532) e-mail: [email protected] - Web: www.hoval.co.uk
Page 1 of 1
By Appointment to Her Majesty the Queen
Boiler Manufacturers & Engineers Hoval Ltd Newark
Registered Number 592844
Solar Pre-commissioning Check List Site Address: Site Contact: Contact Number: K No:
Plant room requirements
230v/110v 1phase electrical supply Cold feed tap available in plant room Drain available close to calorifier
Yes No Access to roof required for Hoval Engineers
Collector sensor must be fitted inside Solar Panel
No valves should be fitted to solar panels
Solar Panels should be covered to aid commissioning
2 core sensor cable to be wired from collector sensor to UVR Control Panel in plant room
Pipework pressure tested to 5 bar
Pipework and connections suitable for Solar temperatures (130°C)
Expansion vessel piped to Solar pump station with isolating and drain valves fitted
UVR Control Panel mounted adjacent to Calorifier
Solar pump station and Anti-Legionella pump wired to UVR Control Panel
230v 1phase supply to UVR Control Panel
Solar fluid left in plant room