Alluminium Smelter-5 Model

download Alluminium Smelter-5 Model

of 21

Transcript of Alluminium Smelter-5 Model

  • 8/8/2019 Alluminium Smelter-5 Model

    1/21

    Green land Alum in ium

    CRU STRATEGIES conf ident ia l

    Chapt er 5Ow nersh ip m odels

    SummaryIn this section we consider four potential ownership models that we believe are available to the

    Greenland government. A brief introduction into the mechanics of each option is followed by a

    comparison between them based on the risk factors involved and their potential implications for

    the success of the project. This comparison will form the basis for our recommendation.

    It is worth noting that although some benchmark examples are outlined in the introduction,

    the nature of the Greenland project is such that only tentative links may be drawn between these

    examples and the problem at hand, and therefore our final recommendation is based on risk

    management considerations alone. The remote location of the power source makes it impossible

    to consider the energy supply outside the context of the smelter. Equally, the proposed smelter

    has been purposely located in Greenland for cheap power that it cannot source elsewhere. There

    is therefore an even stronger mutual dependence than usual between the smelter and its

    dedicated power source. Added to this are the logistical peculiarities of building a three-plant

    network and preparing an adequate flat location for the positioning of the smelter in a harsh

    environment.

  • 8/8/2019 Alluminium Smelter-5 Model

    2/21

    1-2 Greenland Alum inium ch a p te r 5

    CRU STRAT EGIES conf ident ia l

    Inextricably linked, or stranded individual assets

    there is no alternativecustomer for the powergenerated by the plants

    Greenland was chosen as

    smelter location preciselyfor cheap energy

  • 8/8/2019 Alluminium Smelter-5 Model

    3/21

    Green land Alum in ium chap te r 5 1-3

    CRU STRATEGIES conf ident ia l

    1. The ow nership optionsThe following four options were identified on the basis of our perception of the Greenland

    Governments aims, expectations and potential budget. The merits of each alternative will be

    discussed from a risk management perspective in the next section.

    1.1.Water r ight s Selling the water rights for the area to Alcoa would effectively mean no active involvement

    in the project on behalf of the GHR. Alcoa would remain responsible for building the

    infrastructure it requires, both for the smelter and for the power plants.

    The GHR would incur no significant costs under this alternative. GHR can nevertheless generate both income and a market-related profit, through a

    combination of the following:

    A. A one-offup-front nominal fee: this would give Alcoa the right to operate within thestipulations of the contract;

    B. A moderate fixed price per MWh, which would guarantee a meaningful income;C. An escalation fee proportional to the price of aluminium once it exceeds a defined

    threshold, with a built-in accelerator if the individual projects return exceeds a defined

    amount; to compensate for this premium, the GHR can offer long term ownership of the

    energy resource;

    D. A minor interest in the project in the form of shares.

    Ownership options for GHR

    GHR SmelterParticipation

    GHR

    Hydropowerparticipation

    WATERRIGHTS

    SOLE

    POWERSUPPLIER

    JV POWER

    SUPPLIER

    JV PARTNERIN

    INTEGRATEDPROJECT

    No active participation in project

    X % participation in hydropower

    100 % control of hydropower

    Y % participation in smelter,Y % participation in hydropower

    WATER RIGHTS

    JV POWER SUPPLIER

    SOLE POWER

    SUPPLIER

    JV PARTNER IN

    INTEGRATED PROJECT

  • 8/8/2019 Alluminium Smelter-5 Model

    4/21

    1-4 Greenland Alum inium ch a p te r 5

    CRU STRAT EGIES conf ident ia l

    Probably the best example of such a scheme being used are Alcans smelters in Canada, such

    as Grande Baie, Beauharnois and Laterriere. All three are powered by self-generated

    hydroelectric power from rivers in Quebec, where Alcan holds the water rights in perpetuity

    (with the exception of Peribonka river, where the contract runs out in 2058). Alcan pay an

    annual charge to the Quebec provincial government based on total energy generation in the

    province, escalating at the same rate as the Consumer Price Index in Canada. The rights for

    these rivers were contracted before 1970, hence the advantageous terms for Alcan. Already in

    1984, when the contract for Peribonka river was negotiated, Alcan was tied to an annual

    payment based on sales realisations of aluminium ingot, ensuring that the Quebec provincial

    government participate in any upside generated by strong aluminium prices. The reason this

    example is relevant is that at the time the initial contracts were signed, Quebec was more or less

    in the same position as Greenland is now: the Canadian government in the 1940s wanted

    economic activity in the sparse North-West, while Alcan wanted a location for smelters that had

    both ocean access and, crucially, cheap energy. Nevertheless, the competitive nature of todays

    global market, as well as the strong demand for aluminium should enable the GHR to push for a

    more favourable agreement.

    The North Atlantic:

    cheap energy, small economic density

    Alcan 1943-68

    Quebec rivers

    water rights inperpetuity

    annual tax per

    energy produced

    escalator based

    on CPI

    1984, Peribonka

    water rights till2058

    annual tax persales of Al ingot

    Alcoa, 2008

    Greenland

    ? long-term waterrights (2038)

    ? up-front payment

    ? annual tax perenergy produced

    ? escalator basedon Al price

    ? potentialaccelerator once

    the projects

    returns exceed athreshold

    ? shares in project

  • 8/8/2019 Alluminium Smelter-5 Model

    5/21

    Green land Alum in ium chap te r 5 1-5

    CRU STRATEGIES conf ident ia l

    1.2.Jo in t Venture par tner in pow er supp ly Depending on the available financing, the GHR could opt to become a minority or majority

    partner in a Joint Venture with Alcoa that only covers the energy side of the project.

    The GHR would have to contribute to the cost of construction, but would incur smalloperating costs. Therefore the Greenland government would need initial access to cheap

    capital, for instance infrastructure subsidies from the Danish government.

    Alcoas smelter would not run on self-generated energy, but would in effect purchase theenergy from the Joint Venture company. Two basic types of tariff arrangement exist at

    present:

    A. Power price-relatedUnder this arrangement, the smelter would purchase power from the Joint Venture based on

    a fixed base price to which an escalator is applied. The aim of the GHR would be to secure a

    profit proportional to the global increase in energy prices, which can be achieved in twoways that are not necessarily mutually exclusive. Firstly, the escalator would have to be an

    index reflecting price changes (similar to the Alcan example, where it was the Consumer

    Price Index).

    Secondly, the Greenland government, as owners of the power source, can attempt to

    lock the position of the power provided to the Alcoa smelter on the global smelting power

    price curve. With hydropower operating costs remaining low regardless of the global energy

    context, such a measure introduced in the contract with Alcoa would guarantee that

    whenever energy prices increase, the profit margin increases proportionally. Furthermore,

    this is an attractive option for the smelter, as it guarantees that it remains competitive in

    terms of power costs.

    Locking in the profit: establishing a fixed position on

    the tariff curve

    tariff

    production

    2007 prices

    2012 prices

    2017 prices

    2007 position onthe curve is fixed

    minimum tariff

    threshold

  • 8/8/2019 Alluminium Smelter-5 Model

    6/21

    1-6 Greenland Alum inium chap te r 5

    CRU STRATEGIES conf ident ia l

    B. Metal-relatedThis arrangement basically ties the power tariff to the price of Aluminium, so that the owner

    of the power plant, in this case the Joint Venture, can take advantage of the profitable

    commodities market. The formula for the calculation of the tariff can be proportional to the

    aluminium price as traded on a major exchange such as the LME, or it can include

    thresholds, where the proportion between power tariff and the price of aluminium is

    variable according to certain aluminium price brackets stipulated in the contract. The

    percentage of the aluminium price that will determine the power tariff can also be

    renegotiated periodically. Below is an example:

    1.3. Sole suppl ier o f e lect r ic i ty

    This is the most expensive option available to the GHR, involving the building and fullcontrol of the hydropower plants. For this option to be feasible, a very sizeable capital fundwould have to be available to the GHR at relatively low interest.

    The building of the power plants would have to begin between 15-30 months prior to thestart-up of construction for the smelter, as construction time is longer.

    The Greenland government would set up a company independent of the smelter project tocommission the building of the dams and power plants.

    The Alcoa smelter would then purchase the electricity from the GHR. The same types oftariff as above would apply.

    This type of fully split ownership between the power source and the smelter is very common

    throughout the world. The difference is that most often the smelter is the priority customer for

    Venalum

    State-owned Edelca increases the power tariff,but there are no thresholds

    0%

    5%

    10%

    15%

    20%

    1997 2001 2006

    Power tariff

    proportional to

    LME aluminium

    price

    Example

    If LME price = $1500/t

    Power consumption = 14.8 MWh/t

    Tariff = 16% = $16.2/MWh

  • 8/8/2019 Alluminium Smelter-5 Model

    7/21

    Green land Alum in ium chap te r 5 1-7

    CRU STRATEGIES conf ident ia l

    the power, but not the only available customer. The implications of this distinction will be

    examined further in the next section.

    Smelters that secured long-term energy contracts before 1980 generally still benefit from

    simple, inflation-escalated contracts. By contrast, contracts concluded after 1990 are almost all

    short- or medium term, metal-linked, and contain some provisions regarding escalation based on

    the increase in the global or regional price of energy. These are more advantageous for the

    hydropower owner and allow for more flexibility and renegotiation.

    1.4. Jo in t Venture par tner in an in tegra ted projec t The GHR would commit to part of the investment in an integrated project that includes both

    the hydropower stations and the smelter.

    The share of participation would depend on the availability of viable capital. Alcoa would no longer purchase the energy, which would in effect be self-generated. The Greenland government would gain profits only from the difference between the price of

    aluminium and that of alumina.

    Given the strong interdependence between hydropower and smelter, this option appearslogical.

    Joint Venture enterprises in primary aluminium production are a fairly recent trend, most

    apparent in the projects set up in the Middle East and Asia. The giant EMAL smelter due to be

    built in Abu Dhabi for a capacity of 1.4 mtpy will source power from a dedicated 2000 MW gas

    power plant. The project is a 50-50 Joint Venture between Dubal and Mubadala and will

    become the biggest single smelter in the world. A similar deal was struck between Qatar

    Petroleum and Hydro for the building of Qatalum smelter and its dedicated 1350 MW gas-fired

    Comparable smelters, vividly different deals

    Mosjen, Norway (189,000 tpy), 100% hydropower

    Power purchased mostly on the basis of 1950s and 1960s contracts.

    Fixed long-term contracts.

    Only escalation mechanism is local inflation.

    Good deal for the smelter, BUT the contracts run out in 2007

    THE FUTURE ?

    Sundsval, Sweden (103,000 tpy), 100% hydropower

    Power purchased on medium-term contracts (4-5 years).

    Terms related to the aluminium price.

    Escalation is based on prevailing forward power market prices,with a defined floor and a ceiling: HIGHER TARIFFS

  • 8/8/2019 Alluminium Smelter-5 Model

    8/21

    1-8 Greenland Alum inium ch a p te r 5

    CRU STRAT EGIES conf ident ia l

    power plant. The Russian state has stated it is prepared to finance a third of the Boguchansky

    smelter project, including a dedicated hydropower plant expected to cost $1.3 bn on its own.

    Of the existing smelters, the most relevant is Asahan smelter in Indonesia, owned jointly by

    the Indonesian state (41%) and Nippon Asahan Consortium (59%). The smelter is powered by a

    dedicated hydroelectric plant on Lake Toba in Sumatra.

    Major Joint Venture integrated smelters and projects

    EMAL

    (1.4 mtpy)

    Dubal &

    Mubadala

    2000 MW (gas)

    QATALUM

    (585,000 tpy)

    Qatar

    Petroleum &Hydro

    1350 MW (gas)

    BOGUCHANSKY (600,000 tpy)

    RusAl & Unified Energy Services

    1500 MW (hydro)

    ASAHAN

    (255,000 tpy)

    State & NipponAsahan

    Consortium

    447 MW (hydro)

  • 8/8/2019 Alluminium Smelter-5 Model

    9/21

    Green land Alum in ium ch a p te r 5 1-9

    CRU STRATEGIES conf ident ia l

    2. Econom ic Risk fac torsThe success of the Greenland smelter project from the perspective of the GHR depends on the

    successful management of two key risk factors. The first is the potential cost of building the

    hydropower network relative to the likely profits that ownership of all or part of that network

    would bring. This is a risk that would primarily result in a heavy loss of invested capital,

    although it does have some implications for profit opportunities. The second fundamental risk

    relates to the parallel evolution of alumina and primary aluminium prices, which determines the

    economic success of the smelter. This risk is more closely linked to profit lost or realised,although an abrupt change in the proportion between the two price structures could lead to real

    loss of investment.

    This section analyses each of the options outlined previously from the point of view of these

    two main risk factors. For each option, the risks are identified and quantified according to

    probability and likely impact, and potential management solutions are outlined.

    Risk factors: possible scenarios

    Power network building costs

    Smelter project abandoned orsize reduced: stranded asset

    Costs escalate beyond viabilitylimits during construction phase

    Spread between alumina andaluminium prices

    Alumina price increases at ahigher rate than aluminium price;if alumina supply is constrained,more value will be retained by the

    alumina producers

    LOSS of PROFIT

    LOSS of INVESTMENT

  • 8/8/2019 Alluminium Smelter-5 Model

    10/21

    1-10 Greenland Alum inium chap te r 5

    CRU STRATEGIES conf ident ia l

    2.1. Water r ight sSince this option involves no upfront direct investment on behalf of the GHR, the risks only

    relate to the loss of potential profit. The financial burden of constructing and running the

    smelter and hydropower station would belong exclusively to Alcoa.

    The limited risks associated with this option depend upon the system of payment. Ideally, the

    water rights agreement would incorporate elements of all four types of tariff presented above: an

    upfront payment, a yearly fixed charge, an adequate escalator that varies according to the

    change in the price of aluminium, and a very small equity participation in the project. The best

    ways to ensure that the GHR maximises its returns from the project are shown below.

    RISK: Returns to GHR not maximised

    Probability: Dependent on negotiations. However, we feel that the GHR would

    be in a good position to negotiate a profitable tariff. Impact: Small. Some opportunities for profit may be lost in the negotiation, butthe GHR still stands to make substantial gains.

    A fixed charge of $3/MWh for a usage of 600 MW would yield over$15,000,000 per year!

    Small up-front fee: FIXED, one payment

    Small equity participation: FIXED, shares

    Charge per MWh: FIXED (annual tax) or VARIABLE(% of Al price with or without thresholds)

    Accelerator based on project return: VARIABLE

    NEGOTIATION TERMS: the tariff

  • 8/8/2019 Alluminium Smelter-5 Model

    11/21

    Green land Alum in ium chap te r 5 1-11

    CRU STRATEGIES conf ident ia l

    2.2. Jo in t Venture par tner in pow er supp lyAs mentioned above, this is a suitable option as long as the GHR has access to low-interest

    capital, such as infrastructure subsidies or other forms of credit from the Danish government.

    This would relieve some of the financing pressure off Alcoa. In return, Alcoa would have to

    purchase the energy from the Joint Venture company, at a higher tariff than if they were paying

    for water rights alone. An initial investment would therefore be compensated by higher later

    returns.

    Power purchase tariffs would necessarily be higherthan water rights tax

    OPTION 1.1. WATER RIGHTS

    GHR investment = 0

    GHR revenue = water tariff

    OPTION 1.2. JV partner

    GHR investment = % CAPEX + % OPEX

    GHR revenue = investment + profit margin

    GHR PROFIT = WATER TARIFF

    GHR PROFIT =

    PROFIT MARGIN

    POWER TARIFF > WATER TARIFF + INVESTMENT PAYBACK

    Solutions for maximising the GHRs returns

    Give them part of what they want: grant Alcoa long-term rights to the water (atleast 30 years)

    Only charge what they can afford to pay: the escalator would only apply whenthe price of aluminium exceeds a threshold or when the project makes substantialreturns

    Ask for shares in the project: this is less of a direct cost to Alcoa and means

    some profit in the early phases of the project.

    Prepare for negotiations Good understanding of capital andoperating cost structure of the futurepower network

    Good knowledge of Alcoasalternative options

    PLANTCAPEX

    +OPEX

    ALT.OPTIONTARIFF

    GHR marginfor negotiation

  • 8/8/2019 Alluminium Smelter-5 Model

    12/21

    1-12 Greenland Alum inium ch a p te r 5

    CRU STRAT EGIES conf ident ia l

    Whether the GHR holds a majority or minority stake in the Joint Venture company is

    immaterial: Alcoa would have to purchase the energy regardless, and the hydropower network

    owners, whoever they be, have no other option but to sell it to the smelter. The only real

    variable is in the degree of exposure to risks, not in the nature of those risks.

    The higher the participation of the GHR in the hydropower plant project, the greater the

    exposure to this risk will become. There is no readily available solution, beyond leaving plenty

    of contingency capital for the possibility that costs will escalate. This does not solve the

    problem of losses suffered if capex grows to the extent that power costs are higher than the

    tariff.

    Furthermore, under this option, Alcoa has considerable degree of flexibility in how it can

    react to an increase in construction costs. Given the lag time between the start of construction

    for the power network and the start of construction for the smelter, Alcoa has up to two and a

    half years to reconsider its position regarding the smelter and the size of its own investment in

    the power plant network.

    We do not believe this risk to be acceptable from the GHRs perspective. The only way to

    manage it would be to negotiate a tariff that leaves room for potential cost increases by

    increasing the profit margin. This is unlikely to be acceptable to Alcoa, as it would negate the

    smelters competitive advantage on the cost curve.

    RISK 1: Costs balloon during construction phase

    Probability: Medium.

    3 plants connected to smelter inunforgiving environment high quality

    reinforced transmission lines required.

    Tight construction market and global

    financial uncertainty could run up the cost

    considerably.

    Impact: High.

    If cost exceeds available budget, then

    smelter project may need to be scaleddown or even abandoned strandedasset would have to be sold elsewhereat much reduced price.

    Rising CAPEX can force losses ifpower cost becomes higher than thetariff agreed upon in the off-takecontract.

    EXPECTED

    CAPEX

    PAYBACK

    OPEX

    PAYBACK

    MARGIN

    OPEX

    PAYBACK

    CONTRACTED

    TARIFF

    ACTUAL

    CAPEXPAYBACK

    ACTUAL

    COST

    LOSS

  • 8/8/2019 Alluminium Smelter-5 Model

    13/21

    Green land Alum in ium chap te r 5 1-13

    CRU STRATEGIES conf ident ia l

    This second risk is more easily manageable. While metal-related tariffs have recently

    become the norm, it is still possible to ensure against price drops in aluminium. Over the short

    and medium term this can be done through hedging, but a better long-term solution is locking

    the tariffs position on the price curve as shown above, or providing for safe thresholds below

    which the tariff remains constant. The former solution is more creative and provides more room

    for profit made on the back of energy price surges, while at the same time reassuring Alcoa asthe consumer of energy that it faces no risk of tariffs rising abruptly with energy market

    fluctuations. The latter solution is simpler and more frequently used in contracts worldwide. Its

    appeal lies in the certainty of a fixed range of possible results, which is comforting both to the

    supplier and the consumer of energy.

    2.3. Sole suppl ier o f e lect r ic i t yAs mentioned above, the degree of commitment on behalf of the GHR does not change the

    nature of the risks, only the level of risk. This option carries with it the same risks as above, but

    the potential impact is much more devastating, particularly in the case of the risk 1.

    If the hydropower network construction costs rise above initial estimates, the GHR is now

    alone facing the consequences. Should the project be abandoned, the GHR is faced with

    gigantic losses and a stranded asset with much less potential for revenue. This is of course the

    worst of all potential outcomes, and its likelihood is low. Nevertheless, a substantial increase in

    capex would lead to a shrinking of the profit margin on the contracted tariff, to the point where

    the GHRs initial investment is no longer justified.

    Given that the construction of the power network is likely to cost in excess of $1 billion,

    which would have to be sourced entirely by the GHR, the risk degree is entirely unacceptable.Even if this amount were available at low interest, the particular mutual dependence between

    the smelter and power network and the lag time between their respective construction times

    RISK 2: Smelter profits hit by high alumina price andlow primary aluminium demand

    Probability: Medium to low.

    Strong demand growth forecast for primary aluminium and no imminentshortage of alumina.

    Impact: Low.

    Plant is likely to remain competitive in terms of power costs, although theGHR would lose profit from the metal-related segment of the tariff.

    Solutions:

    Long-term off-take contract that specifies the minimum energy to bebought by Alcoa from the power network: buy-or-pay agreement

    Flexibly constructed tariff system: lock in the hydropower networksposition on the tariff curve as shown previously or fix thresholds in theformulae for calculating tariff on the basis of aluminium price

  • 8/8/2019 Alluminium Smelter-5 Model

    14/21

    1-14 Greenland Alum inium chap te r 5

    CRU STRATEGIES conf ident ia l

    makes separate ownership a risky proposition. Aluminium market fluctuations can be managed

    for. However, this risk is about loss of sizeable hard capital, and under exclusive ownership,

    there are no measures that can mitigate it. We therefore propose that this option be excluded

    from further consideration.

    2.4 Jo in t Venture par tner in an in tegra ted projec tAn integrated project would mean that the smelters power is self-generated. For the GHR, this

    means that since power is no longer purchased, all revenue will be made on the back of the

    strength of the aluminium market. From the projects point of view, this would reduce the

    power costs to operating costs, with no tariffs to pay to the state. This arrangement essentially

    means that the GHR and Alcoa share the exposure to the same two fundamental risks presented

    above.

    The risk of capex rising above expectations has the same probability as before, but a slightly

    different impact on the GHR. The main problem in this case is not the imbalance between

    construction costs and tariffs, but the change in the smelters position on the cost curve. This

    shift upwards will most probably mean loss of potential profit. Given that no tariffs are paid and

    operating costs are so low, it is unlikely that the total power costs could push the smelters costs

    above the equilibrium price and lead to loss of investment.

    RISK 1: Costs balloon during construction phase

    ALCOA

    GHR

    ALCOA

    GHRESTIMATED

    CAPEX

    ACTUALCAPEX

    COST

    QUANTITY

    expected positionactual position

    Impact: Medium

    Fall of profits for GHR, if the smelter is still competitive relative to demand.

    Loss of investment, if production costs exceed equilibrium price unlikely,given the low OPEX

    DEMAND

    equilibrium price

  • 8/8/2019 Alluminium Smelter-5 Model

    15/21

    Green land Alum in ium ch a p te r 5 1-15

    CRU STRATEGIES conf ident ia l

    As with separate ownership, this is a more easily manageable risk, for slightly different

    reasons. The lack of a power tariff gives the smelter project a slight advantage in terms of its

    position on the cost curve, meaning that the project is more likely to be able to afford temporary

    drops in primary aluminium demand.

    Participation in a Joint Venture integrated smelter project would therefore expose the GHR

    to some degree of risk, but the potential impact of these risks is lower and they are easier to

    mitigate. As long as there is readily available capital at low interest at the GHRs disposal, this

    option is worth further consideration.

    2.5 ConclusionsOf the two risks that we have considered the available options against, the construction-related

    one appears to be decisive. The potential impact of the risk and the level of uncertainty that is

    inevitably associated with a construction project of such complex nature in a punishing

    environment leaves very little room for reliable, watertight solutions. We believe that the levelof risk is unacceptable, and therefore that any option involving split ownership of the

    hydropower network and the smelter should be discarded from consideration.

    Probability: Medium to low.

    Strong demand growth for primary aluminium and no imminent shortage ofalumina

    Project has a more advantageous position on the cost curve due to no powertariffs.

    Impact: Medium to low.

    Loss of profit more manageable, better position on the cost curve meansproject can afford lower premiums.

    Solution:

    Hedging for up to 5 years

    RISK 2: Smelter profits hit by high alumina price andlow primary aluminium demand

  • 8/8/2019 Alluminium Smelter-5 Model

    16/21

    1-16 Greenland Alum inium ch a p te r 5

    CRU STRAT EGIES conf ident ia l

    The option of participating in an integrated Joint Venture can be explored further, as the

    risks in this case target the profit levels of the project rather than the investment itself. While the

    GHR and Alcoa alike are exposed to the risk, the issue is likely to be how successful the project

    is, not whether it will make any profit. This option also makes sense from the point of view of

    the mutual dependence between the aluminium mill and the power source.

    An investment of DKK 2.5 billion would secure a participation of up to 15-20% in an

    integrated Joint Venture. If the GHR is confident that such a sizeable amount of capital can be

    secured easily, it would be necessary to examine in detail the returns that participation in an

    integrated Joint Venture would most likely yield, and compare them with the gains to be made

    from selling the water rights.

    At this point, given the respective risks associated with the two options, we believe that the

    latter is the ownership solution that best suits the GHR. in view of the risk of spiralling capital

    expenditure for the building of the power plant network. Water rights for the three rivers should

    be sold to Alcoa for a minimum of 30 years, subject to the payment of an up-front fee, and then

    an annual tax which is varied in accordance with inflation, the performance of the aluminium

    market in general. Such an arrangement would not require any sizeable investment and would

    provide a reliable annual income, which would enable the GHR to benefit from the projects

    overall success freely, at no substantial risk. As long as the tariff is negotiated well, the GHR

    will stand to gain substantial yearly revenue at virtually no cost.

    The options and degrees of risk

    PROBABILITY

    IMPACT

    WATERRIGHTS

    JV POWER SUPPLIER

    SOLE POWERSUPPLIER

    JV PARTNER ININTEGRATED

    PROJECT

  • 8/8/2019 Alluminium Smelter-5 Model

    17/21

    Green land Alum in ium ch a p te r 5 1-17

    CRU STRATEGIES conf ident ia l

    The options compared: water rights vs. Joint Venture

    Returns

    Market risk

    Construction

    risk

    Investment

    ??

    LOWVERY LOW

    MEDIUMNONE

  • 8/8/2019 Alluminium Smelter-5 Model

    18/21

    1-18 Greenland Alum inium ch a p te r 5

    CRU STRAT EGIES conf ident ia l

    3. Soc ial and Polit ica l Considerat ions

    Having discarded the options based on separate ownership, we will now examine the non-

    economic factors we believe the GHR needs to be aware of in determining whether to opt for

    the concession of water rights or for junior participation in a Joint Venture integrated project.

    One important note is that the social and political risks for any smelting project are only as

    significant as the social and political problems in the area where the project will be located. For

    instance, in a country or region of consensus government, where both the incumbent

    government and the opposition are in agreement over industrial development and energy policy,

    a smelting project can expect to meet with much fewer problems in the preliminary negotiation

    phases than in areas where there are considerable differences of perspective. As an example

    below shows, Alcoa has first-hand experience of the effect of political factors on the success of

    its projects. Similarly, if a region has a serious unemployment problem, the aluminium company

    can expect to be tied into more cumbersome negotiations regarding employment development

    and knock-on effects on secondary and auxiliary industries that the state or region in question

    expects the project to achieve.

    In these respects, a project in Greenland is far less complicated both in political and in social

    terms for Alcoa than an alternative in either more congested areas of the developed world (like

    the US or Norway) or in socially struggling environments in the developing world (Trinidad,

    Jamaica or Brazil, all potential Alcoa targets). For any aluminium company, it is important that

    negotiations can proceed smoothly and as quickly as possible. Any deal will be made or broken

    by the energy cost, but bureaucratic efficiency and the extent of likely social and economic

    obligations that the smelter project will likely be burdened with are considerations that can

    make one option safer and more attractive to the aluminium company than others.

    GREENLAND

    Population density:

    negligible

    GDP per capita:

    $20,000/capita

    Unemployment: 8.6%= 5,000 unemployed

    Nearby smelterpower tariff: $21/MWh

    (Nordural, Iceland)

    JAMAICA

    Population density:

    250/sq. km

    GDP per capita:

    $4,000/capita

    Unemployment: 11%

    = 275,000 unemployed

    Nearby smelterpower tariff: $25/MWh

    (Venalum, Venezuela)

    Different challenges, different deals, one goal for

    ALCOA: Low energy costs

  • 8/8/2019 Alluminium Smelter-5 Model

    19/21

    Green land Alum in ium ch a p te r 5 1-19

    CRU STRATEGIES conf ident ia l

    An example of this is Alcoas negotiations with the Icelandic government in the run-up to

    the opening of Fjardaal smelter in June 2007. Negotiations for the smelter began in 2003, with

    the Icelandic government committed to securing a deal that created over 1,000 jobs for the

    economically depressed Eastern coast. Environmental concerns were raised as the smelter

    location overlapped with plans for a national park, but overall Alcoa was satisfied that the

    government was open, forthcoming and committed to a swift resolution. There is no reason whythe same could not apply in Alcoas negotiations with the GHR.

    A lesson learnt : Baie Com eau

    In terms of deciding between ownership options, Alcoas planned modernisation and expansion

    at Baie Comeau, Quebec offers a few useful insights into the political and social risks associated

    with the negotiation process, as well as a useful comparison tool between these and Alcoas cost

    considerations. The smelter is one of the largest in the Western Hemisphere, but its technology

    is outdated and likely to be rendered obsolete within 10 years.

    In 2002, Alcoa and the Quebec government, then ruled by the Parti Quebecois, signed a

    Memorandum of Understanding for modernisation and expansion by 2010. Alcoa committed to

    replacing its Soderberg technology with pre-bake utilities through investments worth C$ 1

    billion. In return, the government agreed to renew the water rights for the McCormick dam for

    25 years beginning in 2011 and to sell Alcoa 175 MW of the remaining necessary energy at

    industrial rate. However, the Liberal government that replaced the Parti Quebecois in power in

    2003 reneged on the non-binding terms of the MOU and called for a renegotiation of those

    terms.

    The new terms proposed by the government included the creation of 500 jobs in secondary

    manufacturing in addition to the 1500 already pledged in the aluminium processing industry by

    Alcoa. However, the most significant issue was over energy tariffs. The Quebecois government

    (HQ) argued that the region was facing shortages before Hydro-Quebecs capacity expansion

    was finalized, and that therefore the initial industrial rate was not satisfactory. Instead, it offered

    to provide low-cost electricity for 50 years, with annual rate hikes no higher than inflation. The

    deal tied the tariff to the energy price, which Alcoa stated as an unacceptable risk. Negotiations

    fell apart and the project was called off in 2006, as Alcoa stated that it cannot commit over C$ 1

    billion for a project where there is the risk that energy costs would escalate over the life of the

    project.

    The contrast between the Baie Comeau and the Fjardaal developments is evident and a small

    part of the reason Alcoa chose Greenland as a site for future development could be an

    association with the image of the latter. However, what is also apparent is that the social,

    environmental and political factors exist, but are superseded by cost considerations. In the case

    of Fjardaal, Alcoa committed to the creation of jobs and infrastructure for the local

    communities, as well as providing substantial environmental assurances, in exchange for a

    quick negotiation process and cheap energy provisions.

    In terms of lessons to learn, one important implication of the Baie Comeau developments isthat Alcoa is adverse to energy-tied accelerators. It is much more likely to adhere to a cost

    structure similar to the one presented above, which varies according to aluminium market

  • 8/8/2019 Alluminium Smelter-5 Model

    20/21

    1-20 Greenland Alum inium chap te r 5

    CRU STRATEGIES conf ident ia l

    factors and to the success of the project, or one where the tariff for the water rights is locked on

    the global power cost curve. It should be much easier for Alcoa to feel that their investment is

    safe in Greenland, as unlike Baie Comeau, where 66% of power was purchased, Alcoa would

    generate all of their own power.

    Another consequence of the failures in Quebec and, later on, in Brazil could be a preference

    on behalf of Alcoa for the Joint Venture model. Political factors play a part here, as by joining

    the project, a government effectively shows its commitment to the project and makes it

    substantially more difficult for a different future government to back out of the venture, once

    the initial investment has been made. These considerations were part of the reason for the

    Asahan Joint Venture in Indonesia, where politics is considerably more volatile.

    2. Financing optionsIf the GHR decides to participate in a Joint Venture integrated project, it will do so as a junior

    partner to Alcoa. If the Joint Venture is incorporated, then Alcoa will take the primary

    responsibility for sourcing the funding. Even if the partners do decide to each source their own

    capital to avoid taking on excess risk, it is a common practice for the junior partner to follow in

    the senior partners footsteps and approach the same financing institutions.

    Most integrated smelter projects are financed through debt or through a mixture of debt and

    equity. The proportion between the two varies, depending on the existence of sponsors for the

    equity package, the availability of creditors at a competitive interest rate, and the degrees of risk

    associated with the project. Sohar smelter in Oman, a recent integrated project, established a

    60:40 split between debt and equity.

    Debt gives the GHR full control of the returns once the loan and interest have been paid

    back. While the issue of bonds would be logistically challenging, there are other commercial

    options that can assist the GHR in finding creditors. One option is through the EKF, Denmarks

    Export Credit Agency, which, by underwriting all or part of the financing, can give the project

    more credibility and encourage investors. The Qatalum smelter project in Qatar recently secured

    $600 million export credit loans, in addition to $2,000 million in a classic commercial tranche.

  • 8/8/2019 Alluminium Smelter-5 Model

    21/21

    Green land Alum in ium ch a p te r 5 1-21

    Issuing shares is a way to attract up-front capital, but it means forfeiting a proportion of the

    returns and possibly allowing a third party to be involved in corporate decision-making. The

    GHR or the Danish Government could sponsor all or part of the stock.

    In order to attract some financing from parties directly interested in the success of the

    project, the equity could be divided between A shares and non-voting equity. A shares would

    be destined for economic entities that have a vested interest in the price and quantity of

    aluminium produced, such as off-take partners for the smelter or equipment providers for either

    the smelter or the power plants. A shareholders would have a say in the floor price for the

    primary aluminium produced and for negotiating interest rates with banks financing the project.

    Non-voting shareholders would not be involved in such decisions, but they would get returns

    proportional to their participation.

    A more detailed evaluation of the mechanics of obtaining the financing can be performed

    once a definite decision is taken by the GHR concerning the type of ownership it will opt forand the definite amount of capital it is looking to secure.

    DEBT OPTIONS

    BONDS cheaper and more secure for investors Logistics are difficult: Danish government would have to issue the bonds,

    potential legal issues if Joint Venture is incorporated

    COMMERCIAL CREDIT more expensive, but more likely to attract takers

    Classic international syndicated loans, which would have to be

    senior -> priority payback

    secured, but limited recourse -> built assets as collateral

    typical interest rates around 1% above London Interbank OfferedRate (LIBOR), lower during construction, higher during production

    typical duration 15-25 years

    Export credits facilitated through Denmarks Eksport Kredit Fonden (EKF)