SFG1690 V9 Public Disclosure Authorized€¦ · 01/02/2016 · Ganga Action Plan-I, Nala tapping...
Transcript of SFG1690 V9 Public Disclosure Authorized€¦ · 01/02/2016 · Ganga Action Plan-I, Nala tapping...
ENVIRONMENTAL AND SOCIAL ASSESSMENT WITH
MANAGEMENT PLAN FOR
ANUPSHAHAR SEWERAGE SCHEME (Distt Bulandshahar)
Joint Director General Manager
Project Implementation Unit Yamuna Pollution
Control
U.P. Jal Nigam Unit U.P. Jal Nigam
Ghaizabad Ghaziabad
SFG1690 V9
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
Content Content ...................................................................................................................................... 2
List of Figure .............................................................................................................................. 6
List of Tables .............................................................................................................................. 7
1 Introduction ...................................................................................................................... 14
1.1 Ganga clean up initiatives ......................................................................................... 14
1.2 The Ganga River Basin Project .................................................................................. 15
1.2.1 World Bank assistance ....................................................................................... 16
1.3 Project components .................................................................................................. 16
1.3.1 Institutional development ................................................................................. 16
1.3.2 Component Two: Priority Infrastructure Investments ...................................... 18
1.4 Structure of the Report ............................................................................................. 20
2 Project description............................................................................................................ 23
2.1 About the City ........................................................................................................... 23
2.1.1 History ................................................................................................................ 23
2.1.2 Town at a Glance ............................................................................................... 23
2.1.3 Existing Sewerage Facilities in City .................................................................... 24
2.1.4 Works Completed under Ganga Action Plan Phase - II (GAP-II) ........................ 25
2.2 Necessity of this project ............................................................................................ 28
2.3 Proposed City Sewerage Plan .................................................................................... 29
2.3.1 Forecasted wastewater generation scenario .................................................... 29
2.4 Proposed Sewerage Treatment Plant (MBBR Technology) ...................................... 31
2.5 Disposal of Treated Effluent ...................................................................................... 32
2.5.2 Manhole ............................................................................................................. 43
2.5.3 House Connection Chamber .............................................................................. 44
2.5.4 Construction Methodology ................................................................................ 44
2.5.5 Muck and Debris Management ......................................................................... 45
2.5.6 U.P.PCB CONSENT .............................................................................................. 45
2.5.7 IMPLEMENTATION SCHEDULE ........................................................................... 45
3
2.5.8 Financial Cost Summary ..................................................................................... 45
3 Approach and Methodology ............................................................................................. 47
3.1 Screening Activity for Project Impact Assessment.................................................... 49
3.2 Conclusion of Screening Activity ............................................................................... 57
4 Regulations and Legal Framework ................................................................................... 58
4.1 Applicable Laws and Regulations – Environmental .................................................. 58
4.1.1 Legal Framework of Government of India ......................................................... 58
4.1.2 Key Environmental Laws and Regulations ......................................................... 59
4.2 Applicable Laws and Regulations - Social .................................................................. 61
4.2.1 National Policies and Acts .................................................................................. 61
4.2.2 The right to fair compensation and transparency in land acquisition,
rehabilitation and resettlement act, 20i3 ........................................................................ 62
4.2.3 Forest Rights Act 2006 ....................................................................................... 63
4.3 Other Legislations applicable to Construction Projects under NGRBP ..................... 74
4.4 Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 .................................................... Error! Bookmark not defined.
5 Baseline Status .................................................................................................................. 78
5.1 Baseline Environmental Status ................................................................................. 78
5.1.1 Physiography and Topography .......................................................................... 78
5.1.2 Climate ............................................................................................................... 80
5.1.3 Land Use Pattern ................................................................................................ 84
5.1.4 Geological and Geophysical features................................................................. 85
5.1.5 Duration of Monitoring to generate the base line ............................................ 88
5.1.6 Meteorology ...................................................................................................... 88
5.1.7 Ambient Air Quality ........................................................................................... 88
5.1.8 Noise Environment ............................................................................................ 93
5.1.9 Water Environment ........................................................................................... 97
5.1.10 Drainage System .............................................................................................. 104
5.1.11 Waste Water Management ............................................................................. 104
5.1.12 Waste generation: ........................................................................................... 105
5.2 Tourism .................................................................................................................... 108
4
5.3 Environmentally Sensitive Zone .............................................................................. 109
5.4 Health Care .............................................................................................................. 110
5.5 Education ................................................................................................................. 111
5.6 Soil ........................................................................................................................... 112
5.6.1 Bathing Ghats ................................................................................................... 114
5.6.2 Biological Environment .................................................................................... 115
5.6.3 Socio Economic Baseline .................................................................................. 120
6 Environmental and Social Impacts ................................................................................. 129
6.1 Environmental Impacts ........................................................................................... 129
6.1.1 Design and Development Phase ...................................................................... 130
6.1.2 Impacts during construction phase ................................................................. 131
6.1.3 Air quality ......................................................................................................... 132
6.1.4 Noise levels ...................................................................................................... 132
6.1.5 Water resources ............................................................................................... 133
6.2 Impacts during operation phase ............................................................................. 133
6.2.1 Water environment ......................................................................................... 134
6.2.2 Noise and air quality ........................................................................................ 134
6.3 Potential Social Impacts .......................................................................................... 134
6.3.1 Social Impacts .................................................................................................. 134
6.4 Conclusion ............................................................................................................... 136
7 Mitigation and Management Plan .................................................................................. 138
7.1 Environmental Management Plan .......................................................................... 138
7.1.1 Implementation of EMP Specific activities by Uttar Pradesh Jal Nigam ......... 138
7.2 Implementation of EMP .......................................................................................... 138
7.3 Environmental Monitoring Plan .............................................................................. 169
7.4 Social Management Plan ......................................................................................... 173
7.4.1 Social mitigation plans during construction phase .......................................... 173
7.4.2 Social mitigation plans during operation phase .............................................. 175
7.4.3 Consultation Framework for Participatory Planning and Implementation of
Mitigation Plan ................................................................................................................. 178
5
7.4.4 Assess the Capacity of Institutions and Mechanisms for Implementing Social
Development Aspects and Social Safeguard Plans; Recommend Capacity building
measures ......................................................................................................................... 180
7.4.5 Develop Monitoring and Evaluation Mechanisms to Assess Social Development
Outcomes ........................................................................................................................ 181
7.5 EMP Budget ............................................................................................................. 181
8 Social Development Outcomes and Issues ..................................................................... 189
8.1 Social Development Outcomes of the sub project ................................................. 198
8.2 Social Development Issues in Project Vicinity and Social Services to be provided by
the project ........................................................................................................................... 199
9 Conclusion ...................................................................................................................... 200
6
List of Figure
Figure 1 Tapped Nala .................................................................................................................... 24
Figure 2 Overflow of Nala falling into the river ............................................................................ 24
Figure 3Existing STPs location ....................................................................................................... 26
Figure 4STP-I, Zone-A, 0.805 MLD ................................................................................................ 28
Figure 5STP-II, Zone-B, 1.75 MLD.................................................................................................. 28
Figure 6 Plan of treated waste water used for irrigation purposes ............................................. 35
Figure 8 Flowchart describing the steps adopted for Project Impact Assessment ...................... 47
Figure 9Distribution of Dolphin in Upper Ganga System population up to October 2012
(source WWF) ............................................................................................................................... 80
Figure 10 Temperature Variation & Precipitation ........................................................................ 82
Figure 11 Annual Temperature ..................................................................................................... 81
Figure 12 Annual Rainfall .............................................................................................................. 83
Figure 13 Land use & Cropping Pattern ........................................................................................ 84
Figure 14 Geology of the town ..................................................................................................... 85
Figure 15 Underground Sewer Line .............................................................................................. 86
Figure 16 Groundwater Scenario of the Town ............................................................................. 87
Figure 17 Wind Rose ..................................................................................................................... 88
Figure 18 Air Sampling in progress ............................................................................................... 92
Figure 19 Noise Sampling .............................................................................................................. 96
Figure 20 Water Sampling Site Pics ............................................................................................ 103
Figure 21 Drainage Pattern in whole State ................................................................................. 104
Figure 22 Tourism Map of the State ........................................................................................... 108
Figure 23 Environmentally Sensitive Zones ................................................................................ 109
Figure 24 Health Care in the State and Town ............................................................................. 110
Figure 25 Education Scenario in the town .................................................................................. 111
Figure 26 Soils in different Parts of State and Town .................................................................. 113
Figure 27 Soil Collection for sampling purposes ......................................................................... 114
Figure 28Distribution of Dolphin in Upper Ganga System population up to October 2012
(source WWF) ............................................................................................................................. 120
Figure 29 Socio-Economic Profile of the town ........................................................................... 121
Figure 30 Density of Population in the town .............................................................................. 124
Figure 31 Mela pictures in Anupshahr ........................................................................................ 126
Figure 32 Cultural Significance in the state ................................................................................ 127
7
List of Tables
Table 1 Zone-A, Wards & Population............................................................................................ 30
Table 2 Zone B-Wards & Population ............................................................................................. 31
Table 3 STP Capacities in Year 2028 & 2048 ................................................................................. 32
Table 4 Plan for 5 & 10 Years of treated water usage .................................................................. 35
Table 5 Land Requirement for MPS ................................................. Error! Bookmark not defined.
Table 6 Length of Sewerage Network for subsequent dia. .......................................................... 42
Table 7 Implementation Schedule ................................................... Error! Bookmark not defined.
Table 8 Form J for the Sewerage Scheme ..................................................................................... 46
Table 9Screening Activity .............................................................................................................. 50
Table 10 Key Environmental Laws & Regulations ......................................................................... 59
Table 11Dolphin habitat parameters in Upper Ganga River (Narora- Anupshahr) ...................... 79
Table 12Depth of Water below Ground level and its Hydro-geological Conditions in
Anupshahr ..................................................................................................................................... 87
Table 13 Air Quality monitoring location ...................................................................................... 89
Table 14 Noise Ambient Quality ................................................................................................... 95
Table 15 Water Quality at STP Inlet .............................................................................................. 97
Table 16 Water Quality at STP Outlet ........................................................................................... 98
Table 17 Water Quality of Ganga River ........................................................................................ 99
Table 18 Soil Parameters examined at the site .......................................................................... 112
Table 19 List of Flora in the town ............................................................................................... 116
Table 20Dolphin habitat parameters in Upper Ganga River (Narora- Anupshahr) .................... 119
Table 21Comparative analysis of various sewage treatment technologies ............................... 130
Table 22 Environment Management Plan .................................................................................. 140
Table 23 Environmental Management Plan for Sewerage Network in Anupshahr ................... 161
Table 24Environment Monitoring Programme .......................................................................... 170
Table 25Social Management Plan ............................................................................................... 176
Table 26Role of stakeholder in implementation and mitigation ................................................ 180
Table 27EMP Budget ................................................................................................................... 183
Table 28Cost of Environmental Monitoring Plan ....................................................................... 188
8
ABBREVEATIONS
AAQM Ambient Air Quality Monitoring
ASI Archaeological Survey of India
CPCB Central Pollution Control Board
ESMF Environmental and Social Management Framework
GoI Government of India
INTACH Indian National Trust for Art and Culture Heritage
WSP Waste Stabilization Pond
MFP Minor Forest Produce
MoEF Ministry of Environment and Forest
MPS Main Pumping Station
MSL Mean Sea Level
NGRBA National Ganga River Basin Authority
NGRBP National Ganga River Basin Programme
O&M Operation and Maintenance
PHED Public Health Engineering Department
PMG Project Management Group
PPE Personal Protection Equipment
SPCB State Pollution Control Boards
SPS Sewage Pumping Station
STP Sewage Treatment Plant
UDD Urban Development Department
USEPA United States Environment Protection Agency
WTP Water Treatment Plant
9
EXECUTIVE SUMMARY
In order to reduce the pollution load on the river, Ganga Action Plan (GAP) was launched. In
the GAP town was taken as the unit of planning. However, in view of the short comings
observed in the approach followed in the GAP it was felt necessary that the river
conservation plan needs to be revamped. To give a fresh impetus to pollution abatement of
River Ganga & its tributaries by adopting a holistic approach with river basin as the unit of
planning and management, National Ganga River Basin Authority (NGRBA) was set up in Feb
2009. Thus the objective has now shifted from town centric to river basin approach.
Anupshahr is a major town in distt. Bulandshahar UP. It is located 115 km away from
Delhi,95 km away from Noida,75 km away from Greater Noida, 55 km away from Aligarh
and 40 KM away from Bulandshahr This city is full of cultural and historical heritage. It is
located on the bank of Holy River Ganga, thousands of people take holy bath in River Ganga
through Anupshahr Ganga Ghat. The Town comprises of 25 nos. of wards and at presents
holds the population of 29700 as per the 2011 population survey data.
The Town comprises of 25 nos. of wards and for each and every ward there is a provision
for water supply line. There is no provision of private tube wells in the town. The water
supply within the area is adequate to cater the total population in different wards. The
Water Supply rate is different for the piped and stand posts connections. The 96 % of the
population is fed through proper piped water supply with the per capita rate of 120lpcd and
the remaining population which is utilizing the hand pumps and other sources will be fed
with a rate of rate of 15 lpcd.
Anupshahr town at present doesn’t have a sewerage network system. However, under
Ganga Action Plan-I, Nala tapping was done by intercepting the flow and diverting it into
two nos. of sewerage treatment Plants of 1.75 mld and 0.805 mld capacity respectively. At
present only the flow of Nalas is tapped and diverted to STP and treated water is discharged
into the River Ganga. However in the rainy seasons and the peak flow period (Mela period)
these 250mm sewer lines are collapsed and the overflow of the waste water creates the
unhygienic conditions for the people residing in the area.
The population projection including the floating population of the town has been worked
out by various statistical methods. The “Incremental Increase Method” has been adopted
10
for the population projections from all other methods as the population increase trends in
the Anupshahr town for the previous years is in accordance with the projected population
calculated from this method. The initial (2018), mid (2033) & ultimate (2048) stage
population adopted for the project are 38795, 49878 & 63635 respectively.
The rate of water supply for preparing the sewerage project has been taken as 135 lpcd
with a return factor of 0.8. Ground water infiltration has also been taken into consideration
where ever applicable. On this basis the waste water generation for initial, mid& ultimate
stage comes to4.19MLD 5.39 MLD & 6.87MLD respectively. The sewerage project has been
prepared on this basis.
The design is done by keeping in mind that there should be no requirement of IPS within
the sewerage network, apart from the main Pumping stations. The route of the sewerage
pipes is laid in such a way that wastewater mostly follows the gravity flow. The drawing
showing the sewerage network and the design sheet of the sewerage network is shown in
the later section of the report. After considering both the options, it is concluded that
option-II is more feasible than the earlier one in terms of financial and technical aspects.
Proposed sewerage system is designed for 30 years period. The major components of the
proposed project include:
The sewage network is designed to be laid down in the town considering the peak factor of
3.0; the total estimated length of sewage network is likely to be 60 kms (approx.) with
sewer ranging from 150mm dia to 600 mm dia. Non clog submersible pumps are proposed
to be provided at MPS and these pumping units are designed for the waste water flows
from the connected sewer. The capacity of each pump will be ¼ of peak flow. Six pumps will
be provided at each pumping station as the 50% standby is proposed. The rising main have
been designed for SPS in Zone-A and Zone-B for the lifting of waste water from the low lying
areas to the corresponding STPs. The design is made for the middle and peak capacities
having make of DI with dia of 300mm. There are two MPS proposed at the site located in
the plan. The existing two MPS will be dismantled once the construction of these new MPS
is done.
The Life Cycle costing (LCC) technique has been adopted to determine the most suitable
Technological option for the STP at Anupshahr. On this basis, MBBR has been adopted. This
11
option is cost effective, acquires lesser area and produces quality results.
The characteristics of the waste water carried by all the three drains in the town were
measured. The waste water characteristics’ of the samples taken from the drains is on
tower side & does not present the real picture of the characteristics of waste water
generated in the town. The STP has therefore been designed for BOD5 -220 mg/I, TSS-350
mg/I, Fecal coliform 106-109 MPN/100 ml, which are in general adopted for design of STPs
in similar towns. The Sewage Treatment Plant has been designed for year 2028 requirement
of 4.96mld capacity. Capacity of STP at Zone A& Zone B are 2.267 mld & 2.688 mld
respectively. Further modules can be added in future as & when required. The land for
proposed STP belongs to Nagar Panchayat.
The treated wastewater is very rich in terms of nutrients such as Nitrogen, Phosphorus.
Therefore, it shall be proposed to utilize it as a resource for agriculture. The treated waste
water will be carried by the RCC pipe of 600 mm dia. having length of 650 m to the River
Ganga for Zone-A and 600 mm dia. having length of 450 m for Zone-B, if it is not being
utilized for irrigation purposes.
The treated effluent is proposed to be disinfected by using a suitable methodology & then
used for irrigation purposes. Provision has also been made for staff quarters, administrative
building & lab, power connections, land for pumping station & 5 years O&M Cost etc.
As per the Environmental and Social Management Framework (NGRBA, 2011), the
implementation of such river pollution mitigation projects under the NGRBP is anticipated
to encounter a variety of environmental and social issues/problems. Therefore the study of
environment and social sector is required for analyzing the impacts of proposed project,
and suggesting the management plans to handle any negative impacts. The Detailed Project
Report and the Environmental and Social Assessment with Management Plan (ESAMP) is
being prepared on the basis of the Detailed Project Report that has been prepared by U.P.
Jal Nigam.
Most of the waste water of the town is discharged directly in the River Ganga which not
only adds to the pollution load of River Ganga but also creates unhygienic conditions in the
town, unhealthy environment & endangers public health. Therefore in order to reduce
pollution load of River Ganga and create a healthy environment in the town, pollution
12
abatement works in which a planned sewerage system is provided to the town, is a must.
The methodology adopted for the environmental and social assessment includes secondary
data analysis carrying out scoping in the field, survey of the host population and discussions
with key stakeholders including government officials, Nagar Panchayat and local residents.
Based on these outcomes, a screening activity was conducted with the help of the screening
checklist format provided in Environmental and Social Management Framework of NGRBA.
Thereafter, environmental and social impacts were identified and assessed and a mitigation
plan was developed based on the aforementioned.
The screening checklist includes criteria that details out the impact level of various activities
during the construction and operation phases. These criteria include environmental factors
such as the presence of eco-sensitive region in and around the project area, clearance of
tree cover, improper storage of excavation spoils, flooding of adjacent areas, noise and dust
levels & damage to existing utilities. Social criteria include factors such as requirement for
land acquisition if needed, displacement of habitants, and loss of livelihood and gender
issues.
Based on the criteria-wise screening activity and the categorization of potential sub projects
of the NGRBP, the present project of Sewerage work in Anupshahr town falls under low
impact category, which does not need any land acquisition and has an overall positive
impact by tapping the wastewater which was earlier polluting the river Ganga.
As a part of ESAMP, baseline study of the Anupshahr town was prepared to understand the
region's existing physical characteristics, cultural and social status of the residing
community.
While in baseline status of social section, it brings out the status of demographic
composition of the population, general land use feature of the wards and also details of the
social survey outcomes at various consultations held in different wards of the town.
Although there would not be any negative or adverse environmental or social impacts, but
these have temporary impacts on air quality (impact on health), traffic blockages, safety
hazards for pedestrians, possible interruption in commercial activity, and accidental
breakage of other public infrastructure such as water pipes.
13
These temporary impacts can be mitigated with appropriate mitigation plans, which have
been suggested in the ESAMP. The probable cost of environmental management plan, has
been estimated to be approximately Rs.70.59 lac. The details have been given in table 7.5 of
this report. The larger environmental value of the project greatly outweighs the temporary
disruptions and impacts mentioned above. The project is expected to benefit the town, as
the wastewater that currently flows untreated into the Ganga River will be arrested &
treated. The treated effluent is proposed to be used for irrigation and afforestation & may
have to be discharged into river Ganga during rainy season.
14
1 Introduction
The river Ganga has significant economic, environmental and cultural value in India.
Rising in the Himalayas and flowing in to the Bay of Bengal, the river traverses a course of
more than 2,500 km through the plains of north and eastern India. The Ganga main stem
- which also extends into parts of Nepal, China and Bangladesh - accounts for 26 per cent
of India's landmass, 30 per cent of its water resources and more than 40 per cent of its
population. The Ganga also serves as one of India's holiest rivers whose cultural and
spiritual significance transcends the boundaries of the basin.
Despite its importance, extreme pollution pressures from increasing population and
industrialization pose a great threat to the biodiversity and environmental sustainability of
the Ganga, with detrimental effects on both the quantity and quality of its flows.
Discharge of untreated sewage and industrial wastewater, non-point pollution sources
from religious activities along the river, agriculture and livestock as well as poor solid
waste management are the main causes for pollution in river Ganga.
1.1 Ganga clean up initiatives
The Government of India (GoI) has undertaken clean-up initiatives in the past. The most
prominent of such efforts was the Ganga Action Plan, launched in 1985 later
complemented by a similar plan for the Yamuna, the biggest tributary of the Ganga.
These programmes have faced significant public scrutiny and, despite some gains made
in slowing the rate of water quality degradation, they have been widely perceived as
failure. The main shortcomings of these initiatives were: (1) inadequate attention to
institutional dimensions, including the absence of a long-tem-basin planning and
implementation framework; (2) little effort made in addressing systemic weakness in the
critical sectors of urban wastewater, solid waste management, environmental
monitoring, regulation and water resources management; and (3) inadequate scale,
coordination and prioritization of investments, with little emphasis on ensuring their
sustainability. These programs also did not pay sufficient attention to the social
dimensions of river clean-up, failing to recognize the importance of consultation,
15
participation and awareness-raising.
The lessons drawn from these prior experiences indicate that improving water quality in
the Ganga cannot be achieved by plugging the infrastructure gap alone. Rather, any
effective initiative will have to adopt a three-pronged approach:
• Establishing a basin-level, multi-sectorial framework for addressing pollution in the
river (including national/state policies and river basin management institutions);
• Making relevant institutions operational and effective (e.g. with the capacity to plan,
implement and manage investments and enforce regulations); and,
• Implementing a phased program of prioritized infrastructure investments (with
emphasis on sustainable operations and mobilization of community support)
1.2 The Ganga River Basin Project
As a major first step in achieving the above, the Government of India (GoI) constituted
the National Ganga River Basin Authority (NGRBA), on 20thFebruary 2009, for the
comprehensive management of the river. The NGRBA will adopt a river-basin approach
and has been given a multi-sector mandate to address both water quantity and quality
aspects. The NGRBA has resolved that by year 2020, no untreated municipal sewage or
industrial effluents will be discharged into River Ganga.
Building on the high-level dialogue with GOI on Ganga, The World Bank has been
formally requested to provide long-term support to NGRBA, through several phases of
substantive financing and knowledge support. While, the overall technical assistance and
program development under the proposed project will focus on the entire Ganga main
stem, the initial emphasis of the specific investments under the first project will focus on
main stem of Ganga flowing through five basin states of Bihar, Jharkhand, Uttar Pradesh,
Uttarakhand and West Bengal in India. Specifically, pollution abatement programs in
cities on the banks of these States which would include a range of municipal investments
such as sewer networks, waste water treatment facilities, industrial pollution control
measures, river front management and solid waste disposal in the river through
improved management in these cities and other required supportive improvements. This
is expected to be enabled through several phases of substantive financing and
knowledge support.
16
The first project of such several phases of support aims at;
1. Establishing and operationalizing central and state level NGRBA institutions capable of
planning and implementing a multi sectorial river water quality improvement
program and;
2. Reducing pollution loads into the river through selected investments.
To achieve the above, the proposed World Bank assisted National Ganga River Basin
Project (NGRBP) envisages two main components.
1.2.1 World Bank assistance
The Government of India has sought programmatic assistance from the World Bank to
support the NGRBA in the long term. This project is the first operation under this
agreement, and aims to support the NGRBA in establishing its operational-level
institutions and implementing priority investments.
1.3 Project components
The project will have two components relating to institutional development and priority
infrastructure investments. The first component would seek to build the institutional
capacity to effectively implement the overall NGRBA program, including infrastructure
investments funded by the second component.
1.3.1 Institutional development
1.3.1.1 Objective
The objectives of this component are to: (i) build functional capacity of the NGRBA's
operational institutions at both the central and state levels; and (ii) provide support to
associated institutions for implementing the NGRBA program.
The activities financed under this component are grouped under the following sub-
components:
(a) Sub-component A: NGRBA Operationalization and Program Management
(b) Sub-component B: Technical Assistance for ULB Service Providers
17
(c) Sub-component C: Technical Assistance for Environmental Regulators
1.3.1.2 Sub Component A: NGRBA Operationalization and Program Management
This sub-component is aimed at supporting the nascent operational institutions
established for implementing the NGRBA program at the central and state levels on a full
time basis.
The NGRBA's operational institutions comprise the Program Management Group (PMG)
at the central level, and SGRCA Program Management Groups (SPMGs) at the state level.
The PMG is being established as a fully owned society of the Government of India, with
suitable structure, staff, powers and leadership, to lead the planning and program
management of the NGRBA program at the national level. It is supported and housed by
the MOEF as the nodal Ministry. Similarly, the SPMGs are being established in the form
of registered societies, to ensure effective planning and program management at the
state level.
Separating Program Management from Investment Execution: The rationale for
establishing the PMG and SPMGs is to have institutions with single point responsibility
for the NGRBA's program planning, management and long-term sustainability.
Program Management for the Entire NGRBA Program: The sub-component will provide
for initial setup costs of office infrastructure and equipment, as well as provision of
critical consultancies, incremental staffing, training, and operation costs. Key NGRBA
program management activities included under this sub-component are described below:
(a) Enhancing Ganga Knowledge Resources
(b) Communications and Public Participation
(c) Innovative Pilots
(d) Program of Action for Carbon Credits
1.3.1.3 Sub component B: Technical Assistance for ULB Service Provider
The long term operation and maintenance of the NGRBA-funded assets is the responsibility
of the ULBs and local service providers, and this sub-component is aimed at providing
assistance that can gradually enable them to take on their role.
18
1.3.1.4 Sub-component C: Technical Assistance for Environmental Regulator
This sub-component is aimed at addressing the key constraints faced by the CPCB and SPCBs
related to their functions regarding the Ganga. The subcomponent will support:
a) Capacity building of the CPCB and SPCBs
b) Up-gradation of Ganga Water Quality Monitoring System
1.3.2 Component Two: Priority Infrastructure Investments
1.3.2.1 Objective
The objective of this component is to finance demonstrative infrastructure investments to
reduce pollution loads in priority locations on the river.
1.3.2.2 Four Investment Sectors
The majority of investments are expected to be in the wastewater sector, particularly in
Wastewater treatment plants and sewerage networks. Investments will also be supported in
industrial pollution control and prevention (e.g. common effluent treatment plants), solid
waste management (e.g. collection, transport and disposal systems), and river front
management (e.g. improvement of the built environment along river stretches,
improvement of small ghats and electric crematoria, and the conservation and preservation
of ecologically sensitive sites). Many investments are likely to combine elements of more
than one of these sectors.
1.3.2.3 The Framework Approach
In lieu of defining and appraising specific investments, the project preparation has focused
on developing investments framework covering all four key sectors of intervention under
the NGRBA program. This single framework will apply to all investments under the NGRBA
program.
The objectives of the investments framework are to:
A) Provide a filter for all the NGRBA investments, for ensuring that the selected investments
are well-prepared and amongst the most effective in reducing the pollution loads;
B) Make transparent the decision-making process on investments selection; and
C) Ensure that the investments are implemented in a sustainable manner
19
1.3.2.3.1 Framework Criteria
The investments framework prescribes the criteria and quality assurance standards covering
various aspects including eligibility, prioritization, planning, technical preparation, financial
and economic analyses, environmental and social management, long term O&M
sustainability, community participation, and local institutional capacity.
1.3.2.4 Investment Execution
The investments program will be planned and managed by the NGRBA PMG and SPMGs,
while the execution of specific infrastructure investments will be done by the selected
existing and qualified state-level technical agencies. To foster competition and tap private
sector efficiencies, the state governments with significant infrastructure investments are
setting up a public-private joint venture infrastructure company, to execute NGRBA and
other similar investments in the respective states in the medium to long term.
1.3.2.5 Rehabilitation of existing infrastructure
Investments involving rehabilitation of existing infrastructure will be included on priority,
due to their intrinsically higher returns in terms of reductions in pollution loads entering the
Ganga.
20
1.4 Structure of the Report
The Environment and Social Assessment with Management Plan for the Sewerage works in
Anupshahr town, Uttar Pradesh rolls out the baseline status of the existing sewage situation
and analyzes the situation if the proposed project is implemented, with its possible
implications and to negate those implications management plan is advised which is as per
the Environment and Social Management Framework.
Chapter 1:starts with the introduction of the programme to clean up River Ganga and
various mechanisms to implement the project. This chapter details out the functionalities of
the institutions involved in the project.
Chapter 2:In this chapter, specific project description is discussed pertaining to the
proposed sewerage project in Anupshahr town. This chapter provides insight into the
various components of the proposed project.
Chapter 3: This chapter of the report talks about the methodology adopted for the
environmental and social assessment included secondary data analysis and identifying
information requirements and their sources, defining the project area and carrying out
scoping in the field, survey of the host population and discussion with key stakeholders
including Nagar Panchayat at government officials and local residents. Based on these
outcomes, a screening activity was conducted with the help of the screening checklist
format provided in ESMF report of NGRBA.
Chapter 4: In this chapter of the report presents the applicable laws and guidelines related
to such kind of projects and are in accordance with the ESMF report. It gives insight to
applicable environmental and social laws including land acquisition act and forest act.
Chapter 5:In this chapter, detailed baseline scenario of the information available for city and
for sewerage in Anupshahr town is presented for both environmental and social aspects.
Baseline scenario helps to assess the situation now and provides an indication of the
scenario after the project execution. In environmental scenario it reflects the status of
environmental entities like status of climate, geological features, air quality, water quality,
waste management. As part of the social scenario, it brings out the status of demographic
21
composition of the population, general land-use features of the wards and also details of
the social survey outcomes at various consultations held in different wards of the sewerage
district.
Chapter 6:In this chapter, environmental and social impacts were identified and assessed
which details out the key issues related to safety, environmental concerns and livelihood. It
identifies issues at various stages of the project cycle i.e. during design and development
phase, construction as well as during the operation phase.
The project activities would not have any negative or adverse environmental or social
impacts. There may however be temporary and very limited impacts due to various
construction activities to be undertaken. The identified environmental impacts have further
been classified under the heads of environmentally sensitive areas, air quality, water
resources and noise quality. The social impacts have further been classified under impacts
on human health, traffic congestion, impact on livelihood, land acquisition, impact on
utilities and existing infrastructure, noise levels, safety hazards and failure to restore
temporary construction sites.
Chapter 7:The temporary impacts which have been broadly described in the ongoing
chapters can be mitigated with appropriate mitigation plans, which have been focused upon
in this Chapter of the report, along with monitoring and evaluation of future projects.
However, keeping in view that the impacts will only be temporary and short lived, it is
concluded that the larger environmental value of the project greatly outweighs them. It also
chalks out management plan with specific environmental management plan and social
management plan and also brings out cost issues related to it. For better execution of the
project it presents the consultation framework for participatory planning and also talks
about the capacity of institutions involved.
Chapter 8: This Chapter is a presentation of social development outcomes of the proposed
project and related issues. It showcases the benefits of having this project and how this
project can also benefit the marginalized sections of society. It suggests measures to extend
the benefit of the proposed activities.
22
Chapter 9: This is the final chapter concludes the inferences brought out from the
environmental and social analysis of the project activities in Anupshahr town. It also
highlights the conclusion based on the analysis which shows that the proposed project can
be categorized as low impact.
23
2 Project description
2.1 About the City
2.1.1 History
According to the Imperial Gazetteer of India, the founder of Anupshahr
was Bargujar Raja Anup Rai, and thus the date of foundation of present day Anupshahr was
between 1605 and 1628 (during the reign of the Moghul emperor Jahangir). Raja Anup Rai
saved Jahangir during a lion hunt, by intercepting and then helping to kill a lion that
attacked the emperor. Jahangir presented this area to Raja Anup Rai, and the city is named
after him. Anup Rai made a fort nearby.
During the period of King Tarasingh (the 8th generation from Raja Anup Singh) this area
progressed very much. At that time the area was known for Ayurvedic medicine and for
business by boats in northern India.
In 1857, during the first war of independence the town of Anupshahr was the scene of
incidents against British rule. One message of revolution was carried
from Aligarh toBulandshahr by Pandit Narayan Sharma on 10 May 1857.
The Gujjars of Dadri and Sikandrabad destroyed inspection bungalows, telegraph offices
and government buildings as they were symbols of foreign rule. Anupshahr is also known
“Choti Kashi”as it is situated at the river bank of Ganges.
2.1.2 Town at a Glance
Location
Anupshahr is a major town in distt. Bulandshahr UP. It is located 115 km away from Delhi,
95 km away from Noida, 75 km away from Greater Noida, 55 km away from Aligarh and 40
KM away from Bulandshahr.
Transport
There is no rail connectivity. To reach through rail one has to deboard at Dibai 22 km away
from the city.
24
This city is full of cultural and historical heritage. It is located on the bank of Holy River
Ganga, thousands of people take holy bath in River Ganga through Anupshahr Ganga
Ghat.In historical background Great Maharshi Dayananda Saraswati visited this place in 18th
century to raise awareness against various social evils present in the society at that time.
This city also have strong educational
infrastructure that's why it is also
known as "choti kashi".Anupshahr
has leading schools like "LDAV,
JAYPEE VIDYA MANDIR” and State
renowned "Durga Prasad Baljit Singh
PG College" and newly opened
"JAYPEE UNIVERSITY".
Two state highways are providing
smooth connectivity to the city to other parts of UP. Bridge over Ganga provides a quick
connectivity to the area from northern parts like Bandaun, Moradabad etc.
2.1.3 Existing Sewerage Facilities in City
At present there is no separate sewerage
system in the town, the municipal
wastewater generated in the town is
discharged into the open drains which are
tapped near the bank of river Ganga and
further transported to the STP’s.
The drainage system of the town is also
very poor; the storm water is transported
through the common open drains along with
domestic waste water. The condition worsens in the rainy season and general problem of
overflow of drains is encountered. The waste water finds its way to low lying areas and
creates unhygienic sanitary conditions.
Figure 1 Tapped Nala
Figure 2 Overflow of Nala falling into the river
25
2.1.4 Works Completed under Ganga Action Plan Phase - II (GAP-II)
3 towns namely Bijnore, Anupshahar and Chunar have been taken up under the GAP (Phase-
II) on the direction of Hon'ble Supreme Court of India. A total of 21 mldwaste water
discharging in the river Ganga is proposed to be intercepted, diverted and treated in these
towns. For this purpose 3 nos. STPs are proposed to be constructed.
A total of 17 schemes proposed for these towns, 10 schemes costing Rs. 12.74 crores have
been approved by Govt. of India, out of which works of 4 schemes have been completed
and an expenditure of Rs. 4.53 Crore has been incurred up to the end of December 2005.
A detail of Work done under GAP-II in Anupshahar is enclosed as Annexure1.
26
The existing location of STPs is marked in the plan shown below.
STP A-Capacity 0.805 MLD
STP B-Capacity 1.75 MLD
Figure 3Existing STPs location
27
28
2.2 Necessity of this project
Anupshahar town doesn’t have a sewerage network system. However, under Ganga Action
Plan-I, Nala tapping was done by intercepting the flow and diverting it into two nos. of
sewerage treatment Plants of 1.75 MLD and 0.805 MLD capacity respectively.
A proposal was issued by the Nagar Parishad on dated 02-01-2013 regarding sewerage
scheme of the town, which specifies that sewerage network has to be laid on the internal
roads has to be provided for the interconnections between the manholes used for tapping
nalas at the river bank so to avoid the overflow of waste water.
At present only the flow of Nalas is tapped and diverted to STP and treated water is
discharged into the River Ganga. However in the rainy seasons and the peak flow period
(Mela period) these 250mm sewer lines are collapsed and the overflow of the waste water
creates the unhygienic conditions for the people residing in the area.
Due to rapid urbanization and for better hygienic and sanitary conditions to improve living
standards sewerage networks along with related facilities are strongly required.
Also Anupshahr is the priority town as it lies on the bank of River Ganga and this river is the
sacred river for the Hindus. Pilgrims from many parts of the country in large quantity used
to visit this place for tasking holy dip in River Ganga, stay in the town and uses the facilities
of this town.
Figure 4STP-I, Zone-A, 0.805 MLD Figure 5STP-II, Zone-B, 1.75MLD
29
Therefore, there is a need of properly designing/constructing the sewer network and
appurtenant works in accordance with the current scenario.
2.3 Proposed City Sewerage Plan
The town is divided into two zones as zone-A and zone-B. The zoning is done in accordance
with the topography of the area. It is proposed that the wastewater generated from zone-A
will be directed towards the STP situated in zone-A with the existing capacity of 0.805 MLD
and similarly, the wastewater generated from zone-B will be directed towards STP in zone-B
with the existing capacity of 1.75 MLD.
The town possesses a tent shape profile as per the ground profile which helps the flow of
wastewater easily discharging into respective STPs in each zone.
The STP condition is fine as the year of construction of the STPs is 2005, the combined
capacity of the two existing STP’s equals to 2.55 MLD. This treatment capacity holds short
for the current discharge quantity and ultimately for the future discharge also. However no
extra land will be required for the construction of STP.On the basis of the discussion with
the Nagar Palika officers and staff, it was concluded that due to insufficient capacity of
existing treatment plants and pumping plants, there is a need of increasing the STPs
capacity.
However, the technology adopted for the treatment of waste water is MBBR Technology as
current i.e. Moving Bed Biofilm Reactor, but only the numbers of tanks are increased to
accommodate all the additional waste water which was flowing into the River Ganga directly
without any treatment from the STPs.
2.3.1 Forecasted wastewater generation scenario
The data considered for determination of sewer discharges over subsequent years is
mentioned below:
Per Capita Rate of Water Supply: 135 lpcd
Interception Factor: 0.8
30
The total quantity of waste water generated in different wards for future years is
summarized below:
Year 2013: 3.84 MLD
Year 2018:4.19 MLD
Year 2028:4.96MLD
Year 2033:5.39MLD
Year 2048:6.87MLD
Zone wise wastewater generation for projected years (i.e. 2018, 2028, 2033 and 2048) in
MLD
Zone-A:
Zone-A comprises of 12 wards of which some portion of 4 wards lies in Zone-B also. The
details of ward wise population for Zone-A for the year 2018, 2028, 2033 and 2048 is shown
in the tabular form:
Table 1 Zone-A, Wards & Population
Ward Nos. Area Name 2018 2028 2033 2048
3 Delhi Dwaar Anshik 1345 1578 1707 2140
10 Delhi Dwaar Anshik , Meera Anshik 2979 3523 3837 4939 12 Gadiyana Anshik , Mori gate Anshik 1705 2060 2263 2985 13 Jatiyana (Khatiyana), Meera anshik 1302 1530 1655 2076 14 Aahar Dwaar Anshik , Gadiyana
Anshik 1505 1797 1963 2535
16 Imli bazar , Ravtaan , Pusht Mandi, Gadiyana Anshik
1030 1218 1321 1664
18 Aahar Dwaar Anshik , Garhi 2008 2421 2659 3505 19 Parkotta , Aahar Dwaar Anshik 1186 1396 1512 1899
23A Bazar Kala , Bazar Delhi Dwaar , Purani Tehsil Anshik
781 947 1038 1348
24A Purani Tehsil 1659 2003 2200 2901 25A Kedar Shah 915 1083 1174 1480
20A Nagar Shaily , Manak Chowk Anshik 1253 1439 1540 1871 Total 17669 20995 22870 29342
Zone-B:
31
Zone-B comprises of 13 wards of which some portion of 4 wards lies in Zone-B also. The
details of ward wise population for Zone-A for the year 2018, 2028, 2033 and 2048 is shown
in the tabular form:
Table 2 Zone B-Wards & Population
Ward Nos.
Area Name 2018 2028 2033 2048
1 Delhi Dwar and Meera Anshik 1761 2010 2146 2594
2 Nehru Ganj and Delhi Dwaar Anshik 1086 1307 1430 1853
4 Delhi Dwaar 2297 2764 3035 3999
5 Nehru Ganj 3679 4408 4835 6367
6 Madaar Dwaar 2508 2972 3238 4171
7 Jama Masjid , Nehru Ganj Anshik 901 1091 1195 1551
8 Nehru Ganj Anshik 838 1028 1134 1499
9 Meera 1093 1265 1358 1660
11 Madaar Gate and Nehru Ganj anshik 830 1019 1124 1486
15 Maanak Chowk Anshik , Ganga Dwaar Anshik
1280 1443 1530 1807
17 Chhatta , Ganga Dwaar Anshik 882 1068 1171 1520
21 Pokhar , khidki , Ganga Dwaar Anshik 1682 1880 1986 2326
22 Pavitra Puri 1777 2028 2165 2616
20B Nagar Shaily , Manak Chowk Anshik 139 160 171 208
25B Kedar Shah 102 120 130 164
24B Purani Tehsil 184 223 244 322
23B Bazar Kala , Bazar Delhi Dwaar , Purani Tehsil anshik
87 105
115 150
Total 21126 24892 27008 34293
2.4 Proposed Sewerage Treatment Plant (MBBR Technology)
STPs are to be designed for ultimate design year capacity, but the phase wise operation will
be followed (i.e. first phase will be comprising of the construction of STP for first 10 years
capacity) year 2028. Further, on the same basis, phase wise construction and augmentation
in STP capacity will be taken up as and when needed.
The technology to be used in both the STPs will be MBBR (Moving Bed Biofilm Reactor)
which is very different from the WSP at present in operation at site. However, this
technology is most feasible for the small towns as this is cost effective&the capacity can be
easily upgraded in available land.
32
Design Parameters for STP
Parameter Range/Value Unit
pH 7 – 8
BOD5 at 20oC 220 mg.L
-1
COD 400 mg.L-1
TSS 350 mg.L-1
Faecal Coliforms 106 – 10
9 MPN/100ml
The proposed augmented capacities of both the STPs worked out are presented below in
the tabular form:
Table 3 STP Capacities in Year 2028 & 2048
Proposed Capacity
of STP for year
2028,MLD
Proposed Capacity
of STP for year
2048,MLD
Shortfall in the
Capacity of STP for
year2028,MLD
STP-A 2.26 3.54 1.50
STP-B 2.68 3.37 1.00
Total 4.94 6.90 2.50
2.5 Disposal of Treated Effluent
After treatment of the sewage in the STPs, The treated waste water will be carried by the
RCC pipe of 300 mm dia. having length of 650 m for Zone-A and 300 mm dia. having length
of 450 m for Zone-B, it is being utilized for irrigation purposes. The gravity flow has been
proposed for the supply of treated water to be used in the irrigation facilities.
The outlet pipes will off shoot from various spots to irrigate the fields and for afforestation.
The land available around the STP area is adequate enough for 100% utilization of treated
33
effluent. Besides above it is also proposed to use the treated effluent in the area proposed
for afforestation in the STP site and nearby. In the rainy season the treated effluent may
have to be discharged in to the river Ganga.
The total area to be irrigated in Zone A is 15 hectares approx. and in zone B it is 12 hectares
approx. The plan of utilizing the treated waste water for next 10 years is presented in Table
4 below.
However, the total length of network laid for the irrigation supply in Zone-A is 200m and for
Zone-B is 200m.
As per the public consultation conclusions with the people, it was observed that people will
use the treated effluent for irrigating their fields.
Govt. of India has made it desirable that at least 20 % of treated wastewater should be
raised in any form. In this case, in the absence of industries in the nearby vicinity, it is
proposed to utilize waste water for the horticulture purposes, gardening or other possible
uses to the maximum extent, if any.
It is proposed to utilize all treated wastewater for agriculture in all seasons except monsoon,
for meeting the requirement of agriculture, necessary channels and pumping, if required
shall be proposed in DPR.
The treated wastewater is very rich in terms of nutrients such as Nitrogen, Phosphorus.
Therefore, it shall be proposed to utilize it as a resource for agriculture.
34
35
2023
2028
Year
12
34
56
78
910
2.09
2.27
%10
1525
3050
6075
8090
100
1.67
1.81
Avail
able
Trea
ted W
ater
in M
LD0.1
670.2
510.4
180.5
010.8
351.0
881.3
601.4
511.6
321.8
14
Avail
able
Trea
ted W
ater
in Lt
s16
7080
2506
2041
7700
5012
4083
5400
1088
160
1360
200
1450
880
1632
240
1813
600
Area
to be
irrig
ated
, Sqm
1500
022
500
3750
045
000
7500
090
000
1125
0012
0000
1350
0015
0000
Wat
er Re
quire
d for
this
area
, Lts
7500
011
2500
1875
0022
5000
3750
0045
0000
5625
0060
0000
6750
0075
0000
Unit
Cost
INR
2.25
2.25
2.25
2.25
2.25
2.52.5
2.52.5
2.5
Dive
rted t
o Rive
r Gan
ga, L
ts92
080
1381
2023
0200
2762
4046
0400
6381
6079
7700
8508
8095
7240
1063
600
Reve
nue f
ro Sa
le of
Wat
er, IN
R/Da
y16
8750
2531
2542
1875
5062
5084
3750
1125
000
1406
250
1500
000
1687
500
1875
000
2.48
2.69
%10
1525
3050
6075
8090
100
1.99
2.15
Avail
able
Trea
ted W
ater
in M
LD0.1
990.2
980.4
970.5
960.9
941.2
901.6
131.7
211.9
362.1
51
Avail
able
Trea
ted W
ater
in Lt
s19
8720
2980
8049
6800
5961
6099
3600
1290
384
1612
980
1720
512
1935
576
2150
640
Area
to be
irrig
ated
, Sqm
1200
018
000
3000
036
000
6000
072
000
9000
096
000
1080
0012
0000
Wat
er Re
quire
d for
this
area
, Lts
6000
090
000
1500
0018
0000
3000
0036
0000
4500
0048
0000
5400
0060
0000
Unit
Cost
INR
2.25
2.25
2.25
2.25
2.25
2.52.5
2.52.5
2.5
Dive
rted t
o Rive
r Gan
ga, L
ts13
8720
2080
8034
6800
4161
6069
3600
9303
8411
6298
012
4051
213
9557
615
5064
0
Reve
nue f
ro Sa
le of
Wat
er, IN
R/Da
y13
5000
2025
0033
7500
4050
0067
5000
9000
0011
2500
012
0000
013
5000
015
0000
0
2023
2028
Zone
-B
Zone
-A
Construction
Methodolo
gy
of
Figure 6 Plan of treated waste water used for irrigation purposes
Table 4 Plan for 5 & 10 Years of treated water usage
36
STP
1. Loss of land use options
The construction of a wastewater treatment plant will involve building large embankment
structures on what is a green field site. This will result in a loss of the options for alternative
land use and thus represents an irreversible commitment of land resources.
Although the loss of optional uses for the land in the future is considered to be a negative
impact, in this case the land is marginal in terms of alternative agricultural or residential use
and the impact is not considered significant.
2. Earth material sourcing
Earth materials needed for construction (e.g. marl, sand) are normally obtained from quarry
and mining operations. Conscious or unwitting purchase of these materials from unlicensed
operations indirectly supports, encourages and promotes environmental degradation at the
illegal quarry sites and causes medium to long-term negative impacts at source.
Mitigation:
Earth materials must be obtained from officially licensed and approved quarries and copies
of the relevant licenses made available for inspection at the site by the Contractor.
3. Materials transportation
The various materials required for pond and building construction (e.g. steel, blocks,
lumber, marl, etc.) will be obtained from sources elsewhere and transported to the site.
Transportation of these materials, typically in over-laden and sometimes uncovered trucks,
usually results in undue road wear-and-tear. In the case of fine earth materials, dusting and
spillages occur on major roadways between source and site. Dusting degrades local air
quality and material spillages worsen driving conditions and increase the risk of road
accidents. These occurrences represent indirect, short-term, reversible, negative impacts on
public health and safety.
37
Mitigation:
All fine earth materials must be enclosed during transportation to the site to prevent
spillage and dusting. Trucks used for that purpose should be fitted with tailgates that close
properly and with tarpaulins to cover the materials. The cleanup of spilled earth and
construction material on the main roads should be the responsibility of the Contractor and
should be done in a timely manner (say within 2 hours) so as not to inconvenience or
endanger other road users. These requirements should be included as clauses within the
contracts made with relevant sub-contractors.
The transportation of lubricants and fuel to the construction site should only be done in the
appropriate vehicles and containers, i.e. fuel tankers and sealed drums. As far as possible,
transport of construction materials should be scheduled for off-peak traffic hours. This will
reduce the risk of traffic congestion and of road accidents on the access roads to the site.
4. Materials storage
The improper siting of stockpiles and storage of sand, gravel, cement, etc., at the
construction site could lead to fine materials being washed away, during heavy rainfall
events. This would not only represent a waste of materials but would also contribute to
turbidity and sedimentation with consequent negative impacts on water quality.
Refueling and maintenance of large vehicles and earth moving equipment will take place at
the construction site and therefore fuel and lubricants will have to be stored on the site.
This will create the opportunity for accidental spills of hydrocarbons and contaminants
could be washed into the river.
Mitigation:
The stockpiling of construction materials should be properly managed and controlled. Fine-
grained materials (sand, marl, etc.) should be stockpiled away from surface drainage
channels and features.
Low berms should be placed around the piles and/or tarpaulin used to cover open piles of
stored materials to prevent them from being washed away during rainfall. Safe storage
38
areas should be identified and retaining structures put in place prior to the arrival and
placement of material. Hazardous chemicals (e.g. fuels) should be properly stored in
appropriate containers and these should be safely locked away. Conspicuous warning signs
(e.g. ‘No Smoking’) should also be posted around hazardous waste storage and handling
facilities.
5. Modification of surface drainage
Mitigation:
The appropriate design of storm water drainage system
6. Construction waste disposal
Solid waste generated during site preparation and construction work would include cut
vegetation and typical construction waste (e.g. wasted concrete, steel, wooden scaffolding
and forms, bags, waste earth materials, etc.). This waste would negatively impact the site
and surrounding environment if not properly managed and disposed of at an approved
dumpsite. Cleared vegetation burnt onsite would generate smoke, possibly impacting
negatively on ambient air quality and human health. Vegetation and solid waste, if allowed
to accumulate in drainage ways, could cause localized pooling and flooding. Pooling of
water, in turn, would create conditions conducive to the breeding ofnuisance and health-
threatening pests such as mosquitoes. Poor construction waste management constitutes a
short-term negative impact.
Mitigation:
A site waste management plan should be prepared by the contractor prior to
commencement of construction works. This should include designation of appropriate
waste storage areas, collection and removal schedule, identification of approved disposal
site*, and a system for supervision and monitoring. Preparation and implementation of the
plan must be made the responsibility of the building contractor with the system being
monitored independently.
39
Vegetation and combustible waste must not be burned on the site. Reusable inorganic
waste (e.g. excavated sand) should be stockpiled away from drainage features and used for
in filling where necessary. Unusable construction waste, such as damaged pipes, formwork
and other construction material, must be disposed of at a dumpsite.
7. Sewage and litter management
Inadequate provision of toilets for use by workers can lead to ad hoc defecation in secluded
areas on the site, thus creating unsanitary conditions and sources of fly infestation.
Improper disposal of food cartons and other domestic forms of construction camp garbage
could lead to littering of the site and pollution of adjacent water body.
Mitigation:
Proper solid waste receptacles and storage containers should be provided, particularly for
the disposal of lunch and drink boxes so as to prevent littering of the site.
Arrangements should be made for the regular collection of litter and for its disposal.
8. Replanting and landscaping
Landscaping and replanting of trees will be needed to recreate some semblance of the
original appearance and condition of the site and to provide some aesthetic quality. No
details of landscaping plans or planting material are available at this stage but the plant
species selected for replanting will in large part determine which types of birds, butterflies,
and other fauna, if any, inhabit the area surrounding the ponds after their construction. In
addition to enhancing the aesthetic appeal of the project site, landscaping provides the
means for partially restoring the site's natural elements and ecological habitats. It is
therefore a significant mitigation activity with a positive impact.
The landscaping plan should seek to avoid the use of non-native and potentially invasive
species. It should include low-maintenance local species and the types of trees and shrubs
used for feeding by local bird species. The landscape design should seek to encourage bird
life, especially for the endemics, and maximize shade.
40
9. Employment/Income generation
Several categories will be required during the construction phase. This will include skilled
and unskilled labourers, engineers, and a small number of other professionals. These levels
of short-term employment would have a positive impact on the local economy and on
regional unemployment.
2.5.1.1 Land Requirement in Zone A and Zone B
The land required for the expansion in the capacity of both the existing STPs will be the only
requirement but it will be limiting to the existing campus of the STPs. No additional
requirement of land will be needed other than the existing campuses of STPs and MPS in
zone A and zone B. The new SPSs in zone A will be requiring same portion of land area but
this will be acquired from the existing MPS campus.
Considering the land requirement of 0.3 Ha/mld for the STP, the land requirement is
calculated. The following land requirement is to be fulfilled to accommodate all the
components of the project for the ultimate year 2048 is presented below:
S.no. Particulars Land available Nature of land Status
1 STP zone A 1.00 ha fields Available with
EA
2 STP zone B 0.40 ha barren Available with
EA
3 MPS- A 0.05 ha barren Available with
EA
4 MPS-B 0.05 ha barren Available with
EA
The land available with the local authorities in Anupshahr town for the STP purposes is
confined to the boundaries of the existing STPs; no additional land will be provided other
than the land available in the STP campus.
41
The ULB has cleared this with the issue of letter in this regard and the same is attached as
the Annexure 15 to this report.
No land has to be purchased for the construction of new SPS of larger capacity in zone-A &B;
this will be located very close to the existing SPS.
2.5.1.2 Land Acquisition
The land required for STPs and MPSs is already in possession of EA, there for acquisition of
land is not required to be done. There is no encroachment in the available land for
construction of STPs and MPSs at Anupshahar.
2.5.1.3 Ramsar Site
Upper Ganga River (Brijghat to Narora Stretch). Uttar Pradesh; 26,590 ha; 28°33'N 078°12'E.
A shallow river stretch of the great Ganges with intermittent small stretches of deep-water
pools and reservoirs upstream from barrages. The river provides habitat for IUCN Red listed
Ganges River Dolphin, Gharial, Crocodile, 6 species of turtles, otters, 82 species of fish and
more than hundred species of birds. Major plant species, some of which have high medicinal
values, include Dalbergia sissoo, Saraca indica, Eucalyptus globulus, Ficus bengalensis,
Dendrocalamus strictus, Tectona grandis, Azadirachta indica and aquatic Eichhorina. This
river stretch has high Hindu religious importance for thousands of pilgrims and is used for
cremation and holy baths for spiritual purification. Major threats are sewage discharge,
agricultural runoff, and intensive fishing. Conservation activities carried out are plantation
to prevent bank erosion, training on organic farming, and lobbying to ban commercial
fishing. Ramsar site no. 1574. Most recent RIS information: 2005.
Ganga stretch at Brijghat to Narora is Ramsar site, the divisional director, deptt. Of forest
vide his letter no.439/14 dated Bulandshahr,july 26,2014 intimated that area in above said
stretch 1500 m on both banks of river Ganga is Ramsar site. But, at present, management
plan is under preparation by department of forest.
42
2.5.1.4 Sewerage Network
The sewage network is designed to be laid down in the town considering the peak
factor of 2.5; the total estimated length of sewage network is likely to be 60
kms(approx.). The length of pipes posing different diameters is presented in the
tabular form.
Table 5 Length of Sewerage Network for subsequent dia.
Diameter(mm) Length (in Meter)
Zone A Zone B
150 11604 8603
200 15841 17000
250 799 1216
300 417 723
350 203 -
400 661 -
450 327 427
500 263 -
600 262 530
Total Length 30377(30.38 kms) 28499(28.49 kms)
43
The largest pipe dia. used in the design consideration is 600 mm and the minimum pipe dia.
is 150 mm. The network drawing of sewerage scheme along with the discharge calculations
and the design sheets are attached herewith:
2.5.2 Manhole
The channels in manholes at junctions and bends shall be smooth with gradual transitions to
avoid turbulence and deposition of solids. Manholes are usually constructed directly over
the line of the sewer. They are circular, rectangular or square in shape. Manholes should be
of such size that will allow necessary cleaning and inspection. The circular manholes have
been proposed on all sewer lines. Poly elastomeric M S flats footrest has been provided for
entry into manholes.
Manhole Description Manhole Size Type of Manhole
For depth below 0.9 m and for outgoing pipe
dia. up to 300 mm
900 X 800mm R-Type Manhole
For depth up to 1.65 m and for outgoing pipe
dia. up to 500 mm
900 mm dia. A-Type Manhole
For depth up to 2.30 m and for outgoing pipe
dia. up to 600 mm
1200 mm dia. B-Type Manhole
For depth up to 9.0 m and for outgoing pipe
dia. up to 900 mm
1500 mm dia. C-Type Manhole
For outgoing pipe dia. of 1000 mm to 1400
mm
1800 mm dia. D-Type Manhole
For outgoing pipe dia. of 1600 mm to 1800
mm
2400 mm dia. E-Type Manhole
Scarper Manhole (outgoing pipe dia. of 450
mm to 900 mm)
1500 X1500 mm G-Type Manhole
Scarper Manhole (outgoing pipe dia. of 1000
mm to 1400 mm)
1800 X1500 mm H-Type Manhole
Scarper Manhole (outgoing pipe dia. of 1600
mm to 1800 mm)
2400 X1800 mm I-Type Manhole
44
2.5.3 House Connection Chamber
House connection: Laterals are proposed along the roads to connect sewage from individual
houses and it is connected to branch sewers. House connections for whole project are
proposed to be executed by or before 2018 end in phase wise manner
2.5.4 Construction Methodology
Construction of Sewers and its appurtenance work, Sewage Pumping Stations and sewage
treatment plant shall be carried out using mechanical tools and equipment’s to achieve
maximum output. Use of prefabricated materials is encouraged to improve the quality of
works, simultaneously improving efficiency of construction schedule.
Pipe preparation and handling
All pipe and fittings shall be inspected prior to lowering into trench to insure no cracked,
broken, or otherwise defective materials are being used. The Contractor shall clean ends of
pipe thoroughly and remove foreign matter and dirt from inside of pipe and keep clean
during and after laying. Proper implements, tools, and facilities shall be used for the safe
and proper protection of the WORK. Pipe shall be lowered into the trench in such a manner
as to avoid any physical damage to the pipe. Pipe shall not be dropped or dumped into
trenches under any circumstances
Sewer pipe laying
Laying of sewer pipe shall be accomplished to line and grade in the trench only after it has
been dewatered and the trench has been prepared in accordance with specifications
outlined in DPR. Mud, silt, gravel and other foreign material shall be kept out of the pipe
and off the jointing surface. All pipe laid shall be retained in position so as to maintain
alignment and joint closure until sufficient backfill has been completed to adequately hold
the pipe in place. All pipes shall be laid to conform to the line and grade shown on the plans.
Variance from established line and grade, at any point along the length of the pipe, shall not
be greater than one-thirty second of an inch per inch of pipe diameter and not to exceed
one-half (½) inch, provided that any such variation does not result in a level or reverse
sloping invert.
45
Trench preparation and pipe bedding
Trench excavation, dewatering, bedding
Material, backfill, compaction, fill and grading
Placement of pipe bedding material
Plugs and connections
Plugs for pipe branches, stubs or other open ends which are not to be immediately
connected shall be made of an approved material and shall be secured in place with a joint
comparable to the main line joint.
2.5.5 Muck and Debris Management
Instead of disposing top soil to low lying areas:
Top soil may be used for agricultural purpose or development of city parks.
Soil and debris may be managed for planned land filling and landscaping;
Debris may be suitably stored to filling back the excavated areas after placing the
trunk sewer lines.
2.5.6 U.P.PCB CONSENT
Application for consent to establish the STP has already online submitted to the competent
authority U.P.Pollution control board, Lucknow on prescribed form with fee and all required
annexures vide letter no. 882/W-4/43 and 883 /W-4/44 dated October 29th and, 2014. The
follow-up joint inspection with UPPCB officials has also concluded. Annexure attached as
Annexure 12& 13.
2.5.7 IMPLEMENTATION SCHEDULE
It is anticipated that entire work will be completed within 42 months from the date
of approval and allotment of funds.
2.5.8 Financial Cost Summary The financial cost summary as per the final DPR is presented below:
46
Table 7 Form J for the Sewerage Scheme
FORM-'J'
c Description Percentage
Charges
Total Cost
of Works
GOI Share 70%
GOUP Share 30%
1 2 3 4 5 6
1 Base cost of work 6587.988 4611.592 1976.396
2 Centage charges:
2.1 Project Preparation Charges 4 263.520 184.464 79.056
2.2 Project Supervision Charges 4 263.520 184.464 79.056
A Sub Total (1+2) 7115.027 4980.519 2134.508
3 Items on which no centage is admissible:
3.1 ESAMP 70.490 49.343 21.147
3.2 Communication and Public Outreach 20.000 14.000 6.000
3.3 GAAP 10.000 7.000 3.000
3.4 Power Connection 23.020 16.114 6.906
3.5 Operation and Maintenance cost for 5 years 340.000 238.000 102.000
B Sub Total (3) 463.510 324.457 139.053
C Project Cost (A+B) 7578.537 5304.976 2273.561
4 Component of works to be borne by GOUP
4.1 T&P for Operation and Maintenance 31.000 31.000
4.2 Cost of land 170.00 170.00
4.3 Contingencies on Rs. 6618.99 lac 2 132.380 132.380
4.4 Labour Cess on Rs 6618.99 lac 1 66.190 66.190
4.5 Centage @ (12.5-8) on Rs 6618.99 lac 4.5 297.855 297.855
D Sub Total (4) 697.424 697.424
Total cost of works (C+D) 8275.961 5304.976 2970.985
Say Rs. 8275.96 Lac
3 Approach and Methodology
As per Environmental and Social Management Frame work (NGRBA, 2011), the river
pollution mitigation projects under the NGRBP is anticipated to encounter a variety of
environmental and social problems. Hence, an environmental and social assessment with
corresponding management plans for the proposed project of sewerage works in Anupshahr
has been conducted using the following methodology:
Figure 7 Flowchart describing the steps adopted for Project Impact Assessment
A. Baseline monitoring of environmental component
In order to get an idea about the existing state of the environment, various
environmental attributes such as meteorology, air quality, water quality, soil quality,
noise level, ecology and socio-economic environment have been
studied/monitored.
48
B. Secondary Data analysis (Identify Information/Data Requirements and their
Sources): All the available information and data (quantitative, qualitative) regarding
the proposed project was collected mainly from the Detailed Project Report (DPR),
consultation with stake-holders. Through this secondary information a brief
description and analysis of the sub-project activities along with baseline
environmental profile of the project influence was established. Based on initial
understanding, the list of required information was drafted before conducting the
field survey.
C. Defining the project area and carrying out scoping in the field: Team undertook the
field survey and transect walk of the town to develop the understanding of the
proposed project. Field visits helped to understand the local knowledge and were
valuable in finding alternatives that help avoid or at least reduce the magnitude and
severity of adverse impacts.
D. Survey of the host population: With the help of questionnaires, local people were
interviewed in groups. A wide range of potentially affected people were interviewed
in town including street vendors, residents of households, residents of temporary
settlements, shop keepers, hospital patients, hospital staff, etc. Both men and
women were interviewed from different sections of the society. Team undertook
three field visits to carry out the survey and understand the ground situation. The
interviewees were asked about their awareness of the project, their response to it
and the project is affecting them (during construction phase) and how it will affect
them (after completion phase). Also they were asked about the mitigation plans they
have adopted or are planning to adopt, suggestions for improvement and any public
grievances. Surveys were conducted along the path of construction site. Minutes of
meeting of stake holder consultation is enclosed with ESAMP report.
E. Discussion with the key stakeholders: Most of the important key stakeholders were
interacted during informal and formal discussions with them. All the associated
government departments were visited to collect the relevant data and their
feedback on the project activities.
F. Conduct Screening: Screening is undertaken in the very beginning stages of project
development. The purpose of screening is to screen out "no significant impacts"
49
from those with significant impacts and get a broad picture of the nature, scale and
magnitude of the issues. Team conducted screening process using the screening
checklist format provided in ESMF report of NGRBA, which is described in
subsequent section.
G. Identify and assess the impacts : Based on the analysis of the data gathered from
field survey, stakeholder interaction/ consultation and secondary sources, issues
related to the environmental and social sectors were been identified. The impacts so
identified were compared with the existing baseline environmental and social
condition of the study region. The impacts of the activities are mostly positive with
few adverse impacts.
H. Develop a mitigation plan: Based on the environmental and social issues identified,
and recommend any measures needed to prevent, minimize, mitigate, or
compensate for adverse impacts and improve environmental performance. The
mitigation plans is suggested in all three stages: designing phase, construction phase
and, operation and maintenance phase.
3.1 Screening Activity for Project Impact Assessment
Screening activity is undertaken in the very beginning stages of project development. The
purpose of screening is to screen out "no significant impacts" from those with significant
impacts and get a broad picture of the nature, scale and magnitude of the issues. Based on
the secondary data analysis, field assessments and stakeholder interaction/ consultation,
the screening activity was conducted as per the guidelines provided in Environmental and
Social Management Framework of NGRBA (NGRBA, 2011) as given in the Table below:-
Table 6Screening Activity
Environment and Social information for screening
Project Title: Sewerage Scheme of Anupshahr town Implementing agency: U.P. Jal Nigam Project cost: 82.75 Crores Project components:
a). Sewer System (60 km long) b). Main Pumping Station (2 Nos.) c). Sewerage treatment plant(2 STPs)
Project location (Area/ district): Anupshahr Town Distt. Bulandshar, Uttar Pradesh
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
1. Is the project in an eco-sensitive area or adjoining an eco-sensitive area? (Yes/No) If Yes, Which is the area? Elaborate impact accordingly.
Yes
There is no eco-sensitive zone in and around Anupshahr protected under wildlife protection act 1972. However the Ganga river stretch between Brijghat to Narora Barrage falls under RAMSAR site. Anupshahr is situated on the bank of river Ganga within this stretch. The proposed sewerage project ensures 50% reuse of treated sewage and over a period of time targeted to reuse of 100% of treated sewage.
2. Will the project create significant/limited/no social impacts?
Land acquisition resulting in loss of No impact Sewer line would be laid on the public Refer Section 2.4
51
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
income from agricultural land, plantation or other existing land-use.
roads. So there is no loss of income from agricultural land.
For the construction of MPS in both the zones land is available with nagar Palika
STP in Zone A and Zone B will be constructed in the old campus.
Loss of livelihood No
Loss of livelihood would not take place since mobile vendors can shift their position and only minor/temporary disruption in terms of access to shops would occur
Consultation with stakeholders)
Land acquisition resulting in Relocation of households.
No social impacts
Land acquisition is not required. Relocation of households is not required.
Google image showing the location of STP components is enclosed as DPR
Any reduction of access to traditional and river dependent communities (to river and areas where they earn for their primary or substantial livelihood).
No social impacts
No access problem to river Field visits and consultations with the shop keepers, expert opinions
Any displacement or adverse impact on tribal Settlement.
No social impacts
There are no tribal settlements in the project area.
Field visits and consultations with the shop keepers.
Will the project create significant / limited / no environmental impacts during the construction stage? (Significant / limited / no impacts)
Clearance of vegetation/ tree cover
No environmental impacts
Sewer line will be laid on existing public roads therefore no cutting of trees will be done.
Topographical map showing roads and other features is enclosed as Annexure 11
52
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
Direct discharge of construction runoff, improper storage and disposal of excavation spoils, wastes and other construction materials adversely affecting water quality and flow regimes.
Limited
Possibility of temporary flushing away of unmanaged spoils and construction wastes during rainfall to river Ganga via storm water drains. If not appropriately managed, there may be potential for temporarily affecting storm water flows by obstruction to flows and blockage of drains, especially during rainfall.
Interaction with UP Jal Nigam and other Government officials and consultation with local residents of town
Flooding of adjacent areas no
As per departmental orders excavation of
trenches for laying of sewers in not taken up
during rains. However, in case of urgency if
sewer is needed to be laid during monsoons,
stockpiled areas to be bordered by berms. As
such there should be no flooding of adjacent
areas.
U.P. Jal Nigam circular dated
17/6/2013.
Improper storage and handling of substances leading to contamination of soil and water
no
The storage of construction related material
will not cause any contamination since these
materials would typically include: Concrete,
pipes, masonry, HDPE pipes.
Image showing a typical sewage construction area is enclosed as Annexure 6
Elevated noise and dust emission Limited
For sewage works, construction is likely to increase dust and noise levels temporarily. Provided that construction works near schools and colleges are carried out during vacations and works near hospitals are completed on priority basis
Consultation with local residents, and interaction with nagar palika and other Government officials
53
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
(inshorter time period with alternate provision of traffic, accessibility of exit/entry gates etc.), the impacts may be limited
Disruption to traffic movements Limited
Sewer construction leads to the temporary tearing up of roads and increase in large construction vehicles, which might impair traffic movement, especially in the narrower roads
Damage to existing infrastructure, public utilities, amenities etc.
Limited
If not appropriately Managed, there may be potential for temporarily affecting the existing public utilities like water supply, telephone, electricity cables etc. Records and layout plans of existing underground utilities and cable networks (like telephone, electricity water etc.) were unavailable.
Interaction with nagar palika and other Government officials
Failure to restore temporary construction sites
Limited
Although temporary, concerns regarding failure to restore construction sites including failure to close and appropriately fence off open pits were cited as safety concerns especially for children.
Field visits and interaction with Nagar Palika and other Government officials and consultation with local residents.
Possible conflicts with and/or disruption Limited For the laying of sewer works, there will Consultation with local
54
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
to local community be temporary disruption to the local community in terms of access to roads (narrow roads), shops and residences. Conflicts/disruption to local community was inferred as limited based on survey responses which indicated the community’s ability to adapt to temporary disruptions, and their overall preference for the project.
people.
Health risks due to unhygienic conditions at workers camps
Limited
However there might be small camps within which, if hygienic conditions are not maintained, there may be temporary impacts
Safety hazards during construction Limited
For safety precautions such as fencing-off construction areas, sign posts etc. were observed. If not appropriately managed, there may be potential for temporary hazards such as injuries and damage to property during the construction phase.
Consultation with local residents of town and interaction with Nagar palika and other Government officials
Will the project create significant / limited / no environmental impacts during the operational stage? (Significant / limited / no impacts)
Flooding of adjacent areas Limited
Due to the construction of sewer lines, raw sewage that currently flows into the
55
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
river and/or overflows into the streets will now be routed to the STP. This will prevent flooding of adjacent areas. However, accidental leakages during the operational stage will lead to flooding. Additionally, overloading and blockage of sewage lines will also lead to backlogging of sewers and flooding of branch sewers.
Impacts to water quality due to effluent discharge
No impacts There will be a significant improvement in water quality due to effluent discharge being treated.
Sewage flow quality values before and after existing STP
Gas emissions No impacts
There will be reduction in gas emissions from open sewage drains since the proposed sewage networks will be underground.
Safety hazards No impacts
There will be minimum safety hazards since the pipes will be underground.
Do projects of this nature / type require prior environmental clearance either from the MOEF or from a relevant state Government department? (MOEF/ relevant State Government department/ No clearance at all)
No clearance at all
Project such as these have an overall positive impact for the environment and society. Hence no clearance would be required under the Environmental Impact Assessment Notification, 2006.
Does the project involve any prior No As the project is in urban provinces and
56
Screening Criteria
Assessment of category
(High/low) Explanatory note for categorization Evidence and references
clearance from the MOEF or State Forest department for either the conversion of forest land or for tree- cutting? (Yes/ No).If yes, which?
does not cover any forested area (Protected nor reserved forest area), hence no prior clearance is required from relevant authorities (MoEF and State Forest departments) under the Forest (Conservation) Act,1980.
3.2 Conclusion of Screening Activity
In order to facilitate effective management and mitigation of the any impacts arising from
the proposed projects, the Environmental and Social Management Framework of NRGBA
(Section # 4 of ESMF report, NGRBA 2011) has grouped the pollution abatement projects/
investments into the following two categories high and low
• High: Mainly include the sub-projects which are likely to have adverse impact on the
environmental and social aspects of the project influence area (including land acquisition).
This category projects will also include mandatory environmental clearance as per the EIA
notification.
• Low: Projects which are likely to cause minimal or no adverse environmental impacts
on human populations.
Based on the screening activity and the categorization of potential sub-projects of the
NGRBP, the present project of Sewerage work in Anupshahr town falls under High impact
category being located in Ramser Area, which however does not have any private land
acquisition. In view of the above, these projects would require preparation of an
Environmental and Social Assessment, as part of the DPR, and implementation of Generic
Safeguard Management Plan (SMP), relevant to the project.
Although there would not be any permanent negative or adverse environmental impacts,
but will have temporary impacts like traffic blockages, dust, noise, safety hazards for
pedestrians, possible damage to private property, possible interruption in commercial
activity, and accidental breakage of other public infrastructure such as water pipes. These
temporary impacts can be mitigated with appropriate mitigation plans. However, the large
environmental benefit of the project greatly outweighs the temporary inconveniences.
58
4 Regulations and Legal Framework
4.1 Applicable Laws and Regulations – Environmental
The following laws and regulations are applicable to the environmental and social aspects of
the investments implemented under the programme:
• Policy and Regulatory Framework of Government of India (GoI)
• Environmental Policy and Regulations of the respective State Governments
• Legislations applicable to construction activities
4.1.1 Legal Framework of Government of India
The Government of India has laid out various policy guidelines, acts and regulations
pertaining to environment. The Environment (Protection) Act, 1986 is umbrella legislation for
the protection of environment. As per this Act, the responsibility to administer the legislation
has been jointly entrusted to the Ministry of Environment and Forests (MoEF) and the
Central Pollution Control Board (CPCB)/ State Pollution Control Boards (SPCBs).
It is worthwhile to mention here that as a matter of prevalent practice once the project is
approved by the G.O.I no further consent of SPCB is obtained for establishing the STP.
However, SPCB regularly monitors the effluent parameters during O &M stage to ensure that
the discharged effluent is as per prescribed standards. However, as desired by NMCG, action
to obtain NOC from SPCB for establishing STP has been initiated. The regional officer UP
Pollution Control Board Shivpuri Bulandshahar has forwarded the case of issuing NOC by UP
Pollution Control Board to the Chief Environmental Officer UPPCB Lucknow after the UP Jal
Nigam submitted the required NOC fees & the desired application to UPPCB Bulandshahar
59
4.1.2 Key Environmental Laws and Regulations
The key environmental laws and regulations as relevant to the projects under the NGRBP are
given in Table below. The key environmental regulations can also be accessed at
www.moef.nic.in/rules-and-regulations.
Table 7 Key Environmental Laws & Regulations
S.No Act / Rules Purpose Applicable
Yes/ No Reason for
Applicability Authority
1. Environment Protection Act-1986
To protect and Improve overall environment.
Yes As all environmental notifications, rules and schedules are issued under this act.
MoEF, Gol, DoE, State Gov. CPCB, SPCB
2. Environmental Impact Assessment Notification 14th Sep-2006
To provide environmental clearance to new development activities following environmental impact assessment
No This notification is applicable only for Solid waste Treatment facility investments
MoEF, EIAA
3. Municipal Wastes(Management and Handling) Rules, 2000
To manage the collection, transportation, segregation, treatment, and disposal of municipal solid wastes
Yes This notification is applicable only for Municipal Solid waste Treatment facility investments
MoEF, EIAA, CPCB, SPCBs
4. The Land Acquisition Act 1894 (As amended in 1985)
Set out rule for acquisition. of land by government
Yes This act will be applicable to as there will be acquisition of land for investments
Revenue Department State Government
5. The Forest (Conservation) Act. 1980
To check deforestation by restricting conversion of forested areas into non forested areas
Yes Applicable if there is diversion of forest land for non-forest activities i.e. forest land if required for any of the investments.
Forest Department, State Government and Ministry of Environment and Forests,
60
S.No Act / Rules Purpose Applicable
Yes/ No Reason for
Applicability Authority
Government of India
6. Wild Life Protection Act 1972
To protect wildlife through certain of National Parks and Sanctuaries
No Not applicable since no such projected area is within 15km radius of project site
Chief Conservator Wildlife, Wildlife Wing, State Forest Department and Ministry of Environment and Forests, Government of India
7. Air (Prevention and Control of Pollution) Act, 1981
To control air pollution by controlling emission of air pollutants as per the prescribed Standards.
Yes This act will be applicable during construction.
SPCBs
8. Water Prevention and Control of Pollution) Act1974
To control water pollution by controlling discharge of pollutants as per the prescribed standards.
Yes This act will be applicable during construction. This act will be further applicable for obtaining consent to establish and consent to operate of the proposed modification of STPs.
SPCBs
9. The Noise Pollution (Regulation and Control) Rules, 2000
The standards for noise for day and night have been promulgated by the MoEF for various land uses.
Yes This act will be applicable for all construction equipment deployed at worksite.
SPCBs
10. Central Motor Vehicle Act 1988
To check vehicular air and noise pollution.
Yes This rule will be applicable to vehicles deployed for construction activities and construction Machinery.
Motor Vehicle Department
61
4.2 Applicable Laws and Regulations - Social
All strategic interventions on human development, spread across all social issues, need
directives of policies and legal support to operationalize the appropriate actions. These
policies and legislations help to overcome the constraints and support administrator,
implementer, community and individual in delivery of justice. This section includes the
National policies and Acts as detailed under:
National Policies and Acts
A. National Tribal Policy, 2006
B. National Resettlement and Rehabilitation Policy, 2007
C. Land (Acquisition) Act 1894 (as amended)
D. Forest Rights Act, 2006
E. The right to fair compensation and transparency in land acquisition,
rehabilitation and resettlement act, 2013
4.2.1 National Policies and Acts
The National Tribal Policy (2006)
The Policy has the following objectives:
Regulatory Protection
Providing an environment conducive to the preservation of traditional and customary
systems and regime of rights and concessions enjoyed by different ST communities,
and reconciliation of modes of socio-economic development with these.
Preventing alienation of land owned by STs and restoring possession of wrongfully
alienated lands.
62
Protection and vesting of rights of STs on forestlands and other forest rights including
ownership over minor forest produce (MFP), minerals and water bodies through
appropriate legislations and conversion of all forest villages into revenue villages.
Providing a legislative frame for rehabilitation and resettlement in order to minimize
displacement, ensure that affected persons are partners in the growth in the zone of
influence, provide for compensation of social and opportunity cost in addition to
market value of the land and rights over common property (NPV).
Empowerment of tribal communities to promote self-governance and self-rule as per
the provisions and spirit of the Panchayats (Extension to the Scheduled Areas) Act,
1996.
Protection of political rights to ensure greater and active participation of tribal
peoples in political bodies at all levels.
However, This act is not applicable for this project.
4.2.2 The right to fair compensation and transparency in land acquisition, rehabilitation
and resettlement act, 2013
An Act to ensure, in consultation with institutions of local self-government and Gram
Sabhas established under the Constitution, a humane, participative, informed and
transparent process for land acquisition for industrialization, development of
essential infrastructural facilities and urbanization with the least disturbance to the
owners of the land and other affected families and provide just and fair
compensation to the affected families whose land has been acquired or proposed to
be acquired or are affected by such acquisition and make adequate provisions for
such affected persons for their rehabilitation and resettlement and for ensuring that
the cumulative outcome of compulsory acquisition should be that affected persons
become partners in development leading to an improvement in their post-acquisition
social and economic status and for matters connected therewith or incidental
thereto.
63
Right to fair compensation and transparency in Land Acquisition, Resettlement
and Rehabilitation Act, 2013 (Not Applicable):
4.2.3 Forest Rights Act 2006
The Act basically does two things:
• Grants legal recognition to the rights of traditional forest dwelling communities,
partially correcting the injustice caused by the forest laws.
• Makes a beginning towards giving communities and the public a voice in forest and
wildlife conservation.
This act is not applicable for this project.
Comparative analysis of RFCTLAR&R, 2013 and World Bank OP 4.12.
Serial
No.
Topics/Issues/Are
as
World Bank OP4.12 RFCTLAR&R, 2013
1 Application of LA Direct economic and social
impacts that both result
from Bank-assisted
investment projects.
Applies to all components
of the project that result in
involuntary resettlement,
regardless of the source of
financing.
Section 2 Applicable to
projects where government
acquires land for its own
use, hold and control,
including PSU and for
public purpose; for PPP
where ownership of land
continues to vest with govt;
private companies where
80% of land owners1 have
given consent or 70% in
case of PPP.
Principle of
avoidance
Involuntary resettlement
should be avoided where
feasible, or minimized,
exploring all viable
alternative project design
Alternatives to be
considered as Act in chapter
II, point # 4 (d) says "extent
of land propsoed for
acquisition is the absolute
bare minimum needed for
the project; and (e ) says
1 Land Owner – whose land and immovable property acquired and land assigned by state or central govt under
any scheme (Section 3 c (i) and (v))
64
land acquisition at an
alternate palce has been
considered and found not
feasible.
Linkages with
other projects
No such provision
2. Application of
R&R
Same as above In addition to the above,
Section 2(3) land purchased
by private company as
prescribed by Govt. or
when part acquired by govt
3. Affected area Involuntary take of land
resulting in loss of shelter,
loss of assets or access to
assets, loss of income
sources or means of
livelihood
Section3(b): Area notified
for ‘acquisition’
4. Family
All adversely affected
people whether have formal
legal rights or do not have
formal legal rights on land
Section 3(m) includes
person, his and her spouse,
minor children, minor
brothers and sisters
dependent.
Widows, divorcees,
abandoned women will be
considered as separate
family.
5. Affected family for
eligibility
Section 3 (a): whose land
and other immovable
property acquired.
(b)&(e): Family residing in
affected area such as
labourers, tenants,
dependent on forest and
water bodies, etc whose
primary source of
65
livelihood is affected due to
acquisition
(c)Scheduled tribes and
other forest dwellers whose
rights recognized under the
Forest Dwellers Act 2006.
(f) Family assigned land by
state or central government
under any schemes
(g) Family residing on any
land in urban area that will
be acquired or primary
source of livelihood affected
by acquisition.
6. Cut-Off date Date established by the
borrower and acceptable to
the Bank. In practice it is the
date of census.
Section 3 c (ii), (iv) (vi):
Families residing for
preceding 3 yrs or more
prior to “acquisition of
land”.
7. Non-application of
Chapter II
Stand-alone SIA for all
investments
Section 6(2): Irrigation
projects where EIA is
required under other laws,
provisions of SIA not
applicable.
7. Consultation –
Phase I during
preparation
Consultation a continuous
process during planning
and implementation
Section 4(1) date issued for
first consultation with PRIs,
Urban local bodies,
Municipalities, etc to carry
out SIA.
Section 5: Public hearing of
SIA in affected area.
Provide adequate publicity
of date and time.
8. Time duration to
prepare SIA and
Draft Social Assessment,
Resettlement Action Plan
Section 4 (2): within six
months from the date of its
66
SIMP and or Social Management
Framework prepared before
appraisal.
commencement.
9. Disclosure – Stage
I
To be disclosed before
appraisal and 120 days
before board date.
Section 6(1): Translated in
local language available in
PRI institutions and local
urban government bodies;
district administrative
offices and websites of
concerned. government
agency.
10. Formation of
Expert Group to
appraise SIA and
SIMP
Appraised by Bank staff Section 7(1): Constitute a
multi-disciplinary Expert
Group include members of
decentralized govt Institutes
(PRIs, ULBs).
11. Time stipulated
for Group to
submit its report
Before the decision meeting
for appraisal
Section 7(4): Submit its
report within two months
from the date of its
constitution
12. Scope of work of
the Expert group
Social Assessment,
resettlement action Plan
reviewed and appraised by
Bank staff and approved by
Regional safeguard advisor
Section 7 (4) (a&b): assess
whether it serves any public
purpose or not; if social
costs outweigh potential
benefits then should be
abandoned;
Section 7 (5) (a&b): if serves
public purpose, then it has
considered minimum land
acquisition, and alternate
options to minimize
displacement; potential
benefits outweigh social
costs
13. Consultation –
Phase II during
In practice consultation
workshops are organized in
Section 2 (2): Prior consent
of 80% and 70% of land
67
appraisal project affected areas at
district and state level.
owners in PPP and where
private company has
approached the govt to
acquire balance land has
been obtained,
14. Disclosure – Stage
II
Information dissemination
through the planning and
implementation
Section 7 (6):
recommendations of expert
group under 7(4&5)to be
made public in local
language in district and
block administrative office
and PRIs
15. Minimize impact
on multi-crop land
Select feasible design that
has minimal adverse
impact.
Section 10: In case multi-
crop land is to be acquired
under exceptional
circumstances, the area to
be acquired cannot exceed
aggregate of land of all
projects in district or state.
The area to be acquired
cannot exceed the total net
sown area of the district or
state.
Wasteland equivalent to
twice the area acquired will
be developed.
16. Information
dissemination of
preliminary notice
Continuous part of the
preparation and
participation
Section 11 (1), (2) & (3):
Notice published in local
language and meetings
called of gram sabahs,
municipalities to provide
full information about the
purpose of the project,
summary of SIA and
particulars of administrator
appointed for R&R’
68
summary of R&R scheme
17. Updating land
records
To be part of RAP Section 11 (5): Once
established that the land is
required for public purpose,
accordingly notice to be
issued under section 19
following which land
records to be updated
within two months
18. Census and
preparation of
R&R schemes
To be part of RAP Section 16 (1) (2): carry out
census of affected people
and their assets to be
affected, livelihood loss and
common property to be
affected; R&R scheme
including time line for
implementation.
19. Information
dissemination and
Public hearing -
Stage III
Consultation throughout
the process is mandatory
Section 16(4)&(5):
mandatory to disseminate
information on R&R scheme
including resettlement area
and organize public hearing
on the Draft R&R scheme in
each Gram Sabha,
Municipality and
consultations in Scheduled
area as required under
PESA.
20. Approval of R&R
Scheme
Section 17 & 18: Draft R&R
Scheme to be finalized after
addressing objections raised
during public hearing and
approved.
21. Final declaration
of R&R Scheme
Approved RAP including
budgetary provisions to
implement it
Section 19 (2): Only after the
requiring body has
deposited the money will
69
the govt issue the notice
along with 19(1).
22. Time period
stipulated.
To be included in RAP -
Time line synchronized
with Government’s
procedures or adopts
innovative methods to
reduce the time which is
based operated on the
principles of participation
and transparency.
Section 19 (2): the entire
process to update land
records, disseminate
information, preliminary
survey, census, hearing of
objections, preparation of
R&R schemes and approval,
deposit of money must
complete within 12 months
from the date on which
section 11, the preliminary
notice issued.
Section 19 (7): If the final
declaration not made within
12 months of section 11 (1),
the process will lapse,
except under special
circumstances.
23. Preparation of
land acquisition
plans
To be included in RAP.
Section 20: Land marked,
measured for preparation of
acquisition plans.
24. Hearing of claims Section 21(1) (2): Notices
issued indicating govt’s
intension to take possession
of land, and claims on
compensation and R&R can
be made not less than one
month and not more than
six month from the date of
issue of section 21(1).
25. Time period
stipulated for
declaring the
award
Section 25: It is required to
announce the award within
12months of issue of
Section 19 (final declaration
70
to acquire land, approved
R&R scheme) after
completing land acquisition
plans, hearing of objection,
settling individual claims
for declaration of the award.
If award not made within
the stipulated time, the
entire proceedings will
lapse.
26. LA Act 1984 deem
to lapse and
RFCTLAR&R is
applicable
Section 24: where award is
not declared under section
11, or where made five
years ago but land not taken
in possession or where
award declared but money
not deposited in the account
of majority of beneficiary.
27. Methodology for
determining
market value for
land
Full replacement Cost Section 26 and First
Schedule: Recognizes 3
methods and whichever is
higher will be considered
which will be multiplied by
a factor given in Schedule
First; compensation given
earlier will not be
considered; if rates not
available floor price can be
set; steps to be taken to
update the market value.
28. Valuation of
structures
Full Replacement cost Section 29 (1) without
deducting the depreciated
value.
29. Solarium and
interest
Section 30(1) 100% of the
compensation amount
Section 30(3): 12% per
71
annum on the market rate
from the date of notification
of SIA to the date of ward
or land taken over
30. R&R Award Total cost included in RAP
to resettle and rehabilitate
the affected persons and
assist in their efforts to
improve their livelihoods
and standards of living or at
least to restore them, in real
terms, to pre-displacement
levels or to levels prevailing
prior to the beginning of
project implementation,
whichever is higher
Section 31, Second Schedule:
A family as a unit will
receive R&R grant over and
above the compensation
and those who are not
entitled to compensation.
Second Schedule: Homeless
entitled to constructed
house, land for land in
irrigation projects in lieu of
compensation, in case of
acquisition for urbanization
20% of developed land
reserved for owners at a
prices equal to
compensation’ jobs or one
time payment or annuity for
20 years’ subsistence grant,
transportation, land and
house registered on joint
name husband and wife, etc
31 Transparency Section 37(1): Information
of each individual family
including loss,
compensation awarded, etc
will be available on the
website.
38. Possession of land Taking of land and related
assets may take place only
after compensation has been
paid and, where applicable,
resettlement sites and
moving allowances have
Section 38(1): Land will be
taken over by the
government within three
months of compensation
and 6 months of R&R
benefits disbursed;
72
been provided to the
displaced persons.
infrastructure facilities at
resettlement sites will be
completed within 18
months from the date of
award made under section
30 for compensation; in case
of irrigation and hydle
projects R&R completed six
months prior to
submergence.
39. Multiple
displacement
Section 39: Additional
compensation equivalent to
compensation determined
will be paid to displaced
31. Acquisition for
emergency
purpose
Not permeable in bank
funded projects
Section 40 (5): 75%
additional compensation
will be paid over and above
the compensation amount
32. Prior consent
before acquisition
and alienation
Mandatory to carry out
Free, Prior, Informed
Consultation with
Indigenous people.
Section 41(3) Mandatory to
get consent from Gram
sabah, Panchayat,
Autonomous Councils in
Scheduled areas.
33. Development
plans for SC and
ST
Indigenous Peoples’
Development plan required
along with RAP.
Land for land for is an
option across all sectors.
Section 41: Separate
development plans to be
prepared, settle land rights
before acquisition;
provision of for alternate
fuel fodder, non-timber
produce on forest land to be
developed within 5 years;
1/3rd compensation amount
to be paid as first
installment and rest at the
time of taking possession;
ST to be resettled within
Scheduled area; land free of
73
cost for community
purpose; land alienation
will be null and void and ST
and SC considered for R&R
benefits; fishing rights
restored in irrigation and
hydle projects; if wish to
settle outside the district
additional benefits to be
provided in monetary
terms; all rights enjoyed
under other laws will
continue.
Second Schedule: additional
provisions for SC&ST for
land for land in irrigation
projects, additional sum
over and above the
subsistence grant,
34. Institutional
arrangement
Institutional arrangement
must be agreed upon and
included in RAP, IPDP.
Section 43-45:
Appointment of
administrator, R&R
Commissioner, when more
than 100 acres of land is to
be acquired, R&R
Committee will be formed
at project level, social audit
to be carried out by Gram
Sabha and Municipalities.
35. Change of land
use
Section 46(4): Land will not
be transferred to the
requisitioning authority till
R&R is not complied with in
full
36 Monitoring and
Evaluation
Indicators and monitoring
system included in RAP
Section 48-50:Set up
National and State level
Monitoring Committee to
74
and IPDP review and monitor
progress
37. Authority to settle
claims
Section 51-74: the Authority
will be set up settle any
legal disputes that arise
from acquisition and R&R,
the aggrieved party can
move to the high court
thereafter.
38. Exempt from tax
and fee
Section 96: Compensation
and agreements will not be
liable to tax
39. No change in
status of land
acquired
Section 99: Once the land is
acquired for a particular
purpose, its purpose cannot
be changed
40. Return of
unutilized land
Section 101: If the acquired
land remains unutilized for
5 years, then it will be
returned to original owner,
heir or included in land
bank
41. Distribution of
increased value of
land transferred
Section102: 40% of
appreciated value of
acquired land will be
distributed to owners
provided no development
has taken place.
4.3 Other Legislations applicable to Construction Projects under NGRBP
Construction stage generally involves equity, safety and public health issues. The
construction agencies therefore will be required to comply with laws of the land, which
include inter alia, the following:
75
1. Workmen's Compensation Act 1923 (the Act provides for compensation in case of injury by
accident arising out of and during the course of employment);
2. Payment of Gratuity Act, 1972 (gratuity is payable to an employee under the Act on
satisfaction of certain conditions on separation if an employee has completed 5 years);
3. Employees PF and Miscellaneous Provision Act 1952 (the Act provides for monthly
contributions by the employer plus workers);
4. Maternity Benefit Act, 1951 (the Act provides for leave and some other benefits to women
employees in case of confinement or miscarriage, etc.);
5. Contract Labor (Regulation and Abolition) Act, 1970 (the Act provides for certain welfare
measures to be provided by the contractor to contract labour);
6. Minimum Wages Act, 1948 (the employer is supposed to pay not less than the Minimum
Wages fixed by the Government as per provisions of the Act);
7. Payment of Wages Act, 1936 (it lays down as to by what date the wages are to be paid,
when it will be paid and what deductions can be made from the wages of the workers);
8. Equal Remuneration Act, 1979 (the Act provides for payment of equal wages for work of
equal nature to Male and Female workers and not for making discrimination against Female
employees);
9. Payment of Bonus Act, 1965 (the Act provides for payments of annual bonus subject to a
minimum of 83.3% of wages and maximum of 20% of wages);
10. Industrial Disputes Act, 1947 (the Act lays down the machinery and procedure for
resolution of industrial disputes, in what situations a strike or lock-out becomes illegal and
what are the requirements for laying off or retrenching the employees or closing down the
establishment);
11. Industrial Employment (Standing Orders) Act; 1946 (the Act provides for laying down
rules governing the conditions of employment);
76
12. Trade Unions Act, 1926 (the Act lays down the procedure for registration of trade unions
of workers and employers. The trade unions registered under the Act have been given
certain immunities from civil and criminal liabilities);
13. Child Labour (Prohibition and Regulation) Act, 1986 (the Act prohibits employment of
children below
14 years of age in certain occupations and processes and provides for regulation of
employment of children in all other occupations and processes. Employment of child labour
is prohibited in Building and Construction Industry);
14. Inter-State Migrant Workmen’s (Regulation of Employment and Conditions of Service)
Act, 1979 (the inter-state migrant workers, in an establishment to which this Act becomes
applicable, are required to be provided certain facilities such as housing, medical aid,
travelling expenses from home to the establishment and back, etc.);
15. The Building and Other Construction Workers (Regulation of Employment and Conditions
of Service) Act, 1996 and the Cess Act of 1996 (all the establishments who carry on any
building or other construction work and employs 10 or more workers are covered under this
Act; the employer of the establishment is required to provide safety measures at the building
or construction work and other welfare measures, such as canteens, first-aid facilities,
ambulance, housing accommodation for Workers near the workplace, etc.);
16. The Factories Act, 1948 (the Act lays down the procedure for approval of plans before
setting up a factory, health and safety provisions, welfare provisions, working hours and
rendering information-regarding accidents or dangerous occurrences to designated
authorities);
4.4 Environmental and Social Management Framework of NGRBA
Project has prepared an Environmental and Social Management Framework to ensure
socially and environmentally sustainable development in NGRBA’s endeavour of
Mission Clean Ganga by effective management of environmental and social issues in all
the investments with a special focus on the following:
ensure that all investments adhere to the national, state and local regulatory requirements
during the design, implementation and operation stages
77
ensure that best environmental and social practices are mainstreamed/ integrated during
design, implementation and operation of the investments
strive to enhance environmental conditions wherever feasible
undertake to develop communication strategy, capacity building and training initiatives
for all stakeholders such as the SPMGs, EAs, ULBs, NGOs and common citizens.
The purpose of the ESMF is to facilitate the management of environmental and social
issues of the river pollution mitigation investments. The Environment and Social
Management Framework (ESMF), therefore, would be used as an umbrella by the
NGRBA program (the PMG and SPMGs) and all implementing agencies while preparing
and/ or appraising, approving and executing the investments. The ESMF includes a
Resettlement Policy and Land Acquisition Framework (RPLAF), which specifies the
procedures, eligibility, grievance redressal and other measures to be followed in the event
that resettlement or land acquisition is required for any sub-project. As part of the ESMF,
a Gender Development Framework has been designed which will help to analyze gender
issues during the preparation stages of the sub-project, and to design interventions to
address women’s needs. Gender analysis will be part of the social assessment at the sub-
project level. The RPLAF, has a screening checklist to identify any adverse impact. The
project has also prepared an entitlement matrix to address the adverse impacts as given
below. The entitlement matrix is based on NPRR 2007 .
78
5 Baseline Status
The baseline environmental and social status is important to understand the region's
existing physical and biological characteristics along with cultural and social status of the
residing community. Information and data presented in this section is based on field
surveys, stake-holder interaction/consultation and secondary data collection which majorly
include the draft Detailed Project Report (DPR) of proposed sewerage work in Anupshahr
town, Baseline generation (Water/ Air/ Noise quality/ Soil monitoring) ,town census data
and others. The information on the baseline environmental conditions forms the basis to
analyses the probable impacts of the proposed project vis-à-vis the present background
environmental quality of the core study area.
5.1 Baseline Environmental Status
5.1.1 Physiographic and Topography
Anupshahr is located at 28.37°N 78.27°E. The general topography of the town is rather
undulating. The general ground is sloping towards River Ganga. Garhi Mohalla is the highest
in the elevation with a significant level difference with respect to ground level.
The topography of the town is generally plain & slopes towards river Ganga. The huge water
body formed upstream of the barrage houses the dolphins. Upper Ganga stretch of the river
from Bijnor to Narora (165 km) is home to dolphins & forms a part of the RAMSAR Site.
WWF India has been working closely since late nineties with river bank communities and
aquatic species that could serve as a reliable indicator of the health of Ganga River. While
79
different strategies have been adopted by them from time to time, the focus has always
remained on the people & species.
The goal being to reduce the huge burden of pollution & other anthropogenic pressures that
Ganga River has borne particularly in the last few decades. The dolphin’s habitat parameters
in Ganga River with active participation of WWE (India) and based on their study during 2007-
2009, the population of dolphins in the study area between Bijnor and Narora was recorded
to have increased .The population of dolphins in the study area was recorded to have increase
(44 in 2007; 49 in 2008; 56 in 2009) during the project period (2007-2009). This signifies that
the recruitment and growth pattern on the population is increasing. This is most likely
because of the improvement in habitat conditions, as well as in the water quality. A decrease
in the death rate between 2007-2009 could also be a factor as of death was recorded in this
stretch.
Table 8Dolphin habitat parameters in Upper Ganga River (Narora- Anupshahr)
River stretch Kms Km Few Important Habitat Parameters
Mid Ganga River
Narora –Anupshahr (Zone I) 0-30 Deep pools, sandy and muddy river
bank island with vegetation
River depth 1.5-4.3 m
River width 200-800 m
River velocity 3.0-5.5 m/sec
Air temp. 10-42° C
Water temp 12-28°C
ph 7.05-8.70
Dissolved Oxygen 6-8 mg/l
Conductivity 200-250 µ S/cm
80
The total dolphin population in upper Ganga system up to October 2012 was 671 with
following distribution. Ganga-261, Yamuna -31, Chambal-85, Ghaghara-231, Rapti-8, Geruwa-
39, Saryu-16. The distribution of total dolphin population is shown in figure below.
5.1.2 Climate
Figure 8Distribution of Dolphin in Upper Ganga System population up to October 2012 (source WWF)
81
The town has very hot climatic conditions in summers, the temperature rises up to 40
degrees Celsius and chilling winter is common. It receives heavy rainfall for three to
four months within a year. Source: http://www.climate-data.org
Figure 9 Annual Temperature
82
Figure 10 Temperature Variation & Precipitation
83
Figure 11 Annual Rainfall
84
5.1.3 Land Use Pattern
According to the land use data of 2004-05, the net area sown and current fallow land was
estimated at 298371 ha. (81.75 per cent) and 2456 (0.70 per cent) respectively of the total
reporting area in district Bulandshahr. The area under forest accounted for 7726 ha (2.12 per
cent). Land put to non-agricultural uses was estimated at 49710 ha. (13.62 per cent) and
uncultivable wasteland at 5111 ha.(1.40 per cent). Grazing land and area under trees and
Figure 12 Land use & Cropping Pattern
85
orchards is negligible. The total reporting area covers 364974 ha. land in the district. It is
interesting to note that total reporting area of the district has decreased by 1.40 per cent
(5096 ha.). The forest area has also declined from 7726 ha, in 2004-05 to 7544 ha. in 2006-07
The net irrigated area in the district during 2004-05 was 263715 ha. which was 88.38 per
cent of the net area sown. Irrigation facilities are well developed in the district. The main
source of irrigation is private Tube wells which covers 220816 ha. land (84 per cent) of the
total net irrigated area. About 958 kms of canals and 199 canal tails provide irrigation to 10
per cent of irrigated area (25102 ha.) and wells account for 4.55 per cent area under
irrigation. States run Tube wells cover only 1.89 per cent area under irrigation
5.1.4 Geological and Geophysical features
The substrata of the town contain boulders, gravel, clay and sand etc. The sub soil water
level is at about 8 m depth. Anupshahr is almost flat with mild slopes towards Ganga River,
except some areas.
Figure 13 Geology of the town
86
Water Quality Status
Although the Ganga flows along the entire length of the NCR fringing its eastern border, any
monitoring station has not been established. Apart from Garhmukhteshwar (Class III town),
Anupshahr (Class IV town) and Narora (Class IV Town), there are no major water pollution
issues in the Ganga Basin in this particular stretch.
Effect on Groundwater by STP/sewer lines
The groundwater near Sewerage Treatment Plant present in zone A & B is more than 5m in
depth, which shows that ground water table there will not be polluted by the presence of
STP. As per survey and studies made, it is observed that in most part of the city the
groundwater is more than 5m.For sewer lines laid in regions having shallow depth,
infiltration factor has been considered.
Moreover, for every joints provision of sealant has been taken into account in order to
prevent intrusion of sewerage into ground water. Proper jointing and provision of cradles
has also been considered for preventing groundwater pollution.
Figure 14 Underground Sewer Line
87
Table 9Depth of Water below Ground level and its Hydro-geological Conditions in Anupshahr
Sub Region/Tehsil/Tow
n Land
Contour
Ground Water
Contour Depth of Ground Water BGL Hydro-Chemical
Conditions
mts mts mts A B C D E
Anupshahr 185-200 195-190 10
Figure 15 Groundwater Scenario of the Town
88
5.1.5 Duration of Monitoring to generate the base line
The monitoring of air, water, soil, and noise quality was conducted during the month
of December 2014.
5.1.6 Meteorology
A meteorological station was set up at the project premises. Meteorological data was
generated during the 15 December 2013 to 15 January 2014.
The following parameters were recorded at hourly intervals continuously during monitoring
period is enclosed as Annexure8
Wind speed
Wind Direction
Air Temperature
5.1.7 Ambient Air Quality
To quantify the impact of the project on the ambient air quality, it is necessary at first to
WRPLOT View - Lakes Environmental Software
PROJECT NO.:
DATE:
24-01-2014
MODELER:
COMPANY NAME:
COMMENTS:WIND ROSE PLOT:
NORTH
SOUTH
WEST EAST
4%
8%
12%
16%
20%DATA PERIOD:
Start Date: 15-12-2013 - 00:00End Date: 15-01-2014 - 23:00
WIND SPEED
(m/s)
>= 11.1
8.8 - 11.1
5.7 - 8.8
3.6 - 5.7
2.1 - 3.6
0.5 - 2.1
Calms: 29.05%
AVG. WIND SPEED:
2.00 m/s
CALM WINDS:
29.05%
TOTAL COUNT:
835 hrs.
DISPLAY:
Wind SpeedDirection (blowing from)
Figure 16 Wind Rose
89
evaluate the existing ambient air quality of the area. To assess the ambient air quality
level, 4 (four) monitoring stations were set up. And one day monitoring has been done
i.e. 15/1/2014.
The existing ambient air quality has been monitored and 12 air parameters are analyzed
such as Particulate Matter-10 (PM10), Particulate Matter- 2.5 (PM2.5), Sulphur-dioxide
(SO2), Nitrogen Oxide (NO2), and Carbon Monoxide (CO), through a planned field
monitoring. All the parameters are within prescribed limit as per EPA.
The maximum concentration of Particulate Matter (PM10 &PM2.5) i.e. 73.4 & 47.65 µg
/m3 has been analyzed in AAQ4 (Near Nav Durga Medical Store) due to commercial place,
and minimum concentration is in campus of both the STPs.
The concentration of Sulphur Dioxide& Nitrogen Dioxide is high Near Bulandshahar Bus
Stand due to emission by huge vehicular traffic and minimum concentration is in campus
of both the STPs.
Similarly the concentration of Carbon Monoxide, Lead (as Pb), Nickel (as Ni), Arsenic (as
As), Ozone (as O3), Ammonia (as NH3), Benzene (as C6H6), Benzo(α) Pyrine- Particulate
Phase are also within the prescribed limit of EPA.Location map is enclosed as Annexure 2.
Table 10 Air Quality monitoring location
Locations Code Locations
AAQ1 Near STP Zone –A, AnupShahar, U.P
AAQ2 Near STP Zone –B, Anupshahar, U.P
AAQ3 Near Buladhahar Bus Stand
AAQ4 Near Nav Durga Medical Store
Methods of Sampling and Analysis
Fine particulate Sampler APM MFC550 was used for monitoring Particulate Matter (PM2.5
and PM10); gaseous pollutants like SO2, and NO2 was collected by Gaseous Pollutant
Sampler APM 433 and CO was monitored by Serinous 30 CO Analyser with NDIR detector.
90
Method for measurement of Particulate matter, SO2 & NO2
Method for measurement of Particulate Matter (PM10) in ambient air is done by Cyclonic
Flow Technique. Particles with aerodynamic diameter less than the cut-point of the inlet are
collected by a filter. Ambient air at the monitoring location is sucked through a cyclone.
Coarse and non-reparable dust is separated from the air stream by centrifugal forces acting
on the solid particles and these particles fall through the cyclone's conical hopper and get
collected in the sampling cap placed at the bottom. The fine dust (<10 microns) forming the
particulate matter (PM10) passes the cyclone and is retained on the filter paper The mass of
these particles is determined by the difference in filter weights prior to and after sampling.
The concentration of PM10 in the designated size range is calculated by dividing the weight
gain of the filter by the volume of air sampled. A tapping is provided on the suction side of
the blower to provide suction for sampling air through a set of impingers for containing
absorbing solutions for SO2 and NO2. Samples of gases are drawn at a flow rate of 0.2 liters
per minute. The APM MFC 550 is used for PM2.5. This system is a manual method for
sampling fine particles (PM2.5 fraction) and is based on Impactor designs standardized by
USEPA for ambient air quality monitoring.
PM2.5& PM10 have been estimated by gravimetric method. Improved West and Gaeke
method (IS-5182 part-II, 1969) has been adopted for estimation of SO2 and Modified Jacobs-
Hochheiser method (IS-5182 part-VI, 1975) has been adopted for the estimation of NO2.
91
Method for measurement of Carbon Monoxide – NDIR method
Instrument used: Ecotech Serinus 30 Carbon Monoxide
This analyzer is used to measure CO in ambient air, in the range of 0-200 ppm (220 mg/m3)
to a sensitivity of 0.05 ppm 55µg/m3). The Serinus 30 combines the benefits of Micro process
control with Non-Dispersive Infrared Spectrophotometry technology.CO Concentration is
automatically corrected for gas temperature and pressure changes.
Ambient Air Quality Monitoring (15.1.2014)
S.No. Parameter Test
Method AAQ1
Results AAQ2
Results AAQ3
Results AAQ4
Results Units
Limits as per EPA.
1 Particulate Matter (PM10)
IS:5182 Part-XXIII
56.7 58.95 69.8 73.4 µg /m3 100
2 Particulate Matter (PM2.5)
CPCB Volume –
1
43.1 42.56 46.5 47.65 µg /m3 60
3 Sulphur Dioxide IS:5182 Part-II
7.6 9.22 13.45 12.2 µg /m3 80
4 Nitrogen Dioxide
IS:5182 Part-VI
12.2 14.65 24.72 22.9 µg /m3 80
5 Carbon Monoxide
IS:5182 Part-X
˂1.15 ˂1.15 ˂1.15 ˂1.15 mg/m3 4
6 Lead(as Pb) IS:5182 Part-XXII
˂0.10 ˂0.10 ˂0.10 ˂0.10 µg /m3 1
7 Nickel (as Ni) APHA-AIR420
˂20.00 ˂20.00 ˂20.00 ˂20.00 ng /m3 20
8 Arsenic ( as As) APHA-AIR302
˂5.00 ˂5.00 ˂5.00 ˂5.00 ng /m3 6
9 Ozone ( as O3) IS:5182 Part-IX
26 24.4 27.5 25.2 µg /m3 180
10 Ammonia (as NH3)
APHA-AIR402
˂20.00
˂20.00
˂20.00
˂20.00
µg /m3 400
11 Benzene ( as C6H6)
IS:5182 Part-XI
˂1.00 ˂1.00 ˂1.00 ˂1.00 µg /m3 5
12 Benzo(α) Pyrine- Particulate Phase
IS:5182 Part-XI
˂1.00 ˂1.00 ˂1.00 ˂1.00 ng /m3 1
92
Figure 17 Air Sampling in progress
93
5.1.8 Noise Environment
Noise is one of the most undesirable and unwanted by-products of our modern life style. It
may not seem as insidious or harmful as air and water pollutants but it affects human health
and well-being and can contribute to deterioration of human well-being in general and can
cause neurological disturbances and physiological damage to the hearing mechanism in
particular. It is therefore, necessary to measure both the quality as well as the quantity of
noise in and around the site.
Methodology
The intensity of sound energy in the environment is measured in a logarithmic scale and is
expressed in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an
additional circuit (filters) is provided, which modifies the received signal in such a way that it
replicates the sound signal as received by the human ear and the magnitude of sound level in
this scale is denoted as dB (A). The sound levels are expressed in dB (A) scale for the purpose
of comparison of noise levels, which is universally accepted by the international community.
Noise levels were measured using an Integrating sound level meter manufactured by Pulsar
Instruments Plc, Model NO. 91 (SL.No.B21625). It has an indicating mode of Lp and Leq.
Keeping the mode in Lp for few minutes and setting the corresponding range and the
weighting network in “A” weighting set the sound level meter was run for one hour time and
Leq was measured at all locations.
The day noise levels have been monitored during 6.00 am to 10.00 pm and night noise levels,
during 10.00 pm to 6.00 am at all the 5 locations, which covers residential areas, highways,
industrial areas, commercial areas, and silence zones, if available within 10 km radius of the
study area.
94
Sampling Locations
A preliminary survey was undertaken to identify the major noise generating sources in the
area. The noise survey was conducted to assess the background noise levels in different
zones. Gazettes Notification (S.O. 123(E)) of MoEF dated February 14, 2000 on ambient air
quality standards has different noise levels for different zones viz. project site, industrial,
commercial, and residential and silence zones.
In Anupshahr town the four locations has been identified for noise level monitoring in which
two are project sites and other two are commercial and silence zone the monitoring has
been done during day (6.00 Am to 10 Pm) and night (10:00 PM to 6:00 Am) both and after
analyzing the results, it is conclude that noise levels during day time and night are in
prescribed limit of CPCB.
Location code is given in table below and location map is enclosed as Annexure 3.
Locations Code Locations
NAQ1 Near STP Zone –A, Anupshahr, U.P
NAQ2 Near STP Zone –B, Anupshahr, U.P
NAQ3 Near Durga Prasad Baljeet Singh, P.G. College,
NAQ4 Near Nav Durga Medical Store
Table 11 Noise Ambient Quality
Noise Ambient Quality
S. No Test Parameters NAQ1
Results NAQ2
Results NAQ3
Results NAQ4
Results Units
Requirement (as per CPCB Guidelines Limits in
dB (A) Leq
EQUIVALENT NOISE LEVEL 58.2 56.7 66.2 72.5
dB(A) Category of Area/ Zone
Day Time Night Time
1 (6.0 AM TO 10.0 PM) Industrial Area 75 70
2
EQUIVALENT NOISE LEVEL
37.7 38.4 42.1 46.4
dB(A)
Commercial Area 65 55
(10.0 PM TO 6.0 AM) Residential Area 55 45
Silence Zone 50 40
Figure 18 Noise Sampling
97
5.1.9 Water Environment
Water quality assessment is one of the essential components of EIA study. Such assessment
helps in evaluating the existing health of water body and suggesting appropriate mitigation
measures to minimize the potential impact from development projects.
The six samples have been drawn for water quality monitoring at STP inlet of both zone, STP
outlet of both Zones, Upstream of Ganga River and downstream of Ganga River with respect
to the discharge point of STPs.
At STP inlet five parameters have been analyzed i.e. which show the characteristics of waste
water in both the zones.
pH is (7.5-7.46),Total Suspended Solid (7432-7560), Chemical Oxygen Demand(as O2) (596-
690) , Biological Oxygen Demand(as O2) (226-244) and Oil & grease (9-8.4).
Table 12 Water Quality at STP Inlet
Water Quality (STP Inlet)
S.No. Parameter Test Method Zone A Results
Zone B Results
Units
1 pH IS:3025(Part-11):1983 7.95 7.46 -
2 Total Suspended Solid
IS:3025(Part-17):1984 7432 7560 mg/l
3 Chemical Oxygen Demand(as O2)
APHA 5220 B:2005 596 690 mg/l
4 Biological Oxygen Demand(as O2)
IS:3025(Part-44):1993 226 244 mg/l
5 Oil & grease IS:3025(Part-19):1984 9 8.4 mg/l
Similarly at STP outlet five parameters have been analyzed i.e. which show the
characteristics of treated water in both the zones
pH is (8.22-8.4), Total Suspended Solid (26-38), Chemical Oxygen Demand(as O2) (104-128)
, Biological Oxygen Demand(as O2) (20-24) and Oil & grease (2.2-2.6).
All the above mention parameters are within the prescribed limit of CPCB norms
98
Table 13 Water Quality at STP Outlet
Water Quality (STP Outlet)
S.No. Parameter Test Method Zone A Results
Zone B Results
Units Limits as per CPCB
norms
1 pH IS:3025(Part-11):1983
8.22 8.4 - 5.0-9.0
2 Total Suspended Solid
IS:3025(Part-17):1984
26 38 mg/l 100
3 Chemical Oxygen Demand(as O2)
APHA 5220 B:2005
104 128 mg/l 250
4 Biological Oxygen Demand(as O2)
IS:3025(Part-44):1993
20 24 mg/l 30
5 Oil & grease IS:3025(Part-19):1984
2.2 2.6 mg/l 10
As mention above samples are also drawn at Upstream and Downstream of Ganga River
with respect to the discharge points of STPs in both zones to assess the changes in water
quality of river due to discharge of waste water in river.
The following parameters have been analyzed:-
1. Microbiological
As per the requirement of IS 10500:2012 the concentration of Total Coliform
Bacteria & Fecal Coliform Bacteria should be absent/250 ml but due to discharge of
effluent at various point in upstream it comes around (520/100 ml & 180/100ml) and
similarly due to discharge of waste water of Anupshahr in river the same parameter
are changed at downstream of river i.e. (630/100 ml & 220/100ml).
2. Organoleptic & Physical Parameters
Under this section six physical parameters are covered Colour (Odour, Taste,
Turbidity, pH, Total dissolve solid (TDS)).
In upstream and downstream both the concentration of all the above six mention
parameters are within Requirement (Acceptable Limit).
99
3. General Parameters Concerning Substances Undesirable In Excessive Amounts
In upstream and downstream both Aluminum (as Al), Total Ammonia, Anionic
surface, Detergents (as MBAS), Barium (as Ba), Chloramines (as Cl2), Free Residual
Chlorine, Magnese (as Mn), Silver (as Ag), Sulphide(as H2S) are below the detection
limit. And Boron (as B), Calcium (as Ca), Chloride (as Cl), Copper (as Cu), Fluoride (as
F), Iron (as Fe), Magnesium (as mg), Nitrate (as NO3), Selenium (as Se), Sulphate (as
SO4), Alkalinity (as Ca CO3), Total hardness (as CaCO3), Zinc (as Zn) are below the
required acceptable limit.
4. Parameters Concerning Toxic Substances
In upstream and downstream Cadmium (as Cd), Cyanide (as CN), Lead (as Pb),
Mercury (as Hg), Nickel (as Ni), Arsenic (as As), Total Chromium (as Cr) are below the
detection level limit.
Water Quality (Ganga Water)
Table 14 Water Quality of Ganga River
MICROBIOLOGICAL REQUIREMENT
S.No. Parameter Test Method
UP Stream Result
Down Stream Result
Required as per IS-10500:2012
1 Total Coliform Bacteria
IS-1622 520/100ml 630/100 ml Absent/250ml
2 Fecal Coliform Bacteria
IS-1622 180/100ml 220/100 ml Absent/250ml
ORGANOLEPTIC & PHYSICAL PARAMETERS
S.NO. Parameter Test method
UP Stream Result
Down Stream Result
Unit Requirement (Acceptable
Limit)
Permissible Limit in
absence of alternate
source
1 Colour IS-3025(P-
04)
<1.0 <1.0 Hazen Unit
5 15
100
2 Odour IS-3025(P-
05)
Agreeable Agreeable - Agreeable Agreeable
3 Taste IS-3025(P-07 & 08)
Agreeable Agreeable - Agreeable -
4 Turbidity IS-3025(P-
10)
<1.0 <1.0 NTU 1 5
5 pH value IS-3025(P-
04)
7.72 8.14 - 6.5-8.5 -
6 Total dissolve solid ( TDS)
IS-3025(P-
16)
144 346 mg/l 500 2000
General parameters concerning substances undesirable in excessive amounts
S.no. Parameter Test method
UP Stream Result
Down Stream Result
Unit Requirement (Acceptable
Limit)
Permissible Limit in
absence of alternate
source
1 Aluminum (as Al)
IS: 3025 (P- 55)
BDL BDL mg/l 0.03 0.2
2 Total Ammonia
IS: 3025 (P- 34)
BDL BDL mg/l 0.5 No Relaxation
3 Anionic surface Detergents(as MBAS)
Annex K of IS-13428
BDL BDL mg/l 0.2 1
4 Barium (as Ba)
IS: 15302
BDL BDL mg/l 0.7 No Relaxation
5 Boron (as B) IS: 3025 (P- 57)
0.12 0.14 mg/l 0.5 1
6 Calcium (as Ca)
IS: 3025 (P- 40)
33.67 51.3 mg/l 75 200
7 Chloramines (as Cl2)
IS: 3025 (P- 26)
BDL BDL mg/l 4 No Relaxation
8 Chloride (as Cl)
IS: 3025 (P- 32)
34.22 21.54 mg/l 250 1000
101
General parameters concerning substances undesirable in excessive amounts
S.no. Parameter Test method
UP Stream Result
Down Stream Result
Unit Requirement (Acceptable
Limit)
Permissible Limit in
absence of alternate
source
9 Copper (as Cu)
IS : 3025 (P-42)
<0.05 <0.05 mg/l 0.05 1.5
10 Fluoride (as F)
IS: 3025 (P-60)
0.29 0.17 mg/l 1 1.5
11 Free Residual Chlorine
IS: 3025 (P-26)
DL BDL mg/l 0.2 1
12 Iron (as Fe) IS: 3025(P-
53)
0.2 0.19 mg/l 0.3 No Relaxation
13 Magnesium (as mg)
IS: 3025 (P-46)
17.4 17.5 mg/l 30 100
14 Magnese (as Mn)
Clause 35 of IS
3025
BDL BDL mg/l 0.1 0.3
15 Nitrate (as NO3)
IS: 3025 (P- 34)
8.9 11.5 mg/l 45 No Relaxation
16 Selenium (as Se)
IS: 3025 (P- 56)
<0.01 <0.01 mg/l 0.01 No Relaxation
17 Silver (as Ag) Annex J IS:
13428
BDL BDL mg/l 0.1 No Relaxation
18 Sulphate (as SO4)
IS: 3025 (P- 24)
15.68 13.4 mg/l 200 400
19 Sulphide(as H2S)
IS-3025 (P-29)
BDL BDL mg/l 0.05 No Relaxation
20 Alkalinity ( as Ca CO3)
IS: 3025 (P- 23)
156 176.2 mg/l 200 600
21 Total hardness (as CaCO3)
IS: 3025 (P- 23)
285 322.4 mg/l 200 600
22 Zinc (as Zn) IS: 3025 (P- 49)
0.08 0.186 mg/l 5.0 15
102
Parameters Concerning Toxic Substances:
S.NO. Parameter Test method
UP Stream Result
Down Stream Result
Unit Requirement (Acceptable
Limit)
Permissible Limit in
absence of alternate
source
1 Cadmium (as Cd)
IS-3025(P-
41)
BDL BDL mg/l 0.003 No Relaxation
2 Cyanide (as CN)
IS-3025(P-
27)
BDL BDL mg/l 0.05 No Relaxation
3 Lead ( as Pb)
IS-3025(P-
47)
BDL BDL mg/l 0.01 No Relaxation
4 Mercury (as Hg)
IS-3025(P-
48)
BDL BDL mg/l 0.001 No Relaxation
5 Nickel (as Ni)
Annex L of IS-
13428
BDL BDL mg/l 0.02 No Relaxation
6 Arsenic (as As)
IS-3025(P-
37)
BDL BDL mg/l 0.01 0.05
7 Total Chromium (as Cr)
Annex J of IS-
13428
BDL BDL mg/l 0.05 No Relaxation
BDL: Below Detection limit.
103
Figure 19 Water Sampling Site Pics
104
5.1.10 Drainage System
The drainage system of the town is also very poor; the storm water is transported through
the common open drains along with domestic waste water. The condition worsens in the
rainy season and general problem of overflow of drains is encountered. The waste water
finds its way to low lying areas and creates unhygienic sanitary conditions.
5.1.11 Waste Water Management
Anupshahar town doesn’t have a sewerage network system. However, under Ganga Action
Plan-I, Nala tapping was done by intercepting the flow and diverting it into two nos. of
sewerage treatment Plants of 1.75 mld and 0.805 mld capacity respectively.
Figure 20 Drainage Pattern in whole State
105
A proposal was issued by the Nagar Parishad on dated 02-01-2013 regarding sewerage
scheme of the town, which specifies that sewerage network has to be laid on the internal
roads has to be provided for the interconnections between the manholes used for tapping
nalas at the river bank so to avoid the overflow of waste water.
At present only the flow of Nalas is tapped and diverted to STP and treated water is
discharged into the River Ganga. However in the rainy seasons and the peak flow period
(Mela period) these 250mm sewer lines are collapsed and the overflow of the waste water
creates the unhygienic conditions for the people residing in the area.
Due to rapid urbanization and for better hygienic and sanitary conditions to improve living
standards sewerage networks along with related facilities are strongly required.
Also Anupshahr is the priority town as it lies on the bank of River Ganga and this river is the
sacred river for the Hindus. Pilgrims from many parts of the country in large quantity used
to visit this place for tasking holy dip in River Ganga, stay in the town and uses the facilities
of this town.
5.1.12 Waste generation:
Waste generation is about 200 gms per capita per day in cities with the population of less
than 1 lac. The larger the city, the higher is the per-capita waste generation rate. The total
waste generation in Anupshahr town is estimated to be 48 metric tonnes per day at present
ie. year 2014. The type of solid waste generated in the town can be broadly classified into
Municipal Solid Waste, E-Waste, Plastic Waste, Construction and Demolition Waste,
Biomedical Waste
The solid waste management in Anupshahr town is handled by Nagar Panchayat Anupshahr.
The Nagar Panchayat has provided bins at different locations in the town where the local
inhabitants put their waste for transportation & disposal. Nagar Panchayat disposes of the
solid waste in the low lying areas of the town.
Composition of Waste:
106
Indian mixed waste has a large proportion of compostable material and inerts. As per NEERI
studies, compostable matters range from 30% to 57% and inert materials from 40% to 54%.
The component of recyclable material is between 5% to 10%.
Waste Management during festivals/Melas:
During the span of festival/melas, the population of the town increases temporarily,
resulting in the increase of solid waste generation. At present, the only thing adopted to
cater this situation is increasing the number of trips of the transportation vehicles to the
dumping site. However no management plan is prepared for the particular span which
results in the collection of large amount of solid waste at the collection points for the longer
duration of time.
Technology adopted for storage, collection, transportation and disposal of waste
The solid wastes collected from 26 localities are dumped on the bypass road but this is
temporary location, final location has not been decided. Recyclable waste material is also
not segregated at source and is disposed of on the streets, along with domestic, trade and
other wastes. Construction and demolition wastes also pose a serious problem as these
wastes are also deposited on the roadside or open spaces, obstructing traffic and causing
nuisance.
Primary Collection
There is no system of primary collection of waste in the town. The waste thrown on the
streets is, therefore, collected from the streets and/or from the street bins, which are
inadequate in number and ill designed.
Waste Storage Depots
Open sites or cement concrete bins, metal bins, masonry bins and structures are used for
temporary bulk storage of wastes. These bins are very unhygienic and necessitate multiple
handling of wastes. Waste is more often seen outside the bins than inside them. They are
not cleared daily.
Street Sweeping
107
Street sweeping is not carried out regularly. Several streets are occasionally swept or are
not swept at all. No sweeping is done on Sundays and public holidays in many cities. The
tools used for street sweeping are also inefficient and outdated.
Transportation of wastes
Transportation of waste is done through a variety of vehicles such as bullock carts, three-
wheelers, tractors. Most transport vehicles are loaded manually and utilized in one shift
only, although the number of transport vehicles is inadequate.
Municipal solid waste is heterogeneous in nature and consists of a number of materials
generated by various activities.
MSW disposals and treatment
The two leading innovative mechanisms of
waste disposal being adopted in India
include composting (aerobic composting
and vermi-composting) and waste-to-
energy (WTE) (incineration, pelletisation,
biomethanation). WTE projects for disposal of MSW are a relatively new concept in India.
The following techniques can be followed to deal with the solid waste scenario of the town.
1. Landfilling
2. Recycling of organic waste
3. Vermicomposting
108
5.2 Tourism
Anupshahris an old town famous for pilgrimages situated on the river Ganga. Several
religious bathings and festivals are organized all the year round. The town was named after
Raja Anup Rai Bargujar. Anupshahr is also called as Mini-Kashi due to river Ganga.
Anupshahrhas historic value and infrastructure support like banking, civic amenities,
dhramshalas, ghaats for Holy in Ganges, Dedicated Ghaats for women. A complete River
front development project will help to recreate and upgrade the existing status. Solid waste
and sanitation projects should also introduced to improve the overall condition of the
tourist to make it tourist friendly.
Figure 21 Tourism Map of the State
109
5.3 Environmentally Sensitive Zone
Anupshahr falls in the Ramsar Site which is highly environmentally sensitive. This region is
endowed with special attributes related to religious tradition, spiritual knowledge and
cosmological beliefs depicting the cultural heritage of humanity and source of aesthetic
aspirations adorned with important local traditions. Dolphins are found in this region which
makes this region more sensitive.
Figure 22 Environmentally Sensitive Zones
110
5.4 Health Care
There are 2 major hospitals in the town. The list of all Hospitals in the town is presented
below:
Janta Hospital
Jahangirabad Community Health Centre
Jeevan Jyoti Clinic
Dr. Ved Prakash Clinic
Kaushik Memorial Clinic
Neetu Clinic & Maternity Home
Jahangirabad Veterinary Hospital
Figure 23 Health Care in the State and Town
111
5.5 Education
There are 4 nos. of schools in the town, 4 nos. of Inter colleges and 1 no. of PG College.
Some of the educational institutes in the town are listed below:
DPBS Degree College
Jaypee Vidya Mandir
Saraswati Shishu Mandir
Sabitri Pragya Mandir School
Shri Kanti Prakash Saraswati Vidya Mandir
RSAK Inter College
Figure 24 Education Scenario in the town
112
5.6 Soil
To identify the existing quality of soil at project area two samples are drawn at STPs in both
zones and in soil quality analysis, analyzed the 18 parameters are listed below:-
Table 15 Soil Parameters examined at the site
SOIL
S.No. Parameter Test Method STP Site Zone A Results
STP Site Zone B Results
Units
1 pH(1:5 suspension) IS:2720(Part-26) 7.94 8.6 -
2 Electrical Conductivity at 25OC (1:5suspension.)
IS:2720(Part-21) 54 102 µS/cm
3 Organic Matter IS:2720(Part-22) 0.42 0.63 % by mass
4 Potassium (as K) STP/SOIL 131.2 172.54 mg/kg
5 Water Holding Capacity STP/SOIL 26 28.5 % by mass
6 Sand STP/SOIL 70.24 62.8 % by mass
7 Clay STP/SOIL 19.38 25.9 % by mass
8 Silt STP/SOIL 6.85 8.15 % by mass
9 Texture STP/SOIL Sandy Sandy -
10 TKN STP/SOIL 1744 2085.5 mg/kg
11 Phosphorus(as P2O5) STP/SOIL 42.1 53.84 mg/kg
12 Bulk Density STP/SOIL 1.16 1.17 gm /cc
13 Calcium STP/SOIL 3014.22 2685.7 mg/ kg
14 Magnesium STP/SOIL 667.5 587.4 mg/ kg
15 Sodium STP/SOIL 139.9 164.9 mg/ kg
16 Specific Gravity STP/SOIL 2.14 2.16 -
17 Oil & Grease STP/SOIL <10.00 <10.00 mg/ kg
113
18 Organic Carbon STP/SOIL 0.3 0.38 %by mass
Figure 25 Soils in different Parts of State and Town
114
5.6.1 Bathing Ghats
There are in total 17 nos. of bathing ghats in the town. This is contributing to the waste
water load into the river to some extent.
These are listed below:
1. Kunj Ghat
2. Rani Ghat
3. Asharfi Ghat
4. Triveni Shankar Ghat
5. Rakesh Ghat
6. Shivsharup Ghat
7. Shyamsunder Ghat
8. Dinesh Ghat
9. Patali Ghat
Figure 26 Soil Collection for sampling purposes
115
10. Ganga Parshad Ghat
11. Lal Mahadev Ghat
12. Ramesh Chand Ghat
13. Jai Krishan Ghat
14. Ganesh Mandir Ghat
15. New Ghat
16. Nagar Palika Ghat
17. Kanna Ghat
5.6.2 Biological Environment
There are no important or archeologically identified gardens/ parks in town. However the
region has small residential parks provided by municipal bodies, which will not be
threatenedby the proposed sewer works, since the sewers are planned to be laid in the
middle of theroad and will not pass through these areas.
Tree Cover: Trees can be seen along the road side in almost all parts of town. Practically
none of the trees will be disturbed nor damaged (tree cutting), since they are located on the
edges and sides of roads, away from the center, along which the sewers are planned to be
laid.
Agriculture: There is no agricultural practice in town. This district is the core city area with
mix of residents, commercial areas, institutes, hospitals etc.
Literally environment stands for the totality of surrounding conditions. Animals and plants
form a vital part of this sum total. Flora and fauna of an area are inter-related to each other
and have a very crucial impact on human life. With changes in environmental conditions,
structure, density and composition of plants and animals undergo changes as well. The
present study was carried out in two separate headings for floral and faunal community.
Flora: Presently there is no forest cover in and around the town. The project site is mostly
residential area and does not have any protected or reserved forest area. The site also does
not fall under India’s notified ecological sensitive areas.
116
Table 16 List of Flora in the town
Scientific name Local name Family Habit
Abrus precatorius L. Karjani Fabaceae Climber
Acacia catechu (L.f.) Willd. Khair Mimosaceae Tree
Acacia nilotica Willd. ex Delile Babul Mimosaceae Tree
Acacia pinnata Arar Mimisaceae Climber
Achyranthes aspera L. Chirchiri Amaranthaceae Herb
Adina cordifolia Hook. f. Karam Rubiaceae Tree
Aegle marmelos (L.) Correa Bel Rutaceae Tree
Aerva lanata Juss. ex Schultes - Amaranthaceae Herb
Ageratum conyzoides L. - Asteraceae Herb
Albizzia lebbek Benth. Siris Mimosaceae Tree
Albizzia odoratissima (L.f.) Benth. Jung sirisr Mimosaceae Tree
Albizzia procera Benth. Safed Siris Mimosaceae Tree
Alternanthera sessilis (L.) DC. - Amaranthaceae Herb
Anogeissus latifolia Edgew. Dhautha Combretaceae Tree
Apluda varia L. Dudhia sauri Poaceae Grass
Arundinella setosa Jharu/Motaminjhar Poaceae Grass
Asparagus racemosus Willd. Satawar Liliaceae Shrub
Azadirachta indica A. Juss Neem Meliaceae Tree
Bambusa arundinaceae Willd Bara bans Poaceae Grass
Bauhinia variegata L. kachnar Caesalpiniaceae Tree
Boerhavia diffusa L. - Nyctaginaceae Herb
Bombax ceiba Burm.f. Semal Bombacaceae Tree
Boswellia serrata Roxb. Salia Burseraceae Tree
Buchnania lanzan Spreng Piar Anacardiaceae Tree
Butea monosperma (Lam.) Taub. Palas Fabaceae Tree
Butea parviflora Cihut Fabaceae Climber
Calotropis gigantea R. Br. Akaon Asclepiadaceae Shrub
Carissa carandas L. Kanwar Apocynaceae Shrub
Cassia fistula L. Dharanj/Amaltash Caesalpiniaceae Tree
Cassia tora Chakor Fabaceae Herb
Cissampelos pareira L. Padh Menispermaceae Climber
Cordia dichotma Forst. L. Bahuar Ehertiaceae Tree
Cymbopogon martini Stapf. Nanha dudhe Poaceae Grass
Cynodon dactylon Pers. Dhoob Poaceae Grass
Cyperus rotundus L. - Cyperaceae Sedge
Scientific name Local name Family Habit
117
Dalbergia sissoo Roxb. Sheesham Fabaceae Tree
Dendrocalamus stricus Nees Bans/Bamboo Poaceae Grass
Dichrostachys cinerea L. - Mimosaceae Shrub
Diospyros melanoxylon Roxb. Tend/Tiril Ebenaceae Tree
Elephantopus scaberL. - Asteraceae Herb
Eulaliopsis binata (Retz.) C.E. Hubb. sabai Poaceae Grass
Euphorbia hirta L. - Euphorbiaceae Herb
Ficus bengalensis L. Bar Moraceae Tree
Ficus religiosa L. Pipal Moraceae Tree
Ficus tomentosa Roxb. Barun Moraceae Tree
Flacourtia Ramontchi Salpani Flacourticeae Shrub
Gmelina arborea Gamhar Verbenaceae Tree
Heteropogon contortus (L.) P. Beauv. Kher/Sauri Poaceae Grass
Holoptelea integrifolia Chilbil Ulmaceae Tree
Hygrophila spinosa T. Anders - Acanthaceae Herb
Imperata cylindrica (L.) P.Beauv. Ulu Poaceae Grass
Indigofera pulchela Jirhul Fabaceae Shrub
Ipomoea carnea Jacq. - Convolvulaceae Shrub
Justicia procumbens L. - Acanthaceae Herb
Kydia calycina Roxb. Puda Malvaceae Tree
Lannea coromandelica (Houttuyn) Merrill Genjan Anacaeaediac Tree
Lantana camara (L.) Moldenke. Putus Verbenaceae Shrub
Leonotis nepataiefolia R.Br. - Lamiaceae Herb
Madhuca indica J.F. Gmel. Mahua Sapotaceae Tree
Mangifera indica L. Aam Anacardiaceae Tree
Mimosa pudica L. - Mimosaceae Herb
Mukia maderaspatana Bilari Cucurbitaceae Climber
Parthenium histerophorus L. - Asteraceae Herb
Phoenix acaulis Roxb. Khejur Arecaceae Shrub
Pongamia pinnata (L.) Pierre. Kranj Fabaceae Tree
Pterocarpus marsupium Tree
Randia dumetorum Lamk Mowar Rubiaceae Shrub
Rubia cordifolia Jotsingh Rubiaceae Tree
Saccharum munja Roxb. Munj Poaceae Grass
Schleichera oleosa (Lour) Oken Kusum Sapindaceae Tree
Shorea robusta Roxb. Sal/ SaKhua Depterocarpaceae Tree
Sida acuta Burm.f. - Malvaceae Herb
Sida rhombifolia L. - Malvaceae Herb
118
Solanum nigrum Makoi Solanaceae Herb
Solanum surattense Burm. f. - Solanaceae Herb
Sphaeranthus indicus L. - Asteraceae Herb
Tectona grandis L.f. Saguan Verbenaceae Tree
Terminalia arjuna Bedd. Arjun Combretaceae Tree
Scientific name Local name Family Habit
Terminalia bellirica (Gaertn.) Roxb. Bahera Combretaceae Tree
Terminalia tomentosa Heyre ex. Roth Asan Combretaceae Tree
Thespesia lampas Ban kapasi Malvaceae Shrub
Tridax procumbens L. - Asteraceae Herb
Vetiveria zizanoides Nash Khus-Khus Poaceae Grass
Vitex negundo L. Sindwar Verbenaceae Shrub
Vitis latifolia Khopri Vitaceae Climber
Woodfordia fruticosa (L.) Kurz. Dhawai Lythraceae Shrub
Xanthium indicum L. - Asteraceae Herb
Zizyphus mauritiana Lam. Ber Rhamnaceae Tree
Zizyphus oenoplia Dhathora Rhamnaceae Shrub
Fauna: The number and species of wild animals are not in around the town. The project site
is mostly residential area and does not have any protected or reserved forest area. The site
also does not fall under India’s notified wild life sanctuaries and national parks. The huge
water body formed upstream of the barrage houses the dolphins. Upper Ganga stretch of
the river from Bijnor to Narora (165 km) is home to dolphins & forms a part of the RAMSAR
Site. WWF India has been working closely since late nineties with river bank communities
and aquatic species that could serve as a reliable indicator of the health of Ganga River.
While different strategies have been adopted by them from time to time, the focus has
always remained on the people & species.
The goal being to reduce the huge burden of pollution & other anthropogenic pressures that
Ganga River has borne particularly in the last few decades. The dolphin’s habitat parameters
in Ganga River
River stretch Kms Km Few Important Habitat Parameters
Mid Ganga River
119
Table 17Dolphin habitat parameters in Upper Ganga River (Narora- Anupshahr)
With active participation of WWE (India) and based on their study during 2007-2009, the
population of dolphins in the study area between Bijnor and Narora was recorded to have
increased .The population of dolphins in the study area was recorded to have increase (44 in
2007; 49 in 2008; 56 in 2009) during the project period (2007-2009). This signifies that the
recruitment and growth pattern on the population is increasing. This is most likely because
of the improvement in habitat conditions, as well as in the water quality. A decrease in the
death rate betweenyear 2007-2009, could also be a factor as o death was recorded in this
stretch.
The total dolphin population in upper Ganga system up to October 2012 was 671 with
following distribution. Ganga-261, Yamuna -31, Chambal-85, Ghaghara-231, Rapti-8,
Geruwa-39, Saryu-16.
Narora –Anupshahr (Zone I) 0-30 Deep pools, sandy and muddy river bank island with vegetation
River depth 1.5-4.3 m
River width 200-800 m
River velocity 3.0-5.5 m/sec
Air temp. 10-42° C
Water temp 12-28°C
ph 7.05-8.70
Dissolved Oxygen 6-8 mg/l
Conductivity 200-250 µ S/cm
120
The distribution of total dolphin population is shown in figure below.
5.6.3 Socio Economic Baseline
Socio-economic impact assessment of the study area of a project is pre-requisite before the
project is put into implementation. The study area consists of the core area where the
proposed project is expected to come up and a buffer area encircling the core area. The
government of India has since made mandatory a “likely impact assessment” study for all
types of upcoming and expansion projects. Socio-economic impact assessment is a
technique to get acquainted with social, cultural and economic conditions of stakeholders,
which includes individuals, groups, communities and organizations.
Figure 27Distribution of Dolphin in Upper Ganga System population up to October 2012 (source WWF)
121
The total population of Anupshahr Town is 29700, the average house hold size (per house) is
6 and total no of households are 3,929. The sex ratio in town is 882 and sex ratio (0-6) is
877, the percentage of literacy rate is about 67.0 % and total no of literates are 13,380. As
per census of India 2011 total no of workers in town are 7,399 in which main workers are
6,170 and marginal workers are 1,229.
Area Profile of Anupshahr (MB) Town of Bulandshahar district, Uttar Pradesh state
Number of Households 3,929 Average Household Size(per Household) 6.0
Population-Total 23,795 Proportion of Urban Population (%) 100
Population-Rural 0 Sex Ratio 882
Population-Urban 23795 Sex Ratio(0-6 Year) 877
Figure 28 Socio-Economic Profile of the town
122
Population(0-6Years) 3,746 Sex Ratio (SC) 877
SC Population 3,072 Sex Ratio (ST) 0.0
ST Population 0 Proportion of SC (%) 13.0
Literates 13,380 Proportion of ST (%) 0.0
Illiterates 10,415 Literacy Rate (%) 67.0
Total Workers 7,399 Work Participation Rate (%) 31.0
Main Worker 6,170 % of Main Workers 26.0
Marginal Worker 1,229 % of Marginal Worker 5.0
Non Worker 16,396 % of non-Workers 69.0
CL (Main+Marginal) 450 Proportion of CL (%) 6.0
Al (Main+Marginal) 424 Proportion of AL (%) 6.0
HHI (Main+Marginal) 621 Proportion of HHI (%) 8.0
OW (Main+Marginal) 5,904 Proportion of OW (%) 80.0
Source Census of India
123
Demography of Anupshahr Town
The Population distribution of Anupshahr town in 25 different wards as per the 2011
population data is given below:-
Ward No Mohalla Population (2001) Population (2011)
1 Delhi Dwar and Meera Anshik 1035 1417
2 Nehru Ganj and Delhi Dwaar Anshik 790 766
3 Delhi Dwaar Anshik 939 1014
4 Delhi Dwaar 1151 1809
5 Nehru Ganj 1022 3011
6 Madaar Dwaar 1040 2019
7 Jama Masjid , Nehru Ganj Anshik 782 603
8 Nehru Ganj Anshik 946 540
9 Meera 784 804
10 Delhi Dwaar Anshik , Meera Anshik 1100 2434
11 Madaar Gate and Nehru Ganj anshik 958 533
12 Gadiyana Anshik , Mori gate Anshik 827 1294
13 Jatiyana (Khatiyana), Meera anshik 1071 976
14 Aahar Dwaar Anshik , Gadiyana Anshik 836 1135
15 Maanak Chowk Anshik , Ganga Dwaar Anshik 841 996
16 Imli bazar , Ravtaan , Pusht Mandi, Gadiyana Anshik 847 731
17 Chhatta , Ganga Dwaar Anshik 862 586
18 Aahar Dwaar Anshik , Garhi 817 1558
19 Parkotta , Aahar Dwaar Anshik 1079 871
20 Nagar Shaily , Manak Chowk Anshik 968 1079
21 Pokhar , khidki , Ganga Dwaar Anshik 1016 1373
22 Pavitra Puri 1030 1432
23 Bazar Kala , Bazar Delhi Dwaar , Purani Tehsil anshik 794 574
24 Purani Tehsil 1135 1415
25 Kedar Shah 1025 719
Total 23695 29700
Source: Nagar Parishad, Anupshahr
The total census population for the year 2011 is 29,700. This population data presented
above is tabulated on the basis of the information provided by the local authorities and the
supporting letter is attached as annexure 15 to this report. However, the present population
i.e. for the year 2013 is 32000.
124
Anoopshahr
Figure 29 Density of Population in the town
125
Cultural significance
The distance between Anupshahr and Bulandshahr is 42 km. Anupshahr is easily accessible
from Bulandshahr by a car or bus.
Anupshahr is quaint town located on the ghats of River Ganga in Bulandshahr district. Best
time to visit Anupshahr is in February, March, October, November and December.
Anupshahr is very popular with the pilgrims especially during annual festivals like Kartik
mela. Anupshahr has been dubbed as “Choti Kashi”. Locals conduct evening aartiand offer
prayers on the banks of River Ganga, pilgrims and locals take baths in the holy
river. Anupshahr has several Hindu temples and guest houses to accommodate the pilgrims
and tourists.
A grand Mela is organized on the eve of Kartik Poornima when peoples use to come for holy
snan in Ganges River & purchase their essential commodities by staying in Anupshahr
city.Besides of this Mela there is a Holy Snan on every Poornima & Amavashiya & Ganga
Dassera
Anupshahr holds testament to the bold uprising of the locals against the British during
India’s War of Independence. Anupshahr is an ancient town founded in the 17th century by
Raja Anup Rai and it reached its most prosperous era during the reign of King Tara Singh.
King Tara Singh made Anupshahr a significant hub for the practice of Ayurvedic medicine.
Legends have it that Anup Rai had saved the life of Emperor Jahangir during his lion
expedition, pleased the Emperor had gifted this area to Anup Rai. King Anup Rai then
established a town and fort in this area.
In historical background Great Maharshi Dayananda Saraswati was visited here in 18th
century to raise awareness against various social evils present in the current society at that
time.
Anupshahr have leading schools like "LDAV, JAYPEE VIDYA MANDIR" etc.
Colleges like State renowned "Durga Prasad Baljit Singh PG College" and
above all newly opened "Jaypee University".
126
Two state highways is providing smooth connectivity to the city to other parts of UP.
Bridge over Ganga provides a quick connectivity to the area from northern parts like bandau,
Moradabad etc.
Figure 30 Mela pictures in Anupshahr
127
Figure 31 Cultural Significance in the state
128
Details of social survey
The approach and methodology followed for social baseline study as well as the social survey
has been discussed in the earlier Section of the report Consultation with stakeholder
consultations were performed during the field surveys to assess the situation and get the
feedback about the project from all the concerned stakeholders. Household owners & other
stake holders in 8 out of 11 wards were consulted, additionally other important set of
locals interviewed or consulted were pedestrians, shop-owners, school teachers, etc.
Some of these wards have academic and government institutions and most of them are
residential in land use.
All the local stakeholders were enthusiastic & had a positive gesture about the oncoming
sewerage project. Household’s survey were from both rich and poor localities. Most of the
household have access to drinking water facilities and electricity and some of the houses
have toilets as well, but since there is no sewerage system most of the waste water flows
directly in river Ganga. People, who were interacted with, were hopeful that the sewerage
scheme will improve the environment of the area & will have a positive impact on their
hygiene and health. They were also positive about taking sewer connections once the project
is implemented. They were also more concerned to do away with the present system of
discharging their waste water directly in the drain. They were hopeful that this would be
done away with after taking sewer connections & thus the overall environment of the town
would improve.
The Detailed analysis of the questionnaire is presented in the chapter 8 of this report.
129
6 Environmental and Social Impacts
This section addresses the basic concepts and methodological approach for conducting a
scientifically based analysis of the potential impacts likely to accrue as a result of the
proposed project. The Impact Assessment for quite a few disciplines is subjective in nature,
and cannot be quantified. Wherever possible, the impacts have been quantified and
otherwise, qualitative assessment has been undertaken. The proposed sub-project consists
of activities which include:
• Construction of approximately 60 km (approx.) long sewerage network
including all required trunk/ branch/ lateral sewer for year 2048.
• Construction of main sewage pumping stations for year 2048.
• Construction of 2 sewage treatment plant of 1.5 and 1 MLD capacity for year
2028.
Pollution abatement projects may prove beneficial for the environment and society or they
may have some adverse impacts as well. Planners and decision makers have realized the
importance of understanding the consequences of any such projects on both environmental
and social sectors, and have started taking steps to avoid any adverse impacts. Based on the
major findings obtained from the field visits and secondary data analysis, the possible
environmental and social issues with reference to the proposed sewer works in Anupshahr
has been discussed in these sections.
6.1 Environmental Impacts
The proposed project of sewer works in town would influence the environment in three
distinct phases:
During Designing phase
During the construction phase which would be temporary and short term;
During the operation phase which would have long term effects
130
6.1.1 Design and Development Phase
Sewer lines
All sewer lines including trunk, lateral and branch sewer lines must be designed considering
the future population and waste generation rate. Otherwise the constructed sewer may not
carry the waste load, leading to failure and financial loss. The alignment of sewer lines and
sewerage pumping station must be properly planned; else it may lead to both technical and
social problems along with environmental issues of back flow creating foul smell and
unhygienic conditions.
Sewerage Treatment Plant
Selection of a suitable technology for sewage treatment is governed by many factors such as
the location of STP, availability of land area, raw sewerage characteristics, capacity of plant,
required effluent quality, proven technology and reliability of process, intended disposal
method or reusing the treated effluent, capital cost, O&M requirement and other local
factors.
Comparative analysis of various technologies considered for selection is given in Table 6.1.
Table 18Comparative analysis of various sewage treatment technologies
Parameter Lagoons Extended
Aeration SBR MBR
MBBR & SAFF
UASB+EA
Foot prints High High Medium Low Low Medium
Energy Consumption
Low High Medium (KWH 1-1.5/m3)
Medium (KWH 1-1.5/m3)
High High
(KWH 0.5/m3)
(KWH 1.8-2.0/m3)
(KWH 1.5-1.8/m3)
(KWH 1.5-1.8/m3)
Operational issues
Low High High Medium High High
Capital cost Low Medium Medium High Medium Medium
Operation cost
Low High Medium Medium Medium Medium
(Rs. 10-15 /m3)
(Rs. 20-25 /m3)
(Rs. 15-18 /m3)
(Rs. 15-20 /m3)
(Rs. 15-20 /m3)
(Rs. 15-20 /m3)
Manual attention
Low High Medium Low High High
Sludge Generation
Low High Medium Medium Medium Medium
Efficiency BOD Removal
60-80% 90-95% 90-95% 95-98% 90-95% 90-95%
Hydraulic Retention
3-7 Days 24-28 Hrs NA 8-10 Hrs 10-12 Hrs 18-28 Hrs
131
Time
Sludge Age (SRT In Days)
NA 20-30 days 30-40 Days
30-40 Days
NA 20-30 days
BOD Loading Rate (Kg/m3/Day)
0.03-0.05 0.3-0.4 NA 0.6-0.8 0.5-0.6 0.3-0.4
F:M NA 0.05-0.15 NA 0.05-0.15
NA 0.05-0.15
Oxygen Requirement (ppm)
Natural Oxygen
0.2-0.4 ppm NA 0.2-0.4 ppm
0.2-0.4 ppm 0.2-0.4 ppm
6.1.2 Impacts during construction phase
The proposed sub-project consists of two major activities which include:
Construction of approximately 60 kms (approx.) long sewerage network including all
required trunk/ branch/ lateral sewer.
Intermediate Sewage Pumping Station
The construction activities would generally include earthworks (excavation, filling,
shuttering, compacting), temporary diversion of existing sewer lines, civil construction
(sewer lines, STP, SPS, etc) and E & M installation and commissioning. The impacts of these
construction stage activities on the various environmental parameters are examined below:
6.1.2.1 Environmental sensitive areas
Based on observations and findings from field visits, interaction with government officials
and consultation with local residents, an assessment of the environmentally and ecologically
sensitive areas was made (Refer to screening checklist Table 1).
The project area falls under Ramsar site which is a sensitive area from the ecological point
of view, but it is not a protected area under wildlife protection act 1972. Prior to
implementation of the proposed project, the previous study of WWF indicates that:
1. The number of Dolphin from 2007 to 2009 has increased between Bijnor to Narora
along Ganga main stream 44 to 56.
132
2. D.O. level of river Ganga at Narora upstream and downstream of the main drain
discharging into it is 6.8 mg/l and 6.6 mg/l respectively which is within the
Dolphin habitat parameter
Therefore even with the present condition, the project area provides a preferred
habitat location for Dolphins and it is expected that with the treatment of waste water
the habitat condition for dolphin will further improve and hence the project overall
will have a positive impact.
As explained in section 5.1.10 of baseline environment status, town does not have any flora
and fauna components; there are no nearest eco-sensitive areas such as National Park and
wild life sanctuaries within a 100 km from the proposed project site. However the region has
small residential parks and road side trees, which will not be affected by the proposed
sewer works, since the sewers are planned to be laid in the middle of the road and will not
pass through these areas. With regard to sensitive aquatic areas and water bodies, there are
none. It was also observed that the major land use pattern of town is residential, with no
agricultural and no forest areas.
6.1.3 Air quality
Based on the field observation and interaction/consultation with stake-holders, it is
expected that the levels of dust (RSPM and SPM), carbon mono- oxide (CO), hydrocarbons
and NOx (NO &NO2) is likely to increase during the construction phase mainly because of:
Excavation, backfilling, compaction activity and movement of vehicles on un-paved
roads (increases dust level)
Vehicle exhausts from construction machinery and from light and heavy vehicles for
transportation of pipes and construction material like cement, etc (increases NO2).
Use of portable diesel generators and other fuel fired machinery, and (increases CO).
6.1.4 Noise levels
The proposed construction activities are expected to increase the noise levels mainly due to
plying of construction vehicles, pumping machines, use of portable generators, mechanical
machinery such as cranes, riveting machines, hammering etc. These activities will occur
round the clock and the noise pollution thus created may affect human habitations,
particularly during the night time. Increase of noise level at night may produce disturbances,
133
causing sleeplessness in people in the vicinity of the site in case construction activity is
extended into the night hours. As per the baseline environmental status, the noise levels in
town are expected to be within permissible limits as the area is mostly residential and has
limited commercial, and no industrial area. Facilities that are expected to feel the temporary
impacts more than others include schools/colleges.
6.1.5 Water resources
From field visits, interactions and consultations, it was found that there were no water
bodies in the project area. The natural drainage channels of the project area are likely to be
affected in the following ways:
Direct discharge from construction activities - If the construction wastes and
construction related material are not properly handled/ managed, then certain
impurities like suspended particles, pollutants like oil, grease, cement etc, may find
their way to the river, storm drains during rainfall. There may also be temporary
blockage of drains due to unmanaged material and construction debris.
Flooding is likely during monsoon as drainage paths could be obstructed and
redirected by the debris; this concern was also voiced by residents. During
construction of sewerage works in town, there may be flooding due to the already
blocked state of drains and nalas, due to poor solid waste management.
The excavation activities will be carried out up to a depth of 8 m or so, and will not
impact the groundwater levels of the region since a provision for dewatering and
lowering of water table has been made in the detailed project report.
6.2 Impacts during operation phase
6.2.1SENSITIVE AREA
The project area falls under Ramsar site for which necessary management plan
is being prepared by the forest to department. The expected impacts from the
operation phase of the project is mostly positive to the Dolphin habitat since the
water quality of Ganga is expected to be further improved from the project
(which is at present having DO level in the range of 6.6-6.8mg/l). However, care
need to be taken to ensure that the noise level from various project facilities like
SPS, STPs are well within the permissible limits for the sensitive area as per the
guidelines of CPCB.
134
As part of the NGRBA programme, Dolphin status surveys are proposed in UP and are in
process of sanctioning which will also be repeated by the forest department on regular interval
(one in 3 years). The present Dolphin concentration in the area (23 in number) will thereby to
be monitored by these status surveys. Corrective actions may need to be taken if Dolphin
number are decreased over a period of time.
6.2.2 Water environment
Water resources in the project area would be the most positively benefited by the
sanitation project since additional sewage will now be routed to the STP. Therefore proper
operation and maintenance mechanism must be followed for efficient working of the
system. The probably environmental impacts related to water during operation stage may
include unpredictable events such as:
Temporary flooding of adjacent areas due to accidental leakages/bursts and also
due to blockages and backlogging of lines.
Water pollution and possibility of mixing with water supply line due to leakages/
overflows from the sewer lines.
Impairment of receiving water quality in surface/sub-surface source due to
inadequate /inefficient sewage treatment process.
6.2.4 Noise and air quality
Improper handling and irregular maintenance of operating machines including pumps,
generators, air diffusers, etc. may lead to increased noise pollution during operation
activity. There will also be minimization of gas being emitted from the sewage drains, since
during operation, most of the works will be laid underground.
6.3 Potential Social Impacts
The proposed project of sewer works in town would influence the social sector in a distinct
phase of construction period which would be temporary and short term.
6.3.1 Social Impacts
6.3.1.1 Impact on human health
One of the potential impacts of the proposed sub-projects will be on the air quality due to
the dust generated during excavation and tunneling. The amount of dust generated will
depend upon the level of digging and the prevailing weather conditions and can have an
adverse impact on the health of the persons residing or working near the project sites. Since
135
the town has more of residential land use, the number of people who will be affected is
more. Residential population includes more vulnerable groups such as the elderly and
children.
The main residential areas of Anupshahr is given below:-Delhi Dwar, Meera Anshik, Nehru
Ganj, Delhi Dwaar Anshik, Nehru Ganj, Madaar Dwaar, Jama Masjid , Nehru Ganj
AnshikMeeraDelhi Dwaar Anshik , Meera AnshikMadaar Gate and Nehru Ganj anshik
6.3.1.2 Traffic Congestion
Due to the excavation work which will take place on the main roads of the city, there will be a
disturbance in the traffic movement. People may suffer some inconvenience during the
morning and evening peak hours. This issue is discussed in the DPR, and suggests de-routing
of the traffic as the mitigation measure.
6.3.1.3 Impact on livelihood
The excavation and tunneling work will lead to road blockage and as a result the commercial
establishments and vendors will have some trouble in operating their business on daily
basis. But there will be no loss of livelihood. Ambulatory vendors can very well shift their
place as and when required. So, overall no loss of livelihood is anticipated during the survey.
6.3.1.4 Impact on existing utility services
The road opening activities may damage the underground water pipelines or electricity poles
in the vicinity of the site for the proposed sub-projects. This will lead to water supply
interruptions, disruption in electricity supply and will involve expensive repair costs.
Flooding of areas could also occur. Officials of UP Jal Nigam stated that they receive some
complaints about water line brakeage during the construction phase. With no other
alternative source readily available, people have to buy water from private tanks or buy
bottled water for drinking purpose till the time service is restored to normal. The DPR also
notes impacts on utility services as a potential issue.
6.3.1.5 Elevated Noise Levels
Increase in noise pollution due to construction from construction equipment. This will
disturb residences, and especially schools and institutes in and around Civil Lines area,
136
Medical College area, etc. For elderly and students, noise is disturbing and affects their
comfort. This could be a problem especially in sensitive areas like school and hospitals.
6.3.1.6 Failure to Restore Temporary Construction Sites
Excessive debris, trash or construction remnants (e.g. dirt piles) would create problems
related to drainage, unhygienic conditions and poor aesthetics; however, clean-up and
debris clearance is budgeted in the DPR so this should not be a concern.
6.3.1.7 Land Acquisition
No land acquisition is proposed in this project hence no relocation would be needed.
6.3.1.8 REUSE OF TREATED EFFLUENT
Based on the enthusiasm and readiness the farmers shows during various
consultations, meeting conducted with them to discuss the issue of reuse the treated
effluent for irrigation purpose, it is clearly evident that the effluent will be recycled.
The network for achieving the 50 % of treated waste water used for irrigation purpose
in first five years and 100 % reuse of next 5 years of operation period will be adopted.
The required written consent from potential end users has already taken. Provision to
use is being made in the mitigation and management plan.
6.3.1.9 DISPOSAL OF STP SLUDGE
The sludge collected from STP will be stack within STP campus for short duration,
which will ultimately be sold/ distributed to farmers as manure. After drying, the
composted sludge as a soil conditioner in agriculture and horticulture returns carbon,
nitrogen, phosphorus essential for plant growth. Reuse may still be possible for
purposes such as highway landscaping or for landfill cover.
The garbage, brick bats, polyethylene waste screen out at screen chamber of pumping
stations will be screen out periodically and collected in the campus to dry. This waste
ultimately disposed of at solid waste disposal site as designated by Nagar Palika
Anupshahr.
Conclusion
Based on the overall secondary data analysis and field investigation, the proposed project is
expected to benefit the Anupshahr town, as the wastewater that currently flows untreated
into the Ganga river will be captured, treated and the remainder of the treated effluent will
137
be allowed to flow into the river. The likely
beneficial impacts of the projects include
• Improvement in sewerage collection and
treatment within the cities/towns
• Prevention of storm drains carrying sanitary
sullage or dry weather flow
• Prevention of ground water and soil
pollution due to infiltration of untreated liquid waste
• Prevention of discharge of untreated sewage
into River Ganga
• Improvement in water quality of River Ganga,
a national resource
• Improvement in environmental sanitation
health and reduction in associated health
hazards within the cities/towns
• Improvement in quality of life, human dignity and increased productivity
• Reduced nuisance of open defecation due to low cost sanitation and reduced malarial
risks and other health hazards
Although there would not be any permanent negative or adverse environmental impacts,
but will have temporary impacts, that can be mitigated with appropriate mitigation plans.
However, the large environmental benefit of the project greatly outweighs the temporary
inconveniences.
138
7 Mitigation and Management Plan
7.1 Environmental Management Plan
Table 24 summarizes the environmental management plan for low category investment that
identifies the potential issues of various activities that are anticipated in the design and
development, construction, and operation phases of the proposed sewer work in
Anupshahr. The environmental management plan ensures to suggest appropriate mitigation
measure against the issues/ concerns identified during the environmental and social
assessment study.
In general, the Uttar Pradesh Jal Nigam (with assistance from Contractor and Independent
Engineer/Supervision Consultant) is the responsible entity for ensuring that the mitigation
measures as suggested in the ESMP. The roles and responsibilities of the involved institutes
are described below.
7.1.1 Implementation of EMP Specific activities by Uttar Pradesh Jal Nigam
The role of Uttar Pradesh Jal Nigam in the implementation of EMP involves the following
activities:
EMP clearance from NMCG and World Bank and disclosure as required;
Integrating the EMP in the bid document of contractor as an addendum;
7.2 Implementation of EMP
The contractor shall be responsible to implement the EMP primarily in assistance with
theProject Management Consultant team. The Environmental Specialist from the
IndependentEngineer / Supervision Consultant shall monitor the compliance of the EMP and
all the designdrawings of various civil structures shall be implemented after his approval.
The State, local Government will be responsible for Coordination, Monitoring and
evaluation ofthe Environment Management Plan. It should ensure all the safeguarding plans
are in line andacted upon. Contractor shall report the implementation of the Environment
Management Plan tothe Environmental Expert and the Project management consultant as
well as to Uttar Pradesh Jal Nigam through monthly reports. Further a quarterly report is
required to be preparedand required to be given to National Mission for Clean Ganga
(NMCG) for the progress made inimplementing the Environment Management Plan.
139
Feedback from the local residents can also be taken from time to time to cross check the
contractor’s report. Project management consultants should make inspection visits at
construction site to check the implementation of Environment Management Plan as per the
contract.
Environment Management Plan
Table 19 Environment Management Plan
Activity Potential Negative Impact/Concern
Duration of impact
Mitigation Measures Responsible agency
Sewerage and Sanitation Investments
A. Design and Development Phase
Sewage treatment plant
Treated water disposal into nearby stream Ganga
Pollution of receiving water body (river) or land due to insufficienttreatment or nonoperation of STP
Temporary The treated water quality shall comply with the prescribed NRCD standards of the bid document and other applicable conditions of consent to establishissued by the state pollution control board.
Parameters NRCD standards
TSS mg/l <20
BOD5 at 20°Cmg/l
<20
Selection of best available sewage treatment technology with High BOD removal efficiency.
Ensuring development and compliance to standard operation and maintenance practices.
Provision of effective screening at inlet of STP for removal of grit, fine plastics and other suspended solids
Provision of effective separation
DBOOperator
141
and controlled disposal of digested sludge
Provision effective disinfection before discharge of treated water for irrigation or to river.
STP Breakdown
Discharge of untreated sewage leading river pollution.
Temporary Provision of adequate holding capacity adequate for storage of sewage to prevent flow of untreated sewage to river.
DBO Operator
Flooding of STP area
Rain water may flood the STP area in absence of adequate provision of diverting rain water flow towards STP.
Temporary Suitable drainage provision shall be made to divert the rain water likely to be accumulated from peripheral catchment area of STP, to natural drainage stream or area.
DBO Operator
Sludge disposal
Disposal of sludge leading to contamination of land and water.
Permanent Efficient sludge dewatering with minimum land requirement shall be adopted.
Provision shall be made for intermittent storage of digested sludge at STP site.
Digested sludge shall be utilized as manure or disposed to suitable site as approved by DBO engineer.
If disposal is made in a land fill site, then it shall be located away from habitation and water bodies and shall be pre-approved by concerned authorities like
DBO Operator
142
Municipal Corporation, Pollution Control Board or Urban Development Authority.
Provision for safety of workers and safe operation of STPs
injury or death of workers (Fall of workers from Height, Fall into deep water tanks, Short Circuiting)
and fall in walk ways or work areas
gas such as Chlorine
Permanent All electric switches (including unit specific on-off switches installed at respective units) and panels shall have adequate protection from rain water to prevent short circuiting Proper earthling with installation of earth circuit breakers shall be made Walk ways designs shall be made with proper slope to avoid accumulation of rain water. Material handling and storage shall be so designed that walk way surface remains free from wet or oil surface situation to prevent slips, trip or fall accidents.
DBO Operator
Location of STP
fly nuisancehazards toneighboringareas.
Permanent Ensure minimum noise generation at STP
Minimize Tree cutting if involved. Tree plantation of around the periphery of STP site and landscaping to prevent spread of bad odour with large canopy/ broad leaves trees. Species of plants shall be finalized with local office of Forest Department.
DBO Operator
143
Criteria for selecting species are: - plant should be fast
growing; - preferably perennial and
evergreen; - indigenous; - resistant to SPM pollution,
and - should maintain the
ecological and hydrological balance of the region. The general consideration involved while developing the greenbelt are:
- Trees growing upto 10 m or above in height with perennial foliage should be planted around the perimeter of the proposed project area.
- Trees should also be planted along the road side in such a way that there is dust control.
- Generally fast growing trees should be planted.
- Since, the tree trunk area is normally devoid of foliage upto a height of 3 m, it may
144
be useful tohave shrubbery in front of the trees so as to give coverage to this portion.
Main sewage pumping station
Pumping of sewage to STP
nuisance hazards to neighboring areas.
Permanent Ensure minimum noise generation at pump station inSPS by use of less noise generating equipment meetingprescribed noise standards as applicable and enclosedgenerators.
No Tree cutting is involved. Tree plantation aroundthe periphery of SPS site and landscaping to prevent spread of bad odour with large canopy/ broad leaves trees like Shisham, Neem, Bargad, Teak, Sal, etc.
Accumulated screenings and grit in each SPM to be cleaned on a daily basis. Spraying of suitable herbicides on accumulated material to reduce odour, if it is not being cleaned on a daily basis due to same exigencies.
Provision for regular maintenance and switching offequipment when not in use.
DBOOperator
Construction Phase:
145
Sewage treatment plant and main sewage pumping station
Excavation Loss of topsoil due to excavation activities.
Temporary Excavation shall be planned in such a manner that such that no damage occurs to existing structures.
Top soil shall be separately stockpiled and utilized for green belt development or landscaping after completion of work
DBOOperator
Construction waste Temporary Excess soil generated from various construction activities shall be proper disposed in low lying areas, other than water bodies.
All construction vehicles, parking location, fuel / lubricant storage sites, vehicle, machinery and equipment maintenance will be located at least 500m from rivers and irrigation canal /ponds.
Normally, muck is disposed in low-lying areas or depressions. Trees, if any, are cut before muckdisposal, however, shrubs, grass or other types of undergrowth in the muck disposal at sites perish. The total area required for muck/sludge/solid waste disposalfor year 2045 is 1 ha.
The dumping of muck will be done
DBOOperator
146
in the scientific manner by providing appropriate protection walls with deep foundations so that muck will not flow and washed away in the river. Masonry work and crate work will also be provided wherever necessary in order to avoid thechances of soil erosion and to ensure flow of silt, free water. Besides these engineering measures, proper plantation will be done at the dumping sites for reclamation of the dumping areas.
Muck generally lacks nutrients and therefore, is difficult to re-vegetate. However, if no attempts to vegetate the slopes are made, the muck could slide lower down during rain and may eventually wash off the protective measures also. Bio-fertilizer technique developed by National Environmental Engineering Research Institute (NEERI) can be adopted in the proposed project.
It is recommended that bituminous waste to be disposed at approved waste disposal sites,
147
which shall be finalized in consultation with district administration and regional offices.
Soil Erosion Temporary Provision of garland drain along construction site, to divert runoff to sumps for storage and settling of separated solids.
The required protective work i.e. formation of traces, construction of garland drains outside the periphery of dump followed by settling tank to avoid wash off.
DBOOperator
Nuisance due to domestic solid waste disposal
Temporary Provide two bins for recyclable and non-recyclable wastes.
Ensure that recyclable and non-recyclable wastes are collected in segregated manner in theses bins before disposal. Recyclable material shall be sold. Non-recyclable material shall be disposed to designated landfill area of the city.
Provide adequate sanitation facility for workers at construction sites.
DBO Operator
Dust Generation due to construction Activities
Temporary Excavated material transported by trucks will be covered and/or wetted to prevent dust nuisance.
DBO Operator
148
Suppressing dust generation by spraying water on stockpiles and unpaved movement areas
Water sprinkling over excavated areas, unpaved movement areas and stockpiles.
Transportation of loose construction material through covered trucks.
Use dust curtains (polysheets/ sheets) around the construction area for containing dust spread.
Construction equipment must comply with pollution norms and carry Pollution under Control certificate
Temporary flooding due to uneven dumping of construction waste
Temporary The construction waste material shall be stored on higher areas of the site and or areas where water may not accumulate creating flooding like situation
DBO Operator
Spillage of fuel and oil Temporary Care to be taken to store fuel and oil (if required) at a place away from any drainage channel/nalla preferably to be stored in drums mounted on a concrete paved platform with slop draining to small spills collection pit.
All location and lay-out plans of
DBO Operator
149
such sites will be submitted prior to the establishment and will be approved by the Engineer.
Ensure that all vehicle / machinery and equipment operation, maintenance and refueling will be carried out in such a fashion that spillage of fuels and lubricants does not contaminate the ground.
Arrangement for collection, storing and disposal of oily wastes to the pre-identified disposal sites (list to be submitted to Engineer) and approved by the Engineer. All spills and collected petroleum products will be disposed off in accordance with MoEF Engineer will certify that all arrangements comply with
Noise and vibration disturbances to residents and businesses
Temporary Construction activities to be carried out in day time with prior intimation to local residents and shop keepers.
Vehicles to be equipped with mufflers recommended by the vehicle manufacturer.
Staging of construction equipment and unnecessary idling of equipment within noise
DBOOperator
150
sensitive areas to be avoided whenever possible.
Operators of heavy machinery and workers in near vicinity will be provided with ear plugs and other protective measures for safety.
Notification will be given to residents within 300 feet (about 90 to 100 m) of major noise generating activities.
The notification will describe the noise abatement measures that will be implemented.
Monitoring of noise levels will be conducted during the construction phase of the project. In case of exceeding of pre-determined acceptable noise levels by the machinery will require the contractor(s) to stop work and remedy the situation prior to continuing construction.
Use of low noise and vibrating equipment (such as enclosed generators with mufflers, instruments with built in vibration dampening and improved exhaust), to meet standards as
151
prescribed by Central Pollution Control Board (CPCB1).
Provision of personal protective equipment (PPE) like ear muffs and plugs for construction workers.
Provision of noise barriers as feasible in inhabited areas, particularly near sensitive zones like hospitals, schools etc.
The maximum permissible sound pressure level shall be75 dB(A) at a distance of 1 m from the source.
Maximum Exposure Periods specified by OSHA
Maximum equivalent continuous noise level
dB(A)
Unprotected exposure period
per day for 8 hrs/day and 5
days/week
90 8
92 6
95 4
97 3
100 2
102 1-1/2
105 1
107 ½
152
110 ¼
115 1/8
Noise from the DG set shall be controlled by providing an acoustic enclosure or by treating the enclosure acoustically.
The acoustic enclosure/acoustic treatment of the room shall be designed for minimum 25 dB(A) Insertion Loss or for meeting the ambient noise standards, whichever is on the higher side.
The DG set shall also be provided with proper exhaust Muffler to attenuate noise level by at-least 25 dB(A).
Efforts will be made to bring down the noise levels due to the DG set, outside its premises, within the ambient noise requirements by proper sitting and control measures.
A proper routine and preventive maintenance procedure for the DG set shall be formulated and followed in consultation with the DG set manufacturer which would help prevent noise levels of the
153
DG set from deteriorating with use.
General: safety during construction
Safety and Health Hazard
Safety hazards to labours and public
Temporary Comply with the Occupational health and Safety act of India Ensure that the contact details of the police or security company and ambulance services nearby to the site.
Ensure that the handling of equipment and materials is supervised and adequately instructed.
Follow safe practices for working at height or confined area or underground working for safety of workers.
Erect warning signs/ tapes and temporary barriers and/or danger tape, marking flags, lights and flagmen around the exposed construction works warn the publicand traffic flow of the inherent dangers.
Provide adequate PPE to workers such as helmets, safety shoes, gloves, dust masks, gumboots, etc. to workersProvide handrails on both sides of walkways close to
DBO Operator
154
deeper tanks and STPs need to be ensured;
Smaller on and off switches at STP units to be installed with protection from rain water to minimize electrical short circuit;
Monthly reporting of all accidents and immediate reporting to DBO engineer and owner
Construction camps (if adopted)
Sanitation Nuisance due to absence of facility of sanitation and solid waste management
Temporary Labour camp if provided, must have
adequate provision of shelter, water
supply, sanitation and solid waste
management
DBO Operator
General: Traffic control
Traffic control
Inconvenience to public Temporary During construction phase, planks/makeshift pathways shall be provided along the construction areas for the public to access their requirements for residential, shopping and other facilities.
Contractor shall deploy more work forces for speedy completion of activities in these areas.
Shopkeepers will be informed prior to construction along the commercial areas.
Activities requiring maximum
DBO Operator
155
access control to be done during non-peak hours.
Excavation along the road to be done in such a way that entire stretch will not be trenched at a time.
Traffic management with diversion through alternate routes will be implemented by providing adequate sign boards.
Trenching and pipe laying along the traffic routes will be planned and integrated to avoid retrenching/ modifying trench during pipe laying along the same line.
Work shall proceed on schedule so as to minimize road closures
Upon project completion, quick clearance of debris, etc. will facilitate access by customers to local business and residents to their households Placement of traffic officers at busy intersections to facilitate easy of movement. Prior public notice indicating the date of start of construction and end date of construction should be provided
156
road-wise to the locals, allowing them to make adjustments accordingly
Damage to existing utilities
Buildings / Water Supply pipe / Electric line etc.
Damage to underground utilities like water, gas line, electricity and telephone conduits etc. due to construction activities.
Temporary Buildings of risk will be identified prior to construction
Review all available drawings, notes, and information on the existing underground lines and structures in determining the location of the existing facilities.
Concerned authorities shall be informed and their assistance sought to remove, relocate and restore services of these utilities prior to commencement of construction.
All these underground utilities encountered in excavating trenches carefully shall be supported, maintained and protected from injury or interruption of service until backfill is complete and settlement has taken place.
Local population shall be made aware of timing/location of all construction, enabling them to respond swiftly to supply disruption, especially in the event
DBO Operator
157
of flooding, etc.
Minimal time for replacement operations; and appropriate scheduling as necessary especially for water supply line
Operation Phase
Sewage treatment plant and Sewage pumping station
Treatment and Disposal of Treated Water and Sludge
River, land or ground water pollution due to discharge of untreated or partially treated sewage due to inadequate or inefficient STP operations.
Permanent Monitor the treated sewage quality and ensure compliance with PCB standards for effluent disposal into surface water bodies, on land or for the agricultural use.
Follow standard operating procedures for operation and maintenance.
Undertake periodic audit as per these procedures.
Comply with all applicable condition of consent to operate Quarterly monitoring of influent sewage, treated sewage, upstream and downstream point of treated sewage disposal point to river.
Quarterly monitoring of influent sewage, treated sewage, upstream and downstream point of treated sewage disposal point to river, to ensure thatNRCD standards of water quality BOD<20 mg/l and SS <30 mg/l mentioned under the design and development phase of this table are met.
DBO Operator
158
Problems arising due to bad odour, insects, polluted air.
Temporary Maintain the green belt as per provision of design to prevent spread of bad odour with large canopy/ broad leaves trees like Shisham, Neem, Bargad, Teak, Sal, etc.
Accumulated sludge and solid waste to be cleared within 24 hours and spraying of suitable herbicides on accumulated sludge/solid waste to reduce odour.
Quarterly monitoring of Ambient Air Quality with respect to PM10, PM2 5, S02 and N02, CO and Odour at three locations (at STP site, minimum 500 m away from STP site in up-wind and down-wind direction of STP area.
DBO Operator
Increase in Ambient Noise Level and discomfort to neighboring people
Temporary Proper handling and regular maintenance of operating machines including pumps, generators, air diffusers, etc.
Quarterly Monitoring of Ambient Noise level to check compliance to standards.
Quarterly monitoring of ambient noise levels (day and night) at same locations as of ambient air monitoring
DBO Operator
Indiscriminate disposal of sludge leading to contamination of land and soil.
Temporary Prepare sludge disposal plan as per desire stage provisions and guidelines and adhere to the same.
DBO Operator
Main pumping station
Waste Handling
Bad odour, Health hazard and public nuisance
Temporary Provision for regular clearance of sludge and solid waste to minimize odour nuisance
Ensure maintenance of Green belt as planned
DBO Operator
159
Periodic disposal of accumulated sludge/solid waste to designated land fill sites of the city.
General Safety
Workers exposure to hazardous materials/ situations
Serious/health/safety hazards
Temporary Safety shoes or boots with non-slip soles will be provided to the workers at site Personal protective equipment and chemical resistant clothing to avoid exposure of skin or eyes to corrosive and/or polluted solids, liquids, gases or vapors Electrical equipment for safety before use will be checked; verified that all electric cables are properly insulated Safety goggles will be provided to operators in all cases where the eyes may be exposed to dust, flying particles, or splashes of harmful liquids Respirator or gas mask will be provided to workers when exposed to harmful aerosols, dusts, vapors or gases Extreme care will be taken when handling highly corrosive agents such as liquid or gaseous chlorine, concentrated acids or alkalis, or when toxic gases may be emitted from the reagents, etc. Workers will not be allowed to smoke, eat or drink in areas where chemical or biological contamination may be expected All workers will undergo periodic examinations by occupational physician to reveal early symptoms of possible chronic effects or allergies Follow safety measures and Emergency preparedness plan evolved
DBO Operator
160
at design stage
161
Table 20 Environmental Management Plan for Sewerage Network in Anupshahr
Activity Potential Negative Impact/Concern
Duration of impact
Mitigation Measures Responsible Agency
Sewerage and Sanitation Investments
A. Design and Development Phase Sewerage Network (Trunk Sewer Line)
Accidental leakages/ bursts
• Due to accidental burst or leakage of sewers, flooding of the nearby areas
• Backlogging due to unexpected heavy flow rates
Temporary • Design sewers with adequate capacity and flow velocity
• Provision for regular inspection and maintenance of the sewers
• Selection of appropriate location away from sensitive locations such as schools and hospitals.
• For pipelines laid in areas close to river Ganga, there could be increased vulnerability to accidental burst or leakage of sewers, due to uplift pressure. In sites, suitable anchoring measures to prevent uplift need to be commissioned as a part of structural design of the sewers. In such, areas frequency of inspection of sewers need to be increased and in such sites, inspection should be conducted at least once in a month.
• Preparation of safety and Emergency Preparedness plan
DBO Operator
Sewage Pumping Station
Location of Sewage Pumping Station and Pumping of sewage from SPS to STP
• Noise and odour nuisance hazards to neighboring areas. Cutting of Trees
Permanent • Ensure minimum noise generation at pump station in SPS by use of less noise generating equipment meeting prescribed noise standards as applicable and enclosed generators.
• Minimize Tree cutting if involved. Tree plantation around the periphery of SPS site and landscaping to prevent spread of bad odour with large canopy/ broad
DBO Operator
162
leaves trees like Shisham, Neem, Bargad, Teak, Sal, etc.
• Accumulated screenings and grits to be cleaned at short intervals and spraying of suitable herbicides on accumulated screenings and grits to reduce odour.
• Provision for regular maintenance and switching off equipment when not in use.
Construction Phase
Sewerage (laying of sewers) and Sewage Pumping station
Excavation, cutting, back filling, compaction and construction operations
Damage to underground utilities like water, gas line, electricity and telephone conduits etc. due to construction activities.
Temporary • Identify existing underground other utility structures, lines through available records and in consultation with concerned authorities and plan construction activities accordingly to minimize damage to such utilities. These underground utilities encountered in excavating trenches carefully shall be supported, maintained and protected from damage or interruption of service until backfill is complete and settlement has taken place.
DBO Operator
Accidents/ damages due to erosion/ sliding of vertical sides of excavated trenches while places the pipes
Temporary • Maintaining the excavation by Shoring trench sides by placing sheeting, timber shores, trench jacks, bracing, piles, or other materials
• Exposed surface shall be resurfaced and stabilized by making the sloping sides of trench to the angle of repose at which the soil will remain safely at rest.
DBO Operator
Generation of substantial debris, top soil and muck during construction
Temporary • Top soil shall be preserved and may be used for agricultural purpose or development of city parks.
• Soil and debris may be managed for planned land filling and landscaping;
• Debris may be suitably stored to filling back the excavated areas after placing
DBO Operator
163
the trunk sewer lines. Dust Generation (Air
Pollution) due to excavation, cutting, back filling and compaction operations
Temporary • Water sprinkling over excavated areas, unpaved movement areas and stockpiles.
• Transportation of loose construction material through covered trucks.
• Use dust curtains (polysheets/ sheets) around the construction area for containing dust spread at SPS building construction site.
• Construction equipment must comply with pollution norms and carry Pollution under Control certificate.
DBO Operator
Noise and vibration disturbances to residents and businesses
Temporary • Construction activities to be carried out in day time with prior intimation to local residents and shop keepers.
• Construction work near schools and colleges to be carried out during vacations and work near hospitals to be completed on priority basis (in shorter time period with alternate provision of traffic, accessibility of exit/entry gates etc.).
• Use of low noise and vibrating equipment meeting prescribed noise standards.
• Provision of personal protective equipment (PPE) like ear muffs and plugs for construction workers.
• Provision of noise barriers in inhabited areas, particularly near sensitive zones like hospitals, schools etc. • DG set to be fitted acoustic enclosure
DBO Operator
164
Temporary flooding due to excavation during monsoons or blockage of surface drains
Temporary • Stockpiled areas to be bordered by berms
• Stockpiles to be done in high areas to avoid flow in storm water run-off channels and erosion.
DBO Operator
Increased traffic inconvenience (emissions, congestions, longer travel times, blockage of access)
Temporary • Alternate traffic routing must be adopted in consultation with concerned traffic police authorities. Proper traffic planning be made for narrow lane areas.
• Work should to be completed on priority near business and market place to minimize business loss.
• Care should be taken to minimize congestion and negative impacts at schools and hospitals. Safe access shall be maintained to these places during construction. Provide temporary crossing/ bridges as may be required to facilitate normal life and business
DBO Operator
Settlement of backfilled area after construction
Temporary • The backfilling material shall be free from petroleum products, slag, cinders, ash or other material.
• Backfilling activity shall be completed within five days of laying of sewer.
• Proper compaction as per the soil condition and retain the original level of alignment and grade.
DBO Operator
Spillage of fuel and oil Temporary Care to be taken to store fuel and oil (if required) at a place away from any drainage channel/nalla preferably to be stored in drums mounted on a concrete paved platform with slop draining to small spills collection pit.
DBO Operator
165
Nuisance due to solid waste disposal
Temporary • Provide two bins for recyclable and non-recyclable wastes.
• Ensure that recyclable and non-recyclable waste is collected in segregated manner in theses bins before disposal. Recyclable material should be sold. Non-recyclable material should be disposed for designated land fill area of the city. • Provide adequate sanitation facility for workers at construction sites.
DBO Operator
Impact in sensitive area Temporary The project area falls under Ramsar site which is
a sensitive area; the management plan for the
same is being prepared by UP forest department;
During construction measures to be taken to
ensure that muck, debris generated from the
construction activities are strictly prohibited for
its entry to river Ganga; necessary signages,
barricades (if construction along Ganga is
envisaged) to be given at specific locations;
High noise in the project area need to be
controlled and hence sheet piling to be avoided
Construction vehicles need to have silencers to
minimize honking noise;
DBO Operator
General: safety during construction
Accidents Safety hazards to labours and public
Temporary • Comply with the Occupational health and Safety Act of India
• Ensure that the contact details of the police or security company and ambulance services nearby to the site.
• Ensure that the handling of equipment and materials is supervised and adequately instructed.
• Erect warning signs/ tapes and temporary barriers and/or danger tape, marking flags, lights and flagmen around the exposed construction works warn the public and traffic flow of the
DBO Operator
166
inherent dangers. • Provide adequate safety precautions
such as helmets, safety shoes, gloves, dust masks, gumboots, etc. to workers Monthly reporting of all accidents and immediate reporting to DBO engineer and owner.
Operation Phase
Sewer line Leakage/ overflows
Water pollution and possibility of mixing with water supply line
Temporary • Regular monitoring of sewer line and manholes for visible leakages/ overflows. Immediate repair operation for the damaged portion of sewer line. De-siltation of blocked sewers/ manholes with sewage pumping machines-storing and disposal at appropriate refusal area after treatment.
E Ensure proper covering of manhole and avoid dumping of solid waste to prevent chocking of sewer line.
DBO Operator
Sewage Pumping Station
Waste Handling Bad odour, Health hazard and public nuisance
Temporary • Provision for regular clearance of sludge and solid waste to minimize odour nuisance
• Ensure maintenance of Green belt as planned
• Periodic disposal of accumulated sludge/solid waste to disposal site as approved by DBO engineer.
DBO Operator
167
Sewage Cleaning Equipment
Extracted Sewage Sludge handling and cleaning equipment maintenance waste handling
Bad odour, Health hazard and public nuisance and possible land contaminations
Temporary • Ensure that extracted sewage sludge collected during sewers cleaning are disposed to disposal site as approved by DBO engineer.
• Sewage solids shall not be disposed on road sides or non-designated areas.
• Equipment cleaning waste shall be disposed to public sewer or STP inlet for treatment
• Waste oil if any generated shall be separately collected. It shall be sold to authorized waste oil recyclers.
DBO Operator
Impact in sensitive area Temporary The project area falls under Ramsar site which is
a sensitive area; the management plan for the
same is being prepared by UP forest department;
Further to monitor the baseline Dolphin
population, a status survey is being planned by
UP forest department which will be repeated
after every 3 years;
Dolphins are sensitive to noise levels and hence
care to be taken that the noise from pumping and
other activities at SPS, STP are controlled
through some enclosures, noise mufflers;
The sewage and STP sludge should be strictly
prohibited from disposing them directly to river
Ganga
DBO Operator
General Safety Workers exposure to toxic gases in sewers and hazardous materials during sewer maintenance work
• Serious/health/ safety hazards
• The toxic gases are likely to contract communicable diseases from exposure to pathogens present in the sewage.
Temporary • During cleaning/ maintenance operation, the sewer line will be adequately vented to ensure that no toxic or hazardous gases are present in the line.
• Ensure availability of PPE for maintenance workers.
• Follow safety and Emergency Preparedness plan prepared at design stage Monthly reporting of all accidents and
DBO Operator
168
immediate reporting to DBO engineer and owner.
7.3 Environmental Monitoring Plan
The Environmental Monitoring Programme has been detailed out in Table 7.3.
Successful implementation of the Environmental Monitoring Program is contingent on
the following:
The Project Management Consultant (PMC) along with Uttar Pradesh Jal Nigam to
request the Contractor to commence all the initial tests for monitoring (i.e. for Air,
Water Quality and Noise Levels) early in the Contract to establish 'base' readings (i.e.
to assess the existing conditions prior to effects from the Construction activities
being felt);
The PMC along with Uttar Pradesh Jal Nigam to request the Concessionaire /
Contractor to submit for approval a proposed schedule of subsequent periodic tests
to be carried out;
Monitoring by the PMC's Environmental Officer of all the environmental monitoring
tests and subsequent analysis of results;
Where indicated by testing results, and any other relevant on-site conditions, PMC
to instruct the Concessionaire / Contractor to:
o Modify the testing schedule (dates, frequency);
o Modify (add to or delete) testing locations;
o Verify testing results with additional testing as/if required;
o Require recalibration of equipment, etc., as necessary; and,
o Request the Concessionaire to stop, modify or defer specific
construction equipment,
o Processes, etc., as necessary, that are deemed to have contributed
significantly to monitoring readings in excess of permissible
environmental "safe" levels.
Table 21Environment Monitoring Programme
Environment Stage
Institutional Responsibilities
Component Parameter Standards/Methods Locations Frequency Implementation Supervision
Air Quality Construction PM10, PM2.5, SO2,
NO2, CO CPCB
Sewer
Construction
Sites
Once in
every season
(except
monsoon)
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Operation PM10, PM2.5, SO2,
NO2, CO
STP / MPS/ SPS
& Sewer Sites
Once in a year
except
monsoon for
first 5 years.
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Water Quality Construction
pH, EC, TDS, Total
Hardness, Total
Alkalinity, BOD, COD,
DO, Ca, Mg, SO4, Fe,
PO4, NO3, Coliform
CPCB
Sewer
Construction
Sites
Once in every
season
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Operation
pH, EC, TDS, BOD,
COD, DO, PO4, NO3,
Coliform
STP Sites Once in every
week
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Meteorology Construction
Rainfall,
humidity, Wind Speed,
Wind direction,
Temperature
USEPA's
Meteorological
Monitoring Guidance
for Regulatory
Modeling
Applications
One location
within
Anupshahr
Once in every
season
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Operation Rainfall,
humidity, Wind
USEPA's
Meteorological
One location
within Once in a year
Contractor through
approved PMC, Anupshahr
Environment Stage
Institutional Responsibilities
Component Parameter Standards/Methods Locations Frequency Implementation Supervision
Speed, Wind
direction,
Temperature
Monitoring Guidance
for Regulatory
Modeling
Applications
Anupshahr monitoring
agency/Lab
Nagar
Parishad and SPMG
Noise Levels Construction
Leq dB (A) (Day
and Night) Average
and Peak values
Ambient Noise
Standard
CPCB
Sewer
Construction
Sites
Once in every
season
(except
monsoon)
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Operation
Leq dB (A) (Day
and Night) Average
and Peak values
Sewer
Construction
Sites
Once in a year
except
monsoon for
first 5 years.
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Soil Construction
Physical
Parameters:
Texture, Grain
Size, Gravel,
Sand, Silt, Clay;
Chemical
Parameters: pH,
Conductivity,
Calcium,
Magnesium,
Sodium, Nitrogen,
Absorption Ratio
Consider the
following methods:
IS-2720 (Various part);
Soil Chemical
Analysis by M.L.
JACKSON.
Soil Test Method by
Ministry of
agriculture
Sewer
Construction
Sites and SPS
Once in every
season
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and SPMG
Environment
Component Stage
Institutional Responsibilities
Parameter Standards/Methods Locations Frequency Implementation Supervision
Operation
Physical
Parameter :
Texture, Grain
Size, Gravel,
Sand, Silt, Clay;
Chemical
Parameter: pH,
Conductivity,
Calcium,
Magnesium,
Sodium,
Nitrogen,
Absorption Ratio
Consider the following
methods:
IS-2720 (Various part);
Soil Chemical Analysis by
M.L. JACKSON.
Soil Test Method by
Ministry of agriculture
Along sewer
construction
sites, SPS
Twice in a
year (Pre-
monsoon and
Post
monsoon) for
first 5 years,
Contractor through
approved monitoring
agency/Lab
PMC,
Anupshahr
Nagar
Parishad and
SPMG
7.4 Social Management Plan
7.4.1 Social mitigation plans during construction phase
Based on the identified social issues, doable mitigation plans are proposed. Some of these
measures are already listed in the DPRs, and some of them are additionally recommended
for social development of the project and the concerned stakeholders.
1. Impact on human health
Mitigation Measure: Acoustic enclosures or hoardings can be constructed at the proposed
sites.
Mitigation plan involves the erection of temporary enclosures around construction sites.
These barriers will help entrap some of the dust that is brought up in digging. They will also
provide safety benefits, to be detailed below. According to the interaction/consultation
with the key stakeholders, it was said that contractors are doing water sprinkling in the
construction area.
2. Traffic Congestion
Mitigation Measure: Re-route traffic whenever possible and employing traffic police to
manage the traffic movement.
Traffic must be re-routed to facilitate ease of movement. Proper signage should provide
detailed information on the dates and duration of road closures and which detours will be
available, ideally well in advance of actual construction so residents can plan accordingly.
Strategic placement of traffic police at critical intersections will also facilitate better flow of
traffic. Plans and budget for these measures are already included in the DPR.
3. Impact on livelihood
Sewer constructions will invariable lead to road closures, which will adversely affect shops
on those streets. The first priority is for the contractor to take the necessary measures to
ensure that pedestrians always have access to shops, vendors, etc. For mobile vendors, this
may include adjusting the location of the cart, etc. to a similar location in the immediate
vicinity of the original location for the duration of the project. Projects should also proceed
on schedule so as to minimize disruption.
174
Additionally, clean-up of debris and clearance of blockages should commence immediately
after project completion so as to remove any potential obstacles that might prevent
customers from accessing businesses or other disruptions.
In the event that the contractor, despite best efforts, is unable to avoid blockages of the
roads and/or disruption of local businesses, some compensation is necessary. The ESMF
currently mandates compensation only in the case of permanent livelihood loss or
displacement and provides no provisions for livelihood loss of mobile vendors. Additionally,
no regulation, policy, guideline, etc. exists which can provide precedent or guidance in this
instance. ESMF clearly states that mobile/ambulatory hawkers: fruit cart vendors, etc. who
can easily relocate fall into this category. These vendors are most eligible for a temporary
relocation just outside the construction area, and will thus not be eligible for compensation
as is the case for this proposed project.
However if during the construction of the project any party faces livelihood loss due to the
proposed project, then that party should be compensated according to the entitlement
matrix given in the ESMF report.
4. Impact on existing utility services
Mitigation Measure:
• Circulating the layout plans of the existing underground alignment near the
work site
• Contacting the relevant department in case there is any damage to any of the
utility services and ensuring prompt fixing/replacing of damaged infrastructure
Temporary shifting of power/water lines for construction purposes is already budgeted for
in the DPR. Nevertheless, all construction personnel must receive detailed layout plans of
existing underground structures to prevent accidental water/electricity supply disruptions.
The relevant departments should also be made aware of the timing and location of digging
near supply lines so they can make the necessary preparations to respond swiftly to
disruptions.
175
5. Safety hazards
Mitigation Measure: Fencing of the excavation site and providing proper caution sign
boards. As mentioned above, fencing should be erected around construction sites and
appropriately marked with caution signage. These fences/signs should remain in place even
if construction is not active, so long as a hazard (e.g. open pit) remains.
6. Elevated Noise Levels
According to UP Jal Nigam officials, construction will take place after school hours or at
other times of school closing to avoid interfering with school functioning sensitive locations.
Beyond that, construction must simply proceed in a deliberate and judicious manner to
avoid unnecessary noise pollution. Noise barriers will be placed near sensitive receptors like
hospitals and schools
7. Failure to Restore Temporary Construction Sites
As mentioned above, provisions to rehabilitate roads and clear debris are already included
in the DPR.
8. Public Notice: According to the suggestion given by locals during the interview.
Government and contractor should give a prior notice to each and every locality with the
details of project, street wise start date of construction and street wise end date of
construction, contact person during emergency. This information would help them better
adjust to the situation and make necessary adjustments and provisions.
9. Health Programme for Workers: If un-sanitary conditions prevail at labours camp,
health programmes for their well-being should be implemented.
7.4.2 Social mitigation plans during operation phase
Noise pollution due to improper handling of machines: proper O&M should be carried out
during the operation phase to ensure least disturbance is caused to the neighboring
residents.
176
Table 22Social Management Plan
Activity Potential Negative Impact/Concern
Mitigation Measures Cost Issues
I. Sewerage and Sanitation Projects
A. Design and Development Phase
Land Acquisition for new pumping station
NA
•STP/SPS is planned on land that is easily obtained by the govt. authorities
NA
Laying of sewer network
Safety hazards to workers and residents
•Provide workers with Adequate safety equipment such as helmets, safety shoes, gloves, etc. Fences/temporary enclosures should be put around construction sites (even inactive ones, if hazards, like open pits, remain); enclosures should be properly marked with
NA
Dust generation, with resulting implications for human health
•Water sprinkling, removal of excess materials, cleaning of sites upon completion of activities. •Construction of temporary enclosures to entrap dust
•Considered in EMP Budget
Reduced pedestrian and vehicle access to residences and businesses, with inverse effects on livelihoods
Work should proceed on schedule so as to minimize road closures Upon project completion, quick clearance of debris etc. will facilitate access by customers to local business and residents
NA
177
Activity Potential Negative Impact/Concern
Mitigation Measures Cost Issues
Temporary water , electricity, supply interruptions
Circulation of layout plan for all underground infrastructure to ensure that contractor is aware of water/electricity lines in construction zones •Local utilities should beamed aware of timing/location of all construction, enabling them to respond swiftly to supply disruption, especially in the event of flooding, etc.
Provision of Feeder pillars has been made for the proposed infrastructure construction
Increased traffic inconvenience (emissions, congestions, longer travel times)
•Use of alternate traffic routes; signage should clearly indicate dates of road closures and new routes so residents can plan accordingly •Placement of traffic officer sat busy intersections to facilitate easy of movement
Residents will follow alternate routes and no such heavy vehicular movement is seen on these roads.
Impact to daily life Prior public notice indicating the date of start of construction and end date of construction should be provided road-wise to the locals, allowing them to make adjustments accordingly
178
7.4.3 Consultation Framework for Participatory Planning and Implementation of
Mitigation Plan
Relevant stakeholders, especially community members (residents, shop owners, etc.)
may be informed about the details of the proposed mitigation plan. A public
consultation may be conducted where the mitigation plan is presented, and feedback
solicited from the community. Individual meetings with other key stake holders -
government officials, relevant NGOs, etc. could be scheduled to solicit their feedback as
well. Once construction begins and the mitigation plan is put into effect, third party
audits should be taken up so as to evaluate the efficacy of the mitigation plan, as well as
gauge local sentiments related to the construction and identify/address new issues that
may have arisen during construction.
Stakeholders that should be involved in planning and implementation of the mitigation
plan include;
Decision makers, policy makers, elected representatives of people, community
and citizens, NGOs etc;
Staff of executing agency, implementing agencies, GPCU, etc.
Officials of the revenue departments, social welfare department etc; and
Representatives of the various state government departments, as required.
7.4.4 TRANSPARENCY AND CITIZEN VOICE
Besides the activities mentioned in the above para, it is essential for the success of the
project that complete transparency about it is maintained. Citizens voice about the
project shall be heard & all the grievances of the stake holders/citizens must be
properly addressed to. This is to be achieved by:-
a Disclosure and dissemination of information
This is to be achieved by Municipality disclosures act, RTI and NGRBA guidelines on
stake holders, consultations.
b Citizen voice
This is sought to be achieved by the following:-
i Disclosure of information regarding the project to the public at regular intervals.
ii Consultation and engagement of genuine stake holders on investments regarding the
project.
179
c Use of social audits
This is sought to be achieved by the “people’s audit” which provides the real view
regarding the performance of the project based on the society’s perception & analysis.
d Adherence to RTI Act
The Right to Information act will be used to ensure transparency on all aspects of the
programme by proactive disclosure & sharing of information voluntarily & on demand
as prescribed under the law with key stake holders, communities and beneficiaries.
This information would be provided regarding all components of the project including
cost estimates, procurement plans, details of tender notices, details of award of
Contracts, Contract amounts, Selection of consultants & the details of officials
implementing the project.
GRIEVANCE REDRESSAL
Redressal of grievances contributes to a great extent to the positive perception of the
public regarding the project implementation. Therefore it is essential that any query or
a complaint vis a vis any aspect of the project implementation is promptly,
effectively& positively addressed. The Grievances will be submitted through various
mediums, in person, through phone calls, online or through letters. A single system for
redressal of grievances shall be adopted at the project level to ensure that its purpose is
met. The integrated grievance system will include the following.
i Establishing Grievances Redressal Cell (GRC) with dedicated project officer and
system at the local EA & ULB .At project level the proposed GRC includes Executive
Officer, Anupshahar Nagar Palika. Assistant Engineer, U.P.Jal Nigam will be
Grievance redressal officer at EA level including representative of DBO. Name and
contact information of GRO will be displayed at project site/Notice Board and also
disclosed on website of ULB, EA and SPMG.
ii The public also can submit their unresolved grievances at Tehsil Divas on every
second and fourth Tuesday of every month between 10:00 to 14:00, to District
Magistrate/Sub District Magistrate and all district level officials for quick redressal.
iii The SPMG & EA will prepare a half yearly report on grievance redressal under
GAAP and will be reviewed during meeting of CMCs and Social Audit.
iv The above arrangement will be in addition to the PIO official appointed under RTI
Act, under office of the General Manager, Yamuna Pollution Control Unit, U.P.Jal
Nigam, Ghaziabad.
INSPECTION AND AUDIT
180
Third party inspecting agencies engaged will review the implementation of project
based on site visits & discussions with executing agencies & stake holders to assure
the quality & implementation schedule. Similarly financial audits both internal and
external will be conducted annually at regular intervals to ensure that the financial
investments are put to proper use.
7.4.5 Assess the Capacity of Institutions and Mechanisms for Implementing Social
Development Aspects and Social Safeguard Plans; Recommend Capacity building measures
Roles and functions of the institutions are pre-defined, but they can enhance their
capacity for better implementation and operation of the project. There should be
synergies and continual interaction amongst the departments for better coordination.
The officers of the relevant departments can be trained in social sciences, social
management plan, etc.
Table 23Role of stakeholder in implementation and mitigation
Stakeholder Category Role in project implementation
Role in mitigation
NMCG Monitoring at National Level Coordinating so that the mitigation plan is implemented well Ensuring funds for mitigationplan execution
Executing agencies (UP Jal Nigam, Ganga Pollution Control Unit)
Implementation of the project by awarding the project to the suitable contractor and regional coordination Informing the relevant departments about the progress of the project
Ensuring that the relevant departments are available for mitigation plans Enough safety provisions are available for the project implementation.
Jal Sansthan While execution of projects related to sewerage line, Jal Sansthan is responsible for the damage caused to the public utility functions like drinking water pipe line.
Should ensure that the basic amenities are in order during the construction and operational phase of the project
Municipality Ensuring better access to households
Should ensure all the households envisaged at project planning phase gets access to the services. Weaker section of the society should get equitable share.
181
State, local Government Coordination Monitoring and evaluation
Coordination Monitoring and evaluation Ensure all the safeguarding plans are in line and acted upon.
NGOs, CSOs Awareness creation about the project activities Community participation for better project implementation
Public participation and coordination
7.4.6 Develop Monitoring and Evaluation Mechanisms to Assess Social Development
Outcomes
Regular monitoring and evaluation of the project activities should be carried out to judge its
success or any gaps. Certain key parameters can be taken as the benchmark for monitoring
and evaluation of the project based on the identified development outcomes. Some of the
indicators are listed below;
• Increase in sewer access (number of households linked to the sewer network)
• Decrease in effluent discharge into the Ganga (water quality assessment of the river)
• Proper sites for industries, building etc.
• Accessibility of the service to backward and weaker sections of the society
• Increase in public toilet
• Increase in the land rate (property appreciation value)
• Decrease in water borne disease incidence in the area
7.5 EMP Budget
The environmental budget for the various environmental management measures proposed
in the ESMP is detailed in Table 27 and the cost of the Environmental Monitoring is given in
Table 28. There are several other environmental issues that have been addressed as part of
good engineering practices, the costs for which have been accounted for in the Engineering
Cost. The rates adopted for the budget has been worked out on the basis of market rates
and the Schedule of rates. Various environmental aspects covered/will are covered under
engineering costs are listed below:
Proper drainage arrangements to prevent water stagnation/ flooding in SPS and STP
site area
182
Appropriate siting, and enclosing within building to reduce noise and odour nuisance
to surrounding area. Drainage along the ghats to collect the discharge from the
residents and connecting to city sewer.
Alternate traffic re-routing,
Ensuring storage of excavated soil material on the higher lying areas
Solid Waste Management
The tentative cost breakup of the EMP is given in Table 7.4. These costs are to be considered
as estimated on a lump-sum basis, since the detailed cost estimates depend on site
condition and construction/operation practices.
Table 24 EMP Budget
Phase Component of EMP Mitigation measure Cost included in
the DPR (Yes/no/not clear)
Cost in Rupees (or Details if provided in DPR)
Remarks
Design and Development
Design of efficient STP Selection of appropriate technology
Yes (not specific but included as a part of
associated construction activity)
DPR for Sewerage System at Anupshahr, Chapter - 7, Estimate
MBBR technology has been chosen in the proposed DPR
Sludge disposal design in STP
Appropriate technology/ sludge management
Yes (not specific but included as a part of
associated construction activity)
DPR for Sewerage System at Anupshahr, Chapter - 7, Estimate
The proposed DPR includes these activities
Provision for accidental leakages / bursts in
STP/SPS
Proper drainage arrangements to prevent water stagnation/ flooding in STP/SPS site area
Yes (not specific but included as a part of
associated construction activity)
DPR for Sewerage System at Anupshahr, Chapter - 7, Estimate
The proposed DPR includes these activities
Location of STP Provision of trees as noise
barriers and to reduce odour nuisance if any
Yes (provision of plantation and
development of STP campus)
DPR for Sewerage System at Anupshahr, Chapter - 7, Estimate
The proposed STP is placed away from main residential area and its enclosed nature prevents odour and due to the MBBR technique being used no such noise pollution is taking place.
Tree plantation: Suggested to grow trees which are suitable to grow in the study area. Trees like Neem, Sal, Arjun, Jamun, Nahera, Pongamia, Harar, Drek, Bahera, Ailanthus are suitable for the present project area.
Location of SPS
Appropriate siting, and enclosing within building to
reduce noise and odour nuisance to surrounding area
Yes DPR for Sewerage
System at Anupshahr, Chapter - 7, Estimate
The proposed SPS will be indoor which will prevent noise and enclosed nature and appropriate cleaning and maintenance will prevent odour nuisance
Construction Excavation, Cutting and
filling operations
Review of existing
infrastructure, shoring trenches,
reinstatement/
Yes DPR for Sewerage
System at Anupshahr, Chapter - 7, Estimate
The proposed DPR includes these activities
184
resurfacing
Damage public utilities
Proper reviewing of existing drawings of utilities, informing
concern authorities and reinstatement of public
utilities
Yes DPR for Sewerage
System at Anupshahr, Chapter - 7, Estimate
The proposed DPR includes these activities
Dust
generation
Water sprinkling on excavated material to suppress dust and provision of top cover when transported through vehicles
No
Water tanker: Rs. 108000.00
Top cover for dumper truck: Rs. 22,500
Water sprinkling: As per time schedule 24 months - 60 excluding monsoon period. Per day, as estimated 100m will be covered1000 L water will be consumed every-day for 100m using sprinkler, average 2 times a day. Labour cost = Rs. 150/day Rs 300/tanker + Rs. 150/labourer = Rs. 450 Per meter cost = Rs.450/100m = Rs. 4.50 Total cost for 60 km = Rs.4.50 x 60,000 = Rs. 2,70,000
Keeping a 2-day margin for construction and re-instatement per site:
= 4 x 270000 = Rs1080000/- Top cover:
Approximately 30 Sqm of top cover may be required for each vehicle. Assume that 10 such vehicles are required in transporting excess soil to dumping location (considering construction schedule and max excavated earth disposal). Therefore: 10 trucks x required top cover 30 Sqm xCost of Tripol cover @Rs. 75/ Sqm = Rs. 22500
Phase Component of EMP Mitigation measure
Cost included in the DPR (Yes/no/not
clear)
Cost in Rupees (or Details if provided in
DPR)
Remarks
185
Noise and vibrations Usage of sound barriers or
sheets. No
Setting up barricades: Rs. 43,500/-
Setting up noise barriers (installing GI sheets): Rs.
3,37,000
As per the schedule, the construction of 60km has to be executed in 24 months which implies that approximately 10 days are required for completing 1km or 100 m/day. Setting up barricade frame: • wooden rod (bamboo or babool) length = 10ft = 3m Total rods (vertical) required = 250/3 = 83.3 ~ 90. Total rods (horizontal) required (2 layers) = 250/3 x 2 = 83.3 x 2 ~ 90 x 2 = 180. Total one side = 180 + 90 = 270 rods Total opposite side Total = 180+ 90 = 270 Rate for 1 wooden rod = Rs.75 per rod. Total cost for frame = Rs.300 * 540 rods = Rs. 40,500 Labour Cost: 2 labourers per day = 2 x 150 = Rs.300 Total = Rs.300 x 10days for barricading= Rs. 3000 Using Galvanized Iron (GI) sheets as noise barriers in sensitive zones: Based on discussions with SPMG, noise barriers will be setup only in sensitive regions hence, only 2.0 kms (estimated) of noise barrier would be required. 2.0 km@250m/day would require 10 days. Approximately 250 m of barricade is set up
On each side of construction site= 250mx2=500m per site Each Gi sheet has dimensions of 10ft x 4ft=3m x 1.2m Laying each sheet horizontally, 2 sheets would cover a height of 1.2 m + 1.2 m=2.4 m and a length of 3.0 m Number of GI sheets required for 250m
186
stretch(Left side)= 250/3*2=167 sheets Number of GI sheets required for 250m stretch(Right side)= 250/3*2=167 sheets Total=334 sheets Hence, 334 sheets x Cost of GI sheet Rs. 1000per sheet (Rs. 70-100 per Kg)+ Labour cost for 10 Days(two laborers at average rate of Rs. 150.0 per day). =334x 1000+(150x2x10)=Rs. 3,37,000.00 The above mentioned costs are generalized cost for a 250m stretch for barricades, GI sheets separately.
Temporary Flooding or water logging
Alternate traffic rerouting Ensuring storage of excavated
soil material on the higher lying areas
No NA All the flooded water will be diverted in gravity to the existing nalas.
Increased traffic inconvenience
Traffic re-routing No
No such Heavy traffic can be seen in the town.
Labour camps (if adopted)
Health hazards and nuisance due to absence
of facility for sanitation or solid waste management
Sanitation No
Cost of construction of pit and toilet building
approximately Rs. 10,00,000
Cleaning of all pits 1,20,000
Total number of labourers is estimated assuming 35% of total project working for average 20 months (24 months for sewerage and 16 months for STP). The labour camps can be divided into 2 camps, for appropriate management and maintenance work. Each camp will have around 2000 labourers A toilet with septic tank is been suggested for sanitation facility at labour camps.
• Pit: Assuming single pit of 100cum would cover 1000 people.2 pits are needed in 1 camp. Construction of one pit would cost approximately Rs. 1, 50,000/-. So for 2 camps 2 pits each is required. So total cost of pit construction would be Rs. 6,00,000
• Construction of toilet building consisting of 15
187
toilets cost Rs 80,000. 5 such buildings will cost 4,00,000
• Pit cleaning: The filled pit has to be cleaned after 9 months by either disposing off at refusal site or STP by concerned Municipal agency. Cleaning of one pit would be approximately
• Rs15, 000/-. So, for 4 pits in the given project duration twice cleaning would be needed, So total cost would be Rs. 1,20,000
Water Supply No Approximately Rs. 11,22,500/-
As estimated 2000 labourers will be at one camp, so approximately 400 families. Around 25 stand posts will be needed at one camp. One stand post cost is Rs 6250/-So total cost of construction will be Rs. 3,12,500.00 For the standard of 135 LPCD, 5, 40,000 L of water is needed for both the camps. At the rate of Rs 2.5KL, the cost of water provisioning would be Rs 1350.00 per day. For 20 months, cost will be Rs. 8,10,000/-
Dust bins No Approximately
Rs. 4,00,000
Solid waste generation: Generally about 200 grams of solid waste is generated per 5 persons every day. Hence 4 cluster dustbin (one for biodegradable waste and one for non-biodegradable waste of 1 cum size at the rate of Rs. 2000/-) may handle solid waste generated.
Treatment and disposal of sludge
Ensure proper functioning of STP for digestion of sludge
Aesthetic appearance by green cover
No
No treatment of sludge is required as the yearly exercise of sludge removal will take place and the sludge removed will be used as the manure.
The estimated cost of the environmental management plans that are not included in the DPR amount to Rs. 41, 25,500.00/-.
Table 25Cost of Environmental Monitoring Plan
Item Location Season Year Total
Samples in
No.
Unit Cost
Rs. Total Cost Rs.
Environment Monitoring during Construction Stage
Air quality monitoring 4 3 2 24 7,100 170400
Metrological data 1 3 2 6 5,000 30000
Noise / vibration 4 3 2 24 2,000 48000
Soil analysis 4 3 2 24 5,500 132000
Water Quality Assessment at
2 STP and 2 SPS sites 4 4 2 32 6,500 208000
Travel and Transportation of
monitoring Team Lump sum 3,00,000
Green Belt Development
along the periphery of STP's
and SPS's
Lump sum 2,00,000
Sub total Rs.1088400.00
Environment Monitoring Cost (Operation Stage)
Air quality monitoring 4 1 5 20 7,000 140000
Metrological data 1 1 5 5 5,000 25000
Noise / vibration 4 1 5 20 2,000 40000
Soil analysis 4 1 5 20 5,500 110000
Water Quality Analysis 4 4 5 80 6,500 520000
Travel and Transportation of
monitoring Team Lumpsum
4,50,000
Accidental Bursts Lumpsum 3,00,000
Green Belt monitoring Lumpsum 2,50,000
Subtotal 1835000
Total for Environmental Monitoring (Construction and Operation Phase) Rs. 2923400.00
The estimated cost of the Environmental Management Plans that are not included in the DPR amount
toRs. 41, 25,500.00/-. Total Cost of Environmental Monitoring is Rs. 2923400/-. Total EMP Budget
including monitoring cost is Rs.70, 48,900.00/- (Say 70.49 Lac).
189
8 Social Development Outcomes and Issues
Introduction:
The cultural and social status of the residing community is very important and can be
understand in accordance with the region's existing baseline social status. The various
suggestions were given in the public consultation and during focus group discussion (FGD).
The discussion with the stake holders are put forwarded in this chapter.
Public consultation/stakeholder consultation and focus group discussion
The public consultation and focus group discussion (FGD) were conducted on 10th January,
2014 and 14th January 2014 wherein social expert has interacted in a well prescribed
Questionnaire, which is enclosed as Annexure 7. The details of public consultation are
presented below:
Major components/ Key issues of the project discussed like
1. STP Zone-A, Anupshahr (Location, Odour, Treated effluent, Land requirement etc.)
2. STP Zone-B, Anupshahr (Location, Odour, Treated effluent, Land requirement etc.)
3. MPS Zone-A, Anupshahr (Location, Noise, Approach to MPS, Land requirement etc.)
4. MPS Zone-B, Anupshahr (Location, Noise, Approach to MPS, Land requirement etc.)
Minutes:-
1. The land adjacent of Existing campus of STPs in both zones are vacant and local
people and stake holders have no objection in acquisition of land for construction
STPs for subsequent years up to 2048.
2. Land acquisition resulting in Relocation of households.
3. The people of Anupshahr are highly appreciate the sewerage project introduced by
Jal Nigam and also show their cooperative nature in listening the objective and
significance of project. There are no tribal settlements in the project area.
4. Construction works near schools and colleges are carried out during vacations and
works near hospitals are completed on priority basis (in shorter time period with
alternate provision of traffic, accessibility of exit/entry gates etc.), the impacts may
be limited
5. Sewer construction leads to the temporary tearing up of roads and increase in large
construction vehicles, which might impair traffic movement, especially in the
narrower roads should also be considered
190
6. Although temporary, concerns regarding failure to restore construction sites
including failure to close and appropriately fence off open pits were cited as safety
concerns especially for children.
7. Due to the construction of sewer lines, raw sewage that currently flows into the river
and/or overflows into the streets will now be routed to the STP. This will prevent
flooding of adjacent areas.
8. There will be a significant improvement in water quality due to effluent discharge
being treated.
9. To avoid the Dust generation provision of Water sprinkling should be provided
10. While execution of projects related to sewerage line, Jal Sansthan is responsible for
the damage caused to the public utility functions like drinking water pipe line.
11. Ensuring better access to household.
191
Discussions at the Ghat, Near Intercept Sewer tapping
Discussions at the STP A in Zone-A
Discussions at STP B in Zone-B
192
Discussions at MPS-A, Zone-A
Discussions at MPS-B, Zone-B
193
Awareness about the project to be implemented under Mission Clean Ganga.
Only 35% people are aware that the project is to be implemented under Mission Clean
Ganga. Majority of the public doesn’t know about the project and only 10% people have
little information regarding the project.
The Awareness of the project has been predicted by means of questionnaire and the results
are presented below:
Necessity of the Project
Majority of people were in favor of the project implementation. The project was favoured
by the people looking the sanitary conditions of the town in the future.
Present Sanitation/Pollution Condition in the city
The conditions in the town are very serious and the people residing are agreed with the fact.
All the population of the town favours the improvement in the present sanitation conditions
except the small chunk of 5 %.The response on the present sanitation conditions in the town
are shown below:
48%
35%
10% 7%
Doesn't know
Know
Little Information
Only heard the name of Mission CleanGanga
194
Household connections
In the present scenario, there are no household connections in the Anupshahr Town.
Connections of toilet to sewer line
Majority people of around 90% are willing that there toilet should be connected to sewer
line while 2% people do not bother regarding such issue and about8 % people do not want
such kind of scheme. The response on the willingness for the sewer connection in the town
is shown below:.
60%
35%
5%
Very Serious Need to Improve
Do not Bother
90%
8% 2%
Yes No Do not Bother
195
Major water borne and vector borne diseases in the area
Diarrhea, Malaria, Typhoid, Cholera and dengue are the major water borne and vector
borne diseases in the area.
Effect on certain parameters due to the construction of the project.
I. Traffic: In general viewpoint there will be inconvenience during construction phase
due to laying of sewer pipes and traffic blockage but this effect will be short term.
II. Parking: Same problem of vehicles is expected on a short term basis lasting during
project construction phase.
III. Aesthetic Value: The aesthetic value of neighbourhood and environment will
improve due to commissioning of the project.
IV. Health: The health related problem can be controlled by using mitigation measures
of dust control, noise pollution check etc. This would be short term effect.
V. Access to River: River water quality will improve and River would be more
accessible.
VI. Noise: Effect on noise would be minimal and shall be mitigated using mitigation
measures. Effect on noise would be short term.
VII. Livelihood: Effect on livelihood would be short term, difficulty in accessibility and
movement due to digging of the roads can be arise but for short duration.
VIII. Impact due to worker’s camp: The unsanitary conditions and safety concerns can be
mitigated by providing the proper sanitation facilities in the labour camps.
Project will help in improving the sanitation status of the city
Mostly all (94 %) people agreed that there will be improvement in the sanitation status of
the city after project implementation. The response on prospect of improving sanitation
status in the town is shown below:
196
Future scenario in the absence of the project
Around 95% of respondents felt that, the condition in the coming future will worsen if such
kinds of schemes are not taken up. This project will help in improving the
sanitation/environment condition in the town as well as the water quality of the river Ganga
will also improve. The response on future scenario in the absence of project is shown below:
94%
3%
3%
Yes No Don't Know
95%
2%
3%
Worst Situation
No effect
Can not Say
197
Effects of project in post completion stage
Pollution reduction: This project will surely help in the pollution reduction of the city.
Better Sanitation: The sanitation conditions in the town will improve.
Reduction in smell/flies: There will be control over such problems as there will be no open
drains.
Access to River: River Ganga would be more accessible as the quality of the water will
improve and there would not be direct discharge of nallah in the river.
Conflicts during implementation/construction of the project
Most of the people are in favour of the project and they do not perceive any conflict during
implementation/construction of the project.
Improvement in Ganga river quality
Around 95% people agreed that the quality of river Ganga will improve as there will be no
direct discharge of untreated sewage in the river.
Implementation of the project in a timely and efficient manner
Around 75% people answered that the state authority will implement the project in a timely
and efficient manner while 20 % people answered that the implementation of the project
will take more time than estimated period of completion.
Redressal mechanism in case of any grievances
Mostly people suggested that there should be a Grievance Redressal Officer and whose
contact number should be available at sites so that general people can contact him and
address him about their grievances.
Cultural issues/threats against similar projects in the past
Mostly people do not perceive any threat and cultural issues for such kind of projects. It was
suggested that implementing agency should give maximum employment to local people for
the project implementation.
Temporary disruption/disturbance during the construction/operation phase
Around 80% people are ready to cope with the temporary disruption/disturbances during
the construction/operation phase as the project is beneficial for the town and river Ganga.
Around 15% people suggested that there should be a provision of compensation if any
property of individual is damaged.
198
8.1 Social Development Outcomes of the sub project
Access to sewer network: This service will cater to the projected population until the
year 2048. According to the DPR, population is expected to increase, approx. 63635 by
2048. In this time, waste water generation is expected to increase approx. 6.87 MLD.
Hence the increase sewerage will prevent outflow of waste water to the Ganga.
Better hygienic conditions: The sewerage network will provide improved
environmental conditions due to the contained handling of wastes, leading to improved
public health conditions and will likely reduce the average medical expenses of the
residents in the project areas. According to DPR this area has sewerage system but the
sewers are very old, under capacity and deteriorated condition, which causes
significant flow of untreated sewage into river and also this sewage, gets accumulated
on road/drain sides. These areas suffer from powerful odors and greater amounts of
flies/mosquitoes, which will be mitigated with the sewerage connection and overall
improvement in environment and health is anticipated from this project.
Decrease in water pollution: Because of the sewer line connection, all the waste water
will be collected and directed to treatment plant, which only after treatment will be
disposed off to the river, hence decreasing the pollutant load in the river.
Increase in aesthetic value of the project area: connection to sewer lines enhance the
aesthetic value of the area, as there will be more cleanliness and no wastewater
discharge to open area. This will also lead to appreciation in the property value. This
will eventually lead to increase in standard of living of the people in the project site.
The support for this statement comes from the counter-factual scenario observed in
areas with only nalas (bad odor, insects, etc.).
Reduction in cost of implementation: According to DPR, wherever possible
development of sewerage will be integrated with existing GAP infrastructure to reduce
the overall investment cost.
Cultural sentiments: Proper sewage disposal would increase the river water quality. As
the holy river is attached to many rituals and customs, enhanced river water quality
199
would connect to sentiments of the people.
8.2 Social Development Issues in Project Vicinity and Social Services to be provided by
the project
The social benefits of the proposed project are given above. The social services required to
ensure that these benefits are realized are given below:
• Ensure backward section of the society gets the facility: Some residents complained
that they did not feel they personally would benefit from the project as their houses
did not have sewer connection. Thus, increasing household connections will ensure
that project benefits are equitably distributed. Plans for increasing connections are
detailed in the DPR. Special care should be taken to ensure access for backward and
vulnerable sections of the society. Full benefits of the facilities proposed under DPR
cannot be realized unless a programme to improve coverage of branch sewers and
household connection is carried in parallel.
• Increasing public toilet facilities: In this project the component of Latrines and
connection to BPL families is taken, to improve or increase the public toilet facilities will
ensure that residents of Anupshahr without permanent housing and tourists
(especially visiting during 'Mela' are able to benefit from the increased sewerage
access. Increasing toilet access will decrease practices such as Open Defecation. This
eventually would lead to better water quality and would have better environment and
social ramifications.
• Targeting of economically weaker communities: for construction jobs related to sub-
project: In order to ensure that the economic benefits of the sub-project is felt by those
in need, those from backward communities should be specifically targeted for relevant
jobs.
• Proper clean-up of project debris: In order to maximize aesthetic benefits and ensure
that debris does not clog sewer path, proper clean-up of project areas must be
performed after the project is completed. Collection and disposal of debris is essential
for proper function of other essential processes like traffic routing, pedestrian
pathways, and clearance of dust and particles causing pollution. Clean area will also
enhance the aesthetic value and increase the property rate of the area.
200
9 Conclusion
The project report of the proposed sub-project for sewerage in Anupshahr town after
environment and social analysis concludes that the project falls in 'low impact' category
and have overall positive benefits on the life and environment of the people. As per
environmental and social management framework guidelines of NGRBA, Environmental
and Social Assessment, with a Generic Safeguard Management Plan was conducted for
addressing possible issues/ concerns arising from proposed project.
Impacts of activities identified during the assessment fell under two separate categories
of Construction and Operation. Although no such permanently negative or adverse
environmental or social impacts were identified, there were certain temporary impacts,
for which appropriate mitigation plans have also been suggested. The environmental
management plan ensures to suggest appropriate mitigation measure against the
issues/ concerns identified during the environmental and social analysis study. All the
social and environmental issues were appropriately studied and have been
substantiated using appropriate evidences, to ascertain the magnitude of their impacts.
Even the issues of public grievances and public notice have been taken care in the
report to confirm transparency during the project implementation. Report also ensures
that well defined institutional mechanism is in place to monitor and evaluate the
progress of the project during construction, implementation and operation phases.
Stakeholder consultations and interviews helped to understand the general perception
of public towards the project and it can be determined that the people of the project
site are happy and welcome such an initiative for their betterment. It was also pointed
out that the large overall environmental benefits of the project such as prevention of
discharge of untreated sewage into River Ganga, improvement in sewerage collection
and treatment, prevention of untreated liquid waste infiltrating into ground water and
soil, improvement in quality of life, human dignity and increased productivity greatly
outweigh the temporary inconveniences faced during the implementation stages.