Smelter start up of new ISA furnace and progress to date
description
Transcript of Smelter start up of new ISA furnace and progress to date
![Page 1: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/1.jpg)
Mopani Copper Mines
![Page 2: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/2.jpg)
1937 2 x Reverbs, 4 x PS Converters
1956 3 x Reverbs, 5 PS Converters,
4 Anode Furnaces, 2 Casting Wheels 1972
36 MVA Electric Furnace, 1 x Reverb, 6 x PS Converters,4 x Anode Furnaces, 2 x Casting Wheels, 1 x Holding Furnace
1991-2006 36 MVA Electric Furnace, 4 PS Converters
4 Anode Furnaces, 2 Casting Wheels 2006-Present
Isasmelt Furnace, 12 MVA Slag cleaning furnace5 x PS Converters,
2 x 400 tonnes Anode furnace, 1 x twin casting wheel(commissioned in March 2009)
![Page 3: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/3.jpg)
Potential to treat > 420,000 tpa (ie toll)
New mines being developed in the region Improve environmental performance
From no SO2 capture to 50% Avoid ~6 m shutdown to rebuild old Electric Furnace
Old furnace at the end of its life. Old Electric Furnace failed during Isasmelt
commissioning Exporting concentrates difficult due to
transport constraints
![Page 4: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/4.jpg)
Isasmelt furnace 850,000 tpa
Matte Settling Electric Furnace (MSEF) 850,000 tpa (equivalent) capacity (SMS Demag)
Acid Plant (Isasmelt offgas only) 1150 tpd (MECS)
Oxygen Plant 650 tpd (Air Products)
Fastest Isasmelt project 28 months from license agreement to feed on.
![Page 5: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/5.jpg)
MCM Concentrators
Concentrate storage
Sulphuric Acid Plant(1150 tpd)
Isasmelt furnace(850,000 tpa)
Oxygen Plant(650 tpd)
Matte Settling Electric Furnace
PS Converters(upgrade from 4 to 5)
Fire Refining and Casting
(install 2 x 400 t AFs,80 tph casting wheel)
Concentrate
Purchasedconcentrate,
coal and fluxes
Cons,reverts,
flux,coal
OffgasCoke
Oxygen Matte
Reverts
Slag
Blister
Tail gas to Atmosphere
Anode Copperto
Refinery
Discard slagto
Dump
Diesel
Offgas to Atmosphere
Offgasto
Atmosphere
Matte,Slag
Equipment Legend
Smelter Upgrade -Phase 1
Smelter Upgrade -Phase 2
![Page 6: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/6.jpg)
ISASMELTCONCEPT
Concentrates (CuFeS2,Cu2S,CuCO3.(OH)X, FeS2,SiO2, and others . . .)
Flux (SiO2,CaCO3)
Coal (C,CH4)
Water (H2O)
Oxygen (O2)
Air (N2,O2)
Diesel / Fuel Oil
ISASMELT Furnace
ISASMELT Lance
Offgas
(CO2,SO2,H2O,N2)
CuFeS2 + O2 Cu-Fe-S + FeO + SO2
(FeS + 3Fe3O4 10FeO + SO2)
FeS2 + 5/2O2 FeO + 2SO2
2FeO + SiO2 2FeO.SiO2
Matte
Slag
Matte-Settling Electric Furnace
SlagCoating Smelting reactions
Matte + Slag
Slag box
Post-combustion air (N2, O2)
Granulation water
![Page 7: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/7.jpg)
Feed materials: Concentrates (Mopani and toll) Reverts (<25 mm) Silica flux (sand) Limestone flux (not normally used) Coal (5-20 mm) Isasmelt ESP dust WHB dust (mixed with reverts)
Feed materials stored in separate stockpiles
![Page 8: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/8.jpg)
Feed materials reclaimed by front end loader
Conveyed to storage bins: Concentrate (4 x 150 t) Flux (2 x 80 t) Reverts (1 x 180 t) Coal (1 x 50 t)
Don’t mix up feed materials!Hopper
CV121
Cons(x4)
CV134 (Shuttle)
Flux (x2)
Coal Reverts
Stockpiles
CV123 CV124
To Furnace
Front End Loader
![Page 9: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/9.jpg)
CV124 (to
bins)
Feed bin building
CV133 (to
furnace)
![Page 10: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/10.jpg)
Feed materials are accurately measured (±2%) and controlled by the PWCS.
Feed rate is controlled by variable speed drives.
Flexible system allows quick blend changes.
Reverts, Coal and Flux bins have 2 conveyors to measure accurately at low rates.
ConBN108
ConBN109
ConBN115
ConBN116
RevertsBN113
CoalBN112
FluxBN111
FluxBN110
CV125 CV126 CV135 CV136 CV140 CV139 CV138 CV137
CV130 CV129 CV128 CV127
CV131To furnace
ESPDust
![Page 11: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/11.jpg)
Cons feeders (x4)
Flux, Reverts and Coal feeders
![Page 12: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/12.jpg)
Combined feed on CV131 Paddle mixer installed, but normally bypassed Furnace feed conveyor (CV701)
Retractable and reversible to prevent heat damage (fires) Conveyor always runs unless retracted.
Otherwise the belt will catch on fire from furnace radiant heat
Coal reduction bin (furnace reductions) Reversible to bypass the furnace
For weigher calibrations For unsuitable feed materialsCV131
(mixed feed)Paddle mixer
CV132
CV133
CV701
Bypassbunker
Isasmelt furnace
Retractable &Reversible
Coal reductionbin
![Page 13: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/13.jpg)
Furnace refractory: 13.3 m tall 4.4 m internal diameter 450 mm Cr-Mg (in most areas) 100 mm insulation brick
Roof Boiler tubes (part of WHB) Openings:
Feed chute Lance Holding burner Offgas
Copper blocks Splash block Tapping blocks (inner and outer)
13.3 m
4.4 m
![Page 14: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/14.jpg)
Feed chute Lance port
Holding burner port
Splash block
WHB
![Page 15: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/15.jpg)
Feed chute Slag box (Lance port)
Holding burner port
![Page 16: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/16.jpg)
Feed chute Lance port
Holding burner port
Isasmelt furnace
![Page 17: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/17.jpg)
Lance 18.1 m long 350 mm body 300 mm tip Single swirler Internal air and tip pressure pipes Changed after ~ 7 days
Process Typical flow 5 Nm3/s (regardless of feed rate) 50 – 80% O2
Process air from dedicated blower Oxygen (95%+ O2) from oxygen plant (650 tpd)
![Page 18: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/18.jpg)
Tapping machine rails
Head section
Bend section
![Page 19: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/19.jpg)
Furnace offgas cooled using a Waste Heat Boiler (WHB) Furnace roof (inlet ~1,200 oC) Cooling screen and Transition piece Shaft 1 Shaft 2 (inlet ~600 oC) Gas cooler (inlet ~400 oC)Transition pieceCooling screen
Furnace roof
Shaft 1
Shaft 2
Gas cooler sprays
To ESP
![Page 20: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/20.jpg)
ESP 3 field ESP. 3 perpendicular (to gas flow) drag link conveyors. Dust is pneumatically conveyed to feed system, and is
directly recycled.
Induced Draft (ID) Fan Single ID Fan. Precise control of furnace draft
Variable speed drive. Inlet damper.
![Page 21: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/21.jpg)
General 12 MVA, 3 in line Electric Furnace 1092 mm Soderberg electrodes
Tapping 4 Matte tap holes (2 mud gun drills) 2 Slag tap holes (manual tapping) Large pit for granulated slag Reclaim slag with a grab crane
Feed materials 2 Return Slag Launders (PS Converter slag) 1 Isasmelt Launder 8 charge bins (coke and reverts)
Offgas Naturally ventilated Cooled by dilution air Discharged without treatment
![Page 22: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/22.jpg)
![Page 23: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/23.jpg)
Concentrates Mufulira (41%Cu, 12%Fe, 21%S, 12% SiO2) Nkana (32%Cu, 22%Fe, 29%S, 7% SiO2) Kansanshi (28%Cu, 27%Fe, 32%S, 5% SiO2) Blend (32%Cu, 22%Fe, 29%S, 7% SiO2)
(concentrate only)
Furnace feed 70-115 tph (Design 113 tph) 30-32%Cu in blended concentrate (excluding reverts) 7-9% Moisture (no water additions) 0-6 tph Silica 1-4.5 tph Coal (typically 2-3 tph) 0-25 tph Reverts Paddle mixer not used
![Page 24: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/24.jpg)
Lance 50-80% O2 5 Nm3/s Total lance flow (design 7 Nm3/s) Minimum lance air ~1.2 Nm3/s 35 lph diesel (average during smelting)
Products 1170-1190 oC 56-58% Cu in matte 0.8 SiO2:Fe 8% Fe3O4 in slag
MSEF Products Matte 58-60% Cu (1180 oC) Slag 0.7% Cu (1250 oC)
![Page 25: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/25.jpg)
![Page 26: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/26.jpg)
![Page 27: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/27.jpg)
Isasmelt Operating Time
0
10
20
30
40
50
60
70
80
90
100
No
v-06
De
c-06
Jan
-07
Fe
b-0
7
Ma
r-07
Ap
r-07
Ma
y-07
Jun
-07
Jul-0
7
Au
g-0
7
Se
p-0
7
Oct-0
7
No
v-07
De
c-07
Jan
-08
Fe
b-0
8
Ma
r-08
Ap
r-08
Ma
y-08
Jun
-08
Jul-0
8
Au
g-0
8
Se
p-0
8
Oct-0
8
% o
f to
tal
tim
e
Overall operating timeOperating time - without aisle and power constraints
Rebrick
Pow
er fa
ilure
, SA
P
Pu
mp
sIsa
smelt ro
of le
ak
Circ p
um
ps, g
rab
, ele
ctrod
es
O2
pla
nt co
mp
resso
r
No venting
![Page 28: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/28.jpg)
General 22 month campaign duration 105 mm minimum brick thickness (~3 m) Air cooling of shell during 2nd year (offtake side of furnace) Low wear above the splash block Unusually symmetrical wear
Wear control Brick monitoring thermocouples (important)
and thermal imaging (not very important, just looking for hotspots) High wear during the first 7 months (high temps, poor slag
chemistry) Wear rates controlled for remainder of campaign Good match between physical measurements and calculations Post combustion control very important for refractory above the
splash block Injecting air through the holding burner damages refractory, and
probably the splash block
![Page 29: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/29.jpg)
![Page 30: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/30.jpg)
![Page 31: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/31.jpg)
Design Single piece, cast in Monel tubes 4 cooling water passages (no air) Copper anchors on the bottom and front face of block 4 thermocouples (3 in block, 1 between block and refractory) Temperature (copper) control by manipulating cooling water flow
Performance 22 months without leaks or apparent damage (apart from anchors) Cooling water flow does vary (occasionally) to control copper
temperature (uncertain if it makes any difference to block’s life) Post combustion air injection via the holding burner heats the top
surface of the block (all slag melts leaving a bare block) 2nd Campaign Design
Anchors added to the top of the block
![Page 32: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/32.jpg)
![Page 33: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/33.jpg)
General Expected refractory life was 5-10 years After 2 years side walls required replacement (partial) Roof required replacement due to furnace explosions
Wear control Brick monitoring thermocouples were initially installed
(SMS Design) 3 separate brick monitoring locations spontaneously
leaked Remaining openings were closed with refractory and a steel
Additional thermocouples were not installed mid campaign due to cooling jacket design (steel cooling jacket behind working lining)
![Page 34: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/34.jpg)
![Page 35: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/35.jpg)
Charging Input launders directed towards dead corners
resulting in launder blockages Burners required to prevent launder blockages
Accretions No accretions on the side walls (no refractory
protection) Bottom accretions of up to 1 metre Accretions largest in non active areas of the
furnace Regular pig iron additions required to control
accretions
![Page 36: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/36.jpg)
Matte tapping Initial tapping arrangement (4 tapholes, 1 ladle at
a time) was a major production constraint, matte bogie installed to minimise tapping delays
Matte taphole inserts (Cr-Mg, installed in outer tapping block) require replacement every 4 days. Therefore only 3 working tapholes
Matte tapholes can not be closed manually 2nd mud gun installed to prevent run aways Taphole design being improved
(eliminating outer tapping block inserts) Tapholes require deep repair every 1-2 months
(requires a 24 hour shutdown)
![Page 37: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/37.jpg)
Refractory Disappointing performance
Low grade brick used by SMS Demag (400 mm RHI ESD) Unable to monitor brick wear, operating parameters not
optimised Technical focus on other areas (due to many other
problems) 2nd Campaign
Isasmelt style brick monitoring implemented for 2nd campaign
Improved process control Higher grade bricks (RHI FG) Consider jacket design change if wear rate can’t be
controlled Target refractory life is >= 2 Isasmelt campaigns
![Page 38: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/38.jpg)
< February 07 ESP exit temp intermittently > inlet temperature
(believed to be instrumentation problems) ESP inspections (external) did not identify problem Shutdown February 2007 to inspect and repair ESP
(ESP could not maintain KVs) ESP internals found to be beyond repair Acid plant not commissioned at this stage
ESP Rebuild September – November 07 (US$1.4M) ESP bypassed for rebuild Additional dust load to gas cleaning plant required daily shutdowns to
remove dust from scrubbers Post Rebuild
No further damage ESP’s performance improved, but still struggles to hold KVs at times
![Page 39: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/39.jpg)
![Page 40: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/40.jpg)
Symptoms ESP Exit temperature increases Sulphur formation in gas cleaning plant
Factors Coal rate (high rates increase problems) Post combustion air Excessive dust in ESP (high dust levels in hoppers cause problems)
Consequences Potential damage to ESP (none since Nov 2007) Damage to gas cleaning pumps (very sensitive to S)
![Page 41: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/41.jpg)
Detection SAP Gas Cooling Tower pump discharge pressure increases
(indicates weak acid coolers are blocking) ESP exit temperature increases Glass rod test (least reliable)
Prevention Implemented post combustion air flow smelting interlock Implemented ESP dT interlock (Outlet temp – Inlet temp) Installing CO, O2, NO monitor at WHB exit (in progress) Post combustion fan operates at maximum rate, so additional post
combustion air is provide by increasing furnace draft(not very efficient)
![Page 42: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/42.jpg)
![Page 43: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/43.jpg)
Problem Large water leak in the WHB’s 2nd shaft
Cause Gas cooler spray malfunctioned Water impingement on tubes causing thinning
Damage and repairs 6 tubes replaced Repair time 5 days (poor welding technique)
Actions Implemented logic to detect failure (using existing instruments) Modified spray design (sprays heads were dissolving) Regular thickness testing of tubes around sprays
![Page 44: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/44.jpg)
![Page 45: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/45.jpg)
Problem Furnace roof leak (bottom of roof)
Cause Consultant’s report indicated localised overheating,
however cause is unknown Damage and repairs
1 tube replaced Lost time - 6.5 days (including reheating furnace)
![Page 46: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/46.jpg)
![Page 47: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/47.jpg)
Problem Furnace roof leak (top of roof)
Cause Holding burner hoist rope failed, dropping holding burner Web ripped off tube causing small leak Leak noticed about 10 hours after hoist failure
Damage and repair Tube welded Web not reattached
(concerned about differential expansion causing leaks) Furnace partially cooled Lost time ~19 hours (including furnace recovery)
Actions Holding burner carriage stopper relocated (was too low) Minor repairs to roof during rebrick (tubes were not straightened) Hoist replaced (original rope was under designed)
![Page 48: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/48.jpg)
![Page 49: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/49.jpg)
Problem WHB design exit temperature 700 oC Actual exit temperature 400-500 oC
(under typical operating conditions) Design condensing capacity 35 tph Required condensing capacity ~50 tph
(for design conditions) Demin capacity 5 tph It is not possible to operate under design conditions Availability would be limited to ~33%
Cause (probable) Fouling on the hot side of the boiler tubes much less
than design, resulting in higher than design heat transfer
Very clean (Pb, Zn, As) concentrates
![Page 50: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/50.jpg)
Air Cooled Condenser
Steam Drum
Blow off valve
SteamCondensate
Heat surfaces
Blow off toatmosphere
Makeup water
![Page 51: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/51.jpg)
Mitigation Increased demin storage from 10 to 70 m3
Decrease lance flow from 7 to 5 Nm3/s Concentrate blend requires less coal than
design (very lucky) Additional 10 MW condenser was installed.
![Page 52: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/52.jpg)
HFO Conversion Currently using diesel for the holding burner, lance and launder
burners Commissioning of HFO on the holding burner is in progress.
Aisle debottlenecking 3 x 55 tonne Main Aisle Cranes Mechanical punching machines are being commissioned.
![Page 53: Smelter start up of new ISA furnace and progress to date](https://reader033.fdocuments.net/reader033/viewer/2022051402/568158b1550346895dc5ff55/html5/thumbnails/53.jpg)