Wen-Hsien Li (李文献) Center for Neutron Beam Applications (中子束應用研究中心) National Central University (中央大學) SIKA- the Taiwan contract cold TAS at OPAL (2009223AONSA EC meeting) [email protected] National Central University National Central University

Transcript of SIKA- the Taiwan contract cold TAS at OPAL...

  • Wen-Hsien Li (李文献)Center for Neutron Beam Applications

    (中子束應用研究中心) National Central University (中央大學)

    SIKA- the Taiwan contract cold TAS at OPAL

    (2009年2月23日AONSA EC meeting)

    [email protected]

    National Central UniversityNational Central University

  • Official Arrangement bet. Taiwan & Australia․ Signed on June 8, 2005 by TECO & ACIO.․ NSC

    (1) Construct a high-performance cold TAS within 4 years.

    (2) 4 scientists to operate the cold TAS.(3) Obtain 70% of one instrument time

    for NSC related scientists.(~240 days neutron beam time)

    (4) Instrument time may be distributed overthe full set of instruments at OPAL reactor.

    緣起緣起

  • *

    Australian Nuclear Science and Technology Organisation (ANSTO)

    OPALreactor

    GuideHall

    The locationThe location

    Taiwanteamoffice

    位於雪梨西南30公里處,時差2小時,飛行時間9小時

  • 計畫目標計畫目標

    1. Construction:To design & build a high performance cold neutron TAS at OPAL to be commissioning by 2010.(Project leads by NCU)

    2. Operation:To run user programs, to operate SIKA. (4 scientists at ANSTO, 50 research projects / year) (From 2010 for 15 years)

  • Formosan sika deer

    Spin-echo Inelastic K-space Analyzer

    Triple-axis spectrometer → Inelastic scattering, analyzing k-space.

    Cold TAS : ΔE ~ 0.1 to 1 meV

    Spin-echo cold neutron triple-axis spectrometer

    Spin-polarized Inelastic K-space AnalyzerUltra-high energy resolution

    → resonance spin echo techniqueWith RSET : ΔE ~ 1 to 100 μeV (optional)

    SIKA projectSIKA project

  • HRPD高解析度中子繞射儀

    TOF DCS飛逝時間散射儀

    Reflectometer反射儀

    Residual stress

    HIPD高強度

    中子繞射儀

    SANS小角度散射儀

    Quasi-LaueDiffractometer

    Thermal-TAS熱三軸散射儀

    Cold-TAS冷三軸散射儀

    SIKA locationSIKA location At the OPAL reactor face, receiving CG4

  • SIKASIKA--The cold neutron tripleThe cold neutron triple--axis spectrometer at ANSTOaxis spectrometer at ANSTO

    Virtual source

    Collimator

    DF Mono.

    2θ=30。~135。

  • Operation areaOperation area

    Sika: 45 m2

    Taipan: 27 m2

    Dance floor : GraniteGrade 0, precession < 10μm1650 × 1095 × 120 mm3

    Interlock Cabinet

    Motion Control Cabinet

    DAE Cabinet

    Dance Floor

    Perimeter wall

    45 m2

  • Spectrometer design

    奈米物性實驗室

  • Beam port CG4Size of beam at reactor face 50 x 200 mm2 (W x H)Take-off angular range 2ΘM 30o ≤ 2ΘM ≤ 120o

    Monochromator crystals HOPG, η = 24’, double focusing, Si(111)

    Monochromator dimensions 220 x 340 mm2 (Width x Height)Useful wavelength range 1.74 Å ≤ λ ≤ 5.8 Å (PG 002)Correspond. wave-vector range 3.6 Å-1 ≤ ki ≤ 1.0 Å-1 (PG 002)Correspond. incident energy range 2.4 meV ≤ Ei ≤ 27 meV (PG 002)Virtual source aperture 0 ≤ W ≤ 65 mm ; H = 220 mmDistances- cold source – monochromator- reactor face – monochromator- virtual source – monochromator- monochromator – sample

    6715 mm2300 mm2100 mm 2100 mm

    Collimators- α1 (pre-monochromator) - α2 (post-monochromator)

    20’, 40’, 60’, open 20’, 40’, 60’, open

    Incident beam filters- Be cooled (10 cm) Ei < 5 meV- PG (8 cm) Ei = 13.7 & 14.7 meV- Sapphire (8 cm) Ei > 15 meV

    Higher order suppression Higher order suppressionFast neutron suppression

    2.4 meV ≤ Ei ≤ 31 meV(Si 111)

    SIKA primary spectrometer specificationSIKA primary spectrometer specification

    Monochromator:Double focusing

    PG and Si

  • 165.1

    mm

    162m

    m

    456m

    m

    210.9

    mm1139.57mm

    209.95mm

    100m

    m

    200

    mm

    50mm

    4.05mm

    1401mm

    1419mm

    20 0 m m

    50mm

    138m

    m

    253

    mm

    68mm

    19.2mm

    Sour

    ce

    Beam TubeExit Port

    4413.99mm Central to Reactor Face

    2824.05mm Supermirror Guide, Top, Buttom, and Side M=32mm

    2100mm

    2100mm

    Monochromator11×11 slabs

    Slab size = 20×20 mm2Gap between slab = 0.5 mm

    2ΘM

    348

    mm

    225mm

    Sample

    Reactor Face

    136m

    m

    259m

    m

    80mm250mm

    VirtualSource

    SecondaryShutter

    Sapphirefilter inside

    Collimators

    900mm

    1200mm

    80 × 240 × 100 mm(L × H × W )

    300mm

    1070mm

    730mm

    250mm

    250mm

    600m

    m

    250mm

    240m

    m

    Reactor core

    Shielding drum

    Reactor face

    Double focusingPG/Si monochromator

    SIKA primary spectrometerSIKA primary spectrometer

    Collimator

    Monochromator to sample : 2.1 m

  • Si mono雙向聚焦單色晶體

    PG mono雙向聚焦單色晶體

    Be, PG, Sapphire

    filters過濾晶體

    Neutron beam中子束

    Collimators準直器

    Beam shutter束線開關

    Components inside the drum Components inside the drum

    Side view

  • Shielding drum assembly videoShielding drum assembly video

  • • By AZ-System• 20 × 22 mm2 HOPG• 11 × 11 crystals• Double focusing

    SIKA SIKA monochromatormonochromator

    • By AZ-System• 17 × 210 × 10 mm3 Si• 13 crystals• Double focusing

    HOPG(002)Si(111)

  • • Manufacture in TaiwanShielding drumShielding drum

    January 2009 at鼎貿

  • SIKA sample stageSIKA sample stageWill go for

    Huber tables

  • 13 HOPG analyzer +1 PSD bank

    SIKA secondary spectrometerSIKA secondary spectrometer

    1 single detector + 1 diffraction PSD

  • SIKA secondary spectrometerSIKA secondary spectrometerAssembly:

    Similar to that of BT-7, NIST but with electronics are placed at the

    bottom

    Electronics

    2.1m

  • The team & timeline

    奈米物性實驗室

  • Peter VorderwischConsultant

    Chun-Chuen YangInstr. Scientist

    Eno ImamovicDesigner

    Chun-Ming WuInstr. Scientist

    Geoff DuranceMCNP Consultant

    Tzu-Neng ChanElectronics

    The SIKA teamThe SIKA team

    Wen-Hsien LiProject Leader

    Jen-Chih PengSpect. control

    Hui-Chia SuData analysis

    Chin-Wei WangPhD. Student

    Yi-Hsuan HungSecretary

  • Task Name2006 2007 2008 2009 2010

    Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3

    SIKA Project PhasePRIMARY Spectrometer

    Conceptual DesignMcStas (Performance, Optimization)MCNP SourceMCNP ShieldingConceptual Design Drawings

    Engineering DesignCollimator change, Input opticsShielding

    ProcurementMonochromator (PG & Si)Collimators, Input opticsSample ModuleShieldingElectronic ComponentsDance Floor (ANSTO)

    SECONDARY SpectrometerConceptual DesignEngineering DesignProcurement

    INSTALLATIONMonochromator ShieldingMechanical PartsElectrical PartsIT Systems

    COMMISSIONINGOPERATION

    t

    SIKASIKA--timelinetimeline

  • SIKAA cold-neutron triple-axisspectrometer at ANSTO

    SIKA project timelineSIKA project timeline

    Conceptual design

    Engineering design

    Manufacture & procure

    Assemble & install

    Commissioning

    Primary Secondary

    2009200820072006 2010

    SecondaryPrimary