Silt fence barrier preventing some of the sediment transport off-site.

14
View of well and location from the northern slope. According to a company representative, the location size has not been reduced because the well still needs to be tubed.

description

View of well and location from the northern slope. According to a company representative, the location size has not been reduced because the well still needs to be tubed. Silt fence barrier preventing some of the sediment transport off-site. Location where silt fence needs to be repaired. - PowerPoint PPT Presentation

Transcript of Silt fence barrier preventing some of the sediment transport off-site.

Page 1: Silt fence barrier preventing some of the sediment transport off-site.

View of well and location from the northern slope. According to a company representative, the location size has not been reduced because the well still needs to be tubed.

Page 2: Silt fence barrier preventing some of the sediment transport off-site.

Silt fence barrier preventing some of the sediment transport off-site.

Page 3: Silt fence barrier preventing some of the sediment transport off-site.

Location where silt fence needs to be repaired.

Page 4: Silt fence barrier preventing some of the sediment transport off-site.

Previous location of mud pit was on this sideslope..

Mud pit location

Page 5: Silt fence barrier preventing some of the sediment transport off-site.

Tree pile and creek flow path towards catchment basin on west side of location.

Creek flow path

Catchment basin

Page 6: Silt fence barrier preventing some of the sediment transport off-site.

Picture 7. Taken southwest. Lease road near bridge. Grading done. Water is cloudy from soil runoff. No cover on slopes along road.

Page 7: Silt fence barrier preventing some of the sediment transport off-site.

Picture 2. Taken north. Northeast corner of pad. Erosion rills in drainage trench with hay bales as velocity dissipater. Trench

continues down hill to the north.

Page 8: Silt fence barrier preventing some of the sediment transport off-site.

Hill cut. The backside of this hill has also been removed, leaving a a small strip of trees on top. Photo taken south.

Page 9: Silt fence barrier preventing some of the sediment transport off-site.

Photo taken north. Erosion on north slopeof pad into a nearby creek.

Page 10: Silt fence barrier preventing some of the sediment transport off-site.

Photo taken north. This is a lease road running on the west side of the well pad. The north and south drainage creeks run into the north flowing creek. Again, note how the creek is attempting to run over the road. Note also how the pad encroaches on the creek.

Page 11: Silt fence barrier preventing some of the sediment transport off-site.

Overview of drilling location with a view to the northeast.

Page 12: Silt fence barrier preventing some of the sediment transport off-site.

Western edge of the mud pit constructed for the location. Silt fence surrounding perimeter.

Page 13: Silt fence barrier preventing some of the sediment transport off-site.

Western slope of the location. This is the resulting cut bank for the hillside removed to generate fill material.

Page 14: Silt fence barrier preventing some of the sediment transport off-site.

Lease road view east. This slope needs some stabilization to reduce the risk of erosion into the stream channel. I recommended that they grade this slope, or stabilize with rip-rap and seed.