    Software Quality Standard List

    Quality Checking

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    3/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 3

    Software Quality Standard ListItem Result

    1 Check ODU received power value whether match with the plan.

    2 Check ODU TX power value whether match the plan

    3 Check ODU TX and RX frequency whether match the plan

    4 Check IF working mode whether match the plan

    5 Check 1+1 configuration

    6 Check 1+1 switch state

    7 Check NE ID and name setting whether match the plan

    8 Check NE time whether synchronous with computer time

    9 Check NE synchronous clock configuration

    10 Check performance monitor state whether enabled

    11 Check current and history alarm whether there are abnormal alarms

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    4/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 4

    1. Check ODU received power value whether match

    with the plan.

    Plan Document

    The actual Rx Power value should within the plan designed receive value range accordingto the customers requirement.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    5/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 5

    2. Check ODU TX power value whether match the

    plan.

    Plan Document

    The setting Tx Power value should equal to the plan designed transmit value.

    The acceptablevalue:

    [25.5]

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    6/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 6

    3. Check ODU TX and RX frequency whether match

    the plan.

    Plan Document

    The Tx Frequency and actual Tx Frequency should equal to the local site plan designed TxFrequency.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    7/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 7

    4. Check IF working mode whether match the plan.

    Plan Document

    The IF Mode should be the same as the plan document.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    8/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 8

    5. Check 1+1 configuration.

    IF 1+1 configuration should correspond with the link design.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    9/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 9

    6. Check 1+1 switch state.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    10/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 10

    7. Check NE ID and name setting whether match the

    plan.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    11/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 11

    8. Check NE time whether synchronous with

    computer time. The NE currently time should be synchronous with your computer clock, and synchronous

    mode is NM.

    The Same

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    12/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 12

    9. Check NE synchronous clock configuration.

    For RTN 620/610, it is necessary to configure synchronous clock.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    13/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 13

    9. Check NE synchronous clock configuration.

    RTN 620/610 RTN 620/610

    Internal InternalPriority

    Priority

    5-IF 5-IF

    5-IF;

    Internal

    5-IF;

    Internal

    Typical mistakes:

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    14/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 14

    10. Check performance monitor state whether

    enabled.

    State: Enable. State: Enable.

    Check on the setting of enabling performance monitor, which is required to be enabled.

  • 8/14/2019 Check Software Commissioning Quality(RTN600)

    15/16

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential Page 15

    11. Check current and history alarm whether there

    are abnormal alarms.

    Browse current alarm, cant exist critical and abnormal alarm. Browse history alarm , cant exist critical and abnormal alarm during normal running time.

    For cant handle alarm, please save it and require help.